EL25-49-000 · 2025-04-23 · Exelon Corporation, American Electric Power Service Corporation and 17 others
Answer of the Indicated PJM Transmission Owners in response to PJM Interconnection, L.L.C.'s 03/24/2025 Answer, et al
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
Large Loads Co-Located at Generating
Facilities
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
Docket No. EL25-20-000
(consolidated)
ANSWER OF THE INDICATED PJM TRANSMISSION OWNERS
Pursuant to Rules 212 and 2131 of the Rules of Practice and Procedure of the Federal
Energy Regulatory Commission (“FERC” or “Commission”) and the Commission’s Show Cause
Order,2 the Indicated PJM Transmission Owners (hereinafter, “Indicated TOs”)3 submit this
1 18 C.F.R. §§ 385.212, 385.213 (2024).
2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at Ordering Paragraph (D) (2025) (“Show Cause Order”).3 The Indicated PJM Transmission Owners include: American Electric Power Service Corporation, on behalf of Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; AMP Transmission, LLC; City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Corporation on behalf of its affiliates Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and Duke Energy Business Services LLC; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation, on behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans- Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”); Old Dominion Electric Cooperative; PPL Electric Utilities Corporation; Rockland Electric Company; Southern Maryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc.
PDF page 2
2
Answer to the March 24, 2025 Answer of PJM Interconnection, L.L.C., the March 24, 2025 Answer of Public Service Electric and Gas Company, and the April 4, 2025 Motion for Clarification of Vistra Corp. Paragraph 87 of the Show Cause Order and the Commission’s Ordering Paragraph (D) permit responses by “[i]nterested entities” within “30 days of PJM’s . . . filing.”4
The record in this proceeding demonstrates that the existing PJM Interconnection, L.L.C. (“PJM”) Open Access Transmission Tariff (“PJM Tariff”) remains just and reasonable and that co- located load is Network Load that uses and relies on the transmission system and should pay for transmission service, and other PJM services. While no changes to the existing PJM Tariff are necessary, to the extent FERC believes it would provide helpful clarity, the Indicated TOs recommend adopting a proposed definition of co-located load clarifying that it is Network Load, so that all parties may proceed with the timely interconnection of co-located arrangements based on clear and common understanding of the applicable rates for service. The definition proposed in the Indicated TOs’ initial response accomplishes that goal.
I. Because the Requisite Showing Has Not Been Made Under Federal Power Act
Section 206, the Commission Should Terminate the Show Cause Proceeding and
Reaffirm that the Existing PJM Tariff Is Just and Reasonable.
The record in this proceeding demonstrates that the existing PJM Tariff is just and reasonable. Consequently, the legally proper course of action is for the Commission to terminate this Federal Power Act (“FPA”) section 206 proceeding. The Commission should act promptly to provide interested stakeholders much needed and much desired certainty.
4 Show Cause Order, 190 FERC ¶ 61,115 at P 87; see also id. at Ordering Paragraph (D).
PDF page 3
3
a. The Existing PJM Tariff Is Just and Reasonable.
PJM—the administrator of the PJM markets and the PJM Tariff—and virtually all of the PJM transmission owners, including investor-owned utilities, municipalities, and cooperatives, are in agreement: the “existing Tariff remains just and reasonable.”5 As PJM explains, “[t]he Tariff today permits co-located loads to interconnect through existing load interconnection processes.”6 Those end-use load connection processes, governed by the states and fully consistent with the PJM Tariff, are available to all, and those processes work. Moreover, the transmission service provided to co-located load under the PJM Tariff is available to all on a non-discriminatory basis. Nowhere in the record is there an allegation—let alone evidence—that the current PJM Tariff impedes the development of or service to any load, co-located or otherwise. Therefore, there is no basis to alter the existing PJM Tariff under section 206 of the FPA.
In a proceeding under section 206 of the FPA, the Commission can only remedy a “rate [or] charge” or “any rule, regulation, practice, or contract affecting such rate [or] charge” after it is found to be “unjust [or] unreasonable.”7 “The burden of proving an unjust or unreasonable rate rests with the party that initiated the proceeding—the Commission [(as in this case)] or the third- party complainant.”8 Only after a successful showing that the prevailing rate is unjust and unreasonable may the Commission order a replacement rate.9 No such showing has been made here.
