EL25-49-000 · 2025-04-23 · Buckeye Power, Inc.

Comments of Buckeye Power, Inc. in support of PJM Interconnection, L.L.C.’s 03/24/2025 response to the show cause order

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company Delmarva Power & Light Company

Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC

Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation Potomac Electric Power Company

Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.

The Dayton Power and Light Company AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc.

AEP Kentucky Transmission Company, Inc AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission Company, Inc.

Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000

PDF page 2

- 2 -
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission
MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
AD24-11-000
EL25-20-000 (Consolidated)
COMMENTS OF BUCKEYE POWER, INC.
Pursuant to the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) February 20, 2025 Order establishing this show cause proceeding under section 206 of the Federal Power Act,1 Buckeye Power, Inc. (“Buckeye”) respectfully files these comments in support of PJM Interconnection, L.L.C.’s (“PJM”) response to the show cause order.2

I. BACKGROUND
New large loads, primarily comprised of data centers, are creating a strain on the electric grid nationwide, and particularly in the PJM region, putting front and center issues of reliability,

1 Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings, 190 FERC ¶ 61,115 (the “Order”).
2 See PJM Response filed March 24, 2025 in this docket (“PJM Answer”).

PDF page 3

- 3 -
resource adequacy, and just and reasonable rates.  Buckeye supports co-location of large loads that are visible to the network.  This includes generation arrangements where the co-located load pays for its share of transmission costs and ensures the grid can continue to rely on existing generation resources.  Buckeye supports PJM’s position that the existing Open Access Transmission Tariff, the Amended and Restated Operating Agreement of PJM, and the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (collectively, the “Tariff”) remains just and reasonable.  Buckeye also supports the additional options PJM has proposed to facilitate front-of-the-meter co-location arrangements where the co-located load is Network Load and resource adequacy is maintained.

While front-of-the-meter, Network Load co-location arrangements are a better alternative for reliability and resource adequacy than non-Network Load behind-the-generator arrangements, even these front-of-the-meter, Network Load arrangements do not resolve all of the significant concerns with the influx of large loads in the PJM footprint.  The risk of significant stranded transmission investment is another critical issue that must be considered, regardless of whether the generation is co-located with load or not.  If the demand of large loads is as expected, that could benefit existing customers by lowering transmission rates.  But there is serious concern that these large loads could drive significant transmission investment and then not show up to pay for it on a sustained basis, shifting costs to everyone else that relies on the expanded grid.  Buckeye supports policies that ensure large loads pay for the costs and impact to the grid they cause.

II. INTEREST OF BUCKEYE
Buckeye Power, Inc. is an Ohio non-profit generation and transmission cooperative that produces, procures, and provides at wholesale all the electric capacity, energy, and transmission

PDF page 4

- 4 -
required by its member electric distribution cooperatives.3  Buckeye operates as a cooperative and is owned by its 25 member distribution cooperatives, which are in turn each owned by their member-consumers.  Buckeye thus operates not for the benefit of shareholders, but for the benefit of its member-consumers.  Buckeye’s mission is to provide “to all member systems, stably and competitively priced, economical and highly reliable wholesale power, for the benefit of their members and their communities.”4

Buckeye arranges transmission services for the delivery of generation to its member
electric distribution cooperatives at over 400 delivery points in the State of Ohio. Those member distribution cooperatives serve over 400,000 residential, commercial, and industrial customers in service territories encompassing primarily rural areas in 77 of Ohio’s 88 counties.  Buckeye is a Transmission Dependent Utility (“TDU”), meaning that it depends almost exclusively on PJM and four transmission owners in Ohio (Duke Energy Ohio, Ohio Power Company/AEP Ohio

Transmission Company, Inc., American Transmission Systems, Inc., and the Dayton Power & Light Company) for transmission of electricity to its member cooperatives.  As a TDU, Buckeye is subject to PJM’s Open Access Transmission Tariff, which includes cost recovery for

transmission upgrades and expansions made by each transmission owner in Ohio and regional transmission projects assigned by PJM.

