EL25-49-000 · 2025-04-23 · Organization of PJM States, Inc.

Comments of the Organization of PJM States, Inc. in response to PJM Interconnection, L.L.C.'s 03/24/2025 Answer

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000

)
Large Loads Co-Located at
)
Generating Facilities
)
Docket No. AD24-11-000

)
Constellation Energy Generation, LLC
)

)
v. )

)
PJM Interconnection, L.L.C.
)
Docket No. EL25-20-000

)
(consolidated)

COMMENTS OF THE
ORGANIZATION OF PJM STATES, INC.

Pursuant to the Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings1 issued by the Federal Energy Regulatory Commission (“FERC” or “Commission”) on February 20, 2025, and in response to PJM’s Answer filed on March 24, 2025,2 the Organization of PJM States, Inc. (“OPSI”) submits the following comments.3 OPSI appreciates the Commission’s detailed investigation to determine whether PJM’s current rules ensure regional resource adequacy and grid reliability, accurately assess the extent to which large, co-located load arrangements use grid services, fairly allocate the costs these arrangements may impose on existing customers, and respect existing jurisdictional boundaries. OPSI discusses each of these topics in more detail below.

1 PJM Interconnection L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”). 2PJM Interconnection L.L.C., Answer of PJM Interconnection, L.L.C. (March 24, 2025) (“PJM Answer”).
3 OPSI’s following members support these Comments: Delaware Public Service Commission, Public Service Commission of the District of Columbia, Illinois Commerce Commission, Indiana Utility Regulatory Commission, Kentucky Public Service Commission, Maryland Public Service Commission, Michigan Public Service Commission, New Jersey Board of Public Utilities, Public Utilities Commission of Ohio, Pennsylvania Public Utility Commission, Tennessee Public Utility Commission, Virginia State Corporation Commission and Public Service Commission of West Virginia. The North Carolina Utilities Commission abstained in the vote on these comments.

PDF page 2

2

I. COMMENTS
PJM’s stated approach to large load expansion—co-located or not—focuses on: “(1) maintaining resource adequacy; (2) enabling reliable system operations; (3) facilitating the states’ and stakeholders’ efforts to timely and effectively integrate large loads in a manner that meets their unique needs; and (4) providing information and analysis that supports the equitable alignment of transmission system usage and compensation.”4 OPSI appreciates this focus, recognizing that in order to facilitate these arrangements quickly and efficiently, the Commission must first ensure that these arrangements do not negatively impact regional resource adequacy and grid reliability in the PJM region and that existing customers are not otherwise harmed by these arrangements. In its previous comments, OPSI urged FERC to require long-term scenario planning, mandate transparent reviews of these arrangements, establish fair cost allocation for these arrangements when they use grid services, and affirm state jurisdiction over co-located retail sales.5 OPSI reiterates these points in response to both the Show Cause Order and PJM’s Answer.

A. RESOURCE ADEQUACY, RELIABILITY, AND TRANSPARENCY
The Commission asks a series of questions about what interconnection modification and deactivation studies PJM should conduct in reviewing co-location arrangements to ensure resource adequacy and protect the reliability of the bulk power system.6 OPSI appreciates that the first component of PJM’s approach to the co-location of large loads is focused on maintaining resource adequacy and believes that PJM and the Commission should promote the development of comprehensive and transparent processes to evaluate the impacts, both individual and cumulative, of these arrangements. PJM’s position is that any portion of a generation resource intending to

4 PJM Answer at 3.
5 OPSI, Post-Technical Conference Comments of the Organization of PJM States, Inc., Docket No. AD24-11-000 (Dec. 9, 2024) (“OPSI Comments”).
6 Show Cause Order at Briefing Question e.iv.

PDF page 3

3

serve co-located load outside the PJM system must first request and obtain removal of its Capacity Resource status under section 6.6(g) of Attachment DD to the PJM Tariff, with approval from both the Market Monitor and PJM or via Commission order.7 PJM emphasizes that capacity resources cannot prioritize serving non-PJM load, even as backup, without undermining system reliability and that sellers should not be allowed to choose between fulfilling PJM obligations or facing penalties.8 OPSI agrees.

The Commission also asks if the necessary study process used for generator
interconnection modifications adequately addresses the impacts of co-located load arrangements or whether other studies like generator deactivation studies are warranted.9 OPSI has emphasized that PJM’s current process of using interconnection modifications to accommodate behind the meter co-located load arrangements lacks transparency and public oversight noting these modifications are privately negotiated and under non-disclosure agreements.10 Because of this, these arrangements are not subject to stakeholder review and avoid a comprehensive reliability analysis.11 The necessary studies process was developed to study modifications to existing generating units, not the addition of large co-located loads that are sometimes as large as metropolitan areas. OPSI continues to call on the Commission to require that transmission providers conduct transparent, publicly reviewable reliability studies pursuant to a PJM tariff for large co-located load arrangements to preserve system reliability.

