EL25-49-000 · 2025-04-23 · Enchanted Rock, LLC

Response of Enchanted Rock, LLC on the Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
Large Loads Co-located at Generating
Facilities
)
)
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC
     v. PJM Interconnection, L.L.C.
)
)
)
)
Docket No. EL25-20-000
(consolidated)
RESPONSE OF ENCHANTED ROCK, LLC
Enchanted Rock, LLC (“Enchanted Rock”) submits this response (“Response”) in connection with the Federal Energy Regulatory Commission (“Commission”)’s February 20, 2025 “Order Instituting Proceeding under Section 206 of the Federal Power Act and Consolidating with Other Proceedings.”1  In the Show Cause Order, the Commission directed PJM Interconnection, L.L.C. (“PJM”) and the PJM transmission owners to show cause as to why the PJM Open Access Transmission Tariff, the Amended and Restated Operating Agreement of PJM, and Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (together, the “Tariff”)2 remains just and reasonable and not unduly discriminatory or preferential, or explain what changes to the Tariff would remedy the identified concerns if the Commission were to determine that the Tariff has become unjust and unreasonable or unduly discriminatory or preferential and establish a replacement Tariff.3

Enchanted Rock submits this response in accordance with the Commission’s directive in the Show Cause Order providing that interested entities may respond within 30 days of the show cause filings to address whether the Tariff remains just and reasonable and not unduly

1 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).
2 Capitalized terms not otherwise defined herein have the same meaning as in the Tariff.
3 See Show Cause Order at P 2.

PDF page 2

2
discriminatory or preferential, and if not, what changes to the Tariff should be implemented as a replacement rate.4

Enchanted Rock’s microgrids and state-of-the-art gas generators provide continuous, dependable power supply to customers including manufacturing facilities, data centers, hospitals, water utilities, and other critical infrastructure.  Enchanted Rock submitted post-technical conference comments in AD24-11-0005 and appreciates the opportunity to further comment on co-location solutions to grid and resource adequacy challenges in PJM.

As further described below, Enchanted Rock offers an additional option6 to facilitate co- location arrangements, which Enchanted Rock refers to herein as the Load Co-located with Dispatchable Generation (“LCDG”) option.  Although the LCDG option is different than the New Options proposed by PJM, the LCDG option shares characteristics similar to New Options

6 and 7.  Changes to the Tariff are necessary to effectuate the LCDG option and, therefore, Enchanted Rock respectfully submits that PJM’s existing Tariff is not just and reasonable.7 Enchanted Rock requests that the Commission issue an order directing replacement tariff provisions that allow customers in PJM to realize the benefits of LCDG as a co-location option. To the extent the Commission determines that further proceedings—either before the Commission, or as part of PJM’s stakeholder process—are needed before directing any changes to PJM’s Tariff, Enchanted Rock is committed to working collaboratively with PJM and stakeholders to develop such necessary changes to the Tariff.8
4 See Show Cause Order at Ordering Para (D). 5 Post-Technical Conference Comments of Enchanted Rock, LLC, Docket No. AD24-11-000 (Dec. 9, 2024) (“Post- Tech. Comments”). 6 PJM presented eight existing or new co-location options (“New Options”).  See Answer of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Mar. 24, 2025) (“PJM Answer”).
7 In support of the LCDG option, Enchanted Rock presents the Affidavit of Dr. Albert W. Bremser, included herewith as Attachment A (“Bremser Affidavit”).  See Bremser Affidavit ¶¶ 9-20.
8 Enchanted Rock, through its subsidiary Electranet REP I, LLC, is a member of PJM and participates through the Other Supplier sector.

PDF page 3

3
I. INTRODUCTION AND NEED FOR REFORM
The United States stands at the precipice of an unprecedented surge in electricity demand from large loads including data centers and large industrial and manufacturing facilities.9 Extraordinary load growth is fueled mostly by the proliferation of data centers that support artificial intelligence, cloud computing, and other services.  Over the next 15 years, PJM anticipates significant peak demand growth, with the summer peak rising by roughly 70 gigawatts (“GW”), and the winter peak rising by roughly 65 GW.10  Enchanted Rock understands that securing a global competitive advantage in artificial intelligence is a U.S. priority and that maintaining data centers within U.S. borders is a critical national security interest.11  These extraordinary changes in demand require federal and state regulators, grid operators, market participants, and customers to pivot and look to innovations that optimize infrastructure without creating new reliability risks—particularly during periods when new generation capacity and transmission infrastructure is planned, permitted, and constructed.  The accelerating demand for electricity coupled with supply delays caused by lengthy permitting processes for generation and transmission infrastructure, as well as persistent supply chain delays for equipment, means the industry must devise immediately implementable solutions that optimize existing infrastructure and ensure that transmission expansion occurs in the most cost-effective way possible.

9 See Large Loads Co-Located at General Facilities Technical Conference Transcript, Docket No. AD24-11-000, 10:25 – 11:6 (Nov. 1, 2024) (“Technical Conf. Tr”) (Commissioner Christie stating “we’re seeing load forecasts shooting up . . . driven by data centers”).
10 See Asim Z. Haque, Sr. Vice President – Governmental and Member Services, PJM Interconnection, L.L.C., Testimony before the U.S. House of Representatives, Committee on Energy & Commerce, Subcommittee on Energy (Mar. 5, 2025), available at: https://www.pjm.com/-/media/DotCom/library/reports- notices/testimony/2025/20250305-haque-testimony-us-house-committee-on-energy-commerce.pdf.
11 See Energy Subcommittee: “Scaling for Growth: Meeting the Demand for Reliable, Affordable Electricity” https://energycommerce.house.gov/events/energy-subcommittee-scaling-for-growth-meeting-the-demand-for- reliable-affordable-electricity (Rep. Gary Palmer (R-AL) stating “My concern today is we’re in an arms race for artificial intelligence,” “And it’s clear we don’t have the capacity to build the data systems that we need in order to win that arms race with China.”).

PDF page 4

4
The Commission has already started work—issuing landmark rulemakings to improve the nation’s generator interconnection processes (via Order No. 202312), regional transmission planning and cost allocation processes (via Order No. 192013), siting interstate electric transmission facilities (via Order No. 197714), and increasing transmission capacity through ambient-adjusted transmission facility ratings (via Order No. 88115).  However, the full benefits of these rules have not yet been realized and will not be enough in the time horizon needed to support interconnection of, and service to, large loads.  Even with new procedures to secure needed generation capacity through surplus interconnection and expedited interconnection processes,16 PJM will still be challenged to meet the needs of rapidly growing demand, particularly for the artificial intelligence race.

These challenges underscore the urgent need for innovative solutions.  A recent white paper from Duke University, entitled “Rethinking Load Growth,” published by the Nicholas Institute for Energy, Environment & Sustainability highlights that the U.S. power system has substantial headroom due to planning decisions to maintain reserves for infrequent peak demand events.17  By strategically curtailing their load during peak periods, flexible loads can tap into this existing headroom,18 allowing the grid to reliably and safely accommodate more load without requiring significant infrastructure upgrades.  According to the report, 98 GW of new 12 See Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023, 184 FERC ¶ 61,054 (2023).

13 See Building for the Future Through Electric Regional Transmission Planning and Cost Allocation, Order No.1920, 187 FERC ¶ 61,068, order on rehearing and clarification, Order No. 1920-A, 189 FERC ¶ 61,126 (2024). 14 See Applications for Permits to Site Interstate Electric Transmission Facilities, Order No. 1977, 187 FERC ¶ 61,069 (2024).

