Comments of EDF Renewables, Inc. in response to PJM Interconnection, L.L.C.’s Answer filed on 03/24/2025
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. EL24-49-000
Allegheny Electric Cooperative, Inc.
American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
PDF page 2
2
Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
Docket No. AD24-11-000
Constellation Energy Generation, LLC
Docket No. EL25-20-000
(consolidated)
v.
PJM Interconnection, L.L.C
COMMENTS OF EDF RENEWABLES, INC.
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (Commission or FERC),1 EDF Renewables, Inc. (EDFR) respectfully submits these comments in response to the answer filed by PJM Interconnection, L.L.C. (PJM) on March 24, 2025 (PJM Answer). The PJM Answer was filed in response to the Commission’s Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings, issued on February 20, 20252 regarding the co-location of large loads in PJM.
1 18 C.F.R. §§ 385.212, 385.213 (2024). 2 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (2025) (February 20 Order).
PDF page 3
3
I. SUMMARY OF COMMENTS
The challenges of serving new large load data centers are present across the country. Data centers and their co-location arrangements can take many forms, including structures with operational flexibility that can provide a host of benefits to the transmission system, and some that have less operational flexibility and thereby place more demands on the transmission system. Although this proceeding is directed at PJM, any decision in this proceeding may have implications for other regions as well. EDFR urges the Commission in this proceeding to adopt a flexible, performance-based framework that recognizes large load diversity within the data center industry and other industries (hydrogen, e-fuels, and Carbon Capture, Utilization and Storage (CCUS)), encourages “grid-light” development structures, and avoids inadvertently penalizing innovative co-located load configuration models. Such a flexible framework can be replicated in other regions.
Co-location can streamline the interconnection process, reduce the need for expensive grid upgrades, and minimize delays in bringing new generation and load online. Not all large electricity-consuming facilities that co-locate with existing or new power generators need to undergo the same interconnection and reliability planning processes. Some large loads can locate in areas with surplus energy – generation pockets where frequently-curtailed energy is “trapped” behind constrained transmission. Locating large loads in these generation pockets will prevent curtailed energy from being wasted, reduce the frequency of the transmission constraints, and may allow the load to be integrated faster with less impact on the bulk electric system. In effect, this load could delay the need for flowrate capacity expansion and reduce congestion cost in the case of an RTO LMP market structure. Due to their flexibility, large curtailable loads can
PDF page 4
4
provide net benefits to the grid by reducing congestion, delaying need for transmission, and providing demand response services when needed.
In contrast, some co-locating loads are highly dependent on uninterruptible service and thus place significantly more demand on the grid. Loads that lack operational flexibility can lead to grid instability, unexpected power shortages and higher costs for other consumers. Large inflexible loads should not dictate a set of rules that apply to more operationally flexible, potentially beneficial, co-location arrangements. Rather, the rules governing large co-located loads should be balanced with the ability for grid operators to use the flexibility of that load to operate the system more reliably. Further, the more flexible the load, the simpler it should be to interconnect behind a generator’s meter, thus warranting different rules for interconnecting. Large loads are not one-size-fits-all and the processes for interconnecting, serving, and allocating costs to large loads should accommodate this diversity. This proceeding presents an opportunity for the Commission to establish rules that (1) encourage co-location development in a way that allows large flexible co-located loads to interconnect expeditiously and efficiently and
(2) can be applied to various reliable and commercially beneficial structures across the country.
II. BACKGROUND
EDFR, develops, builds, operates, and manages renewable energy projects throughout North America, including in PJM, MISO, SPP and ERCOT. As a market-leading independent power producer and service provider for over 35 years, EDFR delivers grid-scale power, including wind (onshore and offshore), solar photovoltaic, and storage projects; distribution- scale power, including solar and storage, and asset optimization. The company also provides technical, operational, and commercial expertise to maximize performance of generating
PDF page 5
5
projects. EDFR is an active participant in interconnection-related policy discussions and rulemaking proceedings, including interconnection reform efforts.
