EL25-49-000 · 2025-04-23 · Talen Energy Corporation
Comments of Talen Energy Corporation on Answer of PJM Interconnection, L.L.C. to the Order Instituting Proceeding Under Section 206 of the Federal Power Act…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
Large Loads Co-Located at Generating
)
Docket No. AD24-11-000
Facilities
)
Constellation Energy Generation, LLC
)
Docket No. EL25-20-000
)
(consolidated)
v. )
)
PJM Interconnection, L.L.C.
)
COMMENTS OF TALEN ENERGY CORPORATION
ON ANSWER OF PJM INTERCONNECTION L.L.C.
TO ORDER INSTITUTING PROCEEDING UNDER SECTION 206 OF THE
FEDERAL POWER ACT AND CONSOLIDATING WITH OTHER PROCEEDINGS
Time is of the essence for the Commission to order PJM Interconnection, L.L.C. (“PJM”) to file revisions to its Open Access Transmission Tariff (“OATT” or “Tariff”) to incorporate all eight of PJM’s proposed co-located load configurations in its Answer to the Show Cause Order (“Answer”).1 Talen Energy Corporation (“Talen”) largely agrees with the jurisdictional principles laid out by the Commission in its Show Cause Order2 and believes that specific grounds for the Commission’s jurisdiction over the types of large-scale co-location arrangements detailed in PJM’s Answer will depend on the specific facts and circumstances of each co-location arrangement.
1 PJM Interconnection, et al., Docket No. EL25-49-000, Answer of PJM Interconnection, L.L.C. (filed Mar. 24, 2025). (“PJM Answer”)2 PJM Interconnection, et al., Docket No. EL25-49-000, Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (filed Feb. 20, 2025) (“Show Cause Order”).
PDF page 2
2
Talen appreciates PJM’s endeavors to devise creative configuration options for the co- location of large load that meet the needs of its diverse stakeholders. All eight options presented by PJM for the co-location of large load are just and reasonable and not unduly discriminatory, and all required tariff changes for the latter five options should be implemented quickly into PJM’s Tariff. Ordering PJM to file amended Tariff language no later than thirty (30) days after such a Commission order is essential. It will provide stakeholders with the regulatory certainty they need to make investments that will support our national security goals and meet resource adequacy and reliability goals.
I. COMMENTS
A. FERC Has Limited Jurisdiction Over Co-Location Arrangements and Should Not
Interfere with Innovative, State-Led Approaches to Co-Located Load.
In broad strokes, Talen agrees with the general jurisdictional principles articulated in Section VI.A of the Commission’s Show Cause Order.3 It is well-settled that the Commission has jurisdiction over wholesale sales and transmission of electricity in interstate commerce, the facilities used for such sale and transmission, and rules or practices that “directly affect the wholesale rate.”4 States, by contrast, have exclusive jurisdiction over retail sales of electricity, and generation and distribution facilities. Congress explicitly “entrusted the choice of electric[ energy] generation to the States,” and States—through their siting, franchise, and other police powers—“retain authority to choose their preferred mix of energy generation resources.”53 Show Cause Order PP 66–73.4 See FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 278 (2016) (“EPSA”) (citation omitted); Show Cause Order P 66 & nn.210–11.5 See Show Cause Order PP 67, 70; Citizens Action Coal. of Ind., Inc. v. FERC, 125 F.4th 229, 238-39 (D.C. Cir. 2025).
PDF page 3
3
As the Commission’s November 2024 technical conference made clear, market
participants urgently require clarification about how the general jurisdictional principles described above apply to the specific issue of co-located load.6 Talen respectfully requests that the Commission use this proceeding to clarify that (1) FERC generally does have jurisdiction over the types of large-scale co-location arrangements discussed in PJM’s Answer to the Show Cause Order, and that (2) the particular basis (or bases) of the Commission’s jurisdiction will vary based on the specifics of the co-location arrangement.
