EL25-49-000 · 2025-04-23 · Bloom Energy Corporation
Comments of Bloom Energy Corporation
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
Docket Nos. EL25-49-000
AD24-11-000
EL25-20-000
(Consolidated)
COMMENTS OF BLOOM ENERGY CORPORATION
Pursuant to Rule 213 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Rules of Practice and Procedure,1 Bloom Energy Corporation (“Bloom”) submits comments in response to the Commission’s February 20, 2025 order.2 In addition to these comments, attached hereto is a report by the Brattle Group (“Brattle”) entitled, “Accelerating Integration of New Co-located Generation and Loads” (“Brattle Report”). Bloom’s comments herein focus on two approaches addressed in the PJM
Interconnection, L.L.C. (“PJM”) answer:3 (i) PJM’s existing Behind the Meter Generation rules (labeled Option 3), and (ii) PJM’s proposal for co-located load that brings its own generation (labeled New Option 6). Bloom appreciates PJM’s desire to expand options available to interconnect large load co-located with generation, but as explained below, finds that PJM has unnecessarily narrowed their applicability and created hurdles to their implementation. As Option 3 and New Option 6 are the only options included in the PJM Answer that apply to co- location with new generation, as opposed to existing generation, they are insufficient.
1 18 C.F.R. § 385.213.2 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (Feb. 20, 2025) (“Order”). Bloom submitted a doc-less motion to intervene in Docket No. EL25-49-000 on March 10, 2025.3 Answer of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Mar. 24, 2025) (“PJM Answer”).
PDF page 2
2
Given the identified national security goal to advance artificial intelligence (“AI”), there is a need to accelerate and coordinate the interconnection of data centers and co-located supply. The options proposed by PJM do not adequately meet this challenge. The Brattle Report assesses the concept of interconnecting new generation and co-located load as a composite facility called an “Energy Park,” which shares some traits with the approach PJM calls New Option 6. An Energy Park as analyzed by Brattle refers to: (i) load designated as Network Load,
(ii) co-located generation that provides primary power to load,4 and (iii) controls and protection mechanisms used to limit physical withdrawals and injections between the Energy Park and the grid to pre-specified amounts. Brattle finds that an integrated interconnection approach in assessing new load and new generation can significantly reduce the need for transmission upgrades, potentially avoiding billions in transmission expansion costs that have in the recent past been allocated to other consumers,5 while also significantly accelerating the interconnection timeline. This approach would in turn creates an incentive for data centers to bring along primary generation resources that supply their needs on-site, ease resource adequacy concerns that have been highlighted by PJM, NERC and others.
Bloom urges the Commission to develop and provide detailed guidance to PJM, as well as clear compliance deadlines for future filings to implement co-location tariff rules, including the reforms proposed in the Brattle Report.
4 Under this approach, there is no limitation on ownership of co-located generation. It may be owned by an independent generator, the co-located load itself, or a local utility. Bloom concurs with PJM and others that generation ownership may in these scenarios be driven by state law. Where, for example, state law grants a franchised utility the exclusive right to make power sales to retail customers, the direct sale by an independent generator to load may be prohibited.5 See, e.g., Protest and Comments of Maryland Office of People’s Counsel, Docket No. ER24-843-000 (Feb. 9, 2024).
PDF page 3
3
I. INTRODUCTION
The Commission has increasingly recognized the national security implications of AI data centers, particularly regarding their large energy demands and their role in supporting technologies. Likewise, both the current and prior administration have explicitly linked the advancement of AI infrastructure (including data centers) to national security. For example, on January 23, 2025, President Trump signed an executive order entitled “Removing Barriers to American Leadership in Artificial Intelligence,” requiring within 180 days of the order an action plan to enhance AI in order to promote economic competitiveness and national security.6 Accelerating the interconnection of data centers co-located with generation is an action that the Commission can take in support of this national security goal.
