Answer of the Indicated PJM Transmission Owners in response to PJM Interconnection, L.L.C.'s 03/24/2025 Answer, et al
Text extracted from the eLibrary original (SHA-256 360fd8f14f52c611…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Filing procedure · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
While no changes to the existing PJM Tariff are necessary, to the extent FERC believes it would provide helpful clarity, the Indicated TOs recommend adopting a proposed definition of co-located load clarifying that it is Network Load, so that all parties may proceed with the timely interconnection…Read this passage Filed comments: Connecting load and generation
I. Because the Requisite Showing Has Not Been Made Under Federal Power Act
printed heading · Topic match: Connecting load and generation
P 17 (explaining that because nuclear units are unable to provide black start services, co-located load must rely on those services from other resources in PJM that are connected to the grid in order to come back online); id.Read this passage Filed comments: Connecting load and generation
II. No Replacement Rate Is Necessary or Appropriate Under FPA Section 206.
printed heading · Topic match: Connecting load and generation
The Commission must prioritize the safety and reliability of the electric grid. c.Read this passage Filed comments: Connecting load and generation
III. Vistra’s Motion for Clarification Should Be Denied.
printed heading · Topic match: Filing procedure
ER24-2172, an Order Addressing Arguments on Rehearing and Granting Clarification, In Part.41 Therein, the Commission addressed Vistra’s request for clarification in the Susquehanna ISA Proceeding.Read this passage Filed comments: Filing procedure
IV. Conclusion
printed heading · Topic match: Connecting load and generation
Conclusion For the reasons stated above, the Indicated TOs respectfully request that the Commission find that the existing PJM Tariff is just and reasonable, that co-located load can be served with the existing forms of transmission service in the PJM Tariff, and that the Commission accordingly…Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Dated at Chicago, IL this 23rd day of April, 2025. /s/ Geneva Kennedy Geneva Kennedy Exelon CorporationRead this passage