Response of Enchanted Rock, LLC on the Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings
Text extracted from the eLibrary original (SHA-256 29307f3748a7ec63…). Download the original from the official source.
Contents · 8 sections
- I. INTRODUCTION AND NEED FOR REFORM
- II. LCDG OPTION: LOAD CO-LOCATED WITH DISPATCHABLE GENERATION
- III. ENCHANTED ROCK’S RESPONSE TO SELECTED COMMISSION
- IV. CONCLUSION
- Attachment A
- III. REASONS TO UPDATE THE PJM TARIFF (POTENTIAL ISSUES WITH THE
- I. INTRODUCTION
- II. AFFIDAVIT PURPOSE AND SUMMARY CONCLUSIONS
Read topic-matched comments in EL25-49
Topics in the text: Cost allocation · Reliability and curtailment · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
Changes to the Tariff are necessary to effectuate the LCDG option and, therefore, Enchanted Rock respectfully submits that PJM’s existing Tariff is not just and reasonable.7 Enchanted Rock requests that the Commission issue an order directing replacement tariff provisions that allow customers in…Read this passage Filed comments: Reliability and curtailment
I. INTRODUCTION AND NEED FOR REFORM
printed heading · Topic match: Cost allocation
The accelerating demand for electricity coupled with supply delays caused by lengthy permitting processes for generation and transmission infrastructure, as well as persistent supply chain delays for equipment, means the industry must devise immediately implementable solutions that optimize…Read this passage Filed comments: Cost allocation
II. LCDG OPTION: LOAD CO-LOCATED WITH DISPATCHABLE GENERATION
printed heading · Topic match: Reliability and curtailment
Additionally, under Phase 1, Enchanted Rock proposes that projects choosing the LCDG option take a variation of non-firm transmission service to be called Available Transmission Capacity Service (“ATCS”),26 with commitments to dispatch co-located generation during PJM curtailments.Read this passage Filed comments: Reliability and curtailment
III. ENCHANTED ROCK’S RESPONSE TO SELECTED COMMISSION
printed heading · Topic match: Reliability and curtailment
Enchanted Rock’s Response: Currently, load and generation interconnection requests are studied separately.Read this passage Filed comments: Reliability and curtailment
IV. CONCLUSION
printed heading
CONCLUSION Wherefore, for the foregoing reasons, Enchanted Rock respectfully requests that the Commission consider the Response, and the recommendations of Enchanted Rock.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 23rd day of April, 2025. /s/ Steven ShparberRead this passage
Attachment A
printed heading
Bremser UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.Read this passage
TABLE OF CONTENTS
printed heading
TABLE OF CONTENTS HEADING PAGE I.Read this passage
III. REASONS TO UPDATE THE PJM TARIFF (POTENTIAL ISSUES WITH THE
printed heading
III.Read this passage
I. INTRODUCTION
printed heading · Topic match: Retail and wholesale authority
For over 20 years, I have been working on matters involving the energy industry in the areas of electricity and pipelines subject to FERC and state jurisdiction.Read this passage Filed comments: Retail and wholesale authority
II. AFFIDAVIT PURPOSE AND SUMMARY CONCLUSIONS
printed heading · Topic match: Cost allocation
Bremser Affidavit, Attachment No. 1 Page 6 of 8 Operating expenses (operations and maintenance (O&M), and general and administrative (G&A)) Application of cost causation principles to determine cost allocations Cost of service Tariff rate filing advisory and preparation of cost of service…Read this passage Filed comments: Cost allocation