EL25-49-000 · 2025-04-23 · American Municipal Power, Inc.

Response of American Municipal Power, Inc

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000

)

Large Loads Co-Located at
  Generating Facilities
)
)
Docket No. AD24-11-000

)

Constellation Energy Generation, LLC

  v.

)
)
)
)
Docket No. EL25-20-000
   (Consolidated)
PJM Interconnection, L.L.C.
)

RESPONSE OF
AMERICAN MUNICIPAL POWER, INC.

Pursuant to the procedures established in the Federal Energy Regulatory
Commission’s (“Commission” or “FERC”) February 20, 2025 order in the above-captioned proceedings,1 American Municipal Power, Inc. (“AMP”) hereby addresses the issues raised in the Show Cause Order and responds to the filings submitted by PJM

Interconnection, L.L.C. (“PJM”) and certain PJM Transmission Owners on those matters.2
I. INTRODUCTION AND SUMMARY OF POSITION
In response to a complaint filed by Constellation Energy Generation, LLC
(“Constellation”)3 and the record developed in connection with the Commission’s November 1, 2024 technical conference on large loads co-located at generating facilities,4

1  PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).
2  See Indicated PJM Transmission Owners, Answer, Docket Nos. EL25-49-000, et al. (March 24, 2025) (“Indicated PJM TOs Answer”); PJM, Answer, Docket Nos. EL25-49-000, et al. (March 24, 2025) (“PJM Answer”); Public Service Electric and Gas Co., Response, Docket Nos. EL25-49-000, et al. (March 24, 2025) (“PSE&G Response”).
3  Constellation, Complaint, Docket No. EL25-20-000 (Nov. 22, 2024) (“Constellation Complaint”).
4  Large Loads Co-Located at Generating Facilities, Docket No. AD24-11-000 (“Co-Located Load Technical Conference”).

PDF page 2

2
the Commission’s Show Cause Order found that PJM’s Open Access Transmission Tariff (“Tariff”) “appears to be unjust and unreasonable or unduly discriminatory or preferential because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements.”5 The Commission accordingly initiated a new proceeding under section 206 of the Federal Power Act (“FPA”), consolidated the new proceeding with the Constellation Complaint and Co-Located Load Technical Conference dockets, and directed PJM and the PJM Transmission Owners: (1) to show cause as to why the PJM Tariff remains just and reasonable and not unduly discriminatory or preferential; or (2) explain what Tariff changes “would remedy the Commission’s identified concerns if the Commission were to determine that the Tariff has in fact become unjust and unreasonable or unduly discriminatory or preferential.”6 The Commission identified a number questions that PJM and Transmission Owners should address in responding to the order.7

PJM, while maintaining that its Tariff remains just and reasonable, identified eight “options” for the treatment of large load co-location.8 In addition to the answer filed by PJM, most PJM Transmission Owners submitted a joint answer to the Show Cause Order, while other Transmission Owners, including PSE&G, filed individual responses. AMP supports the answer filed by the Indicated PJM Transmission Owners. AMP agrees that the existing PJM Tariff is just and reasonable, although additional clarification

5  Show Cause Order at P 74. For purposes of the Show Cause Order, the Commission defines co-located load as “a configuration through which end-use customer load is physically connected to the facilities of an existing or planned generation unit on the interconnection customer’s side of the point of interconnection to the PJM transmission system.” Id. P 3.
6  Id. P 87.
7  Id. P 88.
8  See PJM Answer at 9-20 & Exh. A.

