EL25-49-000 · 2025-04-23 · Earthjustice

Comments of Public Interest Organizations in response to PJM Interconnection, L.L.C.’s 03/24/2025 Answer to FERC’s 02/20/2025 Order

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection L.L.C.
)
)
)

Docket No. EL25-49-000

COMMENTS OF PUBLIC INTEREST ORGANIZATIONS

PDF page 2

2

Table of Contents

I. Introduction … 4
II. PJM’s OATT, the Amended and Restated Operating Agreement of PJM, and the Reliability
Assurance Agreement Among Load Serving Entities in PJM’s Region are Unjust, Unreasonable,
and Unduly Discriminatory and Preferential … 7
A. PJM’s Existing Study Processes to Identify and Allocate Costs for Transmission
Upgrades is Unjust and Unreasonable … 8
1. The Necessary Study Process for Co-Location Arrangements is Opaque and Not Suited
for Co-Location, Causing Unjust and Unreasonable Rates … 9
2. PJM’s Reliance on Transmission Owner Load Integration Studies and Regional
Transmission Expansion Planning to Identify Upgrades to Resolve Transmission Needs
Associated with Co-Located Load Results in Unjust and Unreasonable Rates … 11
B. The Load Forecasting Provisions in PJM’s Practice Manual 19 Lack Controls and
Standards to Ensure Accuracy and Protect Against Speculative Forecast Estimates … 15
1. PJM’s Load Forecast Process Fails to Provide Standard, Comparable Parameters and
Processes to Accurately Forecast Large Loads … 16
2. Consistent with the Commission’s Rule of Reason Doctrine, PJM’s Large Load
Forecast Process Should be in its Tariff … 19
3. The Commission Should Require a Replacement Rate That Considers Principles that
Encourage Comparability and Accuracy … 22
III. Any Replacement Rate that Enables Co-location Arrangements Involving the Use of
Existing Generators Requires Careful Planning Processes to Ensure Rates are Just, Reasonable,
and Not Unduly Discriminatory or Preferential … 24
A. Co-Location Arrangements Must Pay for the Transmission and Ancillary Services from
Which They Benefit … 25
B. The Commission Must Ensure that Co-Location Arrangements With Existing Capacity
Resources Do Not Unjustly Shift Costs of Maintaining Resource Adequacy … 26
C. Co-Location Arrangements Should Not Receive Preferential Interconnection
Treatment … 28
D. The Commission Must Ensure that PJM Conducts Rigorous Reliability Review of Co-
Location Arrangements … 30
E. The Commission Should Fix its Market Power Mitigation Rules to Address the Increased
Incentive to Exercise Market Power and Commit Manipulation that can Result from Co-
locating Load with Existing Generation … 32
IV. Consistent with Precedent, The Commission Should Assert Jurisdiction over Co-Location
Arrangements on PJM’s Transmission System … 34

PDF page 3

3

A. The Commission Must Not Disclaim Jurisdiction Over Interconnection of
Large Loads … 34
B. The Commission Must Plan for Wholesale Sales at Co-Located Facilities … 37
C. PJM Must Not Limit States’ Authority Over the Co-Located Generation Mix … 40
D. The PJM Tariff Should Treat Co-Located Usage As Any Other Consumption … 40
V. Conclusion … 43

Exhibit A: Collection of 2024 Load Adjustment Requests

PDF page 4

4

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection L.L.C.
)
)
)

Docket No. EL25-49-000

COMMENTS OF PUBLIC INTEREST ORGANIZATIONS

Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (FERC or
Commission) Rules of Practice and Procedure,1 Appalachian Voices, Clean Air Task Force, Earthjustice, the Environmental Defense Fund, PennFuture, and the Sierra Club, together Public Interest Organizations (PIOs), respectfully submit these comments to respond to PJM Interconnection, L.L.C.’s (PJM) answer2 to the Commission’s February 20, 2025 Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (Show Cause Order).3

I. Introduction
By 2029, PJM’s load growth forecast is expected to top 24.8 GW,4 which is a stark
contrast from the flat demand growth that most regions have experienced over the last decade.5 Most of the demand increase is attributable to data centers that process Artificial Intelligence (AI), cloud services and search algorithms.  Total energy consumption in the United States from

1 18 C.F.R. § 385.211 (2024).
2 Answer of PJM Interconnection, LLC, Docket No. EL25-49-000 (March 24, 2025), Accession No. 20250324-5313 (“PJM Answer”).
3 PJM Interconnection, L.L.C., Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings, Docket Nos. EL25-49-000, et al. (“Show Cause Order”).
4 Grid Strategies, Strategic Industries Surging – Midcontinent Power Sector Collaborative, at 6, (2025). https://gridstrategiesllc.com/wp-content/uploads/National-Load-Growth-Report-2024-MPSC-Presentation.pdf
5 Grid Strategies, The Era of Flat Power Demand is Over, (2023). https://gridstrategiesllc.com/wpcontent/ uploads/2023/12/National-Load-Growth-Report-2023.pdf

PDF page 5

5

data centers is expected to grow from  4.4 percent of total energy consumption to between 6.7 to 12 percent by 2028.6  Since the Commission supports providing regulatory “certainty and clarity” to data centers seeking to interconnect to the grid,7 and the lead time to construct data centers is shorter than the average time to interconnect new generators and build traditional transmission infrastructure,8 a variety of stakeholders, including data center owners and independent power producers (IPP), are interested in pursuing more co-location arrangements to power those facilities.

One example is Constellation and its complaint against PJM arguing that PJM should revise its tariff to allow co-location arrangements that do not require load to acquire network transmission service.  Relatedly, Constellation is also pursuing approval to merge with Calpine, a transaction that, if approved, would give Constellation leverage to use its existing nuclear generation fleet to co-locate with large loads, according to parties who protested the merger application.9  The IPPs will make decisions regarding co-location based on their profit motive, without accounting for the interests of other ratepayers in reliability and appropriate cost- allocation.  Recent improvements to PJM’s ability to interconnect supply obviate the need for these arrangements.

  RMI’s 2024 study of PJM’s supply projections concluded that even with 10 GW of anticipated generator retirements, PJM is on track to meet or exceed supply needs for 2030 load forecasts.10  RMI’s analysis estimates that between 5.2GW and 6.85 GW of new supply will

6 Arman Shehabi et al, Energy Analysis and Environmental Impacts Division, Lawrence Berkeley National Laboratory, 2024 United State Data Center Energy Usage Report, at 5-6.

7 FERC Chairman Issues Statement on Review of Issues Associated with the Co-location of Large Loads at Generating Facilities, issued Febraury 21, 2025.
8 Grid Strategies, Strategic Industries Surging: Driving U.S. Power Demand, at 5, (2004).
9 Protest of Public Citizen et al, Docket No. EC25-43-000, at 36-44, filed on March 25, 2025.
10 Protest of Sierra Club and Appalachian Voices, Attachment A, Docket No. ER25-712-000, at 3, 11-13, (Jan. 8, 2025).