3 The 25 distribution cooperative members of Buckeye are: Adams Rural Electric Cooperative, Inc.; Buckeye Rural Electric Cooperative, Inc.; Butler Rural Electric Cooperative, Inc.; Carroll Electric Cooperative, Inc.; Consolidated Cooperative, Inc.; Darke Rural Electric Cooperative, Inc.; Firelands Electric Cooperative, Inc.; The Frontier Power Company; Guernsey-Muskingum Electric Cooperative, Inc.; Hancock-Wood Electric Cooperative, Inc.; Holmes-Wayne Electric Cooperative, Inc.; Licking Rural Electrification, Inc.; Logan County Cooperative Power and Light Association, Inc.; Lorain-Medina Rural Electric Cooperative, Inc.; Mid-Ohio Energy Cooperative, Inc.; Midwest Electric, Inc.; Midwest Energy & Communications; North Central Electric Cooperative, Inc.; North Western Electric Cooperative, Inc.; Paulding-Putnam Electric Cooperative, Inc.; Pioneer Rural Electric Cooperative, Inc.; South Central Power Company; Tricounty Rural Electric Cooperative, Inc.; Union Rural Electric Cooperative, Inc.; and Washington Electric Cooperative, Inc.
4 Buckeye’s mission statement can be found on its website at https://ohioec.org/buckeye-power.

PDF page 5

- 5 -
Buckeye also owns and operates generation resources to meet its members’ load
requirements and is a participant in the PJM capacity market as both a generation owner and a load serving entity (“LSE”).  In order for Buckeye to provide reliable and affordable electric supply to its members and their retail members, it is essential that the PJM capacity market ensures resource adequacy and reliability of electric service.

Buckeye appreciates the Commission’s issuance of the Order to address these issues. Communications regarding these proceedings should be directed to:

Kurt P. Helfrich
General Counsel
Lija Kaleps-Clark
Associate General Counsel
Buckeye Power, Inc.
6677 Busch Boulevard
Columbus, Ohio 43229
Telephone: (614) 681-5151
khelfrich@ohioec.org
lkaleps@ohioec.org
III. COMMENTS
A. Large Load Co-located with Generation Should be Network Load in Front of the Meter Buckeye supports co-location arrangements where the large loads are Network Load and in “front of the meter” because these arrangements will ensure visibility to the grid operator, allow PJM to conduct appropriate planning to ensure grid reliability, ensure the load pays for its share of grid costs, and ensure generation resources remain available for the entire grid.  Conversely, co- located large load arrangements where the load is located “behind the meter” of the generator, and is not Network Load, may create significant impacts to the grid, increase costs, and decrease reliability for everyone else that relies on the grid for affordable and reliable electricity.  While certain parties have advocated that these so-called “fully isolated” arrangements will avoid

PDF page 6

- 6 -
transmission investments, those potential cost savings are outweighed by significant concerns about the impacts to reliability, resource adequacy, and just and reasonable rates.5 Front-of-the-meter arrangements where the load is Network Load avoids many of the concerns associated with “behind-the-generator” co-location arrangements that are not Network Load:

Improved Grid Reliability.  When load is located in front of the generation meter rather than behind the generation meter, the generation resource is available for full grid operation, rather than having all or a portion of the generator’s output dedicated to a specific load.  This arrangement provides significant reliability benefits by avoiding reliance on protective relays to operate (which can fail) in the event of a generator outage, provides enhanced ability for PJM to manage which load to curtail and prioritize in response to emergency conditions, and enhances PJM’s visibility and control over the co-located load.  As a result, front-of-the-meter, Network Load arrangements will improve system planning and operation and will have less negative impacts on resource adequacy (particularly if the arrangement is consistent with PJM Options 6, 7, and/or 8).6 In contrast, so-called “fully isolated” co-location arrangements would essentially remove the associated generation (assuming it is existing generation) off the grid so that it can no longer be relied upon by everyone else.  This is particularly problematic because co-location arrangements often seek to use large baseload generation that is needed for grid reliability. Although the ultimate balance of demand and supply is arguably the same whether the load is co- located with the generation and behind the transmission meter, rather than in front of the

5 See, e.g., “The Co-Located Load Solution” at p. 2, authored by Michael Kormos and submitted in Docket AD24-11 on November 4, 2024 (“Because the new load has no ability to ‘lean’ on the grid, there is no need for expensive new network transmission projects to connect the load or the associated regional cost allocations to other customers.”).
6 PJM Answer, pp. 16-20.

