EL25-49-000 · 2025-04-23 · Edison Electric Institute
Comments of Edison Electric Institute in response to FERC’s Order issued on 02/20/2025
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.,
et al.
)
Docket No. EL25-49-000
Large Loads Co-Located at
Generating Facilities
)
Docket No. AD24-11-000
Constellation Energy
Generation, LLC
v. PJM Interconnection, L.L.C.
)
Docket No. EL25-20-000
(consolidated)
COMMENTS OF THE EDISON ELECTRIC INSTITUTE
Pursuant to Rules 206 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”),1 the Edison Electric Institute (“EEI”) respectfully submits the following comments in response to FERC’s order issued on February 20, 2025 (“Show Cause Order”) instituting this proceeding under section 206 of the Federal Power Act (“FPA”)2 and consolidating it with other proceedings.3 In the Show Cause Order, the Commission found that PJM Interconnection, L.L.C.’s (“PJM”) Tariff appears to be unjust, unreasonable, unduly discriminatory or preferential with respect to its treatment of issues related to large loads co-located at generating facilities. FERC directed PJM and the transmission owners of PJM (“PJM TOs”) to either: (1) show cause as to why the PJM Tariff remains just and reasonable and not unduly discriminatory or preferential without provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that
1 18 C.F.R. § 385.206 (2012); see also 18 C.F.R. § 385.213 (2012).2 16 U.S.C. § 824e (2006).3 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).
PDF page 2
2
apply to co-location arrangements; or (2) explain what changes to the PJM Tariff would remedy the identified concerns if the Commission were to determine that the PJM Tariff has in fact become unjust and unreasonable or unduly discriminatory or preferential and, therefore, proceeds to establish a replacement PJM Tariff. PJM, a group of indicated PJM TOs, and Public Service Electric and Gas Company (PSE&G) filed responses to the Show Cause Order on March 24, 2025.
EEI is the association that represents all investor-owned electric companies in the United States. EEI members provide electricity for nearly 250 million Americans and operate in all 50 states and the District of Columbia. The electric power industry supports more than seven million jobs in communities across the United States. EEI’s member companies own and operate generation, transmission, and distribution facilities in regions all throughout the country. EEI members are focused on keeping customer bills as low as possible, and these generation, transmission, and distribution facilities are helping to meet rising demand while creating good- paying jobs and a cleaner, resilient, and affordable energy future for the customers and communities they serve. Accordingly, EEI can provide a broad-based perspective on the issues raised in the Show Cause Order.
I. BACKGROUND
The electric grid has long provided an extraordinary platform to reliably and affordably serve the nation’s electric customers. Among other things, the electric grid supports and facilitates the deployment of resilient, reliable sources of power, at scale, to address customers’ needs. After an extended period of relatively low demand growth rates, the country’s electric sector has entered an era of rapid transformation and unprecedented and sustained load growth. The North American Electric Reliability Corporation (“NERC”), among others, has observed
PDF page 3
3
that load and demand on the nation’s electric system will continue to increase as a result of many factors, including growing digitization and electrification, as well as the “changing resource mix and increased reliance on variable resources and natural gas.”4 The Commission, in its most recent State of the Markets Report, stated that “[r]egions continue to confront challenges in assuring resource adequacy – challenges caused by extreme weather events, a changing resource mix, and shifts in load profiles.”5 The report also noted that most RTO/ISO peak demand forecasts have shown a trend towards faster load growth in recent years, shifting from prior projections of flattening or declining growth to projections of increasing growth. A key facet of this growth in many regions is the emergence of new large load additions (e.g., from data centers). Growth from this segment of the power sector is forecast to persist well into the future, and many regions are likely to see increases in large new loads seeking to connect to the electric system over the next several years. For example, a recent Lawrence Berkeley National Laboratory report estimated that data center load growth tripled over the past decade and is projected to double or triple by 2028.6 A 2024 report by the Electric Power Research Institute (EPRI) projected that data centers will grow to consume up to 9.1 percent of U.S. electricity generation annually by 2030, compared to an estimated 4 percent today.7 At the same time, the electric industry is in the midst of a transformation, both in terms of the generation mix serving customers and customer makeup. The electric system resource mix is evolving rapidly.
4 See Statement of North American Electric Reliability Corporation, Technical Conference on Large Loads Co- located at Generating Facilities, Docket No. AD24-11-000 (Nov. 1, 2024), at 2-3.5 See Fed. Energy Reg. Comm’n, 2024 State of the Markets Staff Report (March 20, 2025) at 8, https://www.ferc.gov/news-events/news/SMR-2024.
6 Dep’t of Energy, DOE Releases New Report Evaluating Increase in Electricity Demand from Data Centers (Dec. 20, 2024), https://www.energy.gov/articles/doe-releases-new-report-evaluating-increase-electricity-demand-data- centers.
7 Elec. Power Research Inst., Powering Intelligence: Analyzing Artificial Intelligence and Data Center Energy Consumption(May 2024) at 2, https://www.epri.com/research/products/3002028905.
PDF page 4
4
Ensuring that the nation’s electric companies can accommodate these generational changes and continue to serve customers in a reliable and affordable manner will require new and upgraded energy infrastructure at all points on the electric value chain: generation, transmission, and distribution. Electric companies stand ready to lead the expansion of energy infrastructure needed to accommodate these changes. The regulatory model that underlies the electric sector is, and will be, critical to meet this extraordinary period of new growth. It ensures collaboration and partnerships between electric companies, stakeholders, and customers. Moreover, it serves as the foundation that supports the financing and construction of long-lived infrastructure.
Against this backdrop, EEI submits the following general comments for the
Commission’s consideration. In doing so, EEI asks that the Commission ensure any action or decision in this proceeding does not adversely affect other regions and/or impede the ability of those regions to address any similar challenges in ways they believe to be just and reasonable.