5 Answer of PJM Interconnection, L.L.C. at 4 (Mar. 24, 2025) (“PJM Answer”); see also id. at 32 (“PJM’s Tariff remains just and reasonable.”).6 Id. at 32.7 16 U.S.C. § 824e(a).8 Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021).9 16 U.S.C. § 824e(a).
PDF page 4
4
Although some entities “may prefer, for their own business reasons, alternative pathways
to co-location,” business preferences “do not render the [PJM] Tariff unjust and unreasonable.”10 Nor should PJM develop its rules addressing co-located load specifically to appease or conform to a particular entity’s business model. As the Indicated TOs explained in their Answer, the PJM Tariff already has mechanisms to allow co-located load to connect to the grid and ensure that, as Network Load, these co-located loads pay for their share of grid services.11 Indeed, PJM’s Answer emphasizes the numerous ways in which the existing PJM Tariff ensures just and reasonable rates for co-located loads. As the Indicated TOs explained, and PJM further validated in its answer, PJM’s Tariff remains just and reasonable because “co-located load is interconnected with the grid and relies on the grid.”12 Just like every other load, those loads connect to and receive service from PJM’s transmission system and there is no indication that the PJM Tariff’s construct does not work. Significantly, PJM agrees.13
While one transmission owner suggests otherwise, citing what it characterizes as
Commission “skepticism” that existing provisions of the PJM Tariff are appropriate for all types
10 PJM Answer at 32.11 See Indicated TOs Answer at 14–17 (Mar. 24, 2025). In appropriate circumstances, the PJM Tariff may alternatively permit Point-to-Point Service as an option.12 Id. at 13.13 See PJM Answer at 4, 32 (stating that the PJM Tariff “remains just and reasonable”); see also id. at 38 (“PJM continues to prefer that co-location arrangements be designated ‘Network Load’ in front of the meter.”); id. at 44 (“Absent an arrangement where both the load and the generator are completely isolated and physically disconnected from the grid, (a situation which is very different from the claimed ‘totally isolated’ configuration offered by some in these proceedings), PJM is not aware of a configuration that would ‘ensure the co-located load never takes any form of transmission service.’ As noted above, grid-connected facilities benefit from their connection and should pay for grid services consumed.”).
PDF page 5
5
of co-located load configurations,14 “skepticism” is not the standard of proof under section 206 of the FPA. The standard is whether the existing PJM Tariff is unjust and unreasonable—a showing that has not been satisfied.
b. Behind the Meter Generation Is Not Similarly Situated to Co-Located Load.
Although the vast majority of PJM transmission owners, including traditional transmission owners, municipalities and cooperatives are aligned, a single transmission owner also claims that “[a]n approach that aligns with cost causation principles is one that treats all co-located customers as [Network Integration Transmission Service] customers with netting rules applied” and that “this is the current construct for [Behind the Meter Generation (“BTMG”)] customers under the PJM Tariff.”15 Notwithstanding this allegation, the two configurations—BTMG and co-located load— remain distinct. Accordingly, reference to behind the meter generation is wholly inapposite to the co-located load inquiry here.
Netting is permitted under the PJM Tariff for BTMG when load takes Network Integration
Transmission Service (“Network Service”) from a network service customer and the load has its own generator.16 Netting occurs when a generator provides power directly to a load and the billing determinant used to compute the Network Service costs for that network load is reduced by the quantity of power consumption offset by its BTMG. By way of example, electric cooperatives in
14 Response of Public Service Electric and Gas Company to the Order to Show Cause at 10 (Mar. 24, 2025) (“PSEG Answer”) (alleging that “[i]t is telling that the Commission acknowledged that while PJM’s preference is that ‘large loads be in front of the meter and designated as PJM Network Load,’ the Commission stated that the PJM Tariff does not appear to require this service” and that the “Commission expressed skepticism that this is the appropriate type of transmission service that should be required of all co-located configurations”).15 Id. at 13.16 PJM OATT, Section 34.2, Netting of Behind the Meter Generation (“The daily load of a Network Customer does not include load served by operating Behind The Meter Generation. The daily load of a Network Customer shall not be reduced by energy injections into the transmission system by the Network Customer.”).
