EL25-49-000 · 2025-04-23 · Southern California Edison Company and Pacific Gas and Elect

Reply Comments of Southern California Edison Company and Pacific Gas and Electric Company in response to PJM Interconnection, L.L.C.'s Answer filed on…

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Technical Conference on Large Loads
Co-Located at Generating Facilities
(AD24-11-000); Constellation Energy
Generation, LLC v. PJM Interconnection,
L.L.C. (EL25-20-000) (Consolidated)
)
)
)
)
)
Docket No. EL25-49-000
REPLY COMMENTS
OF SOUTHERN CALIFORNIA EDISON COMPANY AND PACIFIC GAS AND
ELECTRIC COMPANY
I. INTRODUCTION
Pursuant to Rule 213 of the Federal Energy Regulatory Commission’s (FERC or Commission) Rules of Practice and Procedure,1 Southern California Edison Company (SCE) and Pacific Gas and Electric Company (PG&E) (jointly California Utilities) respectfully submit these Reply Comments to the Answer filed on March 24, 2025 by PJM Interconnection, L.L.C. (PJM Answer) in response to the Commission’s February 20, 2025 Order Instituting Proceeding Under Section 206 of the Federal Power Act (Order to Show Cause).  The California Utilities seek to provide additional information that the California Utilities believe will assist the Commission in its decision-making process.

1 18 C.F.R. § 385.213 (2025).

PDF page 2

2
II. REPLY COMMENTS
The California Utilities fully support the development of co-located load arrangements, which have the potential to create a number of benefits to ratepayers.2  For instance, co-located data centers may provide savings to ratepayers by reducing congestion charges, as these facilities are often drawn to locations with low-cost power, which could include areas with heavily curtailed renewables.  Co-located load configurations can reduce line losses, result in more efficient utilization of existing infrastructure, and free up delivery capacity on the grid.  Co-location arrangements may also provide a cheaper alternative to network upgrades.  However, without proper cost allocation of transmission costs, reliability services, and Resource Adequacy, traditional customers could be forced to subsidize co-located load, or suffer impaired reliability. Neither outcome is acceptable.

In addressing issues related to co-located load, the Commission must ensure that:
• States retain their exclusive authority to determine who may serve co- located load and the rates and regulations for co-located load;

• Co-located loads are adequately studied for Resource Adequacy and
reliability impacts, including impacts relating to the co-located generation being off-line (momentarily, temporarily, or permanently); and

• Co-located load connected to the transmission network pays a fair share of FERC-jurisdictional transmission costs, as determined by its state or local regulator.

2  As used herein, co-located loads do not include retail load served behind the meter of Qualifying Facilities (QF) or by behind the retail meter generation (i.e., net metered load).  Rather, co-located load refers to a load connected to a non-QF, non-customer owned/leased generator that is synchronized to the electric system.

PDF page 3

3
A. Jurisdictional Issues
In its Order to Show Cause, the Commission invited PJM and the parties to opine on the jurisdictional principles outlined in section VI.A.3

The California Utilities appreciate the Commission’s clarification in the Order to Show Cause that “under the FPA, the states get to determine which entities are legally permitted to provide electricity to retail customers in co-location

arrangements…irrespective of where the load interconnects (i.e., to the distribution system, the transmission system, or the generator itself).”4  The Commission also noted that although it “has not historically exercised jurisdiction over any and all transmission- level interconnections of retail load,” the Commission “encourage[d] parties to address when and under what circumstances a co-located load is interconnected to the transmission system in interstate commerce”5 and “whether the Commission must, should, or can exercise jurisdiction over the interconnection of co-location arrangements to the transmission system in interstate commerce as an element of transmission service, including where the purpose is to facilitate a retail sale.”6

Though PJM acknowledges that the various options it presents for co-location arrangements in Exhibit A “are subject to different state law requirements that could disqualify certain options,”7 PJM contends that the Commission has jurisdiction over PJM’s co-located arrangements “due to PJM’s provision of ancillary services and in light of the wholesale sales taking place over certain facilities. . . .Therefore, at a minimum, the Commission has jurisdiction regarding the transmission service associated with the ancillary services utilized in co-location arrangements.”8  The California Utilities agree with PJM that FERC has jurisdiction over the allocation of transmission, ancillary

3  Order to Show Cause at P 88.
4  Order to Show Cause at P 69.
5  Id. at P 73.
6  Id. 7  PJM Answer at p. 29.
8  Id. at p. 30.