PDF page 6

6

come from interconnection projects in PJM’s “Fast Lane” process.11  And on April 18, 2025, PJM announced that its Fast Lane interconnection process cleared for construction approximately 19 GW of new supply.  In addition, implementing Grid Enhancing Technologies (GETs) within the next few years, an approach that the Commission champions in its Order 2023 rule on interconnection reforms,12 could enable PJM to interconnect up to 6.3 GW of new supply once it fully embraces the form and intention of the rule.13

Consistent with the need to address these developments, the Commission’s Show Cause Order seeks input on whether PJM’s existing tariff provisions and related agreements governing co-location arrangements are just, reasonable, and not unduly discriminatory or preferential. While options 1-2 are favorable since they require that load acquire network service, the status quo provisions are not sustainable in the face of a huge influx of these arrangements and need for substantial changes to the study processes, large load forecast process, and cost allocation.14 As discussed below, these options are unjust and unreasonable since they are based on load forecasts that lack adequate vetting mechanisms to remove speculative requests and could enable co-location arrangements that unlawfully shift resulting network upgrade costs to customers that do not receive benefits that are roughly commensurate with the estimated upgrade costs. Inaccurate load forecasts have more definitive consequences for ratepayers: overstating PJM’s regional needs for multi-billion-dollar transmission assets and the reserve margin for its capacity market.

11 Id. at 6.
12 Improvements to Generator Interconnection Procedures and Agreements, 184 FERC ¶ 61,054 (2023) (“Order No. 2023”)
13 RMI, GETting Interconnected in PJM (Feb. 2024) at 5-7, https://rmi.org/insight/analyzing-gets-as-a-tool-for- increasing-interconnection-throughput-from-pjms-queue/.
14 We agree with PJM that large load customers should not be eligible for Option 3.

PDF page 7

7

Since co-location arrangements provide limited, if any, system-wide benefits, the Commission should not authorize the new arrangements that PJM offers in its response (options 4-8), without substantial safeguards to prevent unlawful cost shifting, reliability shortfalls, among other issues.  Options 4 and 5, which allow existing resources to enter into dedicated, co- location arrangements, could unnecessarily increase PJM’s required reserve margins and could require reliability upgrades.  And option 6, which could enable expedited interconnection of generation resources dedicated to large loads, could further exacerbate backlogs in the interconnection queue and, therefore, threaten reliability. Additionally, such expedited interconnection may violate the anti-discrimination provisions of the Federal Power Act. Even allowing a co-location generator to take non-firm service has consequences if the data center’s business model requires it to run 24/7 (options 7-8) since it will rely on back-up diesel generators, which are both harmful to communities and pose reliability risks. In sum, for PJM to meet the moment, it must take measures beyond relying on co-location arrangements. The large scale and quick pace of load growth in PJM’s projections requires PJM to instead focus on implementing a robust forecasting process to guard against speculation, and fully comply with FERC’s rules on transmission planning, generator interconnection, and cost allocation processes to ensure that large load customers that will come online can integrate into the grid without imposing unjust, unreasonable, and unduly discriminatory or preferential rates, terms, and conditions on non-large-load customers.

II. PJM’s OATT, the Amended and Restated Operating Agreement of PJM, and the Reliability Assurance Agreement Among Load Serving Entities in PJM’s Region are Unjust, Unreasonable, and Unduly Discriminatory and Preferential.

At the outset, we reiterate that PJM has a number of tools at its disposal to ensure that new entry can rise to the challenge of new load growth.  Nevertheless, as it pertains specifically

PDF page 8

8

to co-location arrangements between generation and large load customers, we identify two primary issues with PJM’s existing Tariff and current practices.  First, PJM’s use of the Necessary Study Process, Supplemental Projects, and Regional Transmission Expansion Planning (“RTEP”) Process allocate the costs of transmission upgrades in an unjust and unreasonable manner.  Second, PJM’s load forecasting practices under Practice Manual 19 fail to ensure accuracy and protect against speculative or duplicative estimates.

A. PJM’s Existing Study Processes to Identify and Allocate Costs for
Transmission Upgrades is Unjust and Unreasonable.
For co-location arrangement Options 1 and 2, PJM’s current practices assess the transmission upgrades associated with co-location agreements through a combination of three processes: the Necessary Study, Transmission Owner Load Integration Studies, and RTEP.15 Though these studies do result in the co-location arrangement paying for some portion of the identified upgrades, they fail to ensure that the co-location arrangement pays its fair share of these upgrade costs under cost allocation principles.  We note that the cost of transmission upgrades related to interconnection-like processes are distinct from broader transmission rates. Under PJM’s existing co-location options, co-located load is treated as Network Load and thus does pay for transmission service.16  As explained in greater detail in Section III (A), we believe it is appropriate for co-located load to pay for transmission service, and thus support PJM’s treatment of co-located load as Network Load.17  This section focuses solely on the cost- allocation for transmission system upgrades caused by the shift to a co-location agreement, not the costs of ongoing delivery of services via the transmission system following the initial shift.

15 See PJM Answer at 47.
16 PJM Answer at 9-12 (tables of existing options, noting that under each option, load takes NITS service).
17 See infra at 24.

PDF page 9

9

1. The Necessary Study Process for Co-Location Arrangements is
Opaque and Not Suited for Co-Location, Causing Unjust and
Unreasonable Rates.
As the Commission finds in the Show Cause Order, inadequate interconnection service provisions for co-location arrangements, “especially regarding studies of the impacts of those arrangements,” may render PJM’s Tariff unjust and unreasonable.18  We agree that the Necessary Study “may not be fully capturing the transmission system impacts of co-locating load,” and thus could result in co-location arrangements with already-operational generators “not paying the costs of network upgrades that would be caused by the co-location.”19  As Suzanne Glatz and Abraham Silverman explained in the Commission’s technical conference docket, while from an engineering perspective there is little difference between co-location and other load interconnections with generation behind the meter, from a regulatory and cost allocation perspective, they are treated differently—resulting in “similar electrical impacts, but vastly different rate impacts.”20

The Necessary Study Process was designed for studying potential impacts from more minor, routine changes to the electrical characteristics of existing generating units previously studied by PJM,21 and is a poor fit for the more significant nature of an existing generator entering into a co-location arrangement for all or most of its energy production.  As Glatz and Silverman’s comments explain, in the standard usage of the Necessary Study Process for routine maintenance type updates, PJM grants no new grid services or rights.22  For example, the Commission has accepted Necessary Study Agreements that enable generators to replace wind

18 Show Cause Order at P 79.
19 Id.
20 Post-Technical Conference Comments of Suzanne Glatz and Abraham Silverman, Docket No. AD24-11-000 at 1 (Dec. 9, 2024), Accession No. 20241209-5149.
21 See PJM Manual 14G, § 4.5.
22 Comments of Glatz and Silverman at 5.

PDF page 10

10

turbines,23 replace or update transformers and inverters on a solar facility,24 and update software.25  In contrast, however, PJM has not allowed the addition of battery storage to existing generation to go through the Necessary Study Process, in large part because batteries can act as load.26  PJM offers no explanation for why co-located load is thus offered preferential treatment. Moreover, unlike the sorts of routine changes to update and maintain the function of a generator described above, co-location arrangements both make more significant electrical changes and effectively grant the existing generator a new right to serve load directly.  Finally, it’s worth noting that the costs of upgrades that PJM identifies are allocated to the existing generator, rather than the load. This reflects the nature of the Necessary Study Process as originally intended— focused on changes to existing generators.

