EL25-49-000 · 2025-04-23 · Delaware Public Service Commission

Comments and Intervention of Delaware Public Service Commission on the Show Cause Order issued on 02/20/2025

PDF page 1

UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
 Docket Nos. EL25-49-000
Allegheny Electric Cooperative, Inc.

)
American Transmission Systems, Incorporated )

Atlantic City Electric Company

)
Baltimore Gas and Electric Company

)
Delmarva Power & Light Company

)
Duke Energy Ohio, Inc.

)
Duke Energy Kentucky, Inc.

)
East Kentucky Power Cooperative, Inc.

)
Essential Power Rock Springs, LLC

)
Hudson Transmission Partners, LLC

)
Jersey Central Power & Light Company

)
Mid-Atlantic Interstate Transmission, LLC )

Neptune Regional Transmission System, LLC )

Old Dominion Electric Cooperative

)
PECO Energy Company

)
PPL Electric Utilities Corporation

)
Potomac Electric Power Company

)
Public Service Electric and Gas Company

)
Rockland Electric Company

)
Trans-Allegheny Interstate Line Company )

Transource West Virginia, LLC

)
UGI Utilities, Inc.

)
Monongahela Power Company

)
The Potomac Edison Company

)
Commonwealth Edison Company

)
Commonwealth Edison Company of Indiana, Inc. )

The Dayton Power and Light Company

)
AEP Appalachian Transmission Company, Inc. )

AEP Indiana Michigan Transmission Company, Inc.) AEP Kentucky Transmission Company, Inc. )

AEP Ohio Transmission Company, Inc.

)
AEP West Virginia Transmission Company, Inc. )

Appalachian Power Company

)
Indiana Michigan Power Company

)
Kentucky Power Company

)
Kingsport Power Company

)
Ohio Power Company

)
Wheeling Power Company

)
Duquesne Light Company

)
Virginia Electric and Power Company

)
Linden VFT, LLC

)

PDF page 2

City of Cleveland, Department of Public

)
Utilities, Division of Cleveland Public Power
)
City of Hamilton, OH

)
Southern Maryland Electric Cooperative, Inc.
)
Ohio Valley Electric Corporation

)
AMP Transmission, LLC

)
Silver Run Electric, LLC

)
NextEra Energy Transmission MidAtlantic
)
Indiana, Inc.

)
Wabash Valley Power Association, Inc.

)
Keystone Appalachian Transmission Company
)

)
Large Loads Co-Located at Generating Facilities   )
AD24-11-000

)

)
Constellation Energy Generation, LLC

)
EL25-20-000

)
(Consolidated)
          v.

)

)
PJM Interconnection, L.L.C.

)

COMMENTS AND INTERVENTION OF THE
DELAWARE PUBLIC SERVICE COMMISSION

The Delaware Public Service Commission (“DEPSC”) expresses its appreciation to the Federal Energy Regulatory Commission (“Commission” or “FERC”) for instituting this show cause proceeding pursuant to Section 206 of the Federal Power Act (“FPA”). Many of the questions asked by the Commission are of particular interest to Delaware including, in particular, issues around maintenance of adequate transmission and generation necessary to ensure local and regional resource adequacy in light of the unprecedented increase in load forecasts related to mostly data centers and some other large load additions. The issue of co-located loads is front and center to the DEPSC’s interests in ensuring that the energy needs of Delaware are met.

I. BACKGROUND AND CONTEXT
More recent events in the PJM Interconnection, L.L.C. (“PJM”) region give the DEPSC great concern, and the DEPSC agrees with the Commission that the status quo tariff provisions in

