EL25-49-000 · 2025-04-23 · Northeastern Remc

Comments of Northeastern Rural Electric Membership Corporation on the Order Instituting Proceeding Under Section 206 of the Federal Power Act and…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
Docket Nos. EL25-49-000
Allegheny Electric Cooperative, Inc.

)
American Transmission Systems, Incorporated )

Atlantic City Electric Company

)
Baltimore Gas and Electric Company

)
Delmarva Power & Light Company

)
Duke Energy Ohio, Inc.

)
Duke Energy Kentucky, Inc

)
East Kentucky Power Cooperative, Inc.

)
Essential Power Rock Springs, LLC

)
Hudson Transmission Partners, LLC

)
Jersey Central Power & Light Company

)
Mid-Atlantic Interstate Transmission, LLC )

Neptune Regional Transmission System, LLC )

Old Dominion Electric Cooperative

)
PECO Energy Company

)
PPL Electric Utilities Corporation

)
Potomac Electric Power Company

)
Public Service Electric and Gas Company

)
Rockland Electric Company

)
Trans-Allegheny Interstate Line Company

)
Transource West Virginia, LLC

)
UGI Utilities, Inc.

)
Monongahela Power Company

)
The Potomac Edison Company

)
Commonwealth Edison Company

)
Commonwealth Edison Company of  Indiana, Inc. ) The Dayton Power and Light Company

)
AEP Appalachian Transmission Company, Inc. )

AEP Indiana Michigan Transmission Company, Inc. ) AEP Kentucky Transmission Company, Inc. )

AEP Ohio Transmission Company, Inc.

)
AEP West Virginia Transmission Company, Inc. )

Appalachian Power Company

)
Indiana Michigan Power Company

)
Kentucky Power Company

)
Kingsport Power Company

)
Ohio Power Company

)
Wheeling Power Company

)
Duquesne Light Company

)

PDF page 2

Virginia Electric and Power Company

)
Linden VFT, LLC

)
City of Cleveland, Department of Public

)
Utilities, Division of Cleveland Public Power
)
City of Hamilton, OH

)
Southern Maryland Electric Cooperative, Inc.
)
Ohio Valley Electric Corporation

)
AMP Transmission, LLC

)
Silver Run Electric, LLC

)
NextEra Energy Transmission MidAtlantic
)
Indiana, Inc.

)
Wabash Valley Power Association, Inc.

)
Keystone Appalachian Transmission Company
)

)
Large Loads Co-Located at Generating

)
AD24-11-000
Facilities

)

)

)
Constellation Energy Generation, LLC

)
EL25-20-000

)
(Consolidated)
v.

)

)
PJM Interconnection, L.L.C.

)

)

COMMENTS OF NORTHEASTERN REMC
ON THE ORDER INSTITUTING THE PROCEEDING
UNDER SECTION 206 OF THE FEDERAL POWER ACT
AND CONSOLIDATING WITH OTHER PROCEEDINGS

Pursuant to Rule 212 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure1,  Northeastern Rural Electric Membership Corporation (“NREMC”) respectfully submits these comments to the Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings2 issued in the above-captioned proceeding on February 20, 2025.

1 18 C.F.R § 385.212.
2 PJM Interconnection, L.L.C., Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings, Docket Nos. EL25-49-000, et al. (Feb. 20, 2025) (“Show Cause Order”).

PDF page 3

NREMC appreciates the Commission’s initiative in launching this inquiry and commends its leadership in addressing this important matter. Establishing clear guidelines for interconnection, service, and cost allocation for co-located arrangements is essential to supporting grid reliability and safeguarding consumers from unfair cost implications.