Bloom is a manufacturer of solid oxide fuel cell technology that utilizes an
electrochemical process to power non-combustion distributed energy resources that can be located either behind the meter or in front of the meter. Bloom’s solid oxide fuel cell systems are designed in a modular fault-tolerant format that provides critical reliability, and can be designed to provide three nines (99.9%) and five nines (99.999%) availability. Bloom has installed over 1.4 GW of its systems, of which over 300 MW power data centers. The fuel cell systems are baseload, with the ability to quickly ramp up and down to follow load fluctuations, and have been recognized as an excellent option for data centers in PJM and elsewhere.7 While Bloom can install hundreds of megawatts at a site in as little as 6 to 9 months, where grid interconnections are needed and interconnection queues are long, meeting a data center’s request
6 See https://www.whitehouse.gov/presidential-actions/2025/01/removing-barriers-to-american-leadership- in-artificial-intelligence/.7 In 2024, AEP entered into an agreement with Bloom to purchase and co-locate up to 1,000 MW of Bloom’s systems at data centers. See https://www.utilitydive.com/news/aep-bloom-energy-fuel-cell-data-center/733150/ (“AEP, Bloom Energy 1-GW fuel cell deal to power data centers would set new record”) (Nov. 18, 2024).
PDF page 4
4
for timely power is not possible. We urge the Commission to provide guidance to PJM in the development of new options to co-locate large loads and generation.
As highlighted in the eight options presented in the PJM Answer, co-located configurations generally fall into one of two general buckets:
• Network Load, Served by a Co-located Generator. Here, co-located load and generation are configured such that (1) load is designated as Network Load and may take power from the transmission grid to meet a portion of its demand, and (2) the generator makes physical sales directly to the co-located load and also may make PJM market sales (though the generator could also be dedicated solely to serve the co-located load). Current tariff rules require the co-located generator to enter the interconnection queue and be studied for “deliverability” to all PJM load either if the generator intends to engage in wholesale sales or will utilize the transmission grid to deliver energy to load.
• Behind-the-Meter, Isolated Load Served Co-located with an Existing Generator. This is the configuration being pursued by a number of nuclear plant owners located in the PJM region and elsewhere, as well as the owner of a natural gas facility located in Virginia. In this configuration, an existing interconnected generator co-locates new load and seeks to “isolate” the new load behind the co-located generator’s point of interconnection (“POI”). Whether the load must be designated as Network Load is a matter being litigated in this proceeding, but which Bloom does not address.
Both Bloom’s comments and the Brattle Report’s analysis focus on improvements to the interconnection rules associated with the first configuration. In particular, how to expeditiously interconnect generation and co-located load (both new) as a composite facility. The Brattle Report employs the term “Energy Park” to describe this configuration. While the term Energy Park has previously referred to a collection of different supply technologies, focusing on variable energy resources,8 as used in the Brattle Report an Energy Park consists of three functional components: (i) generation that serves as primary power for on-site supply and is subject to PJM
8 See, e.g., https://energyinnovation.org/wp-content/uploads/Energy-Parks-Report.pdf.
PDF page 5
5
interconnection,9 (ii) co-located load, and (iii) a physical control or protection mechanism to potentially limit maximum flows in and out of the Energy Park at the POI.
By planning to co-locate new primary generation that can run at any time, the co-located load can supply all or part of its energy and resource adequacy on-site, thereby minimizing the impact on markets and transmission and supporting the interconnected grid. And by reflecting the controllable nature of Energy Park withdrawals and injections to the grid through one or more control and protection mechanism, properly structured studies that reflect the integrated nature of these resources when performed by PJM and transmission owners are less likely to identify expensive and time-consuming transmission upgrades, thus facilitating the interconnection of new loads and much needed new supply. Any net injections by generation or net withdrawals by load at an Energy Park would depend on what the grid is able to accommodate in real-time operations. Thus, withdrawals by load would be based on available grid capacity, and injections (market sales) by the co-located generator would be on a non-firm basis. Brattle demonstrates that all of this can be accomplished while meeting PJM- and NERC- mandated N-1 and N-1-1 requirements.
Adoption of Brattle’s proposed integrated interconnection process for Energy Parks will require a number of reforms in the studies, protocols and procedures of PJM and transmission owners, which are necessary to achieve the speed and cost benefits of the proposal, including:
• PJM and transmission owners: develop and document protocols for integrated Energy Parks interconnection studies, as an alternative to the currently applicable separate study processes, including the PJM generator interconnection study process, the PJM ‘Do No Harm’ study, transmission owner load integration study, and in limited cases the PJM regional transmission expansion process (RTEP). Protocols would need to include provisions for coordination between separate study processes.
9 Note that PJM interconnection studies are not required for all behind-the-meter generator interconnections. See infra at note 11. Bloom’s comments herein do not seek to expand the scope of PJM’s jurisdiction to study the interconnection of new generation.