Further, in addition to simply evaluating the reliability impacts of individual arrangements, the Commission should also promote processes that allow states to understand the cumulative

7 PJM Answer at 57-59.
8 Id.
9 Show Cause Order at Briefing Question d.i.
10 OPSI Comments at 3.
11 Id.

PDF page 4

4

resource adequacy impacts of these arrangements within individual states and across the PJM region. OPSI has previously called for long-term scenario analyses of these arrangements and called on FERC to review whether these arrangements negatively impact regional reliability.12 Neither the current necessary study process nor PJM’s deactivation study process produces this type of information as it pertains to these arrangements.

Once PJM has conducted appropriate studies to identify the impacts of co-located load arrangements, it should also comprehensively evaluate potential solutions and provide the information necessary for states and stakeholders to understand whether transmission, generation, grid enhancing technologies, or some combination is the most cost-effective response to any reliability violations identified.

B. CONSUMER PROTECTION AND COST ALLOCATION
Beyond ensuring that large, co-located load arrangements do not degrade regional resource adequacy or the reliability of the bulk power system for existing customers, the Commission must also determine the extent to which large, co-located load arrangements rely on the bulk power system as it determines how to allocate transmission costs appropriately and the extent to which these arrangements impact rates for other customers. To that end, the Commission asks how different co-location configurations impose costs on other customers and whether large, co-located load should be required to take Network Integration Transmission Service, among other things.13 It is important that the Commission accurately determine the extent to which these arrangements use ancillary services. PJM objects to the concept of fully or wholly isolated load “as it is contrary to engineering and economic principles.”14 OPSI agrees and discourages the

12 Id. at 2.
13 Show Cause Order at Briefing Questions b.ii – b.v.
14 PJM Answer at 42.

PDF page 5

5

Commission from accepting the premise that load can be wholly isolated from the grid without a comprehensive and conclusive showing that it is impossible for the load to ever receive grid services or impact transmission rates for existing customers.

The Commission asks a series of questions about how co-location arrangements can create costs, including transmission, energy, capacity, and ancillary services charges, for all customers and affect the allocation of those costs when these arrangements come online before PJM’s markets and transmission planning processes are able to respond efficiently.15 OPSI has previously written that the scale of the co-location agreements being negotiated “demands that appropriate cost allocation tariffs be developed that recognize the benefits and services received by the generator and its customer in behind the meter co-location arrangements.”16 Without a framework that studies the individual and cumulative impacts of these arrangements on the bulk power system, it will be difficult to assure stakeholders that large loads co-locating with generation are being accurately assigned the costs of the grid services they use, recognizing these arrangements may also create or shift costs for existing customers.

C. JURISDICTION
In its Post Technical Conference Comments, OPSI asked that the Commission “confirm that the sale between co-located generation and load is a retail transaction subject to state jurisdiction.”17 OPSI further stated “There is no regulatory gap. Sales of electricity from a generator to an end use customer in intrastate commerce are subject to state jurisdiction.”18 PJM challenges this assertion by stating that it is unclear that this is true across the PJM region.19 OPSI’s

15 Show Cause Order at d.iv, v, and ix.
16 OPSI Comments at 4.
17 Id.
18 Id. at 5.
19 PJM Answer at 22-23.

PDF page 6

6

Member States have processes by which jurisdictional issues can be resolved. Interested parties can file a petition for declaratory order seeking a determination from any State Commission regarding the extent to which such service is state jurisdictional. State Commissions allow for formal due process to all affected parties.

OPSI continues to assert that there is no regulatory gap regarding jurisdiction over retail sales. Section 201(b)(1) of the Federal Power Act states that “The provisions of this Part shall apply to the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce.”20 However, it specifically states that it “shall not apply to any other sale of electric energy.”21 The Commission is correct when it states, “First and foremost, states retain exclusive jurisdiction over the terms of retail sales.”22 And the Commission goes on to assert its jurisdiction “If [the sales from generating resources used to serve co-located loads] are not sales for resale—that is, if they are made directly to the end-use consumer—or if they are not in interstate commerce then the co-located generator’s sales are under state jurisdiction.”23 OPSI agrees with this assertion.

II. CONCLUSION
OPSI appreciates the opportunity to comment on the many important topics the
Commission has raised in this Show Cause proceeding.

20 16 U.S.C. § 824(b) (emphasis added) (A wholesale sale is a sale for resale, not end-use.).
21 Id.
22 Show Cause Order at P 68-69.
23 Id.

PDF page 7

7

Respectfully Submitted,
Gregory V. Carmean
Executive Director
Organization of PJM States, Inc.
700 Barksdale Road, Suite 1
Newark, DE 19711
302-266-0914
greg@opsi.us
Benjamin B. Sloan
Director of Legal and Regulatory Affairs
Organization of PJM States, Inc.
700 Barksdale Road, Suite 1
Newark, DE 19711
601-214-8481
ben@opsi.us
Dated: April 23, 2025

PDF page 8

8

CERTIFICA TE OF SERVICE
I hereby certify that the foregoing has been served in accordance with 18 C.F.R. Section 385.2010 upon each person designated on the official service list compiled by the Secretary in this proceeding.

/s/ Gregory V. Carmean
Gregory V. Carmean
Executive Director
Organization of PJM States, Inc.
700 Barksdale Road, Suite 1
Newark, DE 19711
Tel: 302-266-0914

Dated at Newark, Delaware this April 23, 2025.