PDF page 6
6
particular use BTMG including certain diesel generating facilities to serve load and rely on the PJM Tariff provisions that provide for netting of this BTMG for purposes of charges for Network Service and other services used to facilitate the public utility service they provide. Co-located load is distinct from BTMG. Were co-located load netted against generation it would not be measured as load even though it uses the transmission system. The PJM Tariff provisions on BTMG define it as follows:
“Behind The Meter Generation” shall refer to a generation unit that
delivers energy to load without using the Transmission System or
any distribution facilities (unless the entity that owns or leases the
distribution facilities has consented to such use of the distribution
facilities and such consent has been demonstrated to the satisfaction
of the Office of the Interconnection); provided, however, that
Behind The Meter Generation does not include (i) at any time, any
portion of such generating unit’s capacity that is designated as a
Generation Capacity Resource; or (ii) in an hour, any portion of the
output of such generating unit that is sold to another entity for
consumption at another electrical location or into the PJM
Interchange Energy Market.17
Because the record in this proceeding is clear that co-located load arrangements do use the transmission system, they cannot qualify as BTMG. Service to co-located load using generators connected to the transmission system inherently both use and rely on the transmission system.18 Treating co-located load similarly to BTMG would result in “the costs assessed” not “bear[ing] some resemblance ‘to the burdens imposed or benefits drawn by that party.’”19 To
17 PJM OATT, Section 1 (Definitions).18 See, e.g., Declaration of David Weaver, PE at PP 10–24, Attach. 1 to Exelon Comments, Docket No. EL25-20 (Dec. 12, 2024) (“Weaver Decl.”); see also, e.g., id. P 17 (explaining that because nuclear units are unable to provide black start services, co-located load must rely on those services from other resources in PJM that are connected to the grid in order to come back online); id. P 19 (explaining that the co-located load will take service that is dependent “on a strong interconnection with the grid that is supported by reactive power, operating reserves, and black start”). 19 Pub. Serv. Elec. & Gas Co. v. FERC, 989 F.3d 10, 13 (D.C. Cir. 2021) (quoting Midwest ISO Transmission Owners
v. FERC, 373 F.3d 1361, 1368–69 (D.C. Cir. 2004)).
PDF page 7
7
afford similar treatment would be to grant an undue preference to such configurations over others that also rely upon Network Service.20 Just like all other loads, Network Service should be paid when there is co-located load. To restate: the PJM Tariff and Order No. 888’s pro forma open access transmission service tariff contemplate two types—and only two types—of service: (1) Network Service for general network service; and (2) Point-to-Point Transmission Service (“Point- to-Point Service”) for wheeling. As PJM itself has stated, if you are looking to serve co-located load, Network Service is the correct service to take under the Tariff.21
BTMG and co-located load are not similarly situated. As PJM explains, BTMG was conceived for, and has been implemented for, substantially smaller loads.22 Under the PJM Tariff, co-located load is Network Load and should be in front of the meter. The majority of the transmission owners in PJM, inclusive of investor-owned utilities, municipalities, and cooperatives, remain aligned that treating co-located load as Network Load is essential for reliability, transmission planning, PJM’s procurement of adequate capacity, and appropriate cost- allocation.23
The notion that “the data center load could be structured on a front of the meter basis with the co-located generator providing primary power and with back-up power coming from the grid; or the data center load could be fully isolated behind the meter with system protection facilities in
20 See 16 U.S.C. § 824d(b) (“No public utility shall, with respect to any transmission or sale subject to the jurisdiction of the Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”).21 See PJM Answer at 38.22 Id. at 13.23 Cf. id. at 39 n.64.
PDF page 8
8
place to ensure that there is no flow of power from the grid to the load”24 is, at best, inaccurate. As explained by the Indicated TOs, there is no such thing as data center load configured to be “fully isolated” behind the meter through “system protection facilities,” because co-located load that is connected to the electric grid (a) necessarily relies on reliability services, such as ancillary services, including black start; (b) retains the potential to draw real or reactive power from the grid at any time; and (c) relies on and benefits from its connection to the transmission system at all times.25 In other words, there is no such thing as a co-located configuration, connected to and synchronized with the electric grid, that is “fully isolated.” While protection systems may serve important roles, they do not isolate the load from the grid, and the grid must be maintained—with the attendant costs—to accommodate this reality.