PDF page 3

PJM will likely not maintain resource adequacy and reliability despite the best efforts of PJM. PJM is to be commended for seeking to accelerate its interconnection queue process for new generation, reforming its Surplus Interconnection Service (“SIS”) provisions, and implementing a Reliability Resource Initiative (“RRI”) to advance certain generation projects to enhance resource adequacy.  While all of these initiatives are likely to improve the ability of resources to connect to PJM’s system over the status quo, it is far from certain that resource adequacy will be maintained under current and future Base Residual Auction (“BRA”) timelines, given the unprecedented increases in demand related to co-located and non-co-located large loads, mainly new data centers. More specifically, PJM’s most recent 2025 forecast is projecting load increases averaging 6 GW per year in the summer peaks from 2024 through 2032, and 6.5 GW per year in the winter peaks over the same forecast period.  This forecast growth is almost entirely related to the addition of data centers to the grid, with some other minor industrial and manufacturing load adjustments. In short, predominantly very large data center load forecast adjustments are driving unprecedented increases in PJM load growth forecasts. These are the types of facilities that are co-locating behind generation and are the focus of this proceeding. At the same time, PJM is projecting significant retirements of generation during this same forecast period. Between the period 2022 and 2030, PJM projected an average of approximately 4.4 GW per year of generation retirements. In order to maintain resource adequacy, PJM would then need to interconnect roughly 10.4 GWs of unforced capacity (“UCAP”) of new generation every year.

As a reference point, in PJM’s last 2025/2026 BRA, PJM procured only 0.1103 GW of capacity from new generation and 0.7538 GW from uprates to existing or planned generation. The quantity of new generation is down from the previous BRA, in which only 0.3285 GW of new generation was procured.  The 2025/2026 BRA procurement results were low despite an increase

PDF page 4

in the Rest-of-RTO capacity clearing price from $28.92/MW UCAP to $269.92/MW UCAP.  Most concerning, however, was that only 1.022 GW of Effective Load Carrying Capability (“ELCC”) adjusted MWs did not clear in the 2025/2026 BRA. Thus, there is almost no buffer to accommodate future load additions and generation retirements. New demand must be met from new generation and additional Demand Response (“DR”).  It should be noted that some recent PJM market reforms will provide some very temporary boosts to supply, because Reliability Must-Run (“RMR”) units1 that meet certain criteria, and all units (including intermittent and battery units) with Capacity Interconnection Rights (“CIRs”), will now be required to offer their generation into the BRA. As PJM procures resources two or more BRAs out (Delivery Years 2027/2028 and later), PJM will need to rely on new generation resources, much of which will need to be in the current interconnection queue.  Based on PJM’s queue of “active projects” as of December 31, 2024, even if every “active project” comes online, new generation would still be insufficient to meet PJM’s forecasted increase in large load additions, even at today’s ELCC ratings.2  There is almost zero chance that all “active projects” will come on-line, as only a relatively small number of projects actually makes it to the post-construction, in-service phase.

At recent OPSI meetings, many stakeholders identified barriers such as siting, permitting, and continuing supply chain constraints, particularly for large equipment like transformers and turbines, as key drivers in the delays and outright termination of interconnection queue positions. Further, it is unlikely that DR would fully meet any remaining resource adequacy gap, as the day- to-day operational activation of DR would significantly increase, likely causing DR capacity market participation to decline. Further, this analysis assumes a fixed ELCC value for wind, solar,

1 The must-offer requirements for certain RMR units are only applicable for the next two BRAs.
2 Based on the Testimony of Manu Asthana referenced in spreadsheets and current ELCC ratings projected for the 2026/2027 BRA.

PDF page 5

and battery resources.  As a whole, PJM has been projecting significant decreases in battery and solar resource ELCCs as the amount of these resources scales up.  Lastly, any future deactivations would only add to this resource adequacy deficit.  In short, it will be increasingly difficult, if not outright unlikely, for the existing PJM queue, comprised mostly of new intermittent, limited duration resources, combined with future DR resources, to meet the growing demand associated with large load additions.

II. COMMENTS
In response to the Commission’s inquiry, the DEPSC expresses support for the Comments of OPSI in this proceeding as it relates to resource adequacy, transparency, consumer protection, cost allocation, and jurisdiction.  In addition, the DEPSC draws particular attention to the concerns around resource adequacy, underscored by the well-documented tightening of supply and future supply shortage conditions that are rapidly approaching. These tightening conditions should be addressed immediately, as the status quo tariff provisions fail to address the cumulative impacts of large load additions via co-located and non-collocated configurations. More to the point, as disruptive as it seems to subject new large load additions to further reliability analysis under conditions of resource adequacy shortages, the failure to adequately plan for and address these resource adequacy shortages will most certainly result in system load curtailments and extreme shortage prices, the impacts of which will be devasting to low and middle income customers, small businesses, and electricity price-sensitive industrial customers. To avoid these highly disruptive impacts, the DEPSC supports solutions that can effectively mitigate future resource adequacy shortages and operational challenges related to the real-time adequacy of energy and reserves. In its response to the Commission’s show cause Order of February 20, 2025, PJM outlined three potential options that focused acutely on additional supply and operational flexibility:  Option