PDF page 3

3
concerning the treatment of co-located load may be beneficial.9 As the Indicated PJM Transmission Owners explain, it is important that load co-located behind the interconnection point of an adjacent generator in PJM is considered Network Load (or load taking Point-to-Point Transmission Service) to avoid unjust and unreasonable cost- shifting and to promote reliable transmission planning and resource adequacy. While AMP supports the answer of the Indicated PJM Transmission Owners, AMP

is filing this response to emphasize the continuing reasonableness of the PJM Tariff’s treatment of load served by Behind the Meter Generation (“BTMG”) and Non-Retail BTMG, as those terms are defined in the Tariff.10 Specifically, the PJM Tariff allows certain Network Load served by BTMG to be netted for purposes of calculating transmission, and certain other charges.11 These Tariff provisions conform to cost causation principles – as the Commission found in approving them12 – and provide meaningful benefits to electric consumers. Even if the Commission agrees with PJM that “[t]he extent to which netting could or should apply to co-located data center load is not clear at this time,”13 there is no reason to revisit the existing Tariff framework allowing BTMG netting. Indeed, PJM correctly asserts that its existing Tariff remains just and reasonable.14 Any action taken by the Commission in this proceeding should avoid

9  See, e.g., Indicated PJM TOs Answer at 2.
10  In this response, AMP’s references to BTMG should be read to include Non-Retail BTMG unless otherwise indicated.
11  See PJM Tariff, §§ 34.2 and 34.3; see also, e.g., PJM Manual 14D, Appendix A at p. 179 (“The purpose of these rules is to permit market participants operating Behind-the-Meter Generation (BTMG) to receive the associated benefits. These benefits are recognized by allowing such generation to net for the purposes of calculating transmission, capacity, ancillary services, and administrative fee charges.”); PJM Answer at 11-12, 34-37.
12  See PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 28, reh’g denied, 108 FERC ¶ 61,302 (2004). 13  PJM Answer at 35.
14  Id. at 4, 32.

PDF page 4

4
prejudice to entities that have relied on the longstanding provisions allowing for netting of Network Load served by BTMG.

Although PSE&G’s response persuasively documents the benefits of the PJM Tariff’s existing BTMG netting provisions,15 PSE&G incorrectly suggests (as have other parties in these consolidated proceedings) that treating large loads that co-locate behind an adjacent generator’s point of interconnection differently than loads eligible for netting under the BTMG provisions of the Tariff would necessarily raise undue discrimination concerns.16 The record does not support a finding that co-location arrangements for large loads (such as data centers) that appear to be the focus of PSE&G’s discrimination concerns17 would meet the existing requirements for BTMG and/or Non-Retail BTMG netting, or that co-located load is otherwise similarly situated to load served by BTMG and eligible for netting under the PJM Tariff.

II. INTEREST OF AMP
AMP is a nonprofit Ohio corporation with members in Delaware, Indiana, Kentucky, Maryland, Michigan, Ohio, Pennsylvania, Virginia, and West Virginia, the majority of which are load-serving entities within the PJM region. To meet those members’ load service responsibilities, AMP purchases transmission and related services from PJM and also purchases and sells electricity products in the markets operated by PJM.18

15  See PSE&G Response at 18 & Exh. 1.
16  See, e.g., id. at 13-14.
17  See, e.g., id. at 2 (arguing for an approach that, inter alia, “preserves co-location as a viable option to support data center development in New Jersey and elsewhere in PJM”).
18  AMP Transmission LLC (“AMP Transmission”), a wholly owned subsidiary of AMP, is a PJM Transmission Owner. AMP Transmission is a signatory to the Indicated PJM Transmission Owners’ Answer.

PDF page 5

5
III. RESPONSE
A. AMP supports the answer of the Indicated PJM Transmission Owners.
The Indicated PJM Transmission Owners correctly assert that the current PJM Tariff remains just and reasonable19 – a position that is echoed by PJM itself.20 As the Transmission Owners observe, “[c]o-located load can and does fit within the current constructs for providing transmission service” under the pro forma open access transmission tariff and the PJM Tariff.21 In particular, load served under co-location arrangements should be treated as Network Load (or load served by Point-to-Point Service). Treating co-located load as Network Load or load served by Point-to-Point Service avoids unjust and unreasonable transmission cost-shifting,22 while promoting reliable transmission planning and resource adequacy.23

