Brattle Energy Park Integration Report 2025-04-23
Text extracted from the eLibrary original (SHA-256 221ef96d8455745c…). Download the original from the official source.
Contents · 10 sections
- A. EPI-Based Contingency Studies Reduce Transmission Impacts and Interconnection
- C. The Benefits of an EPI Approach Are Highest When Energy Parks Can Dependably
- Executive Summary
- Introduction
- A. EPI-Based Contingency Studies Reduce
- B. Experience Elsewhere Highlights the Practicality of
- C. The Benefits of an EPI Approach Are Highest When
- A. The Status Quo Does not Achieve the Benefits of
- B. Reforms Can Achieve Energy Park Integration
- Conclusion
Read topic-matched comments in EL25-49
Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
Accelerating Integration of New Co-located Generation and Loads Brattle.com | Accelerating Integration of New Co-located Generation and Loads PREPARED BY Andrew Levitt Johannes Pfeifenberger Aniruddh Mohan PREPARED FOR Bloom Energy Accelerating Integration of New Co-located Generation and Loads…Read this passage
TABLE OF CONTENTS
printed heading
TABLE OF CONTENTS Executive Summary................................................................................................. 1 Introduction ...................................................................................................... 7 Energy Park Integration Is a Practical Way to…Read this passage
A. EPI-Based Contingency Studies Reduce Transmission Impacts and Interconnection
printed heading
Experience Elsewhere Highlights the Practicality of Energy Park Integration Studies .. 22Read this passage
C. The Benefits of an EPI Approach Are Highest When Energy Parks Can Dependably
printed heading · Topic match: Reliability and curtailment
C.Read this passage Filed comments: Reliability and curtailment
Executive Summary
printed heading · Topic match: Reliability and curtailment
In some cases, new large loads exceed existing transmission capacity, and new customers must wait while (potentially costly) transmission upgrades are made.Read this passage Filed comments: Reliability and curtailment
Introduction
printed heading · Topic match: Connecting load and generation
In some cases, new large loads must wait years while time-consuming and costly transmission upgrades are made.10 Importantly, PJM has expressed significant concerns over resource adequacy challenges.11 Speed to market is a critical motivation for many new large data center customers, as the ability…Read this passage Filed comments: Connecting load and generation
A. EPI-Based Contingency Studies Reduce
printed heading · Topic match: Connecting load and generation
Accelerating Integration of New Co-located Generation and Loads Brattle.com | 13 which do not need to be deliverable and can be limited operationally to only those intervals in which the grid is available to accommodate them.23 Energy Park customers that wish to request more firm generation…Read this passage Filed comments: Connecting load and generation
B. Experience Elsewhere Highlights the Practicality of
printed heading · Topic match: Connecting load and generation
For interconnecting PUNs to the ERCOT grid, ERCOT and the interconnecting transmission owner study the PUN in an integrated process as independent load, independent generation, and a composite of both load and generation.31 With over 16,000 MW of PUN capacity in ERCOT, a quarter of which has been…Read this passage Filed comments: Connecting load and generation
C. The Benefits of an EPI Approach Are Highest When
printed heading · Topic match: Reliability and curtailment
To ensure a reliable system, planners must know that operators can depend on the Energy Park controller to restrict “non-firm” purchases when the grid is not available to facilitate them.Read this passage Filed comments: Reliability and curtailment
A. The Status Quo Does not Achieve the Benefits of
printed heading · Topic match: Connecting load and generation
At the same time, new load requesting to be integrated in PJM must be studied through a two- step process that involves: (1) a transmission owner retail load integration study that identifies local upgrades required to meet load based on the transmission owner’s criteria;36 and (2) a PJM ‘Do No…Read this passage Filed comments: Connecting load and generation
B. Reforms Can Achieve Energy Park Integration
printed heading · Topic match: Reliability and curtailment
While generators who qualify as Capacity Resources must coordinate their outages with PJM, there are no such provisions for energy-only resources or Energy Parks. 42 Energy Parks with zero net injections can be incorporated into real time operations (SCED) in the same way as injecting Energy Parks.Read this passage Filed comments: Reliability and curtailment
Conclusion
printed heading · Topic match: Reliability and curtailment
First, the dispatchable new Energy Park generation serves the resource adequacy needs of the Energy Park load, mitigating PJM’s resource adequacy challenges.Read this passage Filed comments: Reliability and curtailment