15 See Managing Transmission Line Ratings, Order No. 881, 177 FERC ¶ 61,179 (2021).
16 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,083 (2025); PJM Interconnection, L.L.C., 190 FERC ¶ 61,084 (2025).
17 See Tyler H. Norris, Tim Profeta, Dalia Patino-Echeverri, and Adam Cowie-Haskell, Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems, Nicholas Institute for Energy, Environment & Sustainability (2025), available at: https://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf.
18 See Bremser Affidavit ¶¶ 13-17.

PDF page 5

5
load—equivalent to more than 10% of the nation’s current aggregate peak demand—could be integrated at an average annual load curtailment rate of 0.5%, and 126 GW at a rate of 1.0%.19 In other words, the grid can accommodate a significant increase in demand if users are flexible and reduce their usage during system stress, which can occur during any time of the year, such as during the summer and winter peaks and during unplanned and planned transmission and

generator outages in shoulder months.
A risk exists that investments in new infrastructure responsive to the demand boom may, ultimately, be underutilized.20  Flexibility can hedge against this uncertainty by enabling a more gradual and adaptive approach to infrastructure development as a temporary measure until such time that new infrastructure can be built.  To bridge the timeline for construction of large-scale capacity expansion, flexible arrangements like the LCDG option can reduce demand during periods of system stress, whenever they may occur, in the interim.21  Enabling a temporary flexibility option that large loads can opt into would therefore mitigate some of these risks and allow for faster load interconnection.  Further, recognizing that load forecasting discussions around the country have coalesced around the need for greater transparency, Enchanted Rock believes that an opportunity exists for load forecasting practices to allow for greater granularity and to take into account more sophisticated concepts of flexibility, as the LCDG option would provide.

19 See Tyler H. Norris, Tim Profeta, Dalia Patino-Echeverri, and Adam Cowie-Haskell, Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems, Figure 1, Nicholas Institute for Energy, Environment & Sustainability (2025), available at:

https://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf
20 See, e.g., PJM Answer at 66 (“With any forecast of future load growth, additional transmission and generation capacity may be required, and there is the risk of overbuilding due to a forecast that is too high, or underbuilding due to a forecast that is too low. The same is true with respect to large load additions, regardless of whether the load is co-located with generation. Given the potential size of these individual, large load additions that are in the forecast, uncertainty with respect to whether the large loads are actually added to the system could cause either overbuild or underbuild to occur based on a single customer addition.”).
21 See Bremser Affidavit ¶¶ 18-19.

PDF page 6

6
As Commissioner Rosner recently recognized, flexibility is critical for addressing the rapid increase in the country’s electricity demand.22  As such, Enchanted Rock respectfully urges the Commission to direct changes to PJM’s Tariff to effectuate the LCDG option in order to facilitate large load flexibility in PJM.

II. LCDG OPTION: LOAD CO-LOCATED WITH DISPATCHABLE GENERATION
As PJM demonstrates in its answer, co-location may exist through a spectrum of different configurations.23  Enchanted Rock agrees.  At one end of the spectrum is what Enchanted Rock would describe as “Complete Electrical Isolation,” where the load and generation are entirely self-sufficient and islanded; at the other end is “Full Grid Integration,” with unrestricted power exchange with the grid, operating as a fully integrated load, using exclusively grid-sourced energy and capacity.  As shown below in Figure 1, between these two extremes (but closer to Full Grid Integration, as shown below) lies “Flexible Grid Integration,” which the LCDG option would facilitate.

Figure 1
22 See Technical Conf. Tr at 96:1-7 (Commissioner Rosner acknowledging the value of “flexibility of large load” given the “really rapid increase in demand”).
23 See, e.g., PJM Answer, Exhibit A (Options for Service to Large Loads).

PDF page 7

7
Under Enchanted Rock’s view, Flexible Grid Integration is a co-location arrangement that relies on the PJM-operated transmission network for grid-sourced energy but provides flexibility commitments through dispatch of the customer’s co-located dispatchable generation during periods of system stress.  Flexible Grid Integration facilitates a system committed to grid- sourced energy and regulated markets, integrates large loads into system planning, provides operational transparency into large loads, and enhances grid operator capabilities by giving large loads the opportunity to provide flexibility when grid operators need it.

Enchanted Rock’s LCDG option, a type of Flexible Grid Integration, shares
characteristics with PJM New Options 6 and 7, while also offering additional functionality.  The premise of the LCDG option is that load flexibility provides substantial benefits to a constrained system.  Load flexibility is key to accelerating large load interconnections and optimizing the efficient and cost-effective utilization of grid infrastructure.  Under the LCDG option, load and generation may be separately metered but are studied together for purposes of retail load interconnection and integration, transmission and resource adequacy planning, and operations. Table 1 below summarizes the key components of Enchanted Rock’s LCDG option,

which is discussed in further detail herein.

PDF page 8

8
Table 1
Enchanted Rock’s LCDG Option24
Description
The LCDG option applies to co-located load that takes Interruptible Service and Available Transmission Capacity Service (which, as defined and discussed below, is load willing to “curtail” in advance of Emergency Procedures), and self-supplies generation. The LCDG option includes two-phases, providing an opportunity for load to bring-its-own generation when transmission or generation capacity on the system is not sufficient for full integration, thereby expediting interconnection and dispatch.

During the waiting period for new transmission, or “Phase 1,” large load is treated as a non- capacity backed load and avoids generation capacity costs in exchange for making firm commitments to support reliability in advance of emergency conditions via the dispatch of co- located generation.  Large load also avoids paying full Network Integration Transmission Service (“NITS”) costs as non-Network Load, and instead will pay for Available Transmission Capacity Service (defined below), which would allow load to access generation on the network during time periods when there is available transmission capacity.

During “Phase 2,” the load transitions to full Network status through existing PJM Tariff processes, once system upgrades are in place, or broader resource adequacy concerns are resolved.

The LCDG generator would act to curtail load, if necessary, during Phase 1.  In Phase 2, to the extent the Commission orders fast-track interconnection processes consistent with PJM Option 6, the LCDG generation would also be eligible to be accelerated through the interconnection process.

PJM Preference
N/A
Load Status
During Phase 1, LCDG load would have non-Network status, subject to advance curtailment by PJM.  LCDG generation could be committed to be dispatched to co-located load during PJM curtailment events (consistent with applicable provisions of the PJM Tariff). During Phase 2, the co-located load would be classified as full Network Load. Generation Capacity Status

No, while in Phase 1.
Capacity eligible during Phase 2.
PJM obligation to serve load
Yes, but lower priority (interruptible) during Phase 1
Yes, with standard priority during Phase 2
Load System Used and Charged
Available Transmission Capacity Service, during Phase 1.
NITS (full load during coincident peak), Energy, Capacity (Full load during coincident peak) during Phase 2.

Ancillary Services Used
Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves Ancillary Services Charged

Reactive, Black Start, Regulation, Sync, during Phase 1.
Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves, during Phase 2.