PDF page 7

- 7 -
transmission meter, a behind the transmission meter, non-Network Load co-location arrangement has the potential to accelerate the pace with which the incremental demand arrives on the system, potentially without sufficient, if any, additional incremental supply—exacerbating resource adequacy concerns.7  In addition, the existing transmission system was (and continues to be) planned and built based on studies that consider the locations of loads and generation across the system.  Removing generation that is associated with a “fully-isolated” co-location arrangement (i.e., a behind-the-generator, non-Network Load arrangement) from the rest of the grid is inconsistent with the grid’s planning and operational foundations and thus threatens to alter flows in a manner that could require additional transmission upgrades and impair the operational flexibility that is essential to reliability.  Finally, the abrupt removal of large baseload resources from the system may have additional impacts to grid operation and costs that are not immediately apparent.

Fair Cost Allocation.  Front-of-the meter arrangements also ensure that the co-located load will pay its fair share of transmission costs as Network Load.  Under behind-the-generator arrangements, co-located load will not be subject to any transmission costs, even though the load will be both causing costs and receiving the benefits of the grid (including, at a minimum, ancillary services and black start capabilities).  Indeed, there seems to be no question that these loads will create costs and will receive benefits from the grid, but as non-Network Load will pay for neither. Avoids Conflicts with State Law.  As PJM noted in its answer, non-Network Load, “behind- the-generator” co-location arrangements may not be permissible in all states within the PJM footprint based on whether the state is deregulated for generation supply and the state’s laws on

7 See statements of Stu Bresler on behalf of PJM during the Technical Conference at p. 39, lines 13-24 of the Transcript from Co-Located Large Load Technical Conference in Docket AD24-11.

PDF page 8

- 8 -
requiring the franchised utility to be the sole provider of generation supply to the load.8  The front- of-the-meter, Network Load arrangements currently permitted by the Tariff and as proposed in PJM’s preferred options respect those state laws while providing for consistent application of the Tariff across the PJM footprint.  To the extent a patchwork approach were adopted, with different arrangements possible in certain states but not others, that would only add further complexity and challenges to the important reliability, system planning, and rate issues discussed above. Ultimately, the advantages of front-of-the-meter, Network Load arrangements far

outweigh these numerous concerns with behind-the-generator, non-Network Load arrangements. Moreover, the alleged potential benefits of the non-Network Load, behind-the-generator arrangements rely largely on the fiction that the arrangement is “fully isolated” from the grid.  As noted by PJM’s answer, this is not accurate from either an engineering or economic standpoint because the large co-located load receives services from the grid (e.g., ancillary services), but does not pay for it, and because the “full isolation” is dependent on a protection system that could fail (and has in some circumstances) dumping significant load onto the grid with little notice.9  If these large loads have the potential to appear on the system, even for a short time, this could have a significant impact on the grid.

B. Buckeye Supports PJM’s “Preferred” Options
Buckeye agrees with PJM that the existing Tariff is just and reasonable because it “permits co-located loads to interconnect through existing load interconnection processes,” and the fact that “certain entities may prefer, for their own business reasons, alternative pathways to co-location,”

8 PJM Answer, pp. 5-6.
9 PJM Answer, p. 42.

PDF page 9

- 9 -
does not render the existing Tariff invalid.10  Accordingly, Options 1 and 2 described by PJM are just and reasonable and currently accommodated by the existing Tariff.11

Buckeye supports additional flexibility for large load co-location as spelled out in Options 6, 7, and 8, as each of these options provide flexibility to the load while supporting resource adequacy.

•
Option 6: supports co-located load that elects to be Network Load and bring its own generation, whether that is new generation or generation expecting to be retired and provides incentives for faster interconnection processing of the associated generation.12 •

Option 7: allows co-located load to be classified as “non-capacity backed load” for a transitional period until the appropriate resource adequacy balance is obtained.  This would allow the large load to avoid capacity costs during the transitional period and allow PJM to curtail the large load in emergencies.  This option may allow large loads to be interconnected to the grid more quickly than traditional interconnection processes.13

•
Option 8: co-located load may participate as demand response with potential
expansions on the use of diesel generators as back-up generation.14
Buckeye supports the Commission providing additional clarity or guidance to support these options which provide flexibility for the co-located load, while also addressing resource adequacy issues.

10 PJM Answer, p. 32.
11 Co-location arrangements that are not Network Load are also potentially permissible under the existing Tariff under Option 3, but as recognized by PJM, the Non-Retail Behind the Meter Generation program provided for in the Tariff was not intended for this type of large load arrangement.  PJM Answer, pp. 11-13.
12 PJM Answer, pp. 16-18.
13 PJM Answer, pp. 18-19.
14 PJM Answer, pp. 19-20.