PDF page 6

6 (co-located load that elects to be Network Load and leverages provisional interconnection service or a State Agreement Approach), Option 7 (co-located load that takes a new non-capacity backed service that could be curtailed in advance of emergency procedures), and Option 8 (co-located participates as Demand Response).   The DEPSC is inclined to support these types of frameworks, provided that they can effectively mitigate the risk of resource adequacy shortages and sustained shortage pricing events.

However, none of these solutions, on its own, may be adequate to address the fundamental problem of PJM and others reacting to large load additions rather than addressing large load additions proactively.  To date, many Electric Distribution Companies (“EDCs”) have enabled large load additions without ensuring that adequate on-site supply or adequate deliverable supply was available to meet the energy needs of the large load additions. Rather, the large load is being interconnected and permitted to go into service, forcing PJM, PJM stakeholders, this Commission, and others into a reactive mode, hurriedly scrambling to identify and implement solutions.  The proverbial cart appears to be dragging the proverbial horse.  Consequently, in addition to the PJM options that appear feasible, as identified above, the DEPSC would recommend that this Commission direct the North American Electric Reliability Corporation (“NERC”) to undertake an accelerated process to establish reliability and resource adequacy standards for new large load additions that would apply to Electric Distribution Companies (“EDCs”), to generators involved with co-located large load configurations, and other entities subject to NERC standards, to ensure that regional and local operational reliability and resource adequacy will be maintained as large load additions interconnect to the grid or interconnect in a co-located configuration. As it stands today, reliability and resource adequacy gaps exist in the current regulatory construct. To help fill this gap, the combination of this Commission and NERC could effectively empower and obligate

PDF page 7

all relevant entities involved with large load interconnections to ensure either that large load additions are accompanied with their own adequate supply arrangements or that large load additions can be met with deliverable supply before the large load additions are placed into service. This Commission can and should put the horse back in front of the cart.

III. NOTICE OF INTERVENTION

The DEPSC hereby notifies the Commission of its intervention pursuant to 18 C.F.R. §385.214. The DEPSC is a State Commission as defined in the Commission’s Rules of General Applicability, 18 C.F.R. §1.101(k). The DEPSC's principal place of business is 861 Silver Lake Blvd., Suite 100, Dover, DE 19904. As the state regulator of investor-owned utilities in Delaware, the DEPSC has an interest that may be directly affected by the outcome of the proceeding and its participation is in the public interest.

PDF page 8

IV. CONCLUSION
The DEPSC is very concerned about the tightening supply/demand balance and urges this Commission to require PJM to file provisions to ensure that resource adequacy and operational reliability are maintained in light of unprecedented large load additions, anticipated large generation retirements, and current new generation development barriers. These large load provisions should apply to both co-located and other large load additions. In addition, the Commission should direct NERC to establish standards to ensure that large load additions have access to their own supply or to deliverable supply as a condition to grid interconnection. A sense of urgency is necessary given the alignment of all these factors, and the DEPSC commends this Commission for proactively identifying these issues and seeking solutions to address them. Respectfully submitted,

By:  / s / Matthew Hartigan
Matthew Hartigan, Executive Director
Delaware Public Service Commission
861 Silver Lake Blvd, Suite 100
Dover, DE 19904
Phone:  302-736-7532
Email: Matthew.Hartigan@delaware.gov

Dated:  April 23, 2025

PDF page 9

CERTIFICATE OF SERVICE

I hereby certify that I have this day served, via first-class mail, electronic transmission, or hand-delivery, the foregoing Comments upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated at Dover, DE this 23d day of April, 2025.

/ s / Matthew Hartigan

Matthew Hartigan, Executive Director
Delaware Public Service Commission
861 Silver Lake Blvd, Suite 100
Dover, DE 19904
Phone:  302-736-7532
Email: Matthew.Hartigan@delaware.gov