Comments of Buckeye Power, Inc. in support of PJM Interconnection, L.L.C.’s 03/24/2025 response to the show cause order
Text extracted from the eLibrary original (SHA-256 c25e51f357af07b6…). Download the original from the official source.
Contents · 7 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
I. BACKGROUND
printed heading · Topic match: Reliability and curtailment
The risk of significant stranded transmission investment is another critical issue that must be considered, regardless of whether the generation is co-located with load or not.Read this passage Filed comments: Reliability and curtailment
II. INTEREST OF BUCKEYE
printed heading
In order for Buckeye to provide reliable and affordable electric supply to its members and their retail members, it is essential that the PJM capacity market ensures resource adequacy and reliability of electric service.Read this passage
III. COMMENTS
printed heading
III.Read this passage
A. Large Load Co-located with Generation Should be Network Load in Front of the Meter
printed heading · Topic match: Connecting load and generation
While certain parties have advocated that these so-called “fully isolated” arrangements will avoid - 6 - transmission investments, those potential cost savings are outweighed by significant concerns about the impacts to reliability, resource adequacy, and just and reasonable rates.5…Read this passage Filed comments: Connecting load and generation
B. Buckeye Supports PJM’s “Preferred” Options
printed heading · Topic match: Connecting load and generation
Buckeye Supports PJM’s “Preferred” Options Buckeye agrees with PJM that the existing Tariff is just and reasonable because it “permits co-located loads to interconnect through existing load interconnection processes,” and the fact that “certain entities may prefer, for their own business reasons,…Read this passage Filed comments: Connecting load and generation
C. Transmission Cost Impacts of Large Load
printed heading · Topic match: Cost allocation
These costs do not include the costs of supplemental projects associated with large load growth. - 11 - 10,000 MW of new load in the AEP Zone of PJM by 2030.19 AEP Ohio20 has stated that it has received requests for 30,000 MW of new data center load in Central Ohio, indicating the 10,000 MW may…Read this passage Filed comments: Cost allocation
IV. CONCLUSION
printed heading
CONCLUSION WHEREFORE, Buckeye requests that the Commission give full consideration to these comments and concerns in connection with its examination of the issues surrounding large loads co-locating with generation resources and the larger impact of large loads on the electric grid.Read this passage
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that on this 23rd day of April, 2025, I have caused the foregoing to be served upon each person listed on the Official Service List for this proceeding. /s/ Lija Kaleps-Clark Lija Kaleps-ClarkRead this passage