Generation Revenue
Capacity (based on full CIRs), during Phase 2
Energy and Ancillary Services (based on entire generation output to grid), during Phase 2 Capacity-Related Studies

•TO Load Integration study (Phase 2)
•PJM Do No Harm study (Phase 2)
•RTEP process inclusive of Load Forecast (Phase 2)
•Necessary Study (Phase 2)
•Generator Interconnection Study (Phase 2)
Included in Load Forecast (RTEP)
Yes
Included in RPM Reliability
Requirement
No, for non-capacity backed load, during Phase 1
Yes for load; CIRs included in RPM, during Phase 2.
24 Enchanted Rock recognizes that the LCDG option may be subject to state laws that affect when and how load in a jurisdiction can be served by a supplier other than a franchised public utility.

PDF page 9

9
Cost Allocation for Interconnection
Upgrades
• Supplemental projects pursuant to local TO methodology (Phase 2)
• RTEP upgrades pursuant to RTEP cost allocation (Phase 2)
• Generator for the changes to its facility to accommodate the load (Phase 2) System Protection Requirements

N/A
Demand Response Eligibility
No
Tariff Modifications
Yes
The LCDG option provides more than a traditional demand response or peak shaving program during the operating period.  The flexibility provided by the LCDG option would be considered in the planning and study process for large load interconnection, local and regional planning, and resource adequacy.  The LCDG option therefore permits large loads to utilize flexibility to achieve faster interconnection through the deployment of dispatchable, co-located generation.  Under the LCDG option, the firm commitment to dispatch co-located generation would serve as a bridge to permanent grid upgrades for projects that would otherwise be delayed while new infrastructure is planned, permitted, and constructed.

Specifically, under Phase 1 of Enchanted Rock’s proposal, LCDG load would be treated as curtailable non-Network Load, subscribing to Interruptible Service (as contemplated in PJM’s New Option 7) for generation service, and subscribing to Enchanted Rock’s proposed Available Transmission Capacity Service for transmission service.  Under Phase 1, LCDG generators would be classified as non-Network Resources (i.e., interconnected on a non-network basis), and would be limited to serving the co-located load’s main function of reducing or zeroing demand.25 Under Phase 2, LCDG load would be eligible to go through the normal PJM Tariff process as Network Load, when PJM deems that the supply/demand conditions are no longer constrained, and necessary transmission infrastructure (e.g., Network Upgrades) have been

25 Additionally, during Phase 1, the Commission and PJM should allow the LCDG generators to participate in PJM’s wholesale markets and earn revenue for the services they are capable of providing consistent with the PJM Tariff.

PDF page 10

10
constructed and placed into service.  Unlike PJM’s New Option 6, LCDG load would not be Network Load, but would utilize Interruptible Service as a non-Network Load (i.e., for generation service) as contemplated in PJM’s New Option 7.

Moreover, during Phase 1, the LCDG generator would act to curtail load (to the extent necessary).  Under Phase 2, LCDG generators would be eligible to go through the normal PJM Tariff process as a Network Resource and fast tracked through the generator interconnection process to the extent allowed by the Commission (e.g., consistent with PJM New Option 6). Notably, new load may be incentivized to self-supply generation if that generation were eligible to be fast-tracked in the generator interconnection process.

Additionally, under Phase 1, Enchanted Rock proposes that projects choosing the LCDG option take a variation of non-firm transmission service to be called Available Transmission Capacity Service (“ATCS”),26 with commitments to dispatch co-located generation during PJM curtailments.  ATCS would be a transitional option available only until the transmission infrastructure is constructed and the utility is able to serve the load taking full network transmission service.  The proposed ATCS would allow load to access generation on the network during time periods when there is available transmission capacity.  Given the firm service nature of NITS, it would be appropriate to provide a new solution to unlock the unused capacity as interim transmission service for co-located arrangements.27

Similar to ERCOT’s “Connect and Manage” process for generation resources which expedites the interconnection of new generation resources by prioritizing local grid connections

26 See Bremser Affidavit ¶¶ 6, 12-19
27 See id. ¶¶ 12-19.

PDF page 11

11
and managing broader system impacts in real-time operations,28 LCDG projects create a “Connect and Manage” option for large loads that make firm commitments to dispatch their co- located generation.  During periods of grid stress in the waiting period, PJM operators would direct the dispatch available megawatts (“MWs”) of LCDG generation so that the LCDG load reduces electricity consumption from the grid.  In the event LCDG generation fails to respond to dispatch instructions, the LCDG load would need to be curtailed to provide the requested response.

Enchanted Rock expects that LCDG generation would be dispatched only for a small
number of hours per year.  As shown below in Figure 2, a typical load duration curve (the blue line) reflects the entire annual hourly load for 8760 hours.  The orange line represents a hypothetical addition of X MWs from data centers.  Data centers typically have baseload computing needs and exceptionally high load factors29 due to their high uptime requirements necessary to align with customer needs,30 meaning that the applicable curve will just shift upwards by that amount.

28 See ERCOT Interconnection Process: Generation Entity Winter Weather Preparedness Workship, 2 (Oct. 28, 2024), available at: https://www.ercot.com/files/docs/2024/10/30/0940-AM-ERCOT-Interconnection-Process- Generation-Entity-Winter-Weather-Preparedness-Fernandes.pdf.
29 See I. Riu, D. Smiley, S. Bessasparis, K. Patel, Load Growth Is Here to Stay, but Are Data Centers?: Strategically Managing the Challenges and Opportunities of Load Growth, Energy and Environmental Economics, Inc. (Jul. 2024), available at: https://www.ethree.com/wp-content/uploads/2024/07/E3-White-Paper-2024-Load-Growth-Is- Here-to-Stay-but-Are-Data-Centers-2.pdf.
30 See The Data Center, The Importance of Uptime in the Data Center (Sept. 11, 2019), available at: https://datacenter.com/news_and_insight/the-importance-of-uptime-in-the-data-center/.

PDF page 12

12
Figure 2
Figure 2. Load (blue), plus hypothetical X MWs of data centers (orange), all X MWs of data centers utilize co- located dispatchable generation during the highest load hours of the year (green) In this way, LCDG projects would support efficient utilization of existing generation and transmission capacity, lowering costs for customers of the existing transmission system, and buying time for new infrastructure necessary to serve the load on a firm basis to be placed in service.

PDF page 13

13
III. ENCHANTED ROCK’S RESPONSE TO SELECTED COMMISSION
QUESTIONS
a. General
iv. Parties may also address how co-located loads are similar to or disparate from other types of arrangements where load and generation share the same

point of interconnection (such as Behind the Meter Generation as defined in PJM’s Tariff or non-retail behind the meter generation).

Enchanted Rock’s Response:
Unlike LCDG, the Behind the Meter Generation (“BTMG”) construct assumes
continuous supply if the load cannot draw from the transmission network, whereas a more flexible solution would allow for periodic supply to load but continued access to the transmission network during normal operating conditions.  BTMG assets can reduce customers’ capacity and transmission demand payments via full netting of the load, whereas LCDG projects temporarily relieve constraints on existing infrastructure allowing for immediate utilization of idle or underutilized transmission capacity for faster load interconnections.

d. Interconnection Procedures and Cost Allocation
ii. Please explain whether PJM’s necessary study process allows a colocation arrangement to demonstrate its capability to flexibly adjust its withdrawals from or injections to the transmission system (e.g., by using secondary

backup generation or by curtailing on-site load), and reflect this capability in the operating assumptions PJM considers when estimating the co-location

arrangement’s impacts on the transmission system?  If not, would it be
appropriate to establish a new or revised study process that allows for such a demonstration?

