EL25-49-000 · 2025-04-23 · Delaware Public Service Commission

Comments and Intervention of Delaware Public Service Commission on the Show Cause Order issued on 02/20/2025

Text extracted from the eLibrary original (SHA-256 b9cb0fcba16f21f5…). Download the original from the official source.

Contents · 4 sections
  1. I. BACKGROUND AND CONTEXT p. 2
  2. II. COMMENTS p. 5
  3. III. NOTICE OF INTERVENTION p. 7
  4. IV. CONCLUSION p. 8

Read topic-matched comments in EL25-49

Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

Many of the questions asked by the Commission are of particular interest to Delaware including, in particular, issues around maintenance of adequate transmission and generation necessary to ensure local and regional resource adequacy in light of the unprecedented increase in load forecasts related…
Read this passage Filed comments: Reliability and curtailment

I. BACKGROUND AND CONTEXT

printed heading · Topic match: Reliability and curtailment

New demand must be met from new generation and additional Demand Response (“DR”).
Read this passage Filed comments: Reliability and curtailment

II. COMMENTS

printed heading · Topic match: Reliability and curtailment

In its response to the Commission’s show cause Order of February 20, 2025, PJM outlined three potential options that focused acutely on additional supply and operational flexibility: Option 6 (co-located load that elects to be Network Load and leverages provisional interconnection service or a…
Read this passage Filed comments: Reliability and curtailment

III. NOTICE OF INTERVENTION

printed heading

NOTICE OF INTERVENTION The DEPSC hereby notifies the Commission of its intervention pursuant to 18 C.F.R. §385.214.
Read this passage

IV. CONCLUSION

printed heading · Topic match: Reliability and curtailment

CONCLUSION The DEPSC is very concerned about the tightening supply/demand balance and urges this Commission to require PJM to file provisions to ensure that resource adequacy and operational reliability are maintained in light of unprecedented large load additions, anticipated large generation…
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Dated at Dover, DE this 23d day of April, 2025. / s / Matthew Hartigan Matthew Hartigan, Executive Director Delaware Public Service Commission 861 Silver Lake Blvd, Suite 100 Dover, DE 19904 Phone: 302-736-7532 Email: Matthew.Hartigan@delaware.gov