PJM’s main defense of the narrowness of the Necessary Study Process for studying co- location with an existing generator is that other study processes are also used.27  However, each of the other studies that PJM identifies pass costs to broader sections of load—not the large load customer(s) causing the need for the upgrades. These studies include the Transmission Owner (TO) load integration study, which identifies needed local transmission upgrades that will be proposed to the PJM Transmission Expansion Advisory Committee (TEAC) as Supplemental Projects; the PJM do no harm study, which identifies any broader transmission impacts caused by the proposed Supplemental Project, which will need to be addressed by an expansion of the Supplemental Project; and the RTEP Process, which identifies any regional transmission

23 PJM Interconnection, LLC, Necessary Studies Agreement, Docket No. ER23-189-000, at 11 (Oct. 25, 2022).
24 PJM Interconnection, LLC, Necessary Studies Agreement, Docket No. ER23-1706-000, at 10 (Apr. 25, 2023); PJM Interconnection, LLC, Necessary Studies Agreement, Docket No. ER23-1059-000, at 10 (Feb. 7, 2023).
25 PJM Interconnection, L.L.C., Necessary Studies Agreement, Docket No. ER22-51-000, at 10 (Oct. 6, 2021).
26 PJM Interconnection, L.L.C., Answer, Docket No. EL24-8-000, at 12 (Nov. 30, 2023) (explaining that a change to a generator with an existing Interconnection Service Agreement that “‘involves the addition of storage units that will charge from the grid,’ . . . requires a new Interconnection Request[.]”).
27 See PJM Answer at 47.

PDF page 11

11

upgrades caused by an aggregate of load additions pass costs to broader sections of load.  The unjust and unreasonable nature of this treatment will be detailed in the next section, but at base: the Necessary Study Process is the only process that PJM uses to identify the direct interconnection-related cost responsibility of co-locating large load with an existing generator, and it fails to do so with appropriate accuracy.

Moreover, the Necessary Study Process occurs entirely behind closed doors.  The Commission should independently find the opaqueness of this process to be unjust and unreasonable.  Under the Necessary Study Process, there is no transparency regarding what specific changes to an existing generator that PJM is studying (e.g., what the timeline for the load addition may be, or even how much load addition is requested), and no disclosure of the results of the study.  The public can only access this type of information much later in the study process, when PJM files a revised Interconnection Service Agreement for the existing generator at FERC.  As the Organization of PJM States pointed out in their comments to the technical conference, this is a much different level of transparency than in other circumstances in which generator capacity is removed from the system—e.g., retirement.28

2. PJM’s Reliance on Transmission Owner Load Integration
Studies and Regional Transmission Expansion Planning to
Identify Upgrades to Resolve Transmission Needs Associated
with Co-Located Load Results in Unjust and Unreasonable
Rates.

As PJM explains, the Necessary Study Process, which identifies generator-level upgrades for existing generators, is followed by a TO Load Integration Study to identify upgrades to resolve any local transmission reliability needs that arise as a result of the co-location

28 Post Technical Conference Comments of the Organization of PJM States, Inc., Docket No. AD24-11-000 at 3-4 (Dec. 9, 2024), Accession No. 20241209-5086.

PDF page 12

12

arrangement, and then the RTEP process to identify upgrade needs arising from the aggregation of co-location arrangements.29  Yet when the TO Load Integration Study identifies so-called Supplemental Projects to resolve the needs, the costs of which are allocated not just to the large load customer that triggered the local transmission reliability need, but to the TO’s entire local utility footprint in that zone.  And despite this cost allocation, there is no guarantee that these projects provide greater system benefits.  Thus, this process’s failure to allocate a proportional amount of these costs specifically to large load customers is a straightforward violation of cost causation, and an unjust and unreasonable rate.

We note that the transmission upgrades required to reliably integrate co-location agreements are differently situated from transmission upgrades required to reliably deactivate uneconomic generation (the costs of which are also socialized to load) and thus should be treated differently.  Specifically, co-located load will continue to be the beneficiary of a functional grid going forward—and indeed the principal beneficiary of transmission upgrades specifically triggered by the co-location arrangements—whereas a retiring generator will not derive benefit from the grid in the future.  Thus, while only the remaining load—not the deactivating generator—would utilize the transmission upgrades associated with retirements, co-located load will continue to rely on, and benefit greatly from, such upgrades.

There is no guarantee that Supplemental Projects, nor projects selected through RTEP, provide any system benefits, beyond the circular reasoning that such projects will prevent reliability issues associated with co-location.  As demonstrated in the chart below, many early examples of transmission upgrades driven by data center loads have not led to system benefits,

29 PJM Answer at 6-8.

PDF page 13

13

but rather, only provide the benefit of allowing the large load to operate—disproportionately benefiting the co-location arrangement.

Project / Location
Scope / Cost
Purpose /
Trigger
Why It Doesn’t
Benefit the Whole
System
Planning Process
Who Pays
Source
Wishing Star
Substation –
Loudoun County,
VA
$627.6M – New
500/230 kV
substation with tie-
ins to Mosby and
Brambleton lines
7.5 GW of
projected load
growth in 'Data
Center Alley'
Tailored to serve
hyperscaler
reliability needs;
no evidence of
CETL or transfer
capacity benefit
RTEP – 2022
Window 3
Dominion
Zone
2022 PJM RTEP
Report, p. 61
Marley Neck 115
kV Substation –
BGE Zone
$107.6M –
Substation upgrade
with 230/115 kV
transformers
Overloads at
seven
Baltimore-area
facilities
PJM explicitly
states 'no broader
system benefits'
RTEP – 2024
Window 1
(Baseline Project
b3906)
BGE Zone
(Baseline)
2024 RTEP Window
1 Report, Proposal
295
Beaumeade
STATCOM –
Northern Virginia
300 MVAR Static
Synchronous
Compensator at
Beaumeade
Substation
Reactive power
support for
clustered
datacenter load
Voltage-only fix;
does not improve
bulk power flow or
transfer capability
RTEP – 2023
Baseline
Dominion
Zone
2023 PJM TEAC
Whitepaper, p. 12
Kraken Loop –
Fredericksburg
Corridor
$704M – 500 kV
loop and new
Kraken substation;
230 kV upgrades
deferred
Local overloads
and data center-
driven load
growth near
North Anna
Local components
are deferred to M-3
process; no broader
regional impact
RTEP – 2024
Window 3
(Revised Proposal
967)
Dominion (for
now); 230 kV
deferred to M-
3
2024 RTEP Window
3 Summary,
Proposal 967
Talen–Amazon
Co-Located Load –
Susquehanna
Nuclear
Up to 960 MW
behind-the-meter
load; capped at 480
MW to avoid
violations
Co-located load
increase at
nuclear plant
PJM confirmed
upgrades would be
triggered above
480 MW, with no broader system benefit FERC Interconnection Filing – ER24- 2172 Unknown (but customer would trigger upgrades >480 MW) FERC Order ER24- 2172

Moreover, building out the transmission system in response to discrete, emergent needs
rather than through proactive, forward-looking, system-wide planning fails to identify the most cost-effective future transmission portfolio, which would solve the reliability issues associated with co-location agreements and provide broader system benefits.30  The magnitude of estimated

30 See Order No. 1920 at P 136 (“By expanding the transmission planning horizon and considering factors affecting Long Term Transmission Needs, as well as considering a broader list of benefits, transmission providers will be able to identify, evaluate, and select more efficient or cost-effective transmission solutions to address Long-Term Transmission Needs. Such Long-Term Regional Transmission Planning will: (1) reduce reliance on transmission solutions that are relatively inefficient or less cost-effective because they address only short-term transmission needs; (2) unlock the benefits of economies of scale in transmission investment;(3) enable opportunities to “right

PDF page 14

14

load growth necessitates a more systematic approach to addressing these needs to ensure reliability and affordability for all transmission system users.  Transmission system upgrades are needed and the cost of some upgrades driven by load growth are appropriately shared by load across the region. But the band-aid approach of Supplemental Projects triggered by each new large load customer is going to cost all ratepayers more.