The responses filed by PJM and the Indicated PJM Transmission Owners do not support a finding that the existing PJM Tariff is unjust and unreasonable (they assert the opposite), and, thus, they provide no basis to modify the Tariff under FPA section 206.24 Like the Indicated PJM Transmission Owners, however, AMP is amenable to further discussion and guidance regarding possible Tariff changes to clarify the treatment of co- located load. The Indicated PJM Transmission Owners, for example, suggest a reasonable definition of “Co-located Load” that would appropriately clarify how co-located

19  Indicated PJM TOs Answer at 2.
20  PJM Answer at 4, 32.
21  Indicated PJM TOs Answer at 2.
22  See id. at 3.
23  See id. at 3-4. 24  16 U.S.C. § 824e; see also, e.g., Emera Maine v. FERC, 854 F.3d 9, 24-25 (D.C. Cir. 2017).

PDF page 6

6
arrangements fit within the existing PJM Tariff framework.25 The definition suggested by the Indicated PJM Transmission Owners would appropriately preserve the current treatment of load served by BTMG and Non-Retail BTMG.26

Regardless of whether the Commission concludes that the PJM Tariff should be modified to address co-located arrangements, however, there is no basis to modify the current BTMG netting provisions in the PJM Tariff, as discussed below.27

B. The existing PJM Tariff provisions addressing BTMG netting should
be retained.
1. The BTMG netting provisions were adopted in conformance
with cost causation principles.
Under sections 34.2 and 34.3 of the PJM Tariff, load served by BTMG is, subject to certain requirements and limitations, eligible to be excluded – or netted – from a Network Customer’s daily load for purposes of calculating charges for Network Service and other PJM charges.28 This does not mean that load served by BTMG and Non-Retail

25  See Indicated PJM TOs Answer at 9.
26  Specifically, the suggested definition of Co-located Load would distinguish between the generation resources adjacent to load in a co-located load arrangement and generation resources that meet the definition of BTMG. See id.
27  See Show Cause Order at P 88, question a.iv (“Parties may also address how co-located loads are similar to or disparate from other types of arrangements where load and generation share the same point of interconnection (such as Behind the Meter Generation as defined in PJM’s Tariff or non-retail behind the meter generation) and should consider how any proposed replacement rate would interact with these other arrangements.”).
28  The PJM Tariff defines Behind the Meter Generation as: a generation unit that delivers energy to load without using the Transmission System or any distribution facilities (unless the entity that owns or leases the distribution facilities has consented to such use of the distribution facilities and such consent has been demonstrated to the satisfaction of the Office of the Interconnection); provided, however, that Behind The Meter Generation does not include (i) at any time, any portion of such generating unit’s capacity that is designated as a Generation Capacity Resource; or (ii) in an hour, any portion of the output of such generating unit that is sold to another entity for consumption at another electrical location or into the PJM Interchange Energy Market.

The Tariff, in turn, defines Non-Retail BTMG as “Behind the Meter Generation that is used by municipal electric systems, electric cooperatives, or electric distribution companies to serve load.”

PDF page 7

7
BTMG is not considered Network Load; the relevant netting provisions are only available to Network Customers, and as PJM explains, “all load served by BTM Generation must be designated Network Load.”29

Netting of Network Load served by BTMG conforms to cost causation principles. Load eligible for netting under sections 34.2 and 34.3 of the PJM Tariff is served by generation that, by definition, delivers energy to load without using the transmission system.30 In accepting the original BTMG netting provisions in the PJM Tariff, the Commission specifically observed that PJM’s “charges for the use of PJM’s transmission system should be allocated to network customers based on a network customer’s actual use of PJM's system, consistent with the principle of cost causation.”31 The Commission also agreed that the BTMG netting provisions were consistent with its policy of encouraging demand response programs,32 as PJM observed that its proposal would “encourage the use of behind the meter generation during times of scarcity and high prices.”33