PDF page 6
6
• PJM and/or transmission owners: Document technical standards for the Energy Park controls and protection mechanisms used to limit physical withdrawals and injections between the Energy Park and the grid to the pre-specified amounts. Develop provisions to ensure that PJM and transmission operators can rely on the Energy Park to control net injections or withdrawals when grid capacity is limited (during contingencies) in real time operations.
• PJM: allow for and study non-firm grid injection requests based on “as available” grid capacity (i.e., less firm than current Energy-only interconnections. Study these non-firm Energy Park injections through an expedited screening process similar to that of PJM’s new Surplus Interconnection Service (SIS) or Capacity Interconnection Rights (CIR) replacement processes, given that non-firm net injections by the Energy Park can be controlled automatically so they will not cause transmission impacts beyond the designated levels.
Collectively, the reforms will lead to an accelerated interconnection process and will incentivize new data centers and other large load customers to bring their own generation, thus helping to meet the resource adequacy needs of the region, while also reducing consumer billing impacts from large load growth.
II. Comments
Bloom’s comments in response to the PJM Answer focus on PJM’s Option 3 (existing Behind the Meter Generation rules) and New Option 6 (Co-located load that elects to be Network Load and bring own generation BYOG). As to Option 3, PJM makes clear its lack of support for large loads to use of the Behind the Meter Generation tariff rules and omits that this option has been employed by both large and small loads over the past two decades. Regarding New Option 6, the PJM matrix provides that all generation associated with New Option 6 must be a capacity resource, which as a result calls into question PJM’s statement that the option is available both to physical and financial arrangements by co-located load that brings its own generation. Finally, we briefly describe the attached Brattle Report on “Accelerating Integration of New Co-located Generation and Loads.”
PDF page 7
7
A. Option 3: PJM Should Clarify its Statements that Existing Behind the Meter
Generation Rules were Not Intended for Use by Large Load (Question a.iv)
In describing the existing Behind the Meter Generation rules,10 PJM repeatedly states that its use was never intended for large loads: “While this option is already available under the Tariff, it was conceived for, and has been implemented for, substantially smaller loads (like large warehouse with solar panels) and not on the scale of large data centers.”11 Data centers can have a range of customer loads—from just a few megawatts, to tens of megawatts, to hundreds of megawatts. PJM, however, neither defines what it deems to be a “large load” nor provides the Commission with any sense of the customers being served by Behind the Meter Generation
today, beyond large warehouses and solar panels.
For years, cogeneration facilities have served behind the meter customers. For example, the Linden Cogeneration Plant (Linden 6) sells to a behind the meter customer, the Tosco refinery, up to 160 MW.12 Likewise, Delaware City Refining Company owns a 324 MW
combined cycle cogeneration facility, which has been described as “an integral part of the Delaware City refinery and refining operations.”13 Although the exact amount of customer load served from the co-located generation facility is unknown, it can readily be distinguished from
10 Pursuant to the tariff’s definition of Behind the Meter Generation, there are three criteria that a generator must meet: 1) it delivers generation to load without using the transmission or distribution grids; 2) it is not a capacity resource; and 3) it does not engage in wholesale energy sales. Per PJM Manual 14G, Generation Interconnection Requests Sec. 1.6 Behind the Meter Generation, “generating resources operating “behind the meter,” in isolation from the PJM bulk power transmission system and which do not intend to participate in the PJM wholesale energy market, need only coordinate planning, construction and/or operation with the host Transmission Owner.” Such facilities do not need to complete the interconnection process if the facility does not intend to engage in wholesale sales or utilize the transmission grid to deliver energy to load.11 PJM Answer at 13; see also id. at 11 (Description: “Large load behind generation was not intended”); id. at12 (PJM Preference: “Not for Large Loads”); id. at 34 (Behind the Meter Generation “paradigm does not fit co- location arrangements particularly well because it was not designed with large load co-location in mind”). 12 See https://www.pjm.com/pjmfiles/pub/planning/project-queues/isa/y1_026_isa.pdf.13 See Delaware City Refining Company LLC, Amended Application for Market-Based Rate Authorization, Docket No. ER10-1093, at p. 3 (May 25, 2010). The refinery is owned by an affiliate of Delaware City Refining Company.
PDF page 8
8
smaller loads like a large warehouse and solar panels. In addition, the Commission’s recent consent agreement with Stronghold Digital Mining implies its 85 MW generator serves its vertically integrated Bitcoin mining operation behind the meter, given the significant percentage of hours Stronghold failed to offer in the market.14 And, there are numerous other examples of cogeneration that is co-located and serving load behind a single meter. PJM ought not write off this import existing means to interconnect both large and small load.