We recognize that under PJM’s existing options (Options 1 and 2), co-located load is
treated as Network Load and thus pays for Network Integration Transmission Service (NITS), including the costs of Supplemental Projects folded into NITS rates.31  However, this treatment still puts regular residential consumers on the hook for Supplemental Projects they did not cause—and from which they often do not meaningfully benefit—in violation of the cost

causation principle.  Under PJM’s existing Tariff, there is high risk that co-located load underpays for the upgrades it triggers by only taking sole responsibility for costs arising in the Necessary Study Process (to the extent an existing generator passes the costs on to the co-located load, that is).  Moreover, this potential cost-dodging is especially concerning given that some commenters argue that co-located load should not be charged for transmission service.32 Finally, like the Necessary Study Process, the TO Load Integration Study and the

Supplemental Projects Process that it triggers are opaque and lack critical regulatory oversight. As the Commission has previously noted, “the planning for Supplemental Projects is done almost entirely by the PJM Transmission Owners, with PJM playing a relatively minor role in which it

size” replacement transmission facilities; (4) facilitate the selection of regional transmission facilities that could address multiple transmission needs over different time horizons; and (5) provide states, utilities, customers, and other stakeholders with greater insight and transparency into the costs and benefits of particular transmission solutions to address Long-Term Transmission Needs. We conclude that these regional transmission planning and cost allocation reforms will benefit customers by leading to more efficient or cost-effective transmission investment, thereby helping to ensure just and reasonable rates”).

31 See PJM Answer at 9-12 (tables of existing options, noting that under each option, load takes NITS service).
32 See Show Cause Order at P 24, n. 45 (citing Post-Technical Conference Comments of Amazon, Constellation, LS Power, and Talen).

PDF page 15

15

reviews the proposed Supplemental Projects only to ensure that they do not have adverse reliability impacts.”33  This lack of oversight and transparency is particularly concerning since Supplemental Projects make up the majority of transmission spending in PJM and are a leading cause of cost increases in the region.34  The lack of ready access to information around the TO Load Integration Study and resulting Supplemental Projects perpetuates a paradigm in which ratepayer advocates cannot effectively challenge the prudency of transmission investments and cost allocation at either the federal or the state level.  At a time when affordability of electricity is paramount, the Commission should not bless the continuation of this approach to co-location arrangements.

B. The Load Forecasting Provisions in PJM’s Practice Manual 19 Lack
Controls and Standards to Ensure Accuracy and Protect Against
Speculative Forecast Estimates.
PJM’s Tariff is unjust and unreasonable because it lacks sufficient controls and standards to ensure large load forecast accuracy and to protect against speculative large load forecast estimates.  PJM’s large load forecasting process does not substantively account for speculative load additions, thus rendering the process and resulting forecast, as well as everything that relies on that forecast, unjust and unreasonable.  In addition, PJM’s Tariff is unjust and unreasonable

33 Monongahela Power Company, et al., 162 FERC ¶ 61,129 at P 97 (2018); see also Transmission Planning and Cost Management, Pre-Conference Statement of Gregory J. Poulos, at 2, Docket No. AD22-8 (Oct. 4, 2022), Accession No. 20221004-5185 (Attachment 2) (testifying about the Supplemental Project planning process that “the reality is simple—the process is fundamentally designed to serve the needs of transmission owners at the expense of customers” and that due to the lack of regulatory oversight or procedural recourse, “moving forward, consumers and other stakeholders, who often lack both the basic information and sophisticated information of the transmission owners, need help.”).
34 See PJM Interconnection, L.L.C., Protest of Advocates, at 7-12, Docket Nos. EL24-119-000 and ER24-2338-000 (July 22, 2024) (“Advocates Protest”), Accession No. 20240722-5132 (describing how supplemental projects are poorly overseen and are a leading cause of cost increases in the PJM region).

PDF page 16

16

because provisions governing large load forecasting are contained in PJM Manual 19 and not in the filed tariff, contrary to the long-standing “rule of reason” (Rule of Reason Doctrine).35 In the Show Cause Order, the Commission asked whether PJM should “consider changes to load forecasting methods, informational postings, or the reserve margin study process to better plan for and address the resource adequacy and reliability impacts of co-location arrangements.”36  PJM itself identified that there is a need to “clarify or enhance existing planning processes,” including “addressing risks that arise based on the existing load forecasting process,” for which PJM has requested “Commission guidance.”37  Below we argue that: (1) PJM’s existing large load forecasting process is deficient; (2) the process should be included in the Tariff consistent with the Commission’s Rule of Reason Doctrine; and (3) the Commission should direct PJM to revise its load forecasting process to improve its accuracy.

1. PJM’s Load Forecast Process Fails to Provide Standard,
Comparable Parameters and Processes to Accurately Forecast
Large Loads.
PJM’s load forecasting process, described in its Manual 19, does not include sufficient controls or standards to prevent speculative additions of large load from entering PJM’s load forecast, which can cause significant costs and result in unjust and unreasonable rates.  PJM’s load forecasting procedure can largely be found on three pages in PJM Manual 19, attachment B.38   Also, PJM relies on each load serving entity or electric distribution company (LSE/EDC) to develop its own internal forecasting criteria, which unsurprisingly leads to widely differing

35 Keyspan-Ravenswood, LLC v. FERC, 474 F.3d 804, 811 (D.C. Cir. 2007) (quoting City of Cleveland, 773 F.2d at 1376); see also Hecate Energy Greene Cnty. 3 LLC v. FERC, 72 F.4th 1307, 1312 (D.C. Cir. 2023) (“The Federal Power Act’s ‘amorphous,’ requirement that tariffs include ‘practices affecting rates’ means that FERC has ‘broad discretion’ in giving the Act ‘concrete application.’”) (quoting City of Cleveland, 773 F.2d at 1376); City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022).
36 Show Cause Order at P 88 (e)(v).
37 PJM Answer at 65. 38 PJM Manual 19, attachment B, pgs. 26-28.

PDF page 17

17

methodologies and, potentially, widely differing results.  For example, as a threshold requirement for including data center load projects in load adjustment forecasts, Exelon only includes “projects with signed engineering agreements/financial deposits.”39 But some LSE/EDCs, like AEP appear to use less stringent standards,40 while others, like First Energy, decline to disclose their criteria for including projects in load adjusted forecasts. 41 42 As a result, all the LSE/EDCs in PJM report their large load forecasts in completely different ways, posing a substantial gradient in uncertainty based on the standards and criteria each participant uses in submitting its forecast to PJM.

Perhaps most problematically, PJM’s approach does not, and cannot, account for data centers that have made proposals across LSE/EDCs.  Pursuant to PJM Manual 19, PJM annually solicits information from its member LSE/EDCs for large load shifts, which are known to them but may be unknown to PJM.   In fact, PJM has no way to cross-check whether a data center in, for example, Exelon’s service territory has also made the same proposal in Dominion’s territory, and both proposals end up in PJM’s forecast even though only one will be built. Inaccurate load forecasting can increase rates by leading to transmission projects that are not genuinely necessary or by artificially inflating the reserve margin in PJM’s capacity market. It is undisputed that this is currently happening.  Indeed, in a recent presentation at the Pennsylvania Environmental Law Forum, PJM’s own Senior Manager of Government Services, Stephen Bennett, stated that data center companies “are pitching the same data centers in different locations.”43  And this problem exists in other regions, as the Vice President of System

39 Exhibit A at 2025 Large Load Adjustment Proposal – Exelon, slide 5 (Note that Exelon does not describe what type or form of the engineering or financial agreements).
40 Id. AEP 2024 Load Forecast Adjustments, slide 3. 41 Id. First Energy Large Load Adjustment 2024, slide 3. 42 Id. AEP 2024 Load Forecast Adjustments, slide 3.
43 2025 Pennsylvania Environmental Law Forum (April 14, 2025), https://www.pbi.org/product/pba-environmental- energy-law-section-annual-dinner/.