PDF page 4

4
services, and other related costs between customers (such as investor-owned utilities (IOUs) or other load-serving entities) using or benefitting from the transmission system. However, this does not mean that a state or local regulator cannot reallocate transmission costs in another manner in setting retail rates.9  The Commission indicates that it concurs: [W]hile “a State may not conclude in setting retail rates that

the FERC-approved wholesale rates are unreasonable,” it is
within a state’s exclusive jurisdiction to determine how those
FERC-approved rates are collected among the relevant retail
consumers along with the rates for state-jurisdictional
matters.10
PJM contends that “the Commission’s jurisdiction over transmission service in interstate commerce is also necessarily implicated in matters relating to co-located load arrangements where generator interconnections are being modified.”11  This statement is vague.  It is well established that “unless a transaction falls within FERC’s wholesale or transmission authority, it doesn’t matter how FERC characterizes it,”12 and that retail rates and service are governed by the states.  Though the Commission rightfully dictates the terms and conditions of a wholesale generator interconnection, that does not mean it can bootstrap such jurisdiction to dictate the terms and conditions of service to retail load. Matters related to retail service to a co-located load do not belong in a FERC-

9  State regulators routinely perform such reallocation with regard to load located behind generators. For example, the California Independent System Operator (CAISO) charges for transmission service on a kWh basis.  Grandfathered net metering customers, however, are charged for transmission only if their net output is less than their net consumption over a monthly billing period.  Thus, the CAISO may count load of grandfathered net metered customers in allocating transmission charges to SCE, but SCE reallocates those transmission charges to its other retail customers, as do the other California utilities.
10  Order to Show Cause at P 68.
11  PJM Answer at p. 31. 12  S. Cal. Edison Co. v. FERC, 603 F.3d 996, 1001 (D.C. Cir. 2010).

PDF page 5

5
jurisdictional generator interconnection agreement at all, even where the state has not decided to regulate that retail service.13

The Commission does not obtain authority over what are, in essence, retail sales of electricity to end-use, co-located load solely because the sales may impact a FERC- jurisdictional generator interconnection.  As previously noted in SCE’s Comments in EL25-20-000, jurisdiction over retail load interconnections generally rests with state or local regulators regardless of where the load connects.14  At least in California, regardless of size or service voltage connection to the grid, business or commercial end-use load has always been considered retail load.  The California Utilities do not believe that the Commission is permitted to exercise jurisdiction over the interconnection of a co-located load to the transmission system as an element of transmission service in interstate commerce where the purpose of the arrangement is to facilitate a retail sale.15 In many states, including California, state regulators generally do not permit generators who are not public utilities to make retail sales directly.16  Except under limited circumstances, California end-use load (including data centers) must purchase retail service from a utility whose retail rates are set by the state or from a community choice aggregator (who can only supply a limited set of services, while the regulated

13  See, e.g., Consol. Edison Co. of New York, Inc., 101 FERC ¶ 61,185 at P 43 (2002) (“Therefore, we will require ConEd to remove all language with respect to the sale of station power by ConEd to PSEG because it is beyond our jurisdiction. We suggest that the parties raise the issue of the sale of station power by ConEd to PSEG in a forum that has jurisdiction.”).
14  EL25-20-000, Comments of Southern California Edison Company, at p. 2.
15  See S. Cal. Edison Co. v. FERC, 603 F.3d 996 at 999 (holding that the Commission had no jurisdiction to regulate sales of station power under the Commission’s “jurisdiction over transmission,” as those were retail sales regulated by the states).
16  One exception is limited retail sales by QFs under the Public Utility Regulatory Policies Act of 1978 (PURPA).  In California, QFs may make sales to up to two physically adjacent customers.  See Pub. Utils. Code § 218(b)(2) (“‘Electrical corporation’ does not include a corporation…producing power from other than a conventional power source for the generation of electricity solely for... [t]he use of or sale to not more than two other corporations or persons solely for use on the real property on which the electricity is generated or on real property immediately adjacent thereto...”).