Enchanted Rock’s Response:
Currently, load and generation interconnection requests are studied separately.  This disjointed approach creates several issues, particularly for co-located arrangements where the load and generation components are intended to function as an integrated system.  First, it can lead to a mismatch in timing.  The generation and load portions of a co-located arrangement may

PDF page 14

14
face different timelines for interconnection, making it challenging to bring the entire facility online in a coordinated manner.  This mismatch in study timelines can delay project completion and create bottlenecks, as project timelines become constrained by the interconnection study process with the longest duration.

Second, separate studies fail to account for the interdependencies between the load and generation components of a co-located arrangement.  When studies are conducted independently, the load interconnection study may not consider the impact of the co-located generation, and vice versa.  This can result in inaccurate assessments of the necessary transmission upgrades and can lead to inefficient interconnection solutions.

Recognizing and respecting jurisdictional boundaries between load and generator interconnections, Enchanted Rock recommends improving coordination so that grid planners in multiple jurisdictions can gain a more accurate understanding of the co-located arrangement’s overall impact on the grid.  For example, by enabling the generation component to offset some of the load’s impact on the grid, it may defer the need for certain upgrades for reliable interconnection until such time that infrastructure expansion can occur.  Consideration for co- located arrangements in the retail load integration process would also allow for faster load interconnections and mitigates commercial risks for both load and generation developers. Facilitating improved coordination aligns with the response to the Show Cause Order of certain indicated transmission owners in PJM, which transmission owners also emphasized the need to value load flexibility in the overall planning process.31

31 See Answer of the Indicated PJM Transmission Owners, Docket Nos. EL25-49-000, et al., Attachment A at 13 (Mar. 24, 2025).

PDF page 15

15
vii. Please explain whether changes to interconnection procedures and agreements are necessary to accommodate new generation interconnecting with co-located load, including whether the existing queue process is sufficient for such arrangements.

Enchanted Rock’s Response:
PJM’s interconnection procedures were developed for generation-only projects, not co- located arrangements, which by their nature, integrate generation and load to function as a unified resource, yet the separate processes fail to recognize this fundamental characteristic. This separation manifests in several critical ways within the interconnection process: ·

Uncoordinated Studies: the generation interconnection study (mainly FERC- jurisdictional) and the load interconnection study (mainly state-jurisdictional) are frequently conducted independently, without proper consideration of co-located arrangements’ combined impact.

·
Timing Mismatches: the separate processes can result in different timelines for interconnecting generation and load at co-located arrangements. This can create significant delays and logistical hurdles for co-located projects.

·
Inadequate Agreements: existing interconnection agreements are generally designed for either standalone generation facilities or standalone loads and may not contain the necessary provisions to address the unique operational arrangements of co-located facilities.

·
Queue Management: generator interconnection study processes and queues may not adequately recognize the benefits that co-located arrangements can provide and may require reforms to prioritize the grid flexibility benefits offered by co-located arrangements, like LCDG projects.

Moreover, to the extent that the Commission orders an accelerated interconnection process consistent with PJM’s proposed Option 6, LCDG projects should also be permitted to participate in any accelerated interconnection process for any generation co-located with load. Facilitating the integration of LCDG projects will incentivize the development of resources that align with grid needs.

PDF page 16

16
f.  Other
ii. Please discuss whether back-up service can provide benefits to customers or otherwise help minimize system costs, including with specific examples or best practices, if possible.

Enchanted Rock’s Response:
Backup generators can indeed provide benefits to customers and help minimize system costs.  Large loads, like data centers, may already have capital and ongoing expenses earmarked for backup generation to maintain operational continuity during disruptions of their primary power source as a matter of normal planning.  In PJM’s Option 8, PJM appears to suggest that the easing of existing restrictions, such as EPA’s National Emission Standards for Hazardous Air Pollutants (NESHAP), particularly for Tier 2 diesel generators, could be low hanging fruit to add to the supply stack as grid servicing assets via demand response.

However, the proposition to relax environmental constraints on Tier 2 diesel generators warrants careful scrutiny.  While such a measure may appear to offer increased flexibility in grid management and demand response, it is ultimately unnecessary and potentially counterproductive, given the readily available and cost-competitive cleaner alternatives.  Natural gas generators, for example, present a superior emissions profile,32 yielding lower levels of particulate matter (PM), sulfur oxides (SOX), and nitrogen oxides (NOX).  Additionally, diesel generators carry risks related to fuel availability and delivery, especially after widespread outages when a surge in demand from numerous diesel users simultaneously attempting to refuel GWs of backup generation capacity can quickly overwhelm supply chains.

While the relaxation of environmental limits on Tier 2 diesel generators may offer a seemingly expedient solution for valuing backup power in the supply stack, the adoption of

32 Enchanted Rock Fact Sheet (last visited April 23, 2025), available at: https://enchantedrock.com/enchanted-rock- fact-sheet/.

PDF page 17

17
Enchanted Rock’s proposed LCDG option would encourage large loads to adopt commercially available generation technologies that can improve flexibility on the grid and ultimately provide resource adequacy value to the grid without special environmental waivers.

iii. Parties may also choose to address how co-location arrangements may
provide benefits, including potentially reducing required transmission
upgrades to interconnect large loads, reducing congestion, or providing
operational flexibility during system peaks or emergencies.
Enchanted Rock’s Response:
Co-location arrangements, particularly those involving LCDG, can provide several benefits to the grid and its operation.  By deploying dispatchable co-located generation, a large load can effectively become an interruptible load.  If this capability is valued in the transmission planning process before load interconnection, it may allow grid planners to defer the need for certain transmission upgrades that would otherwise be required to serve the new load.  The co- located generation can be used to offset the load’s impact on the grid during peak demand and stress periods.

In PJM utility territories that rely heavily on centralized transmission and lack sufficient local generation, co-location arrangements can help reduce congestion and backfill any required transmission contingencies in the interim as new transmission is built to solve the violations.  In most cases, these co-located arrangements can even be configured to export excess generation to the grid because normal industry practice is to oversize backup generation for redundancy purposes. This capability helps to stabilize the grid, avert blackouts, and optimize the utilization of existing grid infrastructure.

Co-location also contributes to improve overall system efficiency by reducing transmission line losses, which represent a not insignificant portion of the total electricity

PDF page 18

18
generated, with some amount lost between the generation source and the end-use customer.33 The amount of energy lost is dependent on factors such as the distance the electricity travels, the characteristics of the transmission lines, and the level of current flowing through the lines.  By locating generation sources closer to load, co-location arrangements minimize the distance that electricity needs to travel across the transmission network.  Lower transmission losses mean that less electricity needs to be generated to serve the same amount of load, freeing up capacity on existing transmission infrastructure for use by other customers.

iv. Parties may also address whether, and if so, how, the Tariff should be
modified to best accommodate or encourage co-location arrangements to be
constructed in such a way as to minimize total system costs or otherwise
provide certain benefits, including protections for existing customers and
allocation of costs consistent with the cost-causation principle.
Enchanted Rock’s Response:
For the reasons described herein, Enchanted Rock respectfully submits that the PJM Tariff should be modified to adopt Enchanted Rock’s LCDG option as outlined above, including the proposed Available Transmission Capacity Service.34  Enchanted Rock’s proposed LCDG option would encourage co-location of dispatchable generation with new loads at a time when resource adequacy is being challenged and markets are expecting to continue to deal with thin reserve margins going forward.  In essence, a combination of PJM’s New Option 6 and New Option 7, with additional transmission-related considerations, would enable LCDG projects to provide their full value to the grid.

33 See EIA, Frequently Asked Questions: How much Electricity is Lost in Electricity Transmission and Distribution in the United States (Nov. 7, 2023), available at: https://www.eia.gov/tools/faqs/faq.php?id=105&t=3.
34 See Bremser Affidavit ¶¶ 6, 12-19.

PDF page 19

19
IV. CONCLUSION
Wherefore, for the foregoing reasons, Enchanted Rock respectfully requests that the Commission consider the Response, and the recommendations of Enchanted Rock. Joel Yu

Senior Vice President, Policy & External
Affairs
Enchanted Rock, LLC
1113 Vine Street, Suite 101
Houston, TX 77002
Jyu@enchantedrock.com
James Huang
Director, Wholesale Markets Policy
Enchanted Rock, LLC
1113 Vine Street, Suite 101
Houston, TX 77002
Jhuang@enchantedrock.com
Respectfully submitted,
/s/ Steven Shparber
Steven Shparber
Omar Bustami
Mintz, Levin, Cohn, Ferris, Glovsky and
Popeo, P.C.
555 12th Street NW, Suite 1100
Washington, D.C. 20004
(202) 434-7417
SShparber@mintz.com
OBustami@mintz.com
Counsel to Enchanted Rock, LLC
Enclosed: Attachment A
Dated: April 23, 2025

PDF page 20

CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing and its attachment to be served upon each person designated on the official service list compiled by the Secretary in the captioned proceedings.

Dated at Washington, D.C., this 23rd day of April, 2025.
/s/ Steven Shparber

PDF page 21

Attachment A
Affidavit of Dr. Albert W. Bremser

PDF page 22

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
                      Docket No. EL25-49-000
Large Loads Co-Located at Generating
)
Docket No. AD24-11-000
Facilities
)
Constellation Energy Generation, LLC
)
Docket No. EL25-20-000
)
(consolidated)
v. )
)
PJM Interconnection, L.L.C.
)
Affidavit of Dr. Albert W. Bremser
on behalf of Enchanted Rock, LLC
April 23, 2025

PDF page 23

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit
Page ii of ii
TABLE OF CONTENTS
HEADING
PAGE
I. INTRODUCTION … 1
II. AFFIDAVIT PURPOSE AND SUMMARY CONCLUSIONS … 2
III. REASONS TO UPDATE THE PJM TARIFF (POTENTIAL ISSUES WITH THE
CURRENT PJM TARIFF) … 3
IV. AVAILABLE TRANSMISSION CAPACITY SERVICE … 3
LIST OF ATTACHMENTS
ATTACHMENT NO. 1
CURRICULUM VITAE OF ALBERT W. BREMSER

PDF page 24

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit
Page 1 of 8
AFFIDAVIT
OF DR. ALBERT W. BREMSER
I. INTRODUCTION
1. My name is Albert W. Bremser.  My business address is 11401 Lamar Ave., Overland Park, Kansas 66221.  Black and Veatch Corporation employs me as a Principal Consultant.  My responsibilities include providing advisory services that address the strategic, financial, and regulatory advisory needs of energy and utility clients.

2. I am a financial economist with over twenty years of experience involving energy and non-energy projects including rate-making and regulatory issues subject to state and federal energy regulatory authorities such as the Federal Energy Regulatory Commission (“FERC”).  My business background includes four years at FERC as an Energy Industry Analyst (Litigation) in the Office of Administrative Litigation as part of FERC Trial Staff where I was an expert witness.  I hold a Bachelor of Science in Commerce from the University of Virginia, a Master of Business Administration from the University of Pittsburgh, and a Ph.D. in Finance from Virginia Tech.  I have the professional designation as a Chartered Financial Analyst (CFA).

3. For over 20 years, I have been working on matters involving the energy industry in the areas of electricity and pipelines subject to FERC and state jurisdiction.  I use finance, economic and accounting principles in this work, as well as regulatory principles and practices of regulators.  I have worked on non-energy matters subject to regulation, which includes testimony on public interest considerations in a railroad merger before

PDF page 25

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit
Page 2 of 8
the US Surface Transportation Board.  In 2024, the Commission cited, in Order No. 904 (Final Rule, Compensation for Reactive Power Within the Standard Power Factor Range), affidavits I authored in support of determinations made by the Commission regarding compensation under Schedule 2, under the pro forma open-access transmission tariff (“OATT”).1

4. I have experience with PJM, MISO, the Electric Reliability Council of Texas (“ERCOT”), and the North American Electric Reliability Corporation (“NERC”).

5. My curriculum vitae is Attachment No. 1 hereto.
II. AFFIDAVIT PURPOSE AND SUMMARY CONCLUSIONS
6. The purpose of my affidavit is to provide additional support and analysis supporting the recommendation for PJM to adopt a new class of transmission service, which I refer to as “Available Transmission Capacity Service” or “ATCS.”

7. I am providing this affidavit on behalf of Enchanted Rock, LLC (“Enchanted Rock”).
8. This affidavit is not intended to provide any legal opinions.  I provide citations in this affidavit to provide references for the statements made in the affidavit.

1 Compensation for Reactive Power Within the Standard Power Factor Range, Final Rule, Order No. 904, 189 FERC ¶ 61,034, at PP 89, 118 & n.343, 186 & n.547 (2024).

PDF page 26

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit
Page 3 of 8
III.REASONS TO UPDATE THE PJM TARIFF (POTENTIAL ISSUES WITH THE
CURRENT PJM TARIFF)
9. Co-located arrangements with new generation and new large loads are differently situated than a point of interconnection involving only generation or only load.  Further, co-located arrangements with new generation and new large loads are distinguishable from proposed co-location arrangements where there is a pre-existing relationship with PJM involving assets with current and continuing operations.  For example, with existing generation, the PJM transmission system was likely modified to accommodate that generation.

10. Updating the PJM Tariff to accommodate co-located arrangements with new generation and new large loads would align with removing impediments to competition in the PJM wholesale power markets to serve large loads.  This would align with a fundamental principle of Order No. 888 in promoting competition and efficiency.2

11. Updating the PJM Tariff will help avoid undue discrimination and will help allow open access to the PJM transmission system to co-located arrangements with new generation and new large loads.

IV.AVAILABLE TRANSMISSION CAPACITY SERVICE
12. The Commission should consider creating a new transmission service to unlock the unused capacity of the transmission system, which can be utilized by co-located arrangements.

2 Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission Service by Public Utilities, Order No. 888, 61 Fed. Reg. 21,540 (May 10, 1996).

PDF page 27

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit
Page 4 of 8
13. In Table 1 below, the PJM peak loads for 2023 and 2024 without exports and with exports are shown as provided in the 2024 State of the Market Report for PJM.  The peak loads for the period of 2009 to 2024, which occurred in 2011, is also shown in Table 2.

Table 1
Actual PJM Peak Load Without Exports and With Exports for 2023 and 2024, and Highest Peak for 2009 to 20243

Year
Date
Hour Ending
(EPT)
PJM Load
(MWh)
Peak Load Without Exports
2011 (Peak
Load 2009
to 2024)
July 21 (Thu)
17
154,095
2023
July 27 (Thu)
18
144,215
2024
July 16 (Tue)
18
144,890
Peak Load With Exports
2011 (Peak
Load 2009
to 2024)
July 21 (Thu)
17
169,290
2023
July 27 (Thu)
18
152,797
2024
July 15 (Mon)
17
154,045
14.  The 2024 State of the Market Report for PJM provides a graph, which is shown in Figure 1 below, that shows the real-time monthly average hourly load plus exports for 2023 and 2024.  As shown above in Table 1, the peak load with exports was about 153,000 MWh in 2023 and 154,000 MWh in 2024, which is much higher than the 3 Monitoring Analytics, LLC (Independent Market Monitor for PJM), State of the Market Report for PJM, Volume 2: Detailed Analysis, 2024, Section 3 (Energy Market), page 146 at Table 3-6 (Actual PJM peak load without: 2009 through 2024) and Table 3-7 (Actual PJM peak load plus export: 2009 through 2024), available at:

https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2024/2024-som-pjm- vol2.pdf.

PDF page 28

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit
Page 5 of 8
monthly average.  Since the load is below peak load, this suggests that the transmission system likely has available capacity, because the transmission system is designed to handle peak load conditions.

Figure 1
Copy of Figure 3-11 Showing Hourly Load With Exports
on the Peak Load Day for 2023 and 2024 4
15. The 2024 State of the Market Report for PJM provides a graph, which is shown in Figure 2 below.  Figure 2 shows that even during peak load days there are hours where there is likely available transmission capacity given the load is below the peak load. 4 Monitoring Analytics, LLC (Independent Market Monitor for PJM), State of the Market Report for PJM, Volume 2: Detailed Analysis, 2024, Section 3 (Energy Market), page 148 at Figure 3-11 (Real-time monthly average hourly load plus exports: 2023 through 2024), available 2023 Peak: 152,797; 2024 Peak:154,045

154 045

PDF page 29

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit
Page 6 of 8
Figure 2
Copy of Figure 3-9 Showing Hourly Load With Exports
on the Peak Load Day for 2023 and 20245
16. PJM also provides a “Data Miner” on its website, which includes access to metered hourly load data.  Figure 3 below shows a plot of the metered hourly load data, which shows that the highest load levels occur during a small number of hours during a year. This implies that the transmission system overall has unused transmission capacity at https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2024/2024-som- pjm-vol2.pdf

5 Monitoring Analytics, LLC (Independent Market Monitor for PJM), State of the Market Report for PJM, Volume 2: Detailed Analysis, 2024, Section 3 (Energy Market), page 147 at Figure 3-9 (Peak load and export day comparison), available at

https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2024/2024-som-pjm- vol2.pdf

PDF page 30

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit
Page 7 of 8
most of the time since the transmission system is designed to handle peak load conditions.

Figure 3
Hourly Metered Load for PJM for 20246
17. I recognize that the PJM system has transmission constraints, but in general, there is unused transmission capacity during many hours of the year.

18. Due to the firm service nature of Network Integration Transmission Service (“NITS”), it would be reasonable to provide a new solution to unlock the unused transmission 6 PJM, Data Miner 2, Load, Hourly Load: Metered, available at:

https://dataminer2.pjm.com/feed/hrl_load_metered/definition and
https://dataminer2.pjm.com/feed/hrl_load_metered.
 60,000
 70,000
 80,000
 90,000
 100,000
 110,000
 120,000
 130,000
 140,000
 150,000
 160,000
1/1/2024
2/1/2024 3/1/2024
4/1/2024 5/1/2024
6/1/2024 7/1/2024
8/1/2024
9/1/2024 10/1/2024 11/1/2024 12/1/2024
MWh (Megawatt Hours)
Hours in 2024
HIGHEST VALUE IN 2024 DATA SET

PDF page 31

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit
Page 8 of 8
capacity.  Depending on what the Commission believes is appropriate, it could be an interim-type transmission service or a permanent transmission service for a co-located arrangement.  I have named this concept “Available Transmission Capacity Service.” The service would allow load to access generation on the network during time periods when there is available transmission capacity.  This means that the Available Transmission Capacity Service would be a non-firm transmission service.

19. The Commission might not agree with the general framework I have presented for the Availability Transmission Capacity Service.  If that is the case, I believe the Commission should consider designing a transmission service to unlock the unused transmission capacity for the purpose of facilitating new generation and new large load to join the PJM system without waiting on transmission upgrades and new generation capacity to be built, which will take many, many years.  In a sense, this is analogous to the “connect and manage” approach that ERCOT is using for new generation.7

20. This concludes my affidavit.
7 ERCOT, ERCOT Interconnection Process: Generation Entity Winter Weather Preparedness Workshop, October 28, 2024 (Jenifer Fernandes, Manager, Resource Integration), Slide 2, available at: https://www.ercot.com/files/docs/2024/10/30/0940-AM-ERCOT-Interconnection- Process-Generation-Entity-Winter-Weather-Preparedness-Fernandes.pdf.

PDF page 32

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
                      Docket No. EL25-49-000

Large Loads Co-Located at Generating
)

Docket No. AD24-11-000
Facilities

)

Constellation Energy Generation, LLC
)

Docket No. EL25-20-000

)

(consolidated)
v.

)

)
PJM Interconnection, L.L.C.

)

AFFIDAVIT OF ALBERT W. BREMSER

I, Albert W. Bremser, certify under penalty of perjury that the attached affidavit in this proceeding was prepared by me or under my direct supervision. The statements contained in my affidavit and the supporting attachment are true and correct to the best of my knowledge, information, and belief.

Executed on the 23th day of April 2025.

__________________________________
Albert W. Bremser

PDF page 33

Attachment No. 1

Curriculum Vitae of Dr. Albert W. Bremser

PDF page 34

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit, Attachment No. 1
Page 1 of 8

Albert (Al) Bremser, Ph.D.
Dr. Bremser advises on energy infrastructure issues involving electricity and pipeline transportation. This advisory work includes testifying as an expert witness. He focuses on rates (i.e., prices), policy, and markets for rate-regulated and market-rate participants in the electric and pipeline sectors. His work involves issues overseen by energy regulators. This includes the Federal Energy Regulatory Commission (FERC) and state public utility commissions. Dr. Bremser uses finance, economics, and accounting principles in his work. This includes understanding the regulatory principles and practices of regulators.

Dr. Bremser is a financial economist. He has a Ph.D. in Finance and holds the Chartered Financial Analyst® (CFA®) designation. Dr. Bremser was an expert witness at FERC in the Office of

Administrative Litigation as a member of FERC Trial Staff from 2015 to 2019. He has more than 20 years of experience with energy infrastructure issues.

For regulated rates, he has experience determining a regulated entity's annual revenue requirement from either a cost-of-service analysis or a formula rate analysis. He works with companies making a filing for an initial tariff rate or tariff rate changes, or intervening and protesting a tariff rate filing. He has expertise in cost-of-service and formula rate analysis. This includes return on equity (ROE), cost of debt, capital structure, rate design, and cost allocation. He has worked on cases with regulated rates set by settlement or negotiation.

For non-regulated rates, he has worked on projects involving applications for market-based rate authority to be granted by FERC, complaint cases challenging FERC granted market-based rate authority, or review of current FERC market-based rate authority. Dr. Bremser has served as an expert witness in several cases. He has testified at FERC, the US Surface Transportation Board, and state utility regulatory bodies (Wisconsin, New Hampshire, and Ohio). His work includes written testimony, cross-examination during hearings, and deposition testimony.

As a FERC Trial Staff member, Dr. Bremser was involved in many settlement proceedings before FERC Administrative Law Judges for electric and pipeline cases. Dr. Bremser has participated in settlement proceedings at FERC before and after being a member of FERC Trial Staff. Dr. Education

Ph.D., Finance, Virginia Tech,
1997
M.B.A, University of
Pittsburgh, 1992
B.S., Commerce, University of
Virginia, 1989
Additional Credentials
Chartered Financial Analyst
(CFA)
Years of Experience
25
Specializations and Skills
Return on Equity (ROE); Cost
of Capital; Cost of Service;
Electric Utilities; Pipelines
(Crude Oil, Refined Products
and Natural Gas
Liquids/NGLs); Federal Energy
Regulatory Commission
(FERC) Energy Regulation;
Expert Witness; Dispute
Resolution; Litigation;
Economic Damages.
PRINCIPAL
CONSULTANT

PDF page 35

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit, Attachment No. 1
Page 2 of 8

Bremser completed formal negotiation training in a 5-day executive education program from the Program on Negotiation at Harvard Law School.

Dr. Bremser has experience in proceedings on a hearing track as an expert witness, supporting an expert witness, and being a non-testifying member of FERC Trial Staff case teams. For commercial litigation disputes, Dr. Bremser has experience with determining the dollar amount of economic damages due to alleged defendant conduct. In energy matters, he has analyzed merchant electricity generation, natural gas storage, spent nuclear fuel, and crude oil contracts for proceedings involving breach of contract allegations and the determination of economic damages. He has experience with MTBE gasoline and underground gasoline storage tanks, and solar panels for proceedings to determine economic damages that were not related to breach of contract allegations.

Dr. Bremser holds a B.S. in Commerce from the University of Virginia, an M.B.A. from the University of Pittsburgh, and a Ph.D. in Finance from Virginia Tech. Dr. Bremser has taught finance courses at Virginia Tech, and has published articles in the Journal of Legal Economics. He has completed 28 college credit hours of statistics and econometrics. He also completed an Accounting Career Studies Certificate at Northern Virginia Community College in 2017, which requires completion of 24 credit hours of accounting course that also meets the accounting course requirements of the Virginia Board for Accountancy to take the Certified Public Accountancy (C.P.A.) examination.

PROFESSIONAL EXPERIENCE
 Black & Veatch, Global Advisory, Principal Consultant, Arlington, VA, 2022 – Present  NERA Economic Consulting, Associate Director, Washington, DC, 2019 – 2022  Federal Energy Regulatory Commission, Energy Industry Analyst, Office of Administrative Litigation, Washington, D.C., 2015 – 2019

 Bremser Finance and Economics, Principal, Vienna, VA, 2013 – 2015
 Exponent, Manager, Alexandria, VA, 2011 – 2013
 Bremser Finance and Economics, Principal, Vienna, VA, 2009 – 2011
 LECG, Senior Managing Consultant, Washington, DC, 1999 – 2009
 KPMG, Economic Consulting Services, Senior Consultant, Washington, DC, 1997 – 1999  Virginia Tech, College of Business, Finance Instructor, Blacksburg, VA, Summer 1995, 1996 – 1997

 MCI Telecommunications, Financial Systems Analyst, Arlington, VA, 1990 – 1991  Freddie Mac (Federal Home Loan Mortgage Corp.), Accountant, Vienna, VA, 1989 – 1990

PDF page 36

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit, Attachment No. 1
Page 3 of 8

PROJECT EXPERIENCE
PRIMARY AREAS OF GOVERNMENT AND PRIVATE SECTOR EXPERIENCE
Energy – Regulated and Unregulated (Federal Energy Regulatory Commission (FERC) Trial Staff and private sector)

 Return on equity determination
 Discount cash flow model (DCF)
 Capital asset pricing model (CAPM)
 Risk premium model
 Expected earnings model
 Proxy group selection
 Wholesale electric transmission formula rates and stated rates (annual transmission revenue requirement)

 Revenue requirement/Cost of service elements (electric transmission, reactive power, liquid energy pipelines)

 Return on equity (ROE), cost of debt and capital structure (return on rate base; cost of capital)

 Rate base (original cost rate base, depreciation, net rate base, accumulated deferred income taxes (ADIT), deferred earnings, allowance for funds used during construction (AFUDC))

 Alternative rate base treatments: depreciated original cost (DOC), trended original cost (TOC), levelized original cost

 Income tax allowance (ITA)
 Operating expenses (operations and maintenance (O&M), and general and administrative (G&A))

 Cost allocation of rate base and operating expenses
 Application of cost causation principles to determine cost allocation  Corporate overhead

 Jurisdictional versus non-jurisdictional services
 Separate and joint jurisdictional systems
 Affiliate transactions
 Market-based rate authority
 Federal Energy Regulatory Commission rate making and non-rate making practices  Economic damages in dispute resolution (breach of contract, etc.)

FERC Settlement and Litigation Experience
 FERC settlement negotiations and hearings

PDF page 37

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit, Attachment No. 1
Page 4 of 8

 30+ dockets (not counting related dockets) in settlement proceedings  11 hearing proceedings while in the private sector and as a member of FERC Trial Staff EXPERIENCE BY INDUSTRY SECTOR

Industry: Electric (FERC; wholesale)
 Return on equity (ROE) determination
 DATC Path 15 (ER17-998-001 and EL17-61-001) (and other elements of regulatory cost of capital – cost of debt and capital structure) – electric transmission  System Energy Resources, Inc. (SERI) (EL17-41-001 and EL18-142-000) (two separate compliant cases for different time periods) – electric generation, nuclear power plant  Panda Stonewall (ER17-1821-002), generator based reactive power compensation under Schedule 2 of PJM OATT

 Consolidated Water Power Company (Wisconsin Public Service Commission, 1330-ER- 104) (comparative authorized return on rate base analysis, dividend policy) – electric utility rates to customers

 FERC cost of service and cost of service elements such as income tax allowance, accumulated deferred income taxes (ADIT), and cost of capital (including return on equity (ROE)) for cost of service

 Electric transmission rates
 Formula rates
 Stated rates
 Reactive power capability compensation (generation-based; Schedule 2 of OATT)  Panda Stonewall (ER17-1821-002; Op. No. 574); testimony on fixed charge rate framework, cost allocation, return on equity, cost of debt, capital structure, plant construction costs for a new natural gas fueled power plant, categorization of plant construction cost, appropriateness of recovering plant construction costs and other topic areas; on behalf of FERC Trial Staff

 Affidavits for Initial Comments and Reply Comments in the Notice of Proposed Rulemaking on Compensation Within the Standard Power Range (RM22-2-000)  Generation types


Wind

Solar

Natural gas fueled (combined cycle, combustion turbine)

Coal fueled

Nuclear fueled

Co-generation

Hydro

Other fuel sources

PDF page 38

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit, Attachment No. 1
Page 5 of 8


Fixed charge rate framework
 Non-fuel fixed operations and maintenance (O&M) expenses
 Fixed general and administrative (A&G) expenses
 Depreciation (sinking-fund deprecation)
 Income tax allowance
 Return on rate base (return on equity (ROE), cost of debt and capital structure)  Accumulated deferred income taxes (ADIT)

 Knowledge of certain aspects of PJM, MISO, ERCOT and other RTOs/ISOs  Energy related breach of contract cases involving electricity tolling agreements and spent nuclear fuel

 Valuation of electric power plants
Industry: Natural Gas Pipelines (FERC)
 Knowledge of natural gas pipelines and natural gas storage involving acquisition of assets and investment interests.

 FERC shipper creditworthiness standards and associated tariff language of pipelines.  Return on equity determination.

Industry: Electric Local Distribution Companies (State; Non-FERC)
 Cost of service elements
 Return on equity
 Multi-year investment plan
 Advisory on testimony for filing and stakeholder engagement
Industry: Natural Gas Local Distribution Companies (State; Non-FERC)  Cost of service elements

 Lead-lag studies to determine cash working capital
 Multi-year investment plan
Advisory on testimony for filing and stakeholder engagement
Industry: Crude Oil, Refined Product, and Natural Gas Liquid (NGL) Pipelines (FERC)  Cost of service elements

 Return on equity (ROE), cost of debt and capital structure (return on rate base)  Rate base (net rate base, accumulate deferred income taxes (ADIT), deferred earnings, allowance for funds used during construction (AFUDC))

 Income tax allowance (ITA)

PDF page 39

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit, Attachment No. 1
Page 6 of 8

 Operating expenses (operations and maintenance (O&M), and general and administrative (G&A))

 Application of cost causation principles to determine cost allocations  Cost of service

 Tariff rate filing advisory and preparation of cost of service statements  Cost of service advisory

 Page 700 advisory
 Rate design
 Market-based rate authority
 Seaway Crude Pipeline’s application (OR15-6-000 and -002); testimony on behalf of FERC Trial Staff

 Mobil Pipe Line application (Pegasus system; OR07-21-000); support of Mobil’s expert and support in hearing proceeding. First crude oil pipeline application for market-based rate authority

 Guttman Energy, et al v. Buckeye Pipe Line (OR14-4-000); member of FERC Trial Staff case team for the hearing proceeding. First compliant case challenging market-base rate authority for a refined products pipeline

 Epsilon Trading, et al v Colonial Pipeline (OR18-7-002, et al); support of Colonial’s expert for the market-based rate phase of the hearing proceeding

 Unnamed pipeline; support for an expert for an application that was not filed.  Cost of service rates, settlement rates, index ceiling rates/levels, uncommitted and committed rates

 Non-rate issues – pro-rationing policies and allegations of discriminatory conduct  BP v Sunoco (OR15-25-000 and -001); member of FERC Trial Staff case team  Equinor v Mustang (OR21-5-001); support of Mustang’s expert

 Valuation of refined product pipelines
OTHER EXPERIENCE
Other Energy Experience:
 Energy related breach of contract cases involving natural gas storage and crude oil purchase contacts

 Energy related business tort involving MTBE gasoline and underground gasoline storage tanks

 Energy related dispute involving solar panels

PDF page 40

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit, Attachment No. 1
Page 7 of 8

Other Economic, Financial, and Accounting Analysis
 Economic analysis to determine economic damages in case involving breach of contract or fiduciary duty (non-investment and investment related), business torts, and intellectual property (patent, trademark, copyright, trade secrets)

 Analysis of financial documents, financial statements, and accounting records  Option pricing techniques (derivative securities)

 Railroad transportation rates
 Public interest issues in a railroad merger
 Regulatory proceedings such as those before the Federal Energy Regulatory Commission, the US Surface Transportation Board, the Public Service Commission of Wisconsin, Public Utilities Commission of Ohio, and the New Hampshire Public Utilities Commission.

TESTIMONY/AFFIDAVITS/VERIFIED STATEMENTS
 Seaway Crude Pipeline Company LLC, FERC Docket No. OR15-6-000
 Panda Stonewall, LLC, FERC Docket No. ER17-1821-002
 DATC Path 15, LLC, Docket No. ER17-998-001 and EL17-61-001
 System Energy Resources, Inc., Docket No. EL17-41-001 and EL18-142-000  Consolidated Water Power Company, Public Service Commission of Wisconsin Docket No. 1330-ER-104

 American Electric Power Service Corporation (Appalachian Power Company, et al), FERC Docket No. ER11-46-016, ER11-47-013, et al. Joint affidavit with Julie M. Carey  American Electric Power Service Corporation (Appalachian Power Company, et al), FERC Docket No. ER11-47-014, et al. Joint affidavit with Julie M. Carey

 Railroad Control Application, Canadian Pacific Railway Limited; Canadian Pacific Railway Company; Soo Line Railroad Company; Central Maine & Quebec Railway US Inc; Dakota, Minnesota & Eastern Railroad Corporation; and Delaware & Hudson Railway Company, Inc. – Control – Kansas City Southern; The Kansas City Southern Railway Company; Gateway Eastern Railway Company; and The Texas Mexican Railway Company, U.S. Surface Transportation Board Docket No. FD 36500. Joint Verified Statement with Julie M. Carey  Liberty Utilities (EnergyNorth Natural Gas) Corp. d/b/a Liberty, request for change in distribution rates, New Hampshire Public Utility Commission Docket No. DG23-067

 Unnamed Entity, Utah Tax Commission, Utah Appeal Nos. 18-1322, 19-1325, 20-1512, 21-1212, 22-1345, and 23-957

 Old Dominion Electric Cooperative, Northern Virginia Electric Cooperative, Inc., and Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia, FERC Docket No. RM22-2-000 (2 filings)

 Ohio Power Company Application for New Tariffs Related to Data Centers and Mobile Data Centers, Public Utilities Commission of Ohio, Case No. 24-508-EL-ATA, on behalf of Enchanted Rock

PDF page 41

PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Dr. Bremser Affidavit, Attachment No. 1
Page 8 of 8

REPRESENTATIVE PUBLICATIONS AND PRESENTATIONS
PUBLICATIONS
“Two Essays on Convertible Debt”, Ph.D. dissertation, March 1997.
“Calculating a Taxable Damages Award: A Comparison of Two Calculation Methods”, Journal of Legal Economics, April 2010.

“Valuation of a Trade Subsidy Using Option Pricing Theory”, Journal of Legal Economics, April 2011.

Cantor, R and A. Bremser. “Market Share Liability from an Economics Perspective”, BRG Review, Winter 2014.

PRESENTATIONS
Presentation on issues in discounting cash flows, presentation to the Western States Petroleum Association (WSPA), South Lake Tahoe, CA, August 2007.

“Lost Profits: Principles, Methods and Strategies to Prove and Defend Damages”, presentation for The Knowledge Group, with Richard Eichmann of NERA, October 7, 2019.

“Energy Disputes and Litigation: Effective Strategies and Best Practices for the Year Ahead”, presentation for The Knowledge Group, with Julie Carey of NERA, December 5, 2019. “The Future of the U.S. Renewable Energy Disputes: Decoding Recent Trends and Updates”, presentation for The Knowledge Group, with Julie Carey of NERA, March 24, 2020. “Cost-of-Service and Rate Design for Oil Pipelines”, presentation to Bracewell LLP (law firm), with Julia Williams of NERA, August 31, 2021.

“Federal Energy Regulatory Commission (FERC) 101”, presentation to the Unitary Appraisal School, Western States Association of Tax Administrators Committee on Centrally Assessed Properties (WSATA-CCAP), Utah State University, January 28, 2025.

April 23, 2025