PDF page 18

18

Planning and Competitive Transmission at MISO, Aubrey Johnson, provided testimony to FERC that “in many cases, these data centers are showing up in multiple places, so in reality I could have many members submitting loads that are all the same.”44

Additionally, PJM should also scrutinize load forecasts to assess the possibility of proposed large loads being cancelled.  For example, several high-profile data center development proposals have recently been cancelled.  Last month, Microsoft indicated it is cancelling over two GW of data center projects.45  Additionally, a research note from TD Cohen indicates that they “continue to believe the lease cancellations and deferrals of capacity points to data center oversupply relative to its current demand forecast.”46

The Commission has expressed concerns with regard to large load forecasting accuracy both in the technical conference47 and in the Show Cause Order, and PJM has already agreed that its forecasting process is “worthy of exploration.”48  Incorporating clearly defined baseline reporting requirements would have an immediate effect by significantly increasing the confidence in PJM’s load forecast and reducing the likelihood of unjust and unreasonable rates flowing from the forecast.  Moreover, such standards are easily “susceptible of specification,” as

44 Technical Conference Transcript at 26, Docket No.  AD24-11 (Nov. 1, 2024), https://www.ferc.gov/media/transcript-technical-conference-regarding-large-loads-co-located-generating-facilities (emphasis added).
45 George Butler, Data Center Dynamics, Microsoft Cancels Up to 2GW of Data Center Projects, Says TD Cowen, (March 27, 2025), https://www.datacenterdynamics.com/en/news/microsoft-cancels-up-to-2gw-of-data-center- projects-says-td-cowen/.
46 Wayne Williams, Techradar, Is Microsoft Planning to Eliminate AI-related Data Center Projects Across Europe and US?  Bloomberg Report Says So, (March 31, 2025) https://finance.yahoo.com/news/microsoft-planning- eliminate-ai-related-173300784.html.
47 See, e.g., Technical Conference Transcript, at 23-26, Docket No.  AD24-11 (Nov. 1, 2024), https://www.ferc.gov/media/transcript-technical-conference-regarding-large-loads-co-located-generating-facilities (“How do you go about determining what this load will look like? How do you confirm it? Can you give us some transparency behind how you estimate what it will be, and what do you think is driving it in particular?”).
48 PJM Answer at 66.

PDF page 19

19

many of these proposals have already been provided to the Commission in this consolidated docket.49

2. Consistent with the Commission’s Rule of Reason Doctrine,
PJM’s Large Load Forecast Process Should be in its Tariff.
As a threshold issue, PJM’s large load forecasting process is not codified in the Tariff; rather, it is described in PJM Manual 19.  The Federal Power Act requires public utilities to maintain tariffs on file with the Commission that include not only rates for jurisdictional services but also the practices affecting such rates and charges.50  Commission regulations spell this out in more detail, requiring that rate schedules set forth “clearly and specifically,”51 “all . . . practices . . . which in any manner affect or relate to . . . service, rates, and charges.”52  “[T]he Commission has often invoked the rule of reason to require additional detail be included in jurisdictional tariffs,” and “those directives typically require the addition of methodological or procedural detail . . . .”53

The Commission has stated that it is appropriate to use an FPA Section 206 proceeding to
revisit whether a previously approved tariff complies with the Rule of Reason.54  Tariffs that omit major details may be revised or rejected, and courts have overturned Commission orders

49 See, e.g., Post Technical Conference Comments of Google LLC, at 7, Docket No. AD24-11 (Dec. 10, 2024) (“Requiring load adjustments due to new large load interconnections to be ‘commitment-backed’ through material, up-front financial commitments . . . .”).
50 16 U.S.C. § 824d(c). 51 18 C.F.R. § 35.1(a) (1985).
52 Id. at § 35.2(b).
53 Id. at P 46 (emphasis omitted); see also Am. Elec. Power Serv. Corp. v. Sw. Power Pool, Inc., 184 FERC ¶ 61,207 at PP 31–33 (2023).
54 See Sw. Power Pool, Inc., 136 FERC ¶ 61,050 at P 41 (2011) (An aggrieved party “may bring [a violation of the Rule of Reason] to our attention by filing a complaint under section 206 of the FPA”); see also Cal. Indep. Sys. Operator Corp, 133 FERC ¶ 61,224 at P 159 & n.138 (2010) (“While, presently, we find it acceptable to place the mentioned details used to determine policy-driven elements in the Business Practice Manual, if, once drafted, a party is concerned that these provisions could significantly affect rates and service, it can bring this issue to the Commission's attention under section 206 of the FPA”).

PDF page 20

20

that approved tariffs with insufficient detail.55  Indeed, the U.S. Court of Appeals for the D.C. Circuit concluded that the Rule of Reason required that an unforced capacity accreditation methodology be included in the tariff, resulting in remand.56

In the current proceeding, there is no question that the reporting requirements for PJM’s large load forecasts are practices that directly and significantly affect rates for jurisdictional Commission services.  Inaccurate forecasts create risks that substantial transmission and generation costs to serve new loads will be shifted to other customers. Inaccurate forecasts can also impact installed reserve margins for the region and influence forward investment signals for future resource adequacy.  If large loads that are added to PJM’s load forecast fail to materialize, or fail to materialize as rapidly as the forecast predicts, PJM’s inaccurate load forecast could nevertheless be utilized in forward capacity auctions and the phantom demand could result in unnecessary price increases.  In addition, the large load estimates provided by LSE/EDCs to PJM are inputs that directly influence the planning and development of transmission upgrades that are cost allocated pursuant to the RTEP process.  Many of these additions are proposed to be co- located with generators.

PJM might argue that in response to its proposed revisions to the Reliability Assurance Agreement Among Load Serving Entities (“RAA”), the Commission already determined that including the large load forecasting process in its business process manual is just and reasonable.57  There, however, American Municipal Power (AMP) raised a different argument: PJM’s large load forecasting process “fails to provide for measurement and verification of

55 See, e.g., City & Cnty. of S.F. v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022).
56 Keyspan-Ravenswood, L.L.C. v. FERC, 474 F.3d 804, 811 (D.C. Cir. 2007).
57 See PJM Interconnection L.L.C., Proposal to Better Account for Large Load Adjustments in Forecasted Capacity Obligations, Docket No. ER24-2447 (filed July 1, 2024).

PDF page 21

21

forecasted adjustments to ensure accuracy . . . .”58  PJM argued that “housing implementation details in the PJM Manuals does not demonstrate that PJM is incapable of measuring and verifying the accuracy of load data.”59  Ultimately, the Commission agreed with PJM, finding that “[t]he equations [PJM] filed with this proposal specify that load forecasts will be adjusted by zone/area and specifically include a variable for Load Adjustments, and we agree with PJM that it needs flexibility to implement each such load adjustment.”60

Here, however, we are asking for fundamentally different information in the Tariff than AMP requested.  We are not asking that PJM include “measurement” equations in the Tariff, with the understanding that such details may need to be adjusted over time.  These types of assumptions and methodologies can vary year-by-year and therefore are not “reasonably susceptible to specification.”  In contrast, basic procedures and reporting criteria for large load addition requests by LSE/EDCs are reasonably susceptible to specification.