Indeed, PJM has recognized this, stating that it
objects to the [Commission’s] use of the phrase “wholly isolated
from the grid” [in a question] as it is contrary to engineering and
economic principles. The notion that any of the proposed co-
location arrangements can be “wholly isolated” is misleading. The
load and generator are connected to and synchronized with the
multi-state bulk power system. It is not operating as a micro grid
(nor can it if the generating facility is a nuclear unit). Nor is the
generator delivering power through an intermediary to a load with a
breaker open. Further, by way of example, there are obligations to
ensure power to nuclear plants to ensure safe shutdown (among
other things). The load and generator are benefiting from ancillary
services (including but not limited to black start). Any system
protection facilities are designed to only handle less complex N-1
conditions, and can misoperate (and indeed have misoperated).2624 PSEG Answer at 11.25 See Indicated TOs Answer, Attach. (A) at 4–5.26 PJM Answer at 42–43.
PDF page 9
9
PJM also explained that,
[a]bsent an arrangement where both the load and the generator are
completely isolated and physically disconnected from the grid, (a
situation which is very different from the claimed “totally isolated”
configuration offered by some in these proceedings), PJM is not
aware of a configuration that would “ensure the co-located load
never takes any form of transmission service.” As noted above,
grid-connected facilities benefit from their connection and should
pay for grid services consumed.27
In other words, transmission services are being provided to and relied upon by the co-located load whether or not it is behind the meter. The PJM Tariff allows for service to co-located load as Network Service. Such treatment is needed in order to ensure reliability, effective transmission planning, procurement of adequate capacity, and proper cost allocation.
II. No Replacement Rate Is Necessary or Appropriate Under FPA Section 206.
a. PJM’s Potential Options Are Unnecessary to Resolve the Show Cause
Proceeding.
The Indicated TOs appreciate PJM laying out several “potential options for additional large load co-location.”28 However, it is important to emphasize that the mere presentation of potential options does not establish that the existing PJM Tariff is unjust and unreasonable and therefore cannot be the basis upon which to impose a replacement rate. In this case, moreover, the options are not of all one kind—some are fully available options now; others are not practical. In fact, four of the eight—options 1, 2, 3, and 8 (described below)—are currently available without any
27 Id. at 44.28 Id. at 5.
PDF page 10
10
changes to the existing PJM Tariff.29 In contrast, the record in this proceeding demonstrates that the potential options that would require changes to the PJM Tariff are unnecessary and have not been shown to be just and reasonable. Therefore, no changes to the PJM Tariff may be directed under FPA section 206 in this docket. Indeed, PJM itself asserts that its tariff “remains just and reasonable.”30
The potential options PJM presents are as follows:
1. Load with a separate Point of Interconnection that is Network Load and the load uses and pays for Network Service, Energy, Ancillary Services, and Capacity.
2. Co-located load that is at the same Point of Interconnection but separately metered that is Network Load and the load uses and pays for Network Service, Energy, Ancillary Services, and Capacity. Additionally, the large load is studied and could be connected to the grid pursuant to the existing Transmission Owner/electric distribution company (“EDC”) load interconnection process.
3. Existing BTMG where the load is the customer, the BTMG rules apply, and the load uses and pays for Network Service, Energy, Ancillary Services, and Capacity based on the net withdrawal quantity and dependent on if that withdrawal is during the Peak.
4. Co-located load with connection to the grid with protections to avoid delivery of system energy to serve the load, but relies on and takes grid services such as ancillary services and should pay its fair share of those charges, and carries a risk that should system protections fail, significant energy would be drawn from the system.
29 PJM asserts that three of the options “already exist under PJM’s Tariff.” Id. Of course, only those that meet the tariff criteria would be eligible for the options. For example, to participate in a demand response program, the load would need to satisfy the various tariff criteria for demand response.30 Id. at 4, 32.
PDF page 11
11
5. Co-located load with connection to the grid with protections to avoid delivery of system energy to load (same as option 4) but allowed to use back-up service from PJM with permission. Like option 4, it relies on and takes grid services such as ancillary services and should pay its fair share of those charges, and carries a risk that should system protections fail, significant energy would be drawn from the system.
6. Co-located load that elects to be Network Load and bring its own generation where large load additions interconnecting as Network Load could also bring to PJM
additional generation that could serve as Capacity Resources.
7. Potential new non-capacity backed service as a Transitional Service, with a co-location configuration where load is curtailable.
8. Co-located load participating in Demand Response, where load is Network Load and participates as a Demand Response resource.