I. INTRODUCTION AND BACKGROUND
The Show Cause Order is the culmination of multiple proceedings focused on the issue of co-location. The Commission consolidated this new proceeding, Docket No. EL25-49-000, with Docket Nos. AD 24-11-000 and EL25-20-000.3 Notably, the Show Cause Order is specific and limited to PJM. In its Show Cause Order, the Commission directed the respondents to:

(1) show cause as to why the [Open Access Transmission Tariff], the Amended and Restated Operating Agreement of PJM, and Reliability Assurance Agreement Among Load Serving Entities in the PJM Region [(collectively, the “PJM

Tariff”)] remains just and reasonable and not unduly discriminatory or preferential without provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements; or

(2) explain what changes to the Tariff would remedy the identified concerns if the Commission were to determine that the Tariff has in fact become unjust and unreasonable or unduly discriminatory or preferential and, therefore, proceeds to establish a replacement Tariff.4

The Commission then invited interested entities to address either or both of: “(1) whether the Tariff remains just and reasonable and not unduly discriminatory or preferential; and (2) if not, what changes to the Tariff should be implemented as a replacement rate.”5 NREMC provides these comments from the perspective of a non-profit, member-owned electric distribution utility organized and existing pursuant to the laws of the State of Indiana

3 Id. at 56.
4 Id. at 3.
5 Id. at 57.

PDF page 4

within the PJM region. NREMC supplies electric power to more than 30,000 residential, commercial, and industrial member-consumers. NREMC does so through behind the meter generation and participation in the PJM energy, capacity, and ancillary services markets as a Load- Serving Entity. NREMC agrees with the Indicated Transmission Operators (“TOs”) and PJM that the existing Tariff remains just and reasonable and not unduly discriminatory or preferential.6 NREMC also agrees with PJM and the Indicated TOs that co-located end-use loads should be treated as load in front of the meter and designated as Network Load.7

II. COMMENTS
A. Existing Tariff Framework is Sufficient
NREMC agrees with PJM the Indicated TOs that co-location can be effectively
accommodated within the existing PJM Tariff through established transmission service structures
– as Network Load or Point to Point Service.8 PJM outlined three options currently available under the Tariff for serving co-located load: (1) Option 1 – Load with a separate point of interconnection that is Network Load; (2) Option 2 – Co-located load that is at the same point of interconnection but separately metered that is Network Load; and (3) Option 3 – Existing Behind the Meter Generation where load is the customer.9 Under both existing Options 1 and 2, the load uses and pays for transmission services, ancillary services, energy, and capacity.10

6 Answer of PJM Interconnection, L.L.C. (“PJM Answer”) at 4; Answer of the Indicated PJM Transmission Owners to the Order Instituting the Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (“TO Answer”) at 2.
7 See PJM, PJM Guidance on Co-Located Load, at 1 (originally issued Mar. 22, 2024 and updated Apr. 17, 2024), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.ashx (“PJM continues to recommend that all co-located load be served from the PJM Transmission System as PJM Network Load with applicable firm transmission service (e.g., Regional Network Integration Transmission Service (NITS) under PJM Tariff, Part III).”) (“PJM Guidance on Co-Located Load”); TO Answer at 3.
8 TO Answer at 10; PJM Answer at 9.
9 PJM Answer at 9-11.
10  Id. at 9 -10.

PDF page 5

However, Option 3 was not designed to accommodate large-scale loads. The existing Non-Retail Behind the Meter Generation (“BTMG”) rules are capped annually, as these resources do not maintain reserves equivalent to the installed reserve margin.11 Large co-located loads, such as data centers paired with behind the meter generation, present significantly greater operational risks than traditional BTMG arrangements because they lack adequate reserves.12 Furthermore, this arrangement would require these loads to co-locate with generation through the same point of interconnection (unless an EDC consented to serve) thereby concentrating large amounts of risk from both the load and generation sides of the meter.13  In emergencies or outages, their reliance on the grid could severely impact resource adequacy and system reliability.14 PJM correctly noted that the BTMG model does not apply well to co-location scenarios involving large loads.15 It was originally developed for much smaller and distributed installations – not for high consumption, single point facilities like data centers.16 Additionally, simple netting of generation against load could allow these facilities to avoid most, if not all, costs by netting out to zero as the entire load is supplied by the co-located generator, despite the co-located loads reliance and benefit from the grid.17 This would shift costs and burdens unfairly to other users, violating core principles of just and reasonable ratemaking.

