Response of American Municipal Power, Inc
Text extracted from the eLibrary original (SHA-256 017c7581adccec25…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.Read this passage
I. INTRODUCTION AND SUMMARY OF POSITION
printed heading · Topic match: Connecting load and generation
For purposes of the Show Cause Order, the Commission defines co-located load as “a configuration through which end-use customer load is physically connected to the facilities of an existing or planned generation unit on the interconnection customer’s side of the point of interconnection to the PJM…Read this passage Filed comments: Connecting load and generation
II. INTEREST OF AMP
printed heading
INTEREST OF AMP AMP is a nonprofit Ohio corporation with members in Delaware, Indiana, Kentucky, Maryland, Michigan, Ohio, Pennsylvania, Virginia, and West Virginia, the majority of which are load-serving entities within the PJM region.Read this passage
III. RESPONSE
printed heading
III.Read this passage
A. AMP supports the answer of the Indicated PJM Transmission Owners.
printed heading · Topic match: Connecting load and generation
Treating co-located load as Network Load or load served by Point-to-Point Service avoids unjust and unreasonable transmission cost-shifting,22 while promoting reliable transmission planning and resource adequacy.23 The responses filed by PJM and the Indicated PJM Transmission Owners do not support…Read this passage Filed comments: Connecting load and generation
B. The existing PJM Tariff provisions addressing BTMG netting should
printed heading · Topic match: Connecting load and generation
The Tariff, in turn, defines Non-Retail BTMG as “Behind the Meter Generation that is used by municipal electric systems, electric cooperatives, or electric distribution companies to serve load.” 7 BTMG is not considered Network Load; the relevant netting provisions are only available to Network…Read this passage Filed comments: Connecting load and generation
IV. CONCLUSION
printed heading
CONCLUSION WHEREFORE, for the foregoing reasons, American Municipal Power, Inc. respectfully asks the Commission to consider these comments in these dockets.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 23rd day of April, 2025. /s/ John McCaffrey John McCaffrey Stinson LLP 1775 Pennsylvania Avenue NW Suite 800 Washington, DC 20006 (202) 728-3026 john.mccaffrey@stinson.comRead this passage