PJM’s options reinforce the straightforward conclusion that the existing PJM Tariff is just and reasonable. Options 1, 2, 3, and 8 all lay out fact patterns for load that meets the needs identified in this docket for co-located load. Options 1 and 2 make clear that the addition of load at or near generation, whether or not it shares the same points of interconnection as a generator, can be accomplished quickly and easily. The load simply needs to agree to pay for the services that all load receives and take service as Network Load. No tariff amendments are needed to add load to the system. Some commenters have claimed that netting load and generation that share an interconnection is an important option for co-located load.31 Indeed, Option 3 demonstrates that a path to netting exists under the PJM Tariff, if in fact the particular arrangement has been configured
31 See PSEG Answer at 13.
PDF page 12
12
so that it does qualify as BTMG, as defined under the PJM Tariff. Other entities have argued that co-located load can provide benefits to the system by relying on back-up generation or otherwise leaving the system under certain circumstances. As Option 8 shows, demand response is a well- established regime for compensating load that agrees not to call on the system when required. No new tariff provisions are needed to accomplish that goal.
PJM’s options make clear the high burden presented by FPA section 206 is not met here. For example, if co-located load wishes to be compensated for being interruptible, at the transmission level,32 advocates of that position need to show why that outcome is the correct rate design and why the current demand response rules fail to adequately compensate load appropriately. Such a showing has not been made for any of the currently available Tariff options. Accordingly, PJM’s potential options that would require changes to the PJM Tariff do not present a viable replacement rate, and PJM has not argued otherwise. Indeed, PJM notes that it “does not mean to suggest that all identified ‘options’ . . . are equivalent, desirable, or even necessarily workable.”33
b. Changes to the PJM Tariff May Undercut Reliability.
The North American Electric Reliability Corporation (“NERC”) has warned of impending reliability challenges that will attend the increased demand growth in PJM.34 This is important because the reasonableness of a rate, including any replacement rate set under FPA section 206, “is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and
32 States, which regulate the general terms and conditions governing service to co-located end-use load, can and do offer optional or mandatory interruptible service rates.33 PJM Answer at 5.34 See Indicated TOs Answer at 3–4 (discussing NERC’s 2024 Long-Term Reliability Assessment).
PDF page 13
13
developing plentiful energy supplies.”35 To treat co-located load as anything other than Network Load would increase the risk of reliability failures and resource inadequacy in PJM. As PJM explained in its filing, “[i]f the co-located load is PJM Network Load, PJM and the Transmission Owners have means through existing Tariff provisions and agreements to obtain the information to have both sufficient visibility and sufficient control of this load and ensure the load could be served reliably without compromising overall system reliability.”36 When co-located load is hidden and not appropriately accounted for, however, there is not only a cost-allocation problem, but the study process is undermined and, consequently, PJM may be unable to adequately procure enough capacity to serve the load because the full load will not be accounted for in the Reliability Pricing Model. Nor would the full load be reliably and safely factored into both PJM’s transmission planning and operations processes and protocols.
The Commission must prioritize the safety and reliability of the electric grid. c. The Potential Options that Require Changes to the PJM Tariff Would Slow
Data Center Development, the Opposite of What the Commission Should
Encourage.
As PJM and the Indicated TOs have asserted, the PJM Tariff remains just and reasonable, and no party has shown that the existing PJM Tariff is unjust and unreasonable. As such, the Commission has no basis under FPA section 206 to implement any proposed changes to the PJM Tariff. Moreover, recognizing that several of PJM’s proposed options are wholly consistent with the existing PJM Tariff further supports the Commission in providing additional guidance and
35 Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022).36 PJM Answer at 61.
PDF page 14
14
certainty through an order either stating affirmatively that is the case or simply terminating this proceeding.37
The need to provide power to large load customers is clear and the best way to promote co- located large load customers is to provide all stakeholders—inclusive of customers, EDCs/load serving entities, transmission owners, and investors—with certainty, which the Commission can quickly accomplish by clarifying that co-located loads should seek service under the well- established, just and reasonable terms of the existing PJM Tariff. It is also worth noting that any attempt to change the PJM Tariff would likely stymie data-center development, as such hypothetical new terms would require development through the PJM stakeholder process followed by Commission consideration and acceptance. But no new terms are required. The PJM Tariff already allows co-located load to interconnect to the grid and rely on the grid as Network Load. State-jurisdictional special contracts or rates can continue to provide other financial benefits to the co-located load. But pursuing drastic changes to the PJM Tariff will only increase uncertainty— not just about the development of infrastructure for large load customers but about the future of the very grid that desperately needs development, a task that is only made more difficult when certainty and regulatory clarity are undermined. Not even PJM knows how its options would be affected by other provisions of the PJM Tariff. As noted above, by its own admission, PJM’s proposed new options have not been vetted to determine if they are “desirable, or even necessarily workable.”3837 As explained above, to the extent to which the Commission thinks it would be helpful to have further clarity in the PJM Tariff, the Indicated TOs suggest considering whether the addition of their proposed co-located load definition would improve the PJM Tariff.38 Id. at 5.
