EL25-49-000 · 2025-04-23 · Northeastern Remc

Comments of Northeastern Rural Electric Membership Corporation on the Order Instituting Proceeding Under Section 206 of the Federal Power Act and…

Text extracted from the eLibrary original (SHA-256 7c4f5d260c6842c9…). Download the original from the official source.

Contents · 6 sections
  1. I. INTRODUCTION AND BACKGROUND p. 3
  2. II. COMMENTS p. 4
  3. A. Existing Tariff Framework is Sufficient p. 4
  4. B. Co-located Load Interconnects with and Benefits from the Grid p. 6
  5. C. Co-located Load Should be Treated as Network Load & Pay Fair Share p. 7
  6. III. CONCLUSION p. 8

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

Establishing clear guidelines for interconnection, service, and cost allocation for co-located arrangements is essential to supporting grid reliability and safeguarding consumers from unfair cost implications.
Read this passage Filed comments: Cost allocation

I. INTRODUCTION AND BACKGROUND

printed heading

INTRODUCTION AND BACKGROUND The Show Cause Order is the culmination of multiple proceedings focused on the issue of co-location.
Read this passage

II. COMMENTS

printed heading

II.
Read this passage

A. Existing Tariff Framework is Sufficient

printed heading · Topic match: Connecting load and generation

The PJM Tariff continues to be just and reasonable as it requires all load – regardless of usage consistency – to pay for grid access 11 Id. at 11. 12 Id. at 36. 13 Id. at 12. 14 Id. at 36. 15 Id. at 13, 34. 16 Id. 17 Id. at 36. and services, in accordance with Order No. 888 and the Federal Power…
Read this passage Filed comments: Connecting load and generation

B. Co-located Load Interconnects with and Benefits from the Grid

printed heading · Topic match: Connecting load and generation

Co-located Load Interconnects with and Benefits from the Grid While co-located load may be situated behind the point of interconnection, it remains electrically connected and synchronized with the PJM Transmission System, as noted by both 18 TO Answer at 18. 19 Pub.
Read this passage Filed comments: Connecting load and generation

C. Co-located Load Should be Treated as Network Load & Pay Fair Share

printed heading · Topic match: Connecting load and generation

Co-located Load Should be Treated as Network Load & Pay Fair Share Even if a load connects to the grid indirectly—such as through facilities connecting a generator to the grid—it still requires the ability to be served from the transmission network, as stated by the Indicated TOs.29 As a result,…
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION

printed heading · Topic match: Cost allocation

CONCLUSION For the reasons stated above, NREMC respectfully requests that the Commission find the current PJM Tariff is just, reasonable, and non-discriminatory or preferential as it already accommodates co-location arrangements through Network Service and Point to Point Service, which uphold…
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Dated at Indianapolis, Indiana, this 23rd day of April 2025. /s/ Alexandra L.