Perhaps underlying the assertion that Behind the Meter Generation rules were never intended for larger loads is PJM’s conclusion that it is not clear that the netting of loads served by Behind the Meter Generation should apply to co-located data center load.15 PJM proffers that “very large loads like data centers” (another undefined term) perhaps should be treated differently based on cost causation principles,16 yet provides nothing more. Bloom urges the Commission to take no action that would undermine or call into question the existing Behind the Meter Generation rules based on the limited facts set forth in the PJM Answer.
B. Option 6: PJM’s bring your own generation with incentive for faster
interconnection when the load is Network Load is too narrow (Question d.vii)
Bloom appreciates PJM expanding its ideas on co-located resources by recognizing that faster interconnections ought to be both possible and practical.17 With regard to New Option 6, which PJM describes as a “Bring Your Own Generation” approach for interconnecting new co- located generation and load more quickly, PJM notes that: “[i]ncentives would be explored to offer faster processing of generation that enters the queue through this option [6]” including
14 Stronghold Digital Mining Inc., et al., 190 FERC ¶ 61,059 (2025) (see id. at 8 (failing to offer in the hour- ahead market 67% of the time and the real-time market 69% of the real-time hours, implying that over half of the plant’s available energy during the relevant period was used for mining rather than being sold to the grid)).15 PJM Answer at 35.16 Id. at 36-37.17 See id. at 17.
PDF page 9
9
“providing options for accelerating interconnection studies of new generation proposed as part of this option.”18 Nevertheless, PJM offers no specifics.
PJM’s desire to accelerate interconnection studies for new generation brought on by new large load is in conflict with a requirement in New Option 6 that the co-located generator be a capacity resource.19 As a capacity resource, a generator must have firm Capacity Interconnection Rights. But acquiring Capacity Interconnection Rights should be an option and not a mandate. As discussed further below and in the Brattle Report, where generation is contractually meeting the load requirements of co-located load and only seeking to inject energy—that is, make market sales—on an as-available, non-firm basis, PJM ought not require a generator to be a capacity resource. If co-located generation must have Capacity Interconnection Rights, PJM’s “deliverability” interconnection study process tests the network’s ability to deliver the full output of the new generation to all PJM load, thus ignoring the intent of the generation to supply the co- located load resource on-site at the same grid connection point. Such overbroad studies, in turn, likely will lead to overstated transmission upgrade requirements and long interconnection queue processes.20
Additionally, the requirement to have Capacity Interconnection Rights seems to undermine PJM’s conclusion under New Option 6 that a physical co-location or financial arrangement can be utilized.21 A financial arrangement is in essence a contract for differences associated with the co-located generator’s market sales of energy and capacity. PJM’s capacity resource mandate appears to undermine the physical co-location option. Under the PJM tariff
18 Id.19 See Id., Appendix A, New Option 6 (identifying the generator as a capacity resource and a source of revenues being capacity “based on full CIRs”).20 See Brattle Report at pp. 10-11.21 PJM Answer at 17.
PDF page 10
10
rules, a capacity resource must submit offers into the day-ahead and real-time energy markets.22 As a result, a requirement that a co-located generator be a capacity resource appears to mandate that the generator enter into a financial contract with co-located load, as contractual terms and market clearing prices will differ. Where co-located load is seeking only a physical arrangement, requiring the co-located generator to be a capacity resource could interfere with contracting and, through such a disincentive, undermine the resource adequacy sought by New Option 6.
C. Brattle Report: Integrated Energy Park Interconnection is a Practical
Solution (Questions d.vii, e.v, f.i, f.iii, and f.iv)
The attached Brattle Report assesses the concept of interconnecting new generation and co-located load as a composite facility called an Energy Park. This is not a unique concept. The Electric Reliability Council of Texas (“ERCOT”) has been doing so for years through its approach to interconnecting Private Use Networks. Brattle describes the process it proposes as “Energy Park Integration” (“EPI”) interconnection, where the Energy Park is studied as a composite load and generation facility, instead of studying the load in one process and the generation in another.23
Because an Energy Park supplies all or part of its load on-site, when studied as an integrated unit, it can be connected to the grid with fewer transmission upgrades (thus accelerating the interconnection). That is not the case today, as there are no existing protocols for doing so. Transmission owners may study the new load component of an Energy Park
22 Under the Appendix to Attachment K of PJM’s Tariff, Section 1.10.1A(d), a capacity resource is required to: (1) offer its Installed Capacity (ICAP) equivalent of the resource’s cleared Unforced Capacity (UCAP) into the PJM energy markets every day if not on outage or derated; and (2) be available for scheduling and dispatch unless the unit designates its offers as a “Maximum Emergency” offer (requiring it to fall under at least one of four tariff- defined categories).23 While each of PJM and the transmission owner may have different roles in the study, both would take the Energy Park as a whole into account for purposes of their studies, similar to the coordinated roles currently in place in the interconnection queue for generators.
PDF page 11
11
(without recognizing the co-located generation), while PJM may study interconnection of the new generation (without recognizing the co-located load). These bifurcated, non-integrated processes ignore the on-site supply benefits and overstate the necessary transmission upgrades, which result in slowing down interconnection and unnecessarily increasing costs.24 The proposed EPI approach by Brattle models the composite behavior of load and generation in an Energy Park by accounting for three essential components: the generator, load, and a control mechanism that limits net exchanges with the grid. Net load impacts would be limited to just the nominated net grid withdrawal by load, while net injection impacts from the generation would be limited to the nominated injection level.
The Brattle Report demonstrates that the EPI approach can lower transmission impacts and interconnection time without sacrificing reliability (and indeed, improving it through accelerated integration of new supply). The report steps through the standard contingency studies used for load reliability planning to show that the proposed EPI study approach yields lower transmission impacts even considering the contingency cases used in transmission planning. These analyses also show the role of the control mechanism in reducing such transmission impacts.25
The Brattle Report further explains how the EPI study is practical. ERCOT for one has adopted an integrated approach to studying Private Use Networks, representing over 16,000 MW, a quarter of which was added in the last decade.26 Other regions have considered similar
24 Brattle Report, p. 12-13.25 Id. at pp. 13-22.26 Id. at p. 22.
PDF page 12
12
approaches, and Google recommended fast-track connection of co-located load and generation in Docket No. AD24-11-000.27
The PJM “deliverability” studies currently used to study both network and energy-only generation resources will require reform to implement an EPI approach for Energy Parks that seek to net inject to the grid on a non-firm basis. Because an Energy Park is designed primarily to supply on-site co-located load and would inject energy to the grid only to the extent grid capacity is available or when doing so is beneficial to system reliability, interconnection studies ought to reflect the controllable, as-available, non-firm nature of injections from Energy Parks. Transmission owners studying load likewise would need to adopt processes to incorporate assumptions related to the co-located generator in their load studies. This is possible so long as PJM and transmission owners know that Energy Parks have control and protection mechanisms in place to limit grid injections and withdrawals.28 Interconnection studies of the co-located generation can be performed on an expedited basis using protocols similar to PJM’s recently- revised CIR Replacement process or Surplus Interconnection Service, as controllable net injections will not cause transmission impacts beyond the designated levels. In exchange, PJM could provide for non-firm grid injection requests based on “as available” grid capacity (i.e., less firm than current energy-only interconnections).29
As the Brattle Report concludes: “By avoiding unnecessary transmission upgrades to accommodate new large loads, the EPI process avoids any costs that would otherwise be allocated broadly to all customers. By facilitating and accelerating a ‘bring-your-own capacity’
27
Id. at p. 23 and note 34 (citing Post-Technical Conference Comments of Google LLC, Docket No. AD24- 11-000, at p. 5 (filed Dec. 10, 2024)).
28 Brattle Report at pp. 24-28.29 Id.
PDF page 13
13
approach, the proposal mitigates the resource adequacy impact of load growth, easing price increases in the capacity market ad the commensurate bill impacts for all consumers.”30 The Commission should direct PJM to expeditiously implement the EPI approach for Energy Parks.
III. CONCLUSION
For the foregoing reasons, Bloom urges the Commission to provide detailed guidance to PJM, and set forth compliance deadlines for future filings to implement co-location tariff rules including the EPI approach developed in the Brattle Report for studying Energy Parks.
Respectfully submitted,
/s/ Joel D. Newton
Joel D. Newton
Vice President, Regulatory Law
Bloom Energy Corporation
4353 North First Street
San Jose, CA 95134
(202) 329-1119
joel.newton@bloomenergy.com
April 23, 2025
30 Id. at p. 31.
PDF page 14
14
CERTIFICATE OF SERVICE
I hereby certify that I have on this 23rd day of April, 2025, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.
/s/ Joel D. Newton