EL25-49-000 · 2025-04-23 · EDF Renewables, Inc.

Comments of EDF Renewables, Inc. in response to PJM Interconnection, L.L.C.’s Answer filed on 03/24/2025

Text extracted from the eLibrary original (SHA-256 d90a1a196799f66e…). Download the original from the official source.

Contents · 8 sections
  1. I. SUMMARY OF COMMENTS p. 3
  2. II. BACKGROUND p. 4
  3. III. COMMENTS p. 5
  4. A. The Commission Should Act Expeditiously to Encourage Flexible Co- p. 6
  5. B. Co-Locating Large Loads at Existing Generation Sites Can Provide p. 7
  6. C. Co-Location Arrangements are Not One-Size-Fits-All; Any New Rules p. 8
  7. D. Transmission Costs Should be Assigned Based on the Specific Grid Services p. 10
  8. IV. CONCLUSION p. 12

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. SUMMARY OF COMMENTS

printed heading · Topic match: Connecting load and generation

EDFR urges the Commission in this proceeding to adopt a flexible, performance-based framework that recognizes large load diversity within the data center industry and other industries (hydrogen, e-fuels, and Carbon Capture, Utilization and Storage (CCUS)), encourages “grid-light” development…
Read this passage Filed comments: Connecting load and generation

II. BACKGROUND

printed heading · Topic match: Reliability and curtailment

This innovative power purchase agreement (PPA) structure provides a flexible solution to the challenges of transmission constraints and curtailment, essentially allowing an alternate route to capture under-utilized electricity.
Read this passage Filed comments: Reliability and curtailment

III. COMMENTS

printed heading · Topic match: Cost allocation

COMMENTS As the Commission noted in the February 20 Order, co-located load arrangements are becoming increasingly common, in large part driven by the development of new data centers (e.g., facilities used for AI, cloud data storage, and cryptocurrency mining, etc.).3 Many of these new large load…
Read this passage Filed comments: Cost allocation

A. The Commission Should Act Expeditiously to Encourage Flexible Co-

printed heading · Topic match: Connecting load and generation

Clarify that co-located loads using non-firm grid power and backed by onsite generation may qualify for modified transmission cost allocation (e.g., based on usage, not full network load charges). 2.
Read this passage Filed comments: Connecting load and generation

B. Co-Locating Large Loads at Existing Generation Sites Can Provide

printed heading · Topic match: Connecting load and generation

Large flexible co-located load arrangements can help streamline the generator interconnection process by reducing the need for expensive grid upgrades and avoiding queue delays in bringing new generation online.
Read this passage Filed comments: Connecting load and generation

C. Co-Location Arrangements are Not One-Size-Fits-All; Any New Rules

printed heading · Topic match: Connecting load and generation

See https://en.wikipedia.org/wiki/Five_nines. 10  Implementation of an expedited interconnection process for controllable co-located load resources or voluntary load-shed resources to come online and provide benefits to the grid.  Establishment of a requirement that the size of the co-located…
Read this passage Filed comments: Connecting load and generation

D. Transmission Costs Should be Assigned Based on the Specific Grid Services

printed heading · Topic match: Cost allocation

Co-location structures that place minimum demands on the transmission system (i.e., “grid-light”) or that allow load to be 6 Under the “beneficiary pays” cost causation principle, rates must “reflect to some degree the costs actually caused by the customer who must pay for them.” Midwest ISO…
Read this passage Filed comments: Cost allocation

IV. CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, EDFR requests that the Commission adopt a flexible, performance-based framework that recognizes load diversity, encourages “grid-light” development, and avoids inadvertently penalizing innovative renewable-first load models.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 23rd day of April 2025. /s/ Corban A.