II. COMMENTS
a. Electric companies stand ready to lead energy infrastructure
expansion.
Electric companies are best positioned to lead the expansion of energy infrastructure driven by the dynamics previously described. This year, EEI members will invest $200 billion to make the energy grid smarter, more dynamic, more flexible, and more secure; to diversify the nation’s energy mix; and to integrate new technologies that benefit customers. Electric companies have extensive knowledge of the electric system, deep, collaborative relationships with states and stakeholders, and, for decades, managed the development of infrastructure projects that take years to design, finance, and build. Each of these capabilities is essential in assuring efficient, cost-effective, and timely infrastructure additions. Moreover, experience in
PDF page 5
5
the recent past demonstrates that electric companies are capable of meeting new demand from large loads, including data center-based demand. There is a data center located in every state in the country, and each project required careful planning before going into service. Electric companies have direct experience with the effects of rapid growth of large loads in their service territories. Working in partnership with their states, these companies successfully accommodated that growth over time. Electric companies have also announced numerous agreements and partnerships to facilitate data center development. For example, northern Virginia, Dominion’s service territory, boasts the largest data center market in the world, and Dominion serves more data centers today than the next five largest national data center markets combined.8 In addition, AEP anticipates 20 gigawatts in new load by the end of the decade.9 Exelon serves 200 online data centers in its service territories and projects significant continued load growth from data centers.10 States have also actively worked to prepare for load growth from large customers. In January, the Georgia Public Service Commission voted unanimously to approve new rules that allows for longer contract lengths between and minimum billing requirements for high-load customers.118 Comments of Dominion Energy Services, Docket No. AD24-11-000 (Dec. 9, 2024), at 2.9 Am. Elec. Power, AEP Reports 2024 Earnings Results (Feb. 13, 2025), https://www.aep.com/news/stories/view/10018/.10 Exelon, 2024 Earnings Call Presentation Slides (Feb. 12, 2025), https://investors.exeloncorp.com/events/event- details/q4-2024-exelon-corporation-earnings-conference-call.11 GA Pub. Serv. Comm’n, PSC Approves Rule to Allow New Power Usage Terms for Data Centers (Jan. 23, 2025), https://psc.ga.gov/site/assets/files/8617/media_advisory_data_centers_rule_1-23-2025.pdf.
PDF page 6
6
b. The existing regulatory model can accommodate significant demand
growth.
The regulatory model that governs the electric sector is long-standing, well-understood and provides transparent processes that ensure prudent investment to serve customers. This model successfully accommodated significant demand growth at different periods in the nation’s history and can continue to do so in the current environment. In addition, this model provides stability and facilitates valuable partnerships between electric companies, regulators, stakeholders, and customers. It will be a critical supporting element in meeting this extraordinary period of new demand growth. Further, this regulatory model has been carefully developed over more than one hundred years and, as a result, electric companies, customers, and regulators have long-established approaches for working collaboratively to plan the supply additions and system expansions required to serve customers. When they function properly, these approaches foster collaboration that ensures the necessary investments are made, infrastructure is developed, and critical public services are provided.
This regulatory model has, among other things, helped to build an electric system that evolves and modernizes as it integrates new supply resources and demand (e.g., data centers). This networked system captures economies of scale and allows electric companies to meet new demand efficiently and cost-effectively, as demonstrated by the reliable addition of thousands of data centers across the nation. Indeed, as noted above, America’s electric companies have been at the forefront in partnering with new large loads, such as data centers, to enable timely interconnections to the grid. These instances demonstrate electric companies’ ability to proactively plan and invest in transmission and generation infrastructure that can facilitate large load development while achieving broader benefits for existing customers and communities.
PDF page 7
7
As the Commission recognized in its February 20th order in this proceeding, there are many different co-location configurations. Co-location, depending on configuration, provides optionality to serve data centers and may support data center development necessary for economic development and national security. This could include:
• Access to an integrated network of supply resources that permit cost-efficient operations
• Holistic and comprehensive system planning that identifies new grid infrastructure to ensure reliable delivery of power
• Provision of black start and ancillary services
• Cybersecurity and physical security measures and protections will all contribute benefits to co-located load that is connected to the electric system.
c. Principles for the Commission to bear in mind as it evaluates next
steps.
As the Commission evaluates the comments it receives in response to the Show Cause Order and contemplates its next steps, EEI asks that it keep several key principles in mind. First and foremost, the Commission should strive to ensure that reliable system operations and resource adequacy are maintained and enhanced over the long term. At the same time, co- location policies should be grounded in cost-causation principles, ensuring that data center customers pay just and reasonable rates for service they use and protecting existing customers from any potential undue and unfair shifts in costs. The Commission should also respect the jurisdiction of state regulatory authorities and consider how collaboration with state commissions, and RTOs/ISOs where applicable, may be valuable in addressing specific co- location arrangements. Adherence to these principles will ensure that rules and regulations will enable electric companies to continue their long history of delivering reliable and affordable service to customers and meeting the new system demands in a cost-effective, efficient, and timely way.
PDF page 8
8
III. CONCLUSION
EEI appreciates the opportunity to submit comments in this proceeding and urges the Commission to act in a manner consistent with the principles discussed herein.
Respectfully submitted,
/s/ _
Kevin Huyler
Managing Director, Federal Regulatory Affairs
khuyler@eei.org
Edison Electric Institute
701 Pennsylvania Ave., N.W.
Washington, D.C. 20004
April 23, 2025
PDF page 9
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C. this 23rd day of April 2025.
/s/ _
Sandra Safro
Deputy General Counsel
Edison Electric Institute
SSafro@eei.org
202-508-5129