PDF page 6

6
utility provides delivery and other services).17  Any consideration of jurisdictional issues should recognize that states retain the exclusive authority to set rates for sales to end-use customers, including co-located data centers.  States must retain their authority to assess appropriate public policy charges, such as charges for wildfire mitigation, wildfire recovery, and state-sponsored equity programs, and to regulate the types of generation used in serving retail load.  Moreover, states must retain the ability to regulate the interconnection of retail loads.

Finally, the California Utilities agree with PJM that “many co-located load configurations utilize grid support and consume ancillary services (including, for example, frequency regulation, black start service, and reactive service).”18  The Commission has jurisdiction to determine the cost for services deemed to be used by various wholesale loads, which in turn requires tariffs such as the PJM Tariff to dictate how the retail load, including co-located load, of its wholesale customers will be measured.  Based on well-established cost causation principles, as discussed below at Section II.C, the Commission should ensure that FERC-jurisdictional tariffs measure the amount of end-use load allocated to wholesale customers in a manner that is just and reasonable.  That said, as already noted, state and local regulators retain authority to reallocate wholesale costs among retail customers as long as they permit full cost recovery.

B. Any Tariff Revisions Should Adequately Address Resource Adequacy
and Other Reliability Concerns
The California Utilities appreciate the Commission’s recognition that large co- located loads have the potential to negatively impact Resource Adequacy (i.e., capacity requirements) for existing customers.  Though FERC generally lacks authority to prevent

17  Retail choice was suspended decades ago in California, with a few grandfathered retail customers remaining.
18  PJM Answer at p. 68.

PDF page 7

7
a generator from ultimately making direct or indirect sales to retail co-located load (even those that erode reliability), it is important for the Commission to recognize, when setting policy, that allowing co-located loads may reduce available capacity and accordingly, increase consumer electricity prices.

The Commission does have authority, however, to require wholesale customers to procure adequate capacity.  If an ISO/RTO Tariff sets rules dictating which types of retail load that load-serving entities must purchase capacity for, at a minimum, the Tariff must be clear as to how co-located load will be treated and who will be responsible for procuring capacity for the load.  Cost allocation principles dictate that the entity directly selling at retail to the co-located load should pay capacity costs because of the grid reliability impact the load creates; how these costs are passed on to the co-located load is a matter between the load serving entity and its retail customer.

Additionally, if existing generator capacity is diverted to co-located load rather than selling its energy into the market, this choice may cause power flow changes in a local area that need to be studied.  Thus, it is important for planners to know sufficiently far in advance if an existing generator is going to connect co-located load.  For generators in the queue, knowledge of intent to connect co-located load is similarly important for planning and reliability purposes.

C. Co-Located Loads Must Pay Their Fair Share of Costs
The Commission expressed concern that the absence of PJM Tariff provisions regarding co-located facilities “creates the potential that participants in a co-location arrangement may not be required to pay for wholesale services that they receive, as required by the cost causation principle.”19  Further, the Commission has reiterated that in designing its rates, PJM must ensure that costs are “allocated in a manner that is at

19  Order to Show Cause at P 74.

PDF page 8

8
least roughly commensurate with the benefits that entity receives.”20  The Commission noted that “different co-location arrangements are likely to use or benefit from the transmission system in different ways depending on how they are configured and, moreover, that those different configurations will themselves likely have different impacts on the transmission system.”21

As an initial matter, there is no such thing as fully isolated co-located load unless neither the source generator nor the co-located load is electrically connected to the electric transmission system.22  Thus, this configuration does not need to be addressed by the PJM Tariff.

