Comments of the Organization of PJM States, Inc. in response to PJM Interconnection, L.L.C.'s 03/24/2025 Answer
Text extracted from the eLibrary original (SHA-256 8d8529a5b5b26aa9…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.Read this passage Filed comments: Connecting load and generation
I. COMMENTS
printed heading · Topic match: Reliability and curtailment
COMMENTS PJM’s stated approach to large load expansion—co-located or not—focuses on: “(1) maintaining resource adequacy; (2) enabling reliable system operations; (3) facilitating the states’ and stakeholders’ efforts to timely and effectively integrate large loads in a manner that meets their…Read this passage Filed comments: Reliability and curtailment
A. RESOURCE ADEQUACY, RELIABILITY, AND TRANSPARENCY
printed heading · Topic match: Connecting load and generation
RESOURCE ADEQUACY, RELIABILITY, AND TRANSPARENCY The Commission asks a series of questions about what interconnection modification and deactivation studies PJM should conduct in reviewing co-location arrangements to ensure resource adequacy and protect the reliability of the bulk power system.6…Read this passage Filed comments: Connecting load and generation
B. CONSUMER PROTECTION AND COST ALLOCATION
printed heading · Topic match: Connecting load and generation
CONSUMER PROTECTION AND COST ALLOCATION Beyond ensuring that large, co-located load arrangements do not degrade regional resource adequacy or the reliability of the bulk power system for existing customers, the Commission must also determine the extent to which large, co-located load arrangements…Read this passage Filed comments: Connecting load and generation
C. JURISDICTION
printed heading · Topic match: Retail and wholesale authority
Section 201(b)(1) of the Federal Power Act states that “The provisions of this Part shall apply to the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce.”20 However, it specifically states that it “shall not apply to any…Read this passage Filed comments: Retail and wholesale authority
II. CONCLUSION
printed heading
Carmean Executive Director Organization of PJM States, Inc. 700 Barksdale Road, Suite 1 Newark, DE 19711 302-266-0914 greg@opsi.us Benjamin B.Read this passage