Additionally, circumstances have changed substantially since the Commission’s decision in AMP’s case, because PJM has made significant admissions in this docket that merit the Commission revisiting the issue of what load-forecasting methods must be included in the Tariff. For example, PJM has recognized the “risks that arise based on the existing load forecasting process,” including “the risk of overbuilding due to a forecast that is too high or underbuilding due to a forecast that is too low.”61 Moreover, PJM recognizes that the stakes are high: “the potential size of these individual, large load additions” means that “uncertainty with respect to whether the large loads are actually added to the system could cause either overbuild or

58 American Municipal Power Protest, Docket No. ER24-2447 (filed July 22, 2024), at 2.
59 PJM Interconnection, L.L.C., 188 FERC ¶ 61,200, at P 28 (2024).
60 Id. at P 43.
61 PJM Answer at 66-67.

PDF page 22

22

underbuild to occur based on a single customer addition.”62  Further, PJM has recognized that the risks associated with inaccurate load forecasting accrue “to all demand” in the form of “higher capacity costs” and “transmission cost allocation.”63 Accordingly, PJM has invited “Commission guidance” on “opportunities to enhance the load forecasting process.” PJM’s admissions and invitations for Commission action provide an ample basis for the Commission to determine that it is no longer just and reasonable for critical load-forecasting standards to be omitted from PJM’s Tariff.64

Consistent with the Rule of Reason, the Commission should require PJM to include in its Tariff clear direction on the procedure and reporting criteria for the large load addition requests that must be submitted by LSE/EDCs to PJM for review and inclusion in PJM’s planning processes.65 Absent such direction, PJM’s Tariff will remain unjust and unreasonable.

3. The Commission Should Require a Replacement Rate That
Considers Principles that Encourage Comparability and
Accuracy.
Below we provide several suggestions and principles for what the Commission could require PJM to include in its Tariff with regard to large load forecasting.  These suggestions are intended to assist the Commission in its development of a replacement rate and provide additional certainty in PJM’s load forecasts.

 First, as discussed above, the Commission should require that PJM comply with the Rule of Reason and include at least a portion of the large load adjustment process in its Tariff.  This

62 Id. at 67.
63 Id.
64 See, e.g., Louisiana Pub. Serv. Comm’n v. FERC, 184 F.3d 892, 897 (D.C. Cir. 1999) (noting that “the Commission has the duty—not the option—to reform rates that by virtue of changed circumstances are no longer just and reasonable”).
65 Am. Elec. Power Serv. Corp., et al., 184 FERC ¶ 61,207, at P 33 (2023) (requiring details including the methods and procedures of setting the Planning Reserve Margin value must be included in the Tariff or otherwise violates the Rule of Reason).

PDF page 23

23

will provide both transparency and accountability that is currently lacking.  The entire load forecasting process does not need to be prescribed in the Tariff; rather, we ask—and indeed the Rule of Reason dictates—that PJM include clear standardized baseline forecasting reporting criteria so that all LSE/EDCs use the same baseline when proposing load forecast adjustments. PJM should leave it open for each LSE/EDC to build increased requirements above and beyond those that PJM requires to ensure further accuracy of their adjustment requests. Additionally, the record contains examples of different ways that PJM could increase confidence in its large load forecasting with relatively small changes to its Tariff.  For example, PJM could incorporate a requirement that large load adjustments only include requests that are backed by financial commitments.66  Such firm commitments could be similar in structure to the “readiness deposits” that the Commission requires in the generator interconnection process.  To further reduce speculative requests, PJM could also identify a minimum level of financial commitment that is non-refundable if the project sponsor were to cancel its request. PJM could collect detailed, facility-level information for early stage large-load projects that demonstrate both substantial financial commitment and achievement of key project milestones.67  By requiring clear evidence of investment, PJM could more accurately distinguish genuine corporate commitments from speculative projects seeking price discovery.  PJM could develop a protocol to cross-check whether developers have proposed the same project at different LSE/EDCs so that the same load does not appear in multiple load adjustment forecasts.  If LSE/EDCs are concerned with the disclosure of confidential information, PJM could develop secure data sharing protocols.

66 Post Technical Conference Comments of Google LLC, Docket No. AD24-11 (Dec. 10, 2024) at 7-8.
67 See, e.g., PJM’s Request for Stakeholder Feedback on Corporate Commitments Order 1920 – Category Factor 7, available at: https://www.pjm.com/-/media/DotCom/committees-groups/committees/teac/2024/20241210- special/item-05---ceba---zgi-response-to-pjm-on-corporate-commitments-for-order-1920.ashx, at 3.

PDF page 24

24

Lastly, the current status quo does not provide the right incentives for forecasting accuracy.  It should be a goal of the Commission to shift some of the risk of large load forecasting errors and inaccuracies to individual large load customers.  This could be in the form of penalties or reimbursements.

III. Any Replacement Rate that Enables Co-location Arrangements Involving the Use of Existing Generators Requires Careful Planning Processes to Ensure Rates are

Just, Reasonable, and Not Unduly Discriminatory or Preferential.

In addition to explaining PJM’s existing options for co-location, PJM’s response to the Commission’s Show Cause Order outlines five more potential options.68  In this section, we highlight five potential issues that the Commission should avoid in considering new pathways for co-location arrangements.  First, co-location arrangements must pay their fair share for both the transmission and ancillary services from which they benefit.  Second, we encourage the Commission to prevent a broader system-wide issue in which co-location arrangements unjustly shift the costs of maintaining resource adequacy to other load.  Third, we oppose creating new “fast tracks” for interconnection of co-locating resources, which will come at the expense of the significantly backlogged interconnection process.  Fourth, the Commission should ensure that PJM conducts rigorous reliability studies of co-location arrangements. Fifth, the Commission must take action to prevent market power manipulation.

Because PJM’s proposed options remain high-level, we caution that this list is non- exhaustive.  Additionally, we reiterate that the unjust and unreasonable practices identified in

68 See PJM Answer at 13-20 (New Option 4: Co-located load with connection to the grid with protections to avoid delivery of system energy to serve the load; New Option 5: Co-located load with connection to the grid with protections to avoid delivery of system energy to load, but with back-up service from PJM with permission; New Option 6: Co-located load that elects to be Network Load and bring its own generation; New Option 7: Potential new non-capacity backed service as a Transitional Service; Option 8: Co-located load participating in Demand Response).

PDF page 25

25

Section II (the failure to properly allocate the cost of transmission upgrades, and the lack of proper load forecasting provisions) must also be remedied in order to ensure a just and

reasonable replacement rate.
A. Co-Location Arrangements Must Pay for the Transmission and Ancillary
Services from Which They Benefit.
We agree with the Commission’s findings in the Show Cause Order that the PJM Tariff
may be unjust, unreasonable, unduly discriminatory or preferential insofar as the Tariff fails to ensure that co-location arrangements follow cost causation principles for transmission and ancillary services.69  Through the briefing questions, the Commission correctly underscores two key principles of cost allocation: cost causation and beneficiary pays.70  In essence, costs must be allocated in a manner that is at least roughly commensurate with the estimated benefits that entities receive.71

As applied to this context, co-location arrangements should pay for their share of
transmission and ancillary services costs since the transmission system to which co-location arrangements connect deliver blackstart and other critical services to ensure reliability for these co-location arrangements.  We agree with PJM that none of the proposed co-location

arrangements are “wholly isolated,”72 and further uplift and endorse the comments in this docket submitted by Union of Concerned Scientists detailing the variety of ways that co-location

69 Show Cause Order at PP 78, 82.
70 See Show Cause Order at P 74, Briefing Question b(iv)(“What changes to the rates, terms, and conditions of Network Integration Transmission Service or Point-to-Point Transmission Service or, alternatively, what new form of transmission service(s) may be necessary for different configurations of co-location to ensure that the Tariff is consistent with cost causation principles and the beneficiary pays principle?”) and c(iv)(“What changes to rates, terms, and conditions of ancillary services, including ancillary services procured in PJM’s markets, are necessary for different configurations of co-location arrangements to ensure that the Tariff is consistent with cost causation principles and the beneficiary pays principle?”).
71 See, e.g., Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009). 72 PJM Answer at 42.