Assuming a state or local regulator allows a generator, whether directly or through a sleeving entity, to serve co-located load and the generator is synchronized to the electric grid, and the regulator does not require the co-located load to pay for retail transmission service in the same manner as retail loads served by front of the meter generators, there are a variety of cost allocation options that can be explored.  The Commission should recognize that there will be no uniformity in the PJM region, as states and local regulators may make very different decisions on retail transmission service.  The California Utilities’ thoughts on situations where the state/local regulator does not require that co- located load be treated the same as front of the meter retail load are discussed below. First, the California Utilities do not support generators synchronized to the grid serving co-located load paying no ancillary services costs, as they do not agree that either the generator or the co-located load are fully isolated.  For example, synchronized generators utilize ancillary services (such as Regulation) and benefit from reliability and recovery services such as Spinning Reserve and Black Start.  In such cases, it is up to the

20  Id.
21  Id. at P 76.
22  In this limiting case, it is not obvious that the Commission has any jurisdiction over such a configuration.  The Commission would, however, have jurisdiction over transmission charges assessed to co-located load where either the co-located load or the generator is connected to the transmission system.

PDF page 9

9
generator how or whether such cost is passed onto the co-located load.  If the generator is using a middleman to sleeve power to the co-located load, the PJM Tariff would need to determine if the generator or load-serving middleman should be allocated such charges. As to transmission service, if PJM is going to permit netting of load for

transmission purposes, one option to ensure fair cost allocation is to require the co- located load to pay for retail stand-by transmission services.23  But, even if a state or local regulator permits co-located load to be on a standby tariff, the regulator may still impose state public policy charges on the gross load of the co-located load.  The PJM Tariff should state affirmatively that regulators retain such authority, in order to avoid future disputes.

D. Regional Differences May Require Different Approaches
The California Utilities submit these Reply Comments relating to the PJM Tariff recognizing that the Commission’s decision here may impact the conversation in future proceedings regarding other RTO tariffs.  Nevertheless, it is important to recognize that approaches to co-located facilities will need to be tailored to account for different state regulators, self-regulated non-jurisdictional utilities, and regions.  For instance, as relevant to the California Utilities, any future CAISO Tariff provisions relating to co- located facilities must necessarily function within California’s unique regulatory environment.  The California Utilities respectfully request that the Commission’s Order on PJM’s Tariff acknowledge state/local regulatory rights to prevent confusion and disputes.  Moreover, even without the state and local jurisdictional differences, there is no “one size fits all” just and reasonable approach to this complex issue.

23  In the past, the Commission was able to ensure that certain generators with behind the meter load were permitted to net their load for CAISO Tariff purposes by allowing such netting only if the generator purchased retail standby service.  See Cal. Indep. Sys. Operator Corp., 104 FERC ¶ 61,196 (2003).  There, however, the behind the meter load was not a retail customer of the utility; the generator was a retail customer.  The situation being addressed here, in contrast, assumes that the co- located load must have its own retail account because separate legal entities are involved.

PDF page 10

10
III. CONCLUSION
The California Utilities appreciate the opportunity to provide these Reply Comments to the Commission and respectfully request that the Commission consider the foregoing comments in its Order addressing PJM’s Tariff.

Respectfully submitted,
ELLEN C. KENNEY
/s/ Ellen C. Kenney
By:
Ellen C. Kenney
Attorneys for
SOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue
Post Office Box 800
Rosemead, California 91770
Telephone: (626) 302-9519
E-mail:
Ellen.Kenney@sce.com

CHARLES MIDDLEKAUFF
/s/ Charles Middlekauff
By:
Charles Middlekauff
Attorneys for
PACIFIC GAS AND ELECTRIC COMPANY
300 Lakeside Drive
Oakland, California  94612
Telephone: (650) 766-9147
Email:
Charles.Middlekauff@pge.com
Dated:  April 23, 2025

PDF page 11

11
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing REPLY COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY AND PACIFIC GAS AND

ELECTRIC COMPANY upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated at Rosemead, California, this 23rd day of April 2025.