PDF page 10

- 10 -
C. Transmission Cost Impacts of Large Load
The Commission has raised concerns with issues of transmission cost allocation and
forecasting relating to co-location arrangements.15  PJM recognizes in its response that inaccurate forecasting can result in overbuilt transmission infrastructure, and that this risk is true with respect to all large load additions—not just those co-located with generation.16  PJM notes that for both transmission and capacity costs, “[t]o the extent the forecasted load additions do not actually materialize, these higher capacity [and transmission] costs would be allocated to all other load on the system.”17  Buckeye agrees that forecasting and cost allocation issues associated with large loads are a significant concern and one that the Commission should address, regardless of whether that load is co-located with generation or not.

Load growth of approximately 10,000 MW driven by data centers in the Dominion Zone
resulted in approximately $13 billion in transmission investment to accommodate this load.18 Central Ohio is also experiencing massive load increases that will require significant transmission investment, impacting the transmission rates for everyone in the AEP Zone, including Buckeye and its members.  PJM’s load forecast analysis that drives transmission investment anticipates

15 See Questions (g)(v), (b)(iii), and (f)(iv) from the Order.
16 PJM Answer, p. 65.
17 Id.
18 For the 10,000MW of new load in the Dominion zone, see slide 9 from the PJM Interconnection, L.L.C., Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board (Jan. 2025), available at https://www.pjm.com/-/media/DotCom/committees-groups/committees/teac/2025/20250107/20250107-item-12--- reliability-analysis-update.pdf.  Upgrades in the Dominion Zone developed during 2022 RTEP Window 3 (and approved by PJM in Dec 2023) totaled $5.143 billion.  See PJM Interconnection, L.L.C., Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board (Dec. 2023), available at https://pjm.com/- /media/committees-groups/committees/teac/2023/20231205/20231205-pjm-teac-board-whitepaper-december- 2023.ashx. Baseline improvements in the Dominion Zone developed during 2024 RTEP Window 1 totaled $5.919B. See page 1 of the February 2025 TEAC Whitepaper available at https://www.pjm.com/-/media/DotCom/committees- groups/committees/teac/2025/20250204/20250204-pjm-board-whitepaper-february-2025.pdf.  Adding other baseline improvements approved during 2023 RTEP Window 1 and 2 and prior to 2022 RTEP Window 1 equates to approximately $13 billion.  These costs do not include the costs of supplemental projects associated with large load growth.

PDF page 11

- 11 -
10,000 MW of new load in the AEP Zone of PJM by 2030.19  AEP Ohio20 has stated that it has received requests for 30,000 MW of new data center load in Central Ohio, indicating the 10,000 MW may only be the beginning of massive load growth in Ohio and the AEP Zone generally.21 If the load shows up as expected, the massive investments in new transmission should not result in cost increases to wholesale transmission customers, and ultimately retail ratepayers.  The expansion in the load paying for the increased rate base should maintain or decrease the rates for existing transmission customers.  However, other customers in the applicable zone could face significant cost increases if massive transmission costs are incurred, and the load does not show up as planned for in the transmission expansion, is or becomes significantly lower than the original request, or has the ability to bypass the transmission cost allocation mechanism.22 Currently, other customers are exposed to the potential for these significant cost shifts.  In the AEP Zone of PJM, transmission costs are allocated to wholesale transmission customers based on an annual single coincident peak (1 CP) – meaning that transmission costs are allocated to wholesale transmission customers/LSEs based on their usage during a single hour of the entire year.  Because the massive transmission investments that are driven by these large loads are sunk costs that are recovered over time through transmission rates, rather than directly assigned to the 19 See Slide 10 of the “Load Adjustment Requests Summary for 2025 Load Forecast – Preliminary” presented at the Load Analysis Subcommittee on November 25, 2024 available at https://www.pjm.com/- /media/DotCom/library/reports-notices/load-forecast/2025-load-report.pdf; see also Slide 26 of the “2025 PJM Long- Term

Load
Forecast
Report”
dated
January
24,
2025
available
at
https://www.pjm.com/-
/media/DotCom/library/reports-notices/load-forecast/2025-load-report.pdf.
20 Ohio Power Company d/b/a AEP Ohio is the LSE serving the Central Ohio region and other parts of Ohio.
21 See Supplemental Testimony of Matthew S. McKenzie at p. 4 filed in In the Matter of the Application of Ohio Power Company for New Tariffs Related to Data Centers and Mobile Data Centers, Case No. 24-508-EL- ATA.
22 The load may not show up as expected as the result of any number of factors – the load decided not to build or built less than initially planned for, the load installed behind the meter generation reducing peak demands after transmission has been built to serve the load, the load relocated after coming online, the load uses demand response to reduce its peak demand, or the load gains efficiencies that reduces its energy needs.