The PJM Tariff provisions addressing netting of load served by Non-Retail BTMG were adopted in a 2005 settlement agreement,34 reached after the Commission found that “PJM’s current tariff that excludes from the BTM program all generation that is connected to load through a distribution system may not be just and reasonable, and may

29  PJM Answer at 35.
30  See supra note 28.
31  PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 at P 28 (quoting Occidental Chem. Corp. v. PJM, 102 FERC ¶ 61,275 (2003) (internal quotes omitted)).
32  Id. P 27.
33  Id. P 6.
34  See PJM Interconnection, L.L.C., 113 FERC ¶ 61,279 (2005).

PDF page 8

8
be unjust, unreasonable, unduly discriminatory or preferential or otherwise unlawful.”35 Section 34.3 of the Tariff thus extends the same netting availability, subject to certain conditions, to BTMG used by municipal electric systems, electric cooperatives, or electric distribution companies to serve load, consistent with the cost causation principles recognized by the Commission in accepting the original BTMG netting provisions.

2. The BTMG Tariff provisions provide benefits while protecting
against adverse impacts.
AMP and a number of its load-serving utility members rely on generating units that qualify as Non-Retail BTMG. These resources, while generally small, provide significant benefits to the consumers of AMP’s member utilities. Consistent with the original purposes of the BTMG netting approach, the PJM Tariff allows consumers to avoid costs that do not reflect their actual use of the transmission system. The transmission cost mitigation impacts of Non-Retail BTMG netting are extremely important to AMP’s members at a time of sharply increasing transmission expenses in the PJM region. The answer filed by PSE&G documents similar benefits for customers in New Jersey, including universities, government agencies, manufacturers, and other consumers.36 Other technical conference commenters cited similar benefits.37

Continuing to facilitate BTMG resources is also likely to provide reliability benefits. As noted above, one of PJM’s original justifications in proposing BTMG netting was that it would “encourage the use of behind the meter generation during times of scarcity and

35  PJM Interconnection, L.L.C., 112 FERC ¶ 61,034, at P 18 (2005).
36  PSE&G Response at 18 & Exh. 1.
37  See, e.g., Northeastern Rural Electric Membership Corporation, Post-Technical Conference Comments, Docket No. AD24-11-000 (Dec. 9, 2024).

PDF page 9

9
high prices.”38 Tariff provisions that encourage the operation of BTMG generation as a form of demand response at times of scarcity are likely to enhance reliability. Indeed, in its answer, PJM describes current efforts to facilitate increased use of small generators to promote resource adequacy, explaining that “PJM is also exploring with regulators and generators opportunities to leverage at least 50 hours (or more) of diesel back-up generator service to enhance the available demand response portfolio.”39 In addition to demand response benefits, BTMG installations can provide a source of emergency backup generation for some customers should a major outage occur.

The PJM Tariff, moreover, includes a number of conditions on Non-Retail BTMG netting specifically designed to address initial PJM reservations that adverse reliability impacts could result from greater levels of BTMG if the netting rules were extended to municipals and cooperatives.40 Specifically, even though the definition of BTMG (and by extension Non-Retail BTMG), excludes any portion of “the generating unit’s capacity that is designated as a Generation Capacity Resource,” Non-Retail BTMG must operate during the first ten occurrences of Maximum Generation Emergency conditions each year in the zone where the unit is located.41 Further, section 34.3 of the Tariff caps the total amount of Non-Retail BTMG in the PJM Region in any specific year, and sets a maximum ceiling of 3,000 MW absent a filing by PJM to expand the cap or modify the netting rules.42

38  PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 at P 6.
39  PJM Answer at 9.
40  See PJM, Offer of Settlement, Docket No. EL05-127-000, Explanatory Statement at 9-10 (Oct. 24, 2005); see also PJM Answer at 13 n.5.
41  PJM Tariff, Schedule 15.
42  PJM Tariff, § 34.3; PJM, Offer of Settlement, Docket No. EL05-127-000, Explanatory Statement at 6-7.