1. The Basis for the Commission’s Jurisdiction Is Fact Specific and Will Vary for Each Co-Located Load Arrangement.
Talen agrees with PJM that “the Commission’s jurisdiction over transmission service in interstate commerce” is “necessarily implicated in matters relating to co-located load arrangements where generator interconnections are being modified” or where a generator’s interconnection service agreement (“ISA”) contemplates a co-located load arrangement.7 Phrased differently, the transmission interconnection service received by generators is itself a form of FERC-jurisdictional transmission service. FERC’s jurisdiction to evaluate whether such a generator’s ISA is just and reasonable will also extend to the co-located load arrangement, given that (1) the co-located load will be enabled and facilitated by equipment and facilities described in the FERC-jurisdictional ISA and (2) FERC’s evaluation of the ISA may consider specific reliability concerns, which in turn may require consideration of the co-located load arrangement and the extent to which the specific behind-the-meter configuration affects system reliability.8 In this regard, FERC would
6 Constellation Energy Generation, LLC, Docket No. EL25-20-000, Motion to Intervene and Comments of Talen Energy Corporation at 3 & nn.6–9 (filed Dec. 4, 2024); Constellation Energy Generation, LLC, Docket No. EL25-20- 000, Motion for Leave to Answer and Answer of Talen Energy Corporation at 7 & nn. 24–26 (filed Dec. 23, 2024).7 PJM Answer at 31.8 Under the FPA, FERC’s jurisdiction extends to any “classifications, practices, and regulations affecting . . . rates and charges, together with all contracts which in any manner affect or relate to such rates, charges, classifications, and services.” 16 U.S.C. § 824d(c). FERC explained in Order No. 1920 that its jurisdiction over the
PDF page 4
4
have limited jurisdiction over the co-located load arrangements set out in and contemplated by Options 4 and 5 in PJM’s Answer.
Talen appreciates that, with respect to other co-located load arrangements, there may be different (or supplementary) bases for FERC jurisdiction. For example, there may be situations in which sales from generators to co-located load are interstate sales, or when such sales constitute (or are indirectly enabled by) sales for resale; in either case, the co-location arrangement would be FERC-jurisdictional under Section 205 of the FPA. Moreover, there may be situations in which co-located load takes FERC-jurisdictional transmission service—e.g., when the co-located load is network load that has its own point of interconnection (PJM Option 1), when co-located load shares a point of interconnection with the generator but is separately metered as network load (PJM Option 2), or when co-located load is network load that either takes interruptible service (PJM Option 7) or participates in demand response (PJM Option 8).
The key point is this: Talen of course agrees that co-located load that actually uses transmission network or grid services—i.e., load that is directly connected to a generator with no grid power flow—should pay for those services to the extent they are used, and that the Commission has jurisdiction over the rates and terms of such transmission service, if it is in interstate commerce.9 The basis of FERC jurisdiction over each of the co-location
interstate transmission system includes a power to “respond[] to evolving reliability concerns.” 187 FERC ¶ 61,068, P 261 (2024). Thus, as Talen has previously explained, FERC “can take the reliability of the FERC-jurisdictional transmission grid into account” when evaluating ISAs or tariffs that implicate issues related to co-located load, “but that authority does not extend to changes in electricity demand and load growth presented by co-located load arrangements.” See PJM Interconnection, L.L.C, Docket No. ER24-2172-001, Comments of Susquehanna Nuclear, LLC in Support of the Deficiency Letter Response Filed by PJM Interconnection, L.L.C. at 8 (filed Sept. 24, 2024) (“Susquehanna September 2024 ER24-2172 Comments”).
9 See Large Loads Co-Located at Generating Facilities, Docket No. AD24-11-000, Comments of Talen Energy Corporation on Issues Related to Co-Location of Large Loads at Generating Facilities at 2 (filed Dec. 9, 2024) (“Talen Post-Conference Comments”).
PDF page 5
5
arrangements contemplated by PJM’s Answer is that each co-location arrangement takes a type of jurisdictional service.
However, if the load is not using any transmission network, point-to-point, or ancillary services, then the basis of FERC jurisdiction is not that the co-located load itself takes a FERC- jurisdictional form of transmission service. Instead, in such co-location arrangements, the ISA governing the co-location arrangement is the only part of the arrangement that is FERC- jurisdictional. The sole basis for the Commission’s jurisdiction will be that the co-location arrangement requires an amendment to the generators’ FERC-jurisdictional ISA (or alteration of an RTO/ISO pro forma document). This would occur, for example, when a generator decides to disconnect entirely from the grid to serve a behind-the-meter load. When the load has no grid connection, there can be no jurisdictional service.
2. The Utilities’ Jurisdictional Arguments Are Incorrect.
Exelon Corporation and aligned parties (together, the “Utilities”) have a different view of the Commission’s jurisdiction. In a series of related dockets, the Utilities have sought to extract two holdings from the Commission: (1) that co-located load always takes a form of FERC- jurisdictional transmission service and (2) that the interconnection of co-located load is not FERC jurisdictional. In addition to being internally inconsistent, those two arguments are both wrong. a. FERC Jurisdiction Over Transmission Service Provided to Co-Located
Load.
In the Susquehanna ISA proceeding (Docket No. ER24-2172), the Utilities have insisted that “[a]ll co-located load is grid connected” and that the Commission has jurisdiction due to the transmission service that the co-located load receives.10 These Utilities’ view is essentially that
10 Cf. PJM Interconnection, L.L.C., Docket No. ER24-2172-001, Exelon and AEP Request for Leave to Answer and Answer to Susquehanna, Constellation, and PPL Comments at 15–16 (filed Oct. 16, 2024).
PDF page 6
6
FERC cannot require transmission owners to accommodate interconnection of generators if the configuration involves co-located load. If credited, that view would create a situation even worse than the Attleboro gap, because (in this iteration of the vacuum) the transmission owners would happily occupy the vacant regulatory space, and exercise unilateral power to stop generators from serving co-located load merely by withholding their supposedly “required” consent to an amended ISA, and thus profit in all instances (by, e.g., functionally forcing data centers in front of the meter so as to achieve their long-term financial goals). That arrangement benefits no one except these Utilities. Of course, not all utilities share these views.
The Utilities’ suggestion that co-located load always takes a form of FERC-jurisdictional transmission service is driven not by any coherent description of the facilities in question, but rather by these Utilities’ desire to remain profitable within a market in which certain of their legacy services are increasingly less in demand. Their goal is to either (1) force large loads to interconnect with their systems in front of the meter, which in turn will enable them to build system upgrades, socialize the costs to their ratepayers, and collect a return on their investment; or (2) convince the Commission to adopt a blunt rule under which all behind-the-meter loads would be treated as network customers, which would enable the Utilities to charge rents to co-located load for services that it does not need or use. In short, these Utilities are determined to position themselves as intermediaries with veto power over privately-negotiated economic arrangements that do not involve them, but do limit their ability to collect rent when not actually providing service. It is of course true that co-located load is electrically connected to generation that in turn is often connected to the grid. But the fact that co-located load is indirectly connected to the grid, without more, does not mean that co-located load is taking FERC jurisdictional service from the
PDF page 7
7
grid.11 Indeed, the specifics of Susquehanna’s co-location arrangement make clear why it would be a mistake for the Commission to assert blanket jurisdiction over co-location arrangements based on that load’s supposed receipt of jurisdictional transmission service of ancillary services. As Talen has elsewhere explained at length, the data center co-located with Susquehanna is not a network customer and has no right to take transmission service or backup power from the grid.12 Susquehanna installed a protection scheme under which the co-located load will separate in the event of a loss of output from the generation facilities; in such a case, “redundant signals will be sent to an isolation breaker which will then open and prevent the co-located load from receiving any power or services from the grid,” meaning that it is physically impossible for power to be wheeled from the network to the generator and then to the co-located load.13 It therefore makes no sense to suggest that FERC’s jurisdiction over this type of co-location arrangement stems from any draw that the data center makes on the network, since such a draw would be impossible. Any assertion of FERC jurisdiction premised on the idea that “islanded” co-located load always takes jurisdictional transmission service would be overbroad and arbitrary. The practical effect of such an assertion would be to improperly federalize the entire electric system, in contravention of the careful jurisdictional lines Congress has drawn. Importantly, the Commission can order PJM to implement all five options not currently in its Tariff that it presented for the co- location of large loads while respecting the jurisdictional lines Congress has established.
11 PJM Interconnection, L.L.C., Docket No. ER24-2172-001, Motion for Leave to Answer and Answer of Susquehanna Nuclear, LLC at 2 (filed Oct. 22, 2024) (“Susquehanna October 2024 ER24-2172 Answer”); see id. at 4–6.12 See PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Motion for Leave and Answer of Susquehanna Nuclear, LLC at 9 (filed July 5, 2024).13 Susquehanna October 2024 ER24-2172 Answer at 3; see id. at 4–6.
PDF page 8
8
Further, it is important to consider the fact that large load customers are not opting to co- locate with a generator in an effort to avoid FERC (or state) jurisdiction. Instead, co-location often offers a faster path to energization that traditional utility connections (at least in the short-term). Transmission utility companies should not be permitted to slow down economic development simply to insert themselves and collect rent (at the expense of their ratepayers). b. FERC Jurisdiction Over Interconnection.
In Exelon’s pending PDO Proceeding (EL24-149), the Utilities have argued that the interconnection of end-use load is not FERC jurisdictional, supposedly because the interconnection procedures implemented by Order No. 2003 apply only to generation and not to load.14 At bottom, the Utilities’ position reduces to the notion that, if a State has jurisdiction over one stream of a wholesale generator’s output (e.g., a retail sale to co-located load), then the Commission somehow loses jurisdiction over that generator’s interconnection to the interstate grid.
That makes no sense. These Utilities cannot be right that the presence of non-jurisdictional facilities behind the meter divests FERC of all jurisdiction over the generator’s interconnection, because non-jurisdictional facilities (including the generator itself) always exist behind the meter. Interconnection service is a form of FERC-jurisdictional service, and a generator’s interconnection to the interstate transmission system does not stop being FERC-jurisdictional merely because there is co-located load behind the point of interconnection. For that reason, FERC has for decades approved amendments to ISAs designed to accommodate co-located load. Were that precedent not enough to resolve the question, Order No. 2003 itself expressly rejected the idea that FERC
14 See, e.g., Baltimore Gas & Elec. Co., Docket No. EL24-149-000 Baltimore Gas & Electric Company and PECO Energy Company Petition for a Declaratory Order at 1, 8–12 (filed Sept. 30, 2024).
PDF page 9
9
loses jurisdiction over interconnections if the generator makes behind-the-meter sales.15 The Utilities’ premise is also flatly undermined by the Supreme Court’s decision in EPSA, which confirmed that FERC can exercise jurisdiction over matters the FPA charges it with administering, even if the exercise of jurisdiction indirectly affects the States’ regulatory powers, so long as FERC’s action does not “target” the States’ domain.16
As a final matter, it bears mention that these Utilities’ jurisdictional theories cannot be squared with one another. Indeed, multiple commenters have already flagged how “odd[]” it is for the Utilities to argue in one proceeding that FERC lacks jurisdiction over co-located load, only to turn on a dime and argue in numerous other proceedings that FERC does have jurisdiction over co-located load and should leverage that jurisdiction to approve tariff proposals that would treat co-located load as always taking FERC-jurisdictional transmission service.17 The Commission should reject these Utilities’ outcome-driven jurisdictional theories.
3. The Commission’s Jurisdiction Is Limited to Establishing Operating
Parameters for Co-Located Load Arrangements.
Once the Commission confirms that it does have jurisdiction over the co-location arrangements contemplated by PJM’s Answer to the Show Cause Order, its next task will be to define the scope of that jurisdiction and explain how it will be exercised.
As the Supreme Court has explained, the Federal Power Act contemplates a system of cooperative federalism under which both FERC and the States have important roles to play.18 With
15 Order No. 2003, 104 FERC ¶ 61,103, PP 813–14 (2003).16 See EPSA, 577 U.S. at 264–65; see also Baltimore Gas & Elec. Co., Docket No. EL24-149-000, Protest of Constellation Energy Generation, LLC at 16 (filed Oct. 30, 2024) (“Constellation EL24-149 Protest”); Baltimore Gas & Elec. Co., Docket No. EL24-149-000, Protest of the PSEG Companies at 6–9 (filed Oct. 30, 2024) (“PSEG EL24- 149 Protest”).17 PSEG EL24-149 Protest at 5 n.16; see Baltimore Gas & Elec. Co., Docket No. EL24-149-000, Protest of Calpine Corporation at 4 (filed Oct. 30, 2024); Constellation EL24-149 Protest at 8 & n.25.18 See New York v. FERC, 535 U.S. 1, 20–24 (2002).
PDF page 10
10
respect to co-location, FERC’s limited role is merely to ensure that the rates and practices within its limited jurisdiction are “just and reasonable”19—e.g., that the co-location arrangement does not impair overall system reliability; that interconnections between generators and the grid are safe and reliable; and, when co-located load takes jurisdictional transmission service, that the rate for that service is reasonable. But because States have “regulatory authority over retail sales (as well as intrastate wholesale sales),”20 FERC cannot act to superintend the more granular details of co- located load arrangements.21 Likewise, FERC cannot prohibit or discourage co-location arrangements because of supposed retail rate impacts,22 and cannot force entities to participate in federally regulated energy or capacity markets.23 Nor can FERC put a thumb on the scale and favor one type of co-location arrangement or configuration over another; it is the role of the market—not the Commission—to pick winners and losers.24 In short, FERC’s role is simply to set basic guardrails within which co-location arrangements must operate.
States, by contrast, have the power to fill in the details. States control facility siting and the resource generation mix, as explained above. States decide which entities (if any) can make retail sales in co-location arrangements, and how costs will be recovered with respect to those sales. States should therefore be in the drivers’ seat with respect to crafting the bulk of the on-the- ground regulatory framework governing co-location. Indeed, a central feature of “Our
19 16 U.S.C. § 824d.
20 EPSA, 577 U.S. at 279.
21 The FPA makes clear that, while FERC does have jurisdiction over the “transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce,” it does not have jurisdiction over “any other sale of electric energy” nor over “facilities used for the generation of electric energy.” 16 U.S.C. § 824(b)(1).22 See Susquehanna September 2024 ER24-2172 Comments at 4–5.23 See id. at 4–5, 9.24 Talen Post-Conference Comments at 2.
PDF page 11
11
Federalism”25 is that the role of the federal government and its agencies is sometimes to get out of the States’ way. This is exactly such a case.
States are already rising to the moment. Indeed, many States are well along in developing frameworks to deal with the issue of co-location—frameworks that operate within the scaffolding erected by FERC, but that implement solutions tailored to local problems and reflect collaborative buy-in from a variety of stakeholders.
For example, Talen strongly supports ongoing efforts by regulators and policy leaders in Pennsylvania to develop a workable approach to co-location. On April 24, 2025, the Pennsylvania Public Utility Commission will hold a hearing to discuss large loads.26 At that hearing, numerous stakeholders—including transmission and distribution owners, large load customers, and consumer advocates—will present their views on how best to ensure a fair, transparent, and forward-looking approach to connecting high-energy users to the grid while protecting existing utility customers. The hearing will lay the groundwork for a forthcoming tariff for large loads in Pennsylvania.
These are exactly the kinds of collaborative efforts that FERC should encourage. Congress has elected to place States—the laboratories of democracy27—in a leadership role with respect to retail sales of electricity and behind-the-meter configurations. FERC should allow the States to discharge that duty, and should not use this proceeding to block (or interfere with) States’ efforts to develop solutions that work for them.
25 Younger v. Harris, 401 U.S. 37, 44 (1971).26 See Peter Hall, Pa. Public Utility Commission Sets Hearing on AI Data Centers’ Impacts on Electricity, Pennsylvania Capital Star (Mar. 28, 2025), https://tinyurl.com/msysv8cs. 27 See New State Ice Co. v. Liebmann, 285 U.S. 262, 311 (1932) (Brandeis, J., dissenting).
PDF page 12
12
B. The Eight Options Presented by PJM are Just and Reasonable, and FERC Should Order PJM to Make Necessary Modifications to its Tariff to Effectuate the Five Options Not Already in the PJM Tariff Within 30 Days of FERC’s Order.
