EL25-49-000 · 2025-04-23 · Talen Energy Corporation

Comments of Talen Energy Corporation on Answer of PJM Interconnection, L.L.C. to the Order Instituting Proceeding Under Section 206 of the Federal Power Act…

Text extracted from the eLibrary original (SHA-256 97d5d317c0010832…). Download the original from the official source.

Contents · 4 sections
  1. I. COMMENTS p. 2
  2. A. FERC Has Limited Jurisdiction Over Co-Location Arrangements and Should Not p. 2
  3. B. The Eight Options Presented by PJM are Just and Reasonable, and FERC Should p. 12
  4. II. CONCLUSION p. 14

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

It will provide stakeholders with the regulatory certainty they need to make investments that will support our national security goals and meet resource adequacy and reliability goals.
Read this passage Filed comments: Connecting load and generation

I. COMMENTS

printed heading

I.
Read this passage

A. FERC Has Limited Jurisdiction Over Co-Location Arrangements and Should Not

printed heading · Topic match: Connecting load and generation

Talen agrees with PJM that “the Commission’s jurisdiction over transmission service in interstate commerce” is “necessarily implicated in matters relating to co-located load arrangements where generator interconnections are being modified” or where a generator’s interconnection service agreement…
Read this passage Filed comments: Connecting load and generation

B. The Eight Options Presented by PJM are Just and Reasonable, and FERC Should

printed heading · Topic match: Connecting load and generation

By offering multiple types of co-located load configurations in its Tariff—including ones that allow co-located load arrangements to not be network load and/or not take any jurisdictional services—PJM will be adopting the straightforward and easily applied principle that co-located load will pay…
Read this passage Filed comments: Connecting load and generation

II. CONCLUSION

printed heading

CONCLUSION The framework presented by PJM is just and reasonable and not unduly discriminatory.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, DC, this 23rd day of April 2025. /s/ Melinda J.