PDF page 15
15
III. Vistra’s Motion for Clarification Should Be Denied.
On April 4, 2025, Vistra filed a Motion for Clarification and Request for Expedited Treatment. Vistra seeks the Commission’s interpretation of its order issued in November 2024 in Docket No. ER24-2172 (“Susquehanna ISA Proceeding”).39 According to Vistra, there is confusion on the scope and holding of the Susquehanna ISA Order. The Commission should reject Vistra’s motion.
In the Susquehanna ISA Proceeding, the Commission rejected the amended
interconnection agreement between Susquehanna Nuclear LLC, PJM, and PPL Electric Utilities Corporation because the Commission found that “PJM has not demonstrated that the proposed non-conforming provisions in the Amended ISA are necessary deviations from the pro forma ISA due to specific reliability concerns, novel legal issues, or other unique factors.”40 On April 10, 2025, the Commission issued in Docket No. ER24-2172, an Order Addressing Arguments on Rehearing and Granting Clarification, In Part.41 Therein, the Commission addressed Vistra’s request for clarification in the Susquehanna ISA Proceeding. In Susquehanna ISA Rehearing Order, the Commission clarified that it “uses the necessary standard . . . to determine whether the filing of a non-conforming agreement is justified” and that the Susquehanna ISA Order “does not prevent entities from filing non-conforming interconnection agreements to address matters related to a generator serving co-located load, or prejudge any such future filing.”4239 PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024) (“Susquehanna ISA Order”).40 Id. P 85.41 PJM Interconnection, L.L.C., 191 FERC ¶ 61,025 (2025) (“Susquehanna ISA Rehearing Order”).42 Id. P 30.
PDF page 16
16
Therefore, Vistra’s request for clarification has been addressed and the April 4th motion submitted in this proceeding is moot.
No further clarification is needed in this proceeding. Any attempt by Vistra to seek further clarification in this proceeding would amount to Vistra asking the Commission to tell PJM to alter its view on what is permissible under the PJM Tariff. That is not an appropriate basis for the Commission to grant its motion for clarification in the instant proceeding.
IV. Conclusion
For the reasons stated above, the Indicated TOs respectfully request that the Commission find that the existing PJM Tariff is just and reasonable, that co-located load can be served with the existing forms of transmission service in the PJM Tariff, and that the Commission accordingly terminate this FPA section 206 proceeding and the above-captioned dockets.
Respectfully submitted,
/s/ William Sauer
William Sauer
Vice President, Federal Regulatory Affairs
Exelon Corporation
701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-868-7499
Email: william.sauer@exeloncorp.com
/s/ Max Minzner
Max Minzner
Vice President and Deputy General Counsel
Exelon Corporation
701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-934-4740
Email: max.minzner@exeloncorp.com
On behalf of Exelon Corporation
PDF page 17
17
/s/ Jessica Cano
Jessica Cano
Assistant General Counsel - FERC
American Electric Power Service Corporation 1 Riverside Plaza
Columbus, OH 43215
Telephone: 614-716-2921
Email: jacano@aep.com
/s/ Lisa G. McAlister
Lisa G. McAlister
AMP Transmission, LLC
1111 Schrock Road, Suite 100
Columbus, Ohio 43229
Telephone: 614-540-6400
Email: lmcalister@amppartners.org
On behalf of American Electric Power
Service Corporation
On behalf of AMP Transmission, LLC
/s/ Martin J. Keane
Martin J. Keane
Director of Public Utilities
Cleveland Public Power
1300 Lakeside Ave.
Cleveland, OH 44114
Telephone: 216-664-2444 ext. 75604
Email: martin_keane@clevelandwater.com
/s/Debra D. Roby
Debra D. Roby
Washington Energy Law LLP
900 17th Street N.W., Suite 500-A
Washington, D.C. 20006
Telephone: 703-785-9270
Email: droby@washingtonenergylaw.com
On behalf of City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power
On behalf of the City of Hamilton, OH
/s/ Wesley Walker
Wesley Walker
Senior Assistant General Counsel
Dominion Energy Services, Inc.