PDF page 26

26

arrangements rely on grid services.73  As PJM notes, “[a]ncillary services pass through transmission lines, not the air.”74  While PJM concludes that this means that “at a minimum” cost causation principles support assigning ancillary services costs to co-location arrangements, we urge the Commission to go one step further: conclude that co-location arrangements are also responsible for transmission service costs.  This stems from both the physical reality, as described by PJM, and the resulting economic reality.  The price for ancillary services does not reflect the full cost of providing ancillary services, but rather, the price of providing the ancillary services given the existence of transmission service at that electrical location.  It would therefore violate cost causation and beneficiary pays principles to allow co-location arrangements that rely on ancillary services to avoid paying transmission rates.

For clarity, we note that interconnection fees are distinct from transmission service rates, even if the current state of affairs—in which certain network upgrades are often paid for in the interconnection process—can blur these lines.75  Indeed, particularly because co-location arrangements push much of the needed transmission upgrades into Supplemental Projects and the RTEP Process, where the costs of solutions are allocated to broader load categories, it is essential that co-location arrangements at least pay for transmission service.

B. The Commission Must Ensure that Co-Location Arrangements With
Existing Capacity Resources Do Not Unjustly Shift Costs of Maintaining
Resource Adequacy.
While the Show Cause Order considers the reliability and resource adequacy implications of allowing existing generators to enter into co-location arrangements and notes some parties’

73 Comments of the Union of Concerned Scientists, Docket No. EL25-49-000, (Apr. 10, 2025), Accession No. 20250411-5520.
74 PJM Answer at 36.
75 See Comments of Suzanne Glatz and Abraham Silverman (quoting Order No. 2003-A at P 12, “neither Energy Resource Interconnection Service nor Network Resource Interconnection Service guarantees delivery service”).

PDF page 27

27

concerns regarding the price effects of such arrangements,76 and PJM’s answer contemplates such an arrangement with Options 4 and 5, the Commission must more thoroughly consider how removing existing capacity from the broader system could shift costs, resulting in unjust and unreasonable rates.  As many analysts have warned, steep increases in demand due to load growth from data centers are likely to increase wholesale market prices.77  Indeed, analysis of data center hotspots, such as Northern Virginia, predict wholesale power price increases of up to 30% by 2035.78  Of course, these price increases are broadly concerning.  In this proceeding, though, they are more concerning because co-location arrangements that remove existing capacity from PJM’s capacity market would also shift those cost increases away from the co- located load and onto the other consumers in the PJM region.  The Commission cannot ignore the current realities in PJM: already sky-high capacity prices, as well as an extremely backlogged interconnection queue, supply chain issues for new resources (both generation and transmission), and limited available transmission capacity that further drives up the cost of interconnection. Each of these conditions makes new entry challenging, and if left unaddressed, very expensive. Allowing the key drivers of the tight supply margins – large load customers – to avoid and exacerbate these challenges and associated costs by sequestering access to existing generation would be a cost shift of extreme magnitude.

76 Show Cause Order at PP 83-86 (citing concerns of the PJM Independent Market Monitor and Illinois Attorney General).
77 See Eliza Martin and Ari Peskoe, Harvard Law School Environmental & Energy Law Program, Extracting Profits from the Public: How Utility Ratepayers Are Paying for Big Tech’s Power, at 21 (March 2025), https://eelp.law.harvard.edu/wp-content/uploads/2025/03/Harvard-ELI-Extracting-Profits-from-the-Public.pdf (citing, for example, the PJM Independent Market Monitor). 78 Aurora Energy Research, Impacts of Virginia Data Center Demand Growth on the Power System, at 11 (June 2024), https://go.auroraer.com/l/885013/2024-06- 19/n7nbj/885013/1718806706gUvUPURq/Aurora_Jun_2024_PJM_Load_Growth_Report.pdf.

PDF page 28

28

The Commission does nod to some of these concerns in asking about the effects of co-
location of generators that were paid for in base rates prior to restructuring.79  At a minimum, the Commission should not allow such a cost shift.  However, it would be appropriate to take a broader system view of all existing generation: even generation that was not paid for in base rates was still able to come online at significantly lowered prices because of access to the existing grid, which was paid for by consumers (and the same transmission rates co-location arrangements seek to avoid).

C. Co-Location Arrangements Should Not Receive Preferential
Interconnection Treatment.
The Commission should reject proposals to allow generators seeking co-location
arrangements to access special, expedited interconnection pathways.  Such proposals run counter to the Commission’s recent reforms adopted in Order No. 2023, and moreover, would offer

unduly preferential terms and conditions to a select set of entities.  The Commission has rejected proposals that would “create priority access to the generator interconnection process” for certain generators as unjust and unreasonable.80  Thus, the Commission should similarly reject any proposal that would allow generators seeking co-location arrangements to have priority access to the transmission system (as contemplated under PJM’s proposed Option 6).81  One customer class should not be privileged above all others in the interconnection process.

79 Show Cause Order, Briefing Question V(ii) (“Finally, for generation units paid for originally by consumers in base rates prior to restructuring, is it fair and/or just and reasonable if these units are taken out of the system’s supply stack and devoted exclusively to serving co-location arrangements with one or a few large customers?”).
80 Midcontinent Indep. Sys. Operator, Inc., 186 FERC ¶ 61,054 (2024) at P 176 (also quoting Order No. 888 that “[a]n open access tariff that is not unduly discriminatory or anticompetitive should offer third parties access on the same or comparable basis, and under the same or comparable terms and conditions, as the transmission provider's uses of its system”). See also Order No. 2003, 104 FERC 61,103 at P 12 (“[i]nterconnection is a critical component of open access transmission service”).
81 See PJM Answer at 16-17.

PDF page 29

29

Moreover, granting this privilege to co-location arrangements would directly harm
consumers and other generators seeking interconnection, as well as running counter to Order No. 2023.  The cluster study requirement is the keystone requirement of Order No. 2023 around which other reforms, such as study deadlines and withdrawal penalties, are oriented.82  In developing the record to support this requirement, the Commission examined evidence from a diverse set of stakeholders, finding that cluster studies “increase efficiency because transmission providers can perform larger interconnection studies encompassing many proposed generating facilities, rather than separate studies for each individual interconnection customer.”83  Critically, the Commission specifically denied requests to operate one-off interconnection studies in parallel to cluster studies in Order No. 2023, explaining that “a separate interconnection process outside the cluster study process could detract from transmission providers’ efforts to efficiently process cluster studies, and would be insufficient to ensure that interconnection customers are able to interconnect to the transmission system in a reliable, efficient, transparent, and timely manner.”84 Concerns about detracting resources from the cluster process are particularly poignant in PJM given the extent of the backlog and delays in the current queue.85  There have been no significant developments that have alleviated PJM’s backlog problem since the finalization of Order No. 2023; indeed, PJM has consistently fought Order No. 2023 compliance.86  Notably,

82 See, e.g., Order No. 2023, 184 FERC ¶ 61,0543 at PP 4 (“we adopt reforms to: (1) implement a first-ready, first- served cluster study process”); 5 (“in order to implement a first-ready, first-served cluster study process”).
83 Order No. 2023, 184 FERC ¶ 61,054 at P 177 (citing Improvements to Generator Interconnection Procs. and Agreements, 179 FERC ¶ 61,194, at P 64 (2022)).
84 Id. at P 178.
85 See, e.g., Protest of Public Interest Organizations, at 2-4, 6-11, Docket No. ER24-2045 (June 20, 2024), Accession No. 20240620-5242 (documenting PJM’s badly backlogged interconnection queue and substantial delays in processing interconnection requests).
86 See, e.g., Final Brief of Respondent-Intervenors Interconnection Reform Advocates, at 39-44, Advanced Energy United et al. v. FERC, U.S. Court of Appeals, D.C. Circuit, Case No. 23-1282, Document No. 211411 (Apr. 16, 2025) (opposing PJM’s lawsuit against Order No. 2023 in part by documenting that “PJM had, and still has, one of the longest and most-backlogged interconnection queues of any region” and that “[o]ngoing queue delays are still causing dire challenges for the reliability and affordability of electricity in the region”).