PDF page 10

10
3. The record provides no basis to revisit the current PJM Tariff
provisions addressing BTMG.
AMP strongly agrees with PSE&G’s admonition that the Commission “should allow existing BTMG customers to continue to net and should take no action that would disadvantage these existing customers.”43 Indeed, as discussed above, the PJM and Transmission Owner responses do not provide any basis for finding that the existing BTMG netting provisions are subject to modification under FPA section 206 as unjust and unreasonable, or unduly discriminatory or preferential.

While maintaining that its Tariff remains just and reasonable, PJM discordantly suggests that “discussions in the record regarding PJM’s BTM Generation rules raise questions about the status of those rules,”44 and PJM states that it is “open to exploring . . . whether the 20-year-old method of allocating costs pursuant to the BTM Generation netting rules remains consistent with cost causation principles.”45 PJM does not provide any citations to the “discussions in the record” that supposedly call the existing netting provisions into question, nor does it identify any reason why the longstanding practice of netting loads served by BTMG might no longer be “consistent with cost causation principles.”46 As the Commission found in originally approving the BTMG netting provisions in the PJM Tariff, those provisions allocate transmission system costs to Network Customers based on their actual use of PJM’s system, “consistent with the principle of cost causation.”47 That observation is as true today as it was in 2004. If

43  PSE&G Response at 6; see also, e.g., Northeastern Rural Electric Membership Corporation, Post- Technical Conference Comments, Docket No. AD24-11-000 (Dec. 9, 2024). 44  PJM Answer at 36.
45  Id. at 36-37.
46  Id.
47  PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 at P 28.

PDF page 11

11
anything, the longstanding nature of the netting provisions is a reason to retain, not revisit them, given the reliance interests of PJM market participants in the existing rules.48 PJM suggests that large load co-location arrangements might fall within the Tariff’s existing BTMG netting provisions, and PJM’s “Option 3” is based on this premise.49 PJM nonetheless expresses concern that “the BTM Generation paradigm does not fit co- location arrangements particularly well because it was not designed with large load co- location in mind,”50 and PJM ultimately observes that “[t]he extent to which netting could or should apply to co-located data center load is not clear at this time.”51 AMP agrees that the existing BTMG provisions were not designed with large co-located loads in mind, but concerns about whether and how large loads co-locating at existing generation units fit within the existing BTMG netting framework is not a reason to upset the existing framework, which was adopted in conformance with cost causation principles, and which is reflected in a Tariff that PJM insists remains just and reasonable.

PSE&G correctly argues that the Commission should avoid adversely impacting
entities that rely on the existing BTMG provisions of the PJM Tariff, but goes on to suggest that it would be unduly discriminatory to treat co-located “behind the meter load” differently than load served by BTMG for netting purposes.52 The Commission has

48  See, e.g., Dep’t of Homeland Sec. v. Regents of the Univ. of Cal., 591 U.S. 1, 30 (2020) (explaining that an agency “must be cognizant that longstanding policies may have engendered serious reliance interests that must be taken into account.” (cleaned up)).
49  See, e.g., PJM Answer at 11-13; see also id. at 34 (“The co-located load arrangements at issue here, large data centers, could be viewed as similar to BTM Generation that currently exists under PJM’s Tariff (as reflected in Exhibit A, Option 3).”). 50  Id. at 34; see also id. at 13 (discussing PJM’s Option 3 and noting that “[w]hile this option is already available under the Tariff, it was conceived for, and has been implemented for, substantially smaller loads (like a large warehouse with solar panels) and not on the scale of large data centers.”).
51  Id. at 35.
52  PSE&G Response at 13-14.