120 Tredegar Street
Richmond, VA 23219
Telephone: 804-819-2345
Email: wesley.walker@dominionenergy.com
/s/ Molly Suda
Molly Suda
Associate General Counsel
Annelise Rickert
Federal Government Affairs Director
Duke Energy Corporation
1301 Pennsylvania Ave NW, Suite 200
Washington, DC 20004
Telephone: 202-824-8011
Email: molly.suda@duke-energy.com
Annelise.rickert@duke-energy.com
On behalf of Dominion Energy
On behalf of Duke Energy
PDF page 18
18
/s/ Michael Brechlin
Michael Brechlin
PA Bar # 335424
Duquesne Light Company
411 7th Ave
Pittsburgh, PA 15219
Telephone: 412-393-6431
Email: mbrechlin@duqlight.com
/s/ Amanda P. Parker
Amanda P. Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OH 44308
Telephone: (330) 384-4592
Email: aparker@firstenergycorp.com
On behalf of Duquesne Light Company On behalf of The FirstEnergy Transmission Companies
/s/ Denise R. Foster Cronin
Denise R. Foster Cronin
Vice President, Federal and RTO Regulatory Affairs
East Kentucky Power Cooperative, Inc. 4775 Lexington Road, P.O. Box 707
Winchester, KY 40392-0707
Telephone: 859-745-9615
Email: denise.cronin@ekpc.coop
/s/ Daniel E. Frank
Daniel E. Frank
Kelly Cuthbertson
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Telephone: 202-383-0100
Email:
danielfrank@eversheds-sutherland.com kellycuthbertson@eversheds-sutherland.com
On Behalf of East Kentucky Power
Cooperative, Inc.
/s/ Adrienne E. Clair
Adrienne E. Clair
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C. 20006-1167
Telephone: 202-585-6900
Email: aclair@thompsoncoburn.com
/s/ Steve Nadel
Steven M. Nadel
Senior Counsel
PPL Services Corp.
645 Hamilton Street, Suite 601
Allentown, PA 18101
Telephone: 610-774-4775
Email: SMNadel@pplweb.com
On behalf of Old Dominion Electric Cooperative
On behalf of PPL Electric Utilities Corp.
PDF page 19
19
/s/David Burns
David Burns
Senior Manager,
FERC Policy & Regulatory Affairs
Consolidated Edison Company of New York, Inc.
4 Irving Place
New York, NY 10003
Telephone: 571-678-9152
Email: burnsd@coned.com
/s/Joshua Kirstein
Joshua A. Kirstein
Senior Attorney
Law Department
Consolidated Edison Company of New York, Inc.
4 Irving Place, 18th Floor
New York, NY 10003
Telephone: 929-656-5971
Email: kirsteinj@coned.com
On behalf of Rockland Electric Company
/s/ Damon L. Krieger
Damon L. Krieger
Group Vice President, Legal, Strategy, and Sustainability, and Deputy General Counsel Southern Maryland Electric Cooperative, Inc. 15035 Burnt Store Road
P.O. Box 1937
Hughesville, Maryland 20637-1937
Telephone: 301-274-4323
Email: Damon.Krieger@SMECO.coop
/s/ Jeremy L. Fetty
Jeremy L. Fetty
Parr Richey
251 N. Illinois, Suite 1800
Indianapolis, Indiana 46204
Telephone: 317-269-2500
Email: j_fetty@wvpa.com
On behalf of Southern Maryland Electric Cooperative
On behalf of Wabash Valley Power
Association, Inc.
/s/ Lindsay Berkstresser
Lindsay Berkstresser
Counsel – Energy & Regulatory
UGI Corporation
500 North Gulph Road
King of Prussia, PA 19406
Telephone: 717-504-9925
Email: berkstresserl@ugicorp.com
/s/ Richard P. Bonnifield
Richard P. Bonnifield
Husch Blackwell
1801 Pennsylvania Avenue, NW,
Suite 1000
Washington, DC 20006-3606
Telephone: 202-243-8844
Email:
richard.bonnifield@huschblackwell.com
On behalf of UGI Utilities Inc.
April 23, 2025
PDF page 20
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list in the above captioned dockets. Dated at Chicago, IL this 23rd day of April, 2025.
/s/ Geneva Kennedy
Geneva Kennedy
Exelon Corporation