EDFR has also been exploring data center co-location in other parts of the country and has announced plans for a 166 MW data center to co-locate with EDFR’s 273 MW Las Majadas Wind Project in ERCOT. The data center will connect to EDFR’s private substation and the data center and Las Majadas will co-own as tenants-in-common the private electric delivery facilities interconnected to the grid pursuant to a Shared Facilities Agreement.
The data center will utilize behind-the-meter (BTM) power generated by the wind project, while also curtailing their operations under certain market conditions when energy is most needed by the grid. This BTM offtake arrangement presents a unique advantage for market-exposed renewable projects by physically delivering a portion of a plant’s power directly to the co-located buyer’s facility. This innovative power purchase agreement (PPA) structure provides a flexible solution to the challenges of transmission constraints and curtailment, essentially allowing an alternate route to capture under-utilized electricity. Concurrently, it provides an opportunity for an energy-intensive load that is seeking clean power solutions to fulfill that need while advancing computing applications, including artificial intelligence (AI).
III. COMMENTS
As the Commission noted in the February 20 Order, co-located load arrangements are becoming increasingly common, in large part driven by the development of new data centers (e.g., facilities used for AI, cloud data storage, and cryptocurrency mining, etc.).3 Many of these new large load facilities are already operating, and forecasts suggest that many more are in development. Traditional utility structures and current RTO interconnection rules are often
3 February 20 Order at PP 3, 15
PDF page 6
6
unworkable to meet this new demand, in large part due to the facilities’ near-term need for power. Given the speed with which the new large load facilities can be built, the existing load interconnection process and the congested generator interconnection processes currently in place are often insufficient to meet the timing of power needs. Co-location structures have emerged as a solution to meet this need. The question is how these large load facilities can co-locate with existing power generators in a manner that is just and reasonable and not unduly discriminatory for cost allocation purposes and that is reliable from a grid operation perspective.
A. The Commission Should Act Expeditiously to Encourage Flexible Co-
Location Structures that Will Enable Speedy and Reliable Interconnection
for Large Loads.
This proceeding is an opportunity for the Commission to provide guidance to PJM and other RTO/ISO and non-RTO/ISO regions for developing a standardized and transparent load interconnection process at the federal level. A generic rulemaking proceeding would take too long. It is possible that a case-by-case approach can be workable if it is fair and non- discriminatory, such as the Expedited Project Review Request in MISO. In some instances, existing rules prohibit certain co-location arrangements that should otherwise be allowed. For example, EDFR has found that SPP does not provide a co-location option for optimal commercial operation in that region.4
Here, the Commission has an opportunity to determine what structures work and how costs should be allocated, and to identify the barriers to the efficient and reliable co-location of large loads. Lessons learned and best practices identified here should be applicable across other
4 For example, SPP does not allow netting for grid-connected behind-the-meter generation and most exemptions from network load status are for non-grid connected and non-market participation generation. SPP Tariff, Att. AE.
PDF page 7
7
regions on an expedited basis to ensure that new large loads can be served while maintaining reliability and ensuring that existing customers are not bearing unnecessary costs. The Commission can encourage PJM and other RTOs, as well as transmission providers in non-RTO regions to develop standardized yet flexible rules to accommodate different co- location structures with varying operational capabilities. Specifically, the Commission should:
1. Clarify that co-located loads using non-firm grid power and backed by onsite generation may qualify for modified transmission cost allocation (e.g., based on usage, not full network load charges).
2. Direct each RTO and ISO to develop and file tariff provisions for co-located load and generation under a shared interconnection with clear netting, metering, and settlement rules.
3. Consider standardized registration and modeling of flexible co-located load behind interconnections.
4. Encourage RTOs/non-RTOs, if not already the case, to simultaneously evaluate flexible load and generation with expedited timelines.