It is important for the Commission to provide clarity and certainty to PJM, its stakeholders, and market participants. As such, Talen respectfully requests that the Commission direct PJM to submit Tariff modifications to address the five co-location configuration options proposed by PJM and not already addressed in its Tariff. Talen urges the Commission to order PJM to make all necessary Tariff modifications to effectuate the selection of Options 4 through 8 as a co-located load configuration within 30 days of FERC’s order in this proceeding.
As PJM explained in its Answer, its Tariff already contains language to configure co- located load as: network load with its own point of interconnection (“POI”) to the grid (Option 1); network load that shares the same POI with the generator but is separately metered (Option 2); or network load that has a behind-the-meter generation agreement with a co-located generator (Option 3).28 Conversely, PJM believes it will need to modify its Tariff language to allow co- location configuration arrangements where: co-located load is non-network load connected directly to a generator connected to the PJM transmission system with various protections in place to avoid the potential of delivery of system energy to serve the load (Option 4); co-located load is configured the same as Option 4 and also has conditional approval from PJM to take back-up power from the grid if necessary (Option 5); co-located load is network load and it brings additional generation to the PJM transmission system that could serve as a capacity resource for PJM (Option 6)29; co-located load is network load but it uses a new transitional non-capacity
28 PJM Answer at 9-13; see PJM Answer Ex. A. 29 Talen believes Option 6 is not actually a separate option for configuration. Instead, Talen believes Option 6 is a resource adequacy proposal. However, Talen does oppose PJM referring to and including Option 6 as a co-located load configuration option for the purposes of its Answer.
PDF page 13
13
backed service offering until any resource adequacy issues associated with its load addition are addressed (Option 7); or co-located load is network load and participates in PJM’s demand response programs (Option 8).30
The Commission has stated that it takes the reliability concerns raised by PJM with respect to issues of co-location of large load “extremely seriously.”31 The Commission should act decisively and quickly to support PJM, so that it can meet the needs of its stakeholders and ensure the ongoing reliability and stability of the PJM transmission system.
Talen agrees that co-located load directly connected to a generator connected to the PJM transmission system should pay for jurisdictional services, to the extent they are used. Talen has previously argued that the indirect connection of load to the transmission grid does not alone signify that such load is utilizing any jurisdictional services. If co-located load is not using any FERC jurisdictional services at all, the load should have no financial responsibility to pay for those services, including ancillary services. While Talen continues to believe this position to be correct, in the interest of compromise, Talen supports the current Option 4 that includes the load paying for certain ancillary services.
By offering multiple types of co-located load configurations in its Tariff—including ones that allow co-located load arrangements to not be network load and/or not take any jurisdictional services—PJM will be adopting the straightforward and easily applied principle that co-located load will pay for network or grid services to the extent the load uses those services.32 Ordering PJM to modify its Tariff so that it may implement as soon as possible all five options not currently
30 PJM Answer at 13-20; see PJM Answer Ex. A.31 Show Cause Order P 83.32 See Talen Post-Conference Comments at 2.
PDF page 14
14
in its Tariff will provide the regulatory certainty needed to encourage the growth of large load co- location while at the same time ensuring steady, reliable power for all ratepayers.
II. CONCLUSION
The framework presented by PJM is just and reasonable and not unduly discriminatory. PJM stakeholders rely on the Commission to make it possible for PJM to administer its transmission system in a way that meets the needs of its diverse stakeholders. The Commission has limited jurisdiction to order PJM to enact the framework it introduced. It is urgent that the Commission act in accordance with its jurisdiction as soon as possible to promote economic growth and support PJM in maintaining reliability on its transmission system.
Respectfully submitted,
/s/ William S. Scherman
William S. Scherman
Jeffrey M. Jakubiak
James T. Dawson
Melinda J. Warner
Vinson & Elkins LLP
2200 Pennsylvania Avenue, NW
Suite 500 West
Washington, DC 20037
Jennifer Mansh
Talen Energy Corporation
Senior Vice President, Regulatory and
External Affairs
600 Hamilton St., Suite 600
Allentown, PA 18101
Jennifer.Mansh@TalenEnergy.com
Counsel for Talen Energy Corporation
April 23, 2025
PDF page 15
15
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary in these proceedings. Dated at Washington, DC, this 23rd day of April 2025.
/s/ Melinda J. Warner
Melinda J. Warner
Vinson & Elkins LLP