PDF page 12

12
observed, however, that “different co-location arrangements are likely to use or benefit from the transmission system in different ways depending on how they are configured and, moreover, that those different configurations will themselves likely have different impacts on the transmission system.”53 PSE&G has not demonstrated that large co- located data center loads that appear to be the focus of its discrimination concerns54 would be able to comply with the existing requirements for BTMG or that these loads would otherwise be similarly situated to load served by BTMG behind the load’s point of interconnection, particularly given PSE&G’s acknowledgement that there may be a variety of co-located load configurations.55

As a threshold matter, any co-located load claiming to be similarly situated to load served by BTMG must, at a minimum, be designated Network Load, as only Network Load is eligible for BTMG netting.56 The PJM Tariff also specifically defines BTMG as “a generation unit that delivers energy to load without using the Transmission System.”57 While PSE&G asserts that “[f]rom a technical perspective, there is no material distinction between a BTM load arrangement relative to a BTMG arrangement,”58 generating plants interconnected to the transmission system and serving large co-located loads rely on the transmission system to deliver energy to load in a manner that BTMG connected behind a load meter does not. For example, as Indicated PJM Transmission Owners observe,

53  Show Cause Order at P 76.
54  See, e.g., PSE&G Response at 2 (arguing for an approach that, inter alia, “preserves co-location as a viable option to support data center development in New Jersey and elsewhere in PJM”).
55  See, e.g., id. at 5. To the extent that participants in a co-located load arrangement believe it is eligible for netting under sections 34.2 and 34.3 of the PJM Tariff, they can seek to qualify under those provisions by meeting all the criteria. See Indicated PJM TOs Response, Attachment A at 4 n.6.
56  See, e.g., PJM Answer at 35 (“all load served by BTM Generation must be designated Network Load.”).
57  PJM, Tariff, Definitions A-B (emphasis added). 58  PSE&G Response at 15.

PDF page 13

13
nuclear units are required to be interconnected to the transmission grid, and, thus would necessarily rely directly on the transmission grid to serve co-located load.59 In contrast, as PJM notes, BTMG netting “was conceived for, and has been implemented for, substantially smaller loads (like a large warehouse with solar panels) and not on the scale of large data centers.”60 These on-site generators, the Commission agreed, do not rely on the integrated transmission system (or even the distribution system) to deliver energy to load.61 The Non-Retail BTMG provisions of the PJM Tariff were later adopted, as discussed above, in response to Commission concerns about treating distribution- connected generation differently than on-site generation, given that such generators also may not rely on the integrated transmission system to serve load.62 Indeed, BTMG may even be able to serve as a source of emergency backup generation during a grid outage. Thus, while, as Commissioner Rosner noted, new co-located load proposals may be the “inverse” of traditional BTMG arrangements,63 the Commissioner’s observation only serves to highlight that the arrangements are not the same, and, thus, may warrant different treatment.64 Regardless of whether the Commission agrees that co-located load arrangements should be entitled to some form of netting, however, the Commission should preserve the current BTMG and Non-Retail BTMG netting provisions in the PJM Tariff.

59  See Indicated PJM TOs Answer at 13.
60  PJM Answer at 13.
61  See, e.g., PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 at P 4.
62  PJM Interconnection, L.L.C., 112 FERC ¶ 61,034 at PP 15-19.
63  See PSE&G Response at 16 (citing Technical Conference Transcript at 14).
64  See also PJM Answer at 36.

PDF page 14

14
IV. CONCLUSION
WHEREFORE, for the foregoing reasons, American Municipal Power, Inc. respectfully asks the Commission to consider these comments in these dockets. Respectfully submitted,

/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com

/s/ Gerit F. Hull
Gerit F. Hull
Deputy General Counsel for
  Regulatory Affairs
American Municipal Power, Inc.
1111 Schrock Road, Suite 100
Columbus, OH 43229
(614) 540-1111
ghull@amppartners.org

April 23, 2025

PDF page 15

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary in these proceedings.

Dated at Washington, D.C., this 23rd day of April, 2025.

/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com