Comments of Edison Electric Institute in response to FERC’s Order issued on 02/20/2025
Text extracted from the eLibrary original (SHA-256 03451d8a3c98b2af…). Download the original from the official source.
Contents · 3 sections
Read topic-matched comments in EL25-49
Topics in the text: Reliability and curtailment · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.Read this passage
I. BACKGROUND
printed heading · Topic match: Reliability and curtailment
In doing so, EEI asks that the Commission ensure any action or decision in this proceeding does not adversely affect other regions and/or impede the ability of those regions to address any similar challenges in ways they believe to be just and reasonable.Read this passage Filed comments: Reliability and curtailment
II. COMMENTS
printed heading · Topic match: Connecting load and generation
As the Commission evaluates the comments it receives in response to the Show Cause Order and contemplates its next steps, EEI asks that it keep several key principles in mind.Read this passage Filed comments: Connecting load and generation
III. CONCLUSION
printed heading
CONCLUSION EEI appreciates the opportunity to submit comments in this proceeding and urges the Commission to act in a manner consistent with the principles discussed herein.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 23rd day of April 2025. /s/ _ Sandra Safro Deputy General Counsel Edison Electric Institute SSafro@eei.org 202-508-5129Read this passage