Nevertheless, viable and fair options exist under the current Tariff for co-located load as Network Load in Options 1 or 2 and Point to Point Service. The PJM Tariff continues to be just and reasonable as it requires all load – regardless of usage consistency – to pay for grid access

11 Id. at 11.
12 Id. at 36.
13 Id. at 12.
14 Id. at 36.
15 Id. at 13, 34.
16 Id.
17 Id. at 36.

PDF page 6

and services, in accordance with Order No. 888 and the Federal Power Act.18 A fundamental ratemaking principle establishes that “the costs assessed against a party must bear some resemblance ‘to the burdens imposed or benefits drawn by that party.’”19 Maintaining the existing Tariff provisions for co-located load to interconnect as Network Load or Point to Point Service ensures that costs are equitably shared in line with this principle.20 Creating carve-outs that exempt co-located load from standard transmission charges would undermine this principle and unlawfully shift costs onto other users – an outcome that would be unjust and unreasonable.21

NREMC fully supports the Indicated TOs’ position that the PJM Tariff should apply to all who seek transmission service within the region.22 This ensures that every customer contributes fairly to the shared infrastructure and services from which they benefit.23 Co-location arrangements can be readily accommodated within the existing Tariff framework—either through retail service from a local distribution company or by registering as a Network Customer in PJM (where permitted by state jurisdiction).24 In either case, the co-located load is treated like all other users and pays its fair share.25

B. Co-located Load Interconnects with and Benefits from the Grid
While co-located load may be situated behind the point of interconnection, it remains electrically connected and synchronized with the PJM Transmission System, as noted by both

18 TO Answer at 18. 19  Pub. Serv. Elec. & Gas Co. v. FERC, 989 F.3d 10, 13 (D.C. Cir. 2021) (“PSE&G”) (quoting Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368–69 (D.C. Cir. 2004)).
20 TO Answer at 18.
21 Id. at 18-19.
22 Id. at 19.
23 Id.
24 Id. at 19-20.
25 Id.

PDF page 7

PJM and the Indicated Transmission Owners.26 As a result, co-located load benefits from the full range of Transmission and Ancillary Services. This remains true even when the load is only connected via the distribution system, since both transmission and distribution operators depend on ancillary services to maintain grid reliability, stability, and power quality.27 Essential services that co-located loads rely on—such as voltage support and black start capabilities—require a physical and synchronous connection to the grid.28 Given this reliance, NREMC co-located load should be designated as Network Load and be responsible for its share of transmission and ancillary service costs. The current PJM Tariff appropriately reflects this framework and remains just and reasonable.

C. Co-located Load Should be Treated as Network Load & Pay Fair Share
Even if a load connects to the grid indirectly—such as through facilities connecting a generator to the grid—it still requires the ability to be served from the transmission network, as stated by the Indicated TOs.29 As a result, the transmission system must be planned, built, and maintained to accommodate and support that load.30 The intermittent nature of co-located load does not lessen the need for ongoing investment in infrastructure or the operational costs incurred by transmission owners to ensure reliability.31 Because co-located load is interconnected and relies on the transmission system—it both uses and benefits from it, NREMC agrees with PJM that co-located load must contribute its appropriate share of the associated costs.32

26 Id. at 12.
27 Id.
28 Id. at 12-13. 29 Id. at 8.
30 Id.
31 Id. at 17.
32 PJM Answer at 5.

PDF page 8

III. CONCLUSION
For the reasons stated above, NREMC respectfully requests that the Commission find the current PJM Tariff is just, reasonable, and non-discriminatory or preferential as it already accommodates co-location arrangements through Network Service and Point to Point Service, which uphold equitable cost allocation for the transmission and grid services co-location arrangements benefit from.

Respectfully submitted,

Alexandra L. Jones
Vice-President & Senior Counsel
of Energy and Regulatory Affairs
Northeastern REMC
4901 East Park 30 Drive
Columbia City IN 46725
Telephone: (317) 964-1752
Fax: (260) 625-3407
a_jones@nremc.com

April 23, 2025

PDF page 9

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in the above captioned dockets. Dated at Indianapolis, Indiana, this 23rd day of April 2025.

/s/ Alexandra L. Jones
Alexandra L. Jones
Northeastern REMC
4901 East Park 30 Drive
Columbia City IN 46725
Telephone: (317) 964-1752
Fax: (260) 625-3407
a_jones@nremc.com