PDF page 30

30

delays caused by staffing limits isn’t a problem PJM could easily hire themselves out of. Engineers who run interconnection studies are highly trained specialists, and there is a shortage of people across the country that can do this work.87  To be clear: PJM can and should invest more resources into hiring interconnection engineers and investing in software to accelerate interconnection studies.  However, these investments should be focused on faster processing of the interconnection cluster, not unduly directed towards co-location arrangements at the expense of the rest of the system.

D. The Commission Must Ensure that PJM Conducts Rigorous Reliability
Review of Co-Location Arrangements.
While the addition of large loads like data centers poses reliability risks whether or not they are co-located, the Commission should not compound this problem by allowing co-located load to skip key planning processes and system analysis. This is particularly true where a co- location arrangement is proposed with an existing generator that is a capacity resource. The sequestering of existing generation resource capacity for the purposes of solely serving a co-located load customer could create unique system reliability risks. As noted by PJM’s Market Monitor, “[g]iven that PJM’s excess reserves are currently less than 1,000 MW, removing a relatively small amount of MW to serve co-located load would have a significant impact on reliability and could easily result in a shortfall in reserves in PJM.”88  While PJM has tools at its disposal to provide enough supply to serve large loads, unless PJM is provided clear authority to plan for meeting co-located large load additions in the same way that PJM plans for generation additions, the Commission risks exacerbating and/or causing risks to grid reliability.

87 US DOE, Transmission Interconnection Roadmap (Apr. 2024), https://www.energy.gov/sites/default/files/2024- 04/i2X%20Transmission%20Interconnection%20Roadmap.pdf.
88 Post Technical Conference Comments of the PJM Market Monitor Comment, Docket No. AD24-11 at 3 ( Dec. 16, 2024), at 3.

PDF page 31

31

One of the primary reasons large loads are pursuing co-location arrangements is the speed to market that those arrangements offer.89  However, this speed to market cannot override the Commission’s and PJM’s interests in maintaining the appropriate controls and planning processes to ensure grid reliability and just and reasonable rates.  For example, generators that co-locate with large loads should not be able to preserve their Capacity Interconnection Rights (“CIRs”) in such a way that they can recover for capacity twice, once for the capacity supply obligation, and again for the backup service they provide to the co-located load in the event of an outage.  This creates both reliability and cost allocation problems and was already indirectly rejected by the Commission.90  Additionally, allowing existing generators that are co-located with large loads to reduce their CIRs to serve the large loads without any accompanying planning studies to ensure there are no adverse reliability impacts would also expose the grid to significant reliability risks.  As noted by the PJM Market Monitor in this docket,

[i]t is essential that the addition of significant new loads go through a complete PJM analysis and planning process that includes addressing system reliability and is not narrowly limited to local transmission issues, even if that process is time consuming. Every new generator and every large load addition should go through this process.91

Planned generators that decide to sequester their new generation to serve large load customers should use a process that complements overall system needs and existing interconnection and transmission planning efforts.  For example, as suggested by NERC, the planning process should examine the load associated with a co-located facility so planners and operators “can assess reliability concerns such as contingencies, power flow changes, and

89 Technical Conference Transcript, Docket No.  AD24-11 at 106 (Nov. 1, 2024), https://www.ferc.gov/media/transcript-technical-conference-regarding-large-loads-co-located-generating-facilities.
90 PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 at PP87-88 (Nov. 1, 2024) (Capacity Interconnection Rights issues were raised and argued in this docket, but the Commission rejected the proposal on other grounds).
91 Post Technical Conference Comments of the PJM Market Monitor Comment, at 3, Docket No. AD24-11 (filed December 16, 2024).

PDF page 32

32

voltage that may otherwise be hidden or masked by the generator,” which could cause issues with “voltage support, frequency response, harmonics, stability of neighboring resources, or protection system coordination.”92  The absence of this type of analysis, in particular transient stability load models, is currently “a gap that needs to be addressed.”93  Additionally, currently behind the meter co-located loads are “not part of the PJM load forecast” and “not accounted for holistically in forward-looking planning processes” because these loads are “off the system despite being in the PJM region.”94  The Commission should not accept any of the options proposed by PJM unless this issue is fully addressed and PJM is provided visibility into the full load that co-located data centers potentially add to the system.

E. The Commission Should Fix its Market Power Mitigation Rules to
Address the Increased Incentive to Exercise Market Power and Commit
Manipulation that can Result from Co-locating Load with Existing
Generation.
The Show Cause Order asks for a variety of information on how co-location
arrangements may require changes to the PJM Tariff and the rules governing PJM’s capacity, energy, and ancillary services markets.95  One such area pertains to market power and manipulation.  PJM’s market power mitigation rules are already insufficient to prevent abuses of market power.96  Co-location arrangements involving existing generators can heighten the concern with the prevailing deficiencies in PJM’s market power mitigations rules by

92 Statement of the North American Electric Reliability Corporation Technical Conference on Large Loads Co- Located at Generating Facilities, at 1, Docket No. AD24-11 (Nov. 1, 2024).
93 Id. at 2.
94 Statement of Frederick S. “Stu” Bresler on Behalf of PJM Interconnection, L.L.C., at 4,6, Docket No. AD24-11 (filed November 1, 2024).
95 See Show Cause Order at P 88(e)(i), (f)(i).
96 See Monitoring Analytics, LLC, 2024 State of the Market Report for PJM, Vol. II at 9–10, 24–25, 30–32 (Mar. 13, 2025) (“2024 PJM State of the Market”) (explaining that market participants are exercising aggregate market power in the energy markets and that market participants can exercise local market power despite mitigation).

PDF page 33

33

exacerbating certain market participants’ incentives to abuse market power and engage in market manipulation, as explained below.

Withholding supply is one way to exercise market power or commit market
manipulation.97  The incentive to withhold supply in energy markets grows as the portions of the supply curve used to meet demand are more inelastic.98  This is because a given amount of withheld supply will tend to have a greater impact on price as that portion of the supply curve becomes more inelastic.

Co-location arrangements that allow load to co-locate with existing generators have the potential to exacerbate the incentive to withhold supply by changing the generators on which PJM relies to meet demand.  If existing generators’ co-location causes PJM to more frequently rely on more inelastic portions of the supply curve to meet demand, then market participants’ incentive to withhold supply is greater.

To the extent the incentive to withhold supply is likely to become greater following existing generators co-locating with large loads, the Commission must require changes to the PJM market power mitigation rules to adequately address potential abuses of market power. That effort should begin by addressing the deficiencies in Commission-approved mitigation rules in PJM which, among other things, do not provide for aggregate market power mitigation in PJM energy markets and allