EL25-49-000 · 2025-04-23 · Bloom Energy Corporation

Comments of Bloom Energy Corporation

Text extracted from the eLibrary original (SHA-256 f5e9134e095b0a84…). Download the original from the official source.

Contents · 6 sections
  1. I. INTRODUCTION p. 3
  2. II. Comments p. 6
  3. A. Option 3: PJM Should Clarify its Statements that Existing Behind the Meter p. 7
  4. B. Option 6: PJM’s bring your own generation with incentive for faster p. 8
  5. C. Brattle Report: Integrated Energy Park Interconnection is a Practical p. 10
  6. III. CONCLUSION p. 13

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

Bloom’s comments herein focus on two approaches addressed in the PJM Interconnection, L.L.C. (“PJM”) answer:3 (i) PJM’s existing Behind the Meter Generation rules (labeled Option 3), and (ii) PJM’s proposal for co-located load that brings its own generation (labeled New Option 6).
Read this passage Filed comments: Connecting load and generation

I. INTRODUCTION

printed heading · Topic match: Connecting load and generation

Here, co-located load and generation are configured such that (1) load is designated as Network Load and may take power from the transmission grid to meet a portion of its demand, and (2) the generator makes physical sales directly to the co-located load and also may make PJM market sales (though…
Read this passage Filed comments: Connecting load and generation

II. Comments

printed heading · Topic match: Connecting load and generation

Regarding New Option 6, the PJM matrix provides that all generation associated with New Option 6 must be a capacity resource, which as a result calls into question PJM’s statement that the option is available both to physical and financial arrangements by co-located load that brings its own…
Read this passage Filed comments: Connecting load and generation

A. Option 3: PJM Should Clarify its Statements that Existing Behind the Meter

printed heading · Topic match: Cost allocation

Perhaps underlying the assertion that Behind the Meter Generation rules were never intended for larger loads is PJM’s conclusion that it is not clear that the netting of loads served by Behind the Meter Generation should apply to co-located data center load.15 PJM proffers that “very large loads…
Read this passage Filed comments: Cost allocation

B. Option 6: PJM’s bring your own generation with incentive for faster

printed heading · Topic match: Connecting load and generation

Under the PJM tariff 18 Id. 19 See Id., Appendix A, New Option 6 (identifying the generator as a capacity resource and a source of revenues being capacity “based on full CIRs”). 20 See Brattle Report at pp. 10-11. 21 PJM Answer at 17. 10 rules, a capacity resource must submit offers into the…
Read this passage Filed comments: Connecting load and generation

C. Brattle Report: Integrated Energy Park Interconnection is a Practical

printed heading · Topic match: Connecting load and generation

Brattle describes the process it proposes as “Energy Park Integration” (“EPI”) interconnection, where the Energy Park is studied as a composite load and generation facility, instead of studying the load in one process and the generation in another.23 Because an Energy Park supplies all or part of…
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, Bloom urges the Commission to provide detailed guidance to PJM, and set forth compliance deadlines for future filings to implement co-location tariff rules including the EPI approach developed in the Brattle Report for studying Energy Parks.
Read this passage

CERTIFICATE OF SERVICE