5. Ensure that any capacity market participation requirements for co-located generation should depend on the type of co-location arrangement.
6. Guarantee that states and local communities can make their own policies regarding distribution system interconnection processes and retail rates when co- located generation is not available to supplying load.
While Federal rules should be consistent across all regions, they should also be flexible enough to allow developers to work within different state rules/policies. Any Commission action in response to PJM’s proposal should enable flexibility in other regions.
B. Co-Locating Large Loads at Existing Generation Sites Can Provide
Significant Benefits to Existing Generation and the Transmission System. Co-location arrangements can benefit the transmission system in many ways. Large flexible co-located load arrangements can help streamline the generator interconnection process by reducing the need for expensive grid upgrades and avoiding queue delays in bringing new generation online. Even where new transmission needs to be built, co-location can minimize
PDF page 8
8
required new upgrades. Co-locating large loads can also reduce congestion costs and provide demand response services if the power demands are flexible. When near-term load growth forecasts are high, co-location can help with transmission planning as well.
Co-location arrangements can provide significant benefits to existing generators. For instance, by locating in areas with surplus energy, large loads can help prevent wasteful curtailments. By using energy that would otherwise be curtailed, large flexible loads like crypto mining or batch AI data centers can significantly improve generator economics without stressing the grid. As a result, large interruptible co-located load pairs well with resources like wind and solar by using underutilized resources and not requiring new transmission build. Co-location arrangements also provide benefits to American industries looking for affordable, carbon-free energy. Industrial consumers can access areas of surplus energy to foster the growth of globally competitive industries otherwise subject to expensive utility pricing and potentially lacking alternative energy options.
Finally, co-location arrangements will provide benefits to states and communities. Large load facilities can provide a host of benefits to local communities in the form of tax revenues, construction jobs, and employment. In this regard, it is important that any rule coming out of this proceeding allows states and local communities the freedom to make their own policies regarding retail rates and distribution system interconnection processes.
C. Co-Location Arrangements are Not One-Size-Fits-All; Any New Rules
Should Be Flexible.
As demonstrated by PJM’s eight options to facilitate co-location arrangements, there are many potential co-location structures that vary depending on the size and operational flexibility
PDF page 9
9
of the load. AI data centers that need “five-nines”5 power reliability should not be treated the same as crypto mining load that has considerable operating flexibility. For example, EDFR’s Las Majadas project is a flexible BTM structure where the data center can curtail when Las Majadas generation capacity is needed in the ERCOT market. In contrast, AI data centers typically require 24/7 firm service and do not provide the same flexibility for the co-located generation resource to inject into the grid. Some industries able to co-locate load behind the generator’s meter do not require grid firming beyond their auxiliary power needs at all.
The Commission should ensure that any new rules and processes that are developed have flexibility for different co-location arrangements. Rules should accommodate diverse structures while ensuring that those structures pay their fair share of grid costs. AI data centers with five- nines reliability needs should not dictate rules for large loads that have significant flexibility. The recent PJM example involving Talen Energy’s AI data center paired with the Susquehanna nuclear facility presents a much different set of needs and risks than a flexible crypto-mining facility paired with an intermittent wind resource. The latter has significant operational flexibility and can even offer services back to the grid that can help with grid operations.
As was developed in ERCOT, the Commission should encourage PJM and other ISOs to develop an expedited process for controllable load to interconnect and economically dispatch in the wholesale market, or to participate as voluntary load shed resources. These flexible resources present a minimal impact on the transmission system and can even offer system-wide reliability benefits while maximizing the efficient use of otherwise underutilized energy resources. In this proceeding, the Commission should encourage:
5 This is a reference to high availability of services, such as when a service is available for 99.999% of the time, or around 5 minutes of downtime per year. See https://en.wikipedia.org/wiki/Five_nines.
PDF page 10
10
Implementation of an expedited interconnection process for controllable co-located load resources or voluntary load-shed resources to come online and provide benefits to the grid.
Establishment of a requirement that the size of the co-located load must be a certain percentage less than the generation at an interconnection point. (E.g., Load can be up to 70% of the Main Power Transformer).
Implementation of an ERCOT-type settlement rules during production period so that large loads and generation resources that are co-located behind a shared Point of Interconnection (POI) are netted together.
In addition, the Commission should recognize the importance of allowing co-location to evolve with RTO design. The Commission should ensure that flexibility is maintained as market designs evolve, including recognition of load response, load netting, and demand-side dispatch.
D. Transmission Costs Should be Assigned Based on the Specific Grid Services
Used in a Particular Co-Location Structure Consistent with the
Commission’s Beneficiary Pays Principle.
Consistent with the Commission’s beneficiary pays principle,6 transmission charges should be assigned to large load facilities based on the specific grid services that the load uses and the configuration of the co-location structure. Therefore, a range of transmission system charges should be available that match the load’s reliance on the grid. Co-location structures that place minimum demands on the transmission system (i.e., “grid-light”) or that allow load to be
6 Under the “beneficiary pays” cost causation principle, rates must “reflect to some degree the costs actually caused by the customer who must pay for them.” Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004). Costs must be allocated in a manner that is at least roughly commensurate with the benefits an entity receives. Ill. Com. Comm’n v. FERC, 576 F.3d 470, 474-78 (7th Cir. 2009) (remanding Commission order for further proceedings in light of Commission’s failure to provide substantial evidence supporting Commission’s approval of cost allocation method as complying with “beneficiary pays” principle).
PDF page 11
11
available for demand response or periodic outages to respond to grid congestion should pay less in grid costs than co-location structures where the load requires five-nines reliability. Full network load charges should not be the default rate charged to all co-location structures. Flexible co-located load that does not rely on the transmission system the same way as network connected load should only be assigned charges for grid services when they are taking power from the grid. For example, under ERCOT’s generation netting rules, generation resources that are co-located behind a shared POI are netted together such that in each market settlement interval if more power is flowing out (net generation) then it is settled as generation and no grid charges apply. If more power is flowing in during the interval (net load), then it is settled as load with applicable grid charges.
EDFR appreciates PJM’s efforts to develop Options 1 through 8 outlining potential co- location structures.7 These options, some already existing and some that need further development, show that there is considerable variation in potential co-location configurations with differing reliance on grid services. Grid charges should be assessed according to the co- location arrangement, the flexibility of that load, and its reliance on the grid. Thus, the Commission should affirm that discrete delivery points with flexible arrangements, mostly behind-the-meter use, and minimal reliance on the grid should not be swept into a network load classification. Only co-location structures with load that regularly and materially use the grid should pay network load transmission charges, consistent with the Commission’s beneficiary pays principle.
7 PJM Answer, Ex. A.
PDF page 12
12
IV. CONCLUSION
For the foregoing reasons, EDFR requests that the Commission adopt a flexible, performance-based framework that recognizes load diversity, encourages “grid-light” development, and avoids inadvertently penalizing innovative renewable-first load models. Respectfully submitted,
/s/ Linda Walsh_____
Temujin Roach
Linda Walsh
Emma Nix Simon
Carrie Collier-Brown
EDF Renewables, Inc.
Michael Blackwell
15445 Innovation Dr.
Husch Blackwell LLP
Suite 1000
1801 Pennsylvania Ave., NW
San Diego, CA 92128
Washington, DC 20006
Tel: (612) 486-4498
Tel: (202) 378-2308
Temujin.Roach@edf-re.com
linda.walsh@huschblackwell.com
EmmaNix.Simon@edf-re.com
michael.blackwell@huschblackwell.com
Counsel to EDF Renewables, Inc.
Dated: April 23, 2025
PDF page 13
CERTIFICATE OF SERVICE
Pursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C. this 23rd day of April 2025.
/s/ Corban A. Coffman
Corban A. Coffman