PDF page 12

- 12 -
loads, reduction in the load during a single hour after building the transmission infrastructure to serve that load will not reduce overall costs.  Rather, it would shift the costs from the LSE for which the costs were incurred to other LSEs, and their retail customers, in the transmission zone. To address these cost-shifting concerns caused by new large loads, the Commission should consider the following solutions, as more fully addressed in Buckeye’s Comments filed on December 9, 2024 in Docket AD24-11:

LSE Responsibility.  The Commission should consider requiring the LSE that is driving the transmission investment (i.e., the LSE in whose territory the retail large load is locating) to be responsible for any cost-shifting caused by large loads that do not show up as expected, thereby covering the costs of transmission investments caused by their retail load.  The LSE with the large new load should be the entity that receives this price signal, because it has a retail relationship with the large load that creates the potential for stranded transmission investment and is therefore able to pass the stranded cost responsibility to that retail load.  For instance, the LSE could enter into retail-level agreements with the large loads driving such transmission investments that address cost responsibility in the event that load does not materialize as anticipated (e.g., through a minimum demand charge, and minimum contract term, backed by appropriate credit support requirements). Importantly, any costs collected under such retail arrangements should be credited to the wholesale transmission revenue requirement to ensure that any stranded transmission costs associated with such large loads are not shifted to other LSEs in the zone.23

12 CP or NCP Billing Determinants.  In addition to the LSE responsibility, another potential mechanism that should be considered to help mitigate unreasonable cost shifts is

23 For an example of this approach, see the Transmission Customer New or Upgraded Service Construction Service Agreement tariff filing submitted by The Dayton Power and Light Company in FERC Docket No. ER25- 192 on October 23, 2024, accession number 20241023-3047, and accepted by FERC on December 20, 2024.

PDF page 13

- 13 -
changing the 1 CP billing determinant for the PJM transmission cost allocation for wholesale transmission rates under the PJM Open Access Transmission Tariff to twelve coincident peaks (12 CP) or to one or more non-coincident peaks (NCP).  This billing determinant adjustment may not address stranded costs in the event that a large load fully fails to materialize, or reduces or terminates operations contrary to expectations, but it would make it more difficult for large loads, particularly hyperscale data centers, to reduce peak load during the single coincident peak, thereby shifting costs to other wholesale customers and their retail members without reducing any of the actual transmission costs that have already been incurred.  A 12 CP approach is a more accurate way to assign transmission costs to the loads based on their actual use of the system.  This approach was recently proposed by Virginia Electric and Power Co., d/b/a Dominion Energy Virginia (“Dominion”) and approved by FERC.24  And it is also being considered by the Texas Legislature in the Electric Reliability Council of Texas (ERCOT) region in response to the large influx of data center load in that region.25

24 See PJM Interconnection, L.L.C. and Virginia Electric and Power Company, FERC Docket Nos. ER19- 1661-000, ER19-1661-001 and PJM Interconnection, L.L.C., 169 FERC ¶ 61,041, October 17, 2019.
25 See Senate Bill 6 Relating to electricity planning and infrastructure costs for large loads, introduced in February 2025.

PDF page 14

- 14 -
IV. CONCLUSION
WHEREFORE, Buckeye requests that the Commission give full consideration to these comments and concerns in connection with its examination of the issues surrounding large loads co-locating with generation resources and the larger impact of large loads on the electric grid. Respectfully submitted,

/s/ Lija Kaleps-Clark
Kurt P. Helfrich
General Counsel
Lija Kaleps-Clark
Associate General Counsel
Buckeye Power, Inc.
6677 Busch Boulevard
Columbus, Ohio 43229
Telephone: (614) 681-5151
khelfrich@ohioec.org
lkaleps@ohioec.org
Its counsel
Dated:  April 23, 2025

PDF page 15

- 15 -
CERTIFICATE OF SERVICE
I hereby certify that on this 23rd day of April, 2025, I have caused the foregoing to be served upon each person listed on the Official Service List for this proceeding.

 /s/ Lija Kaleps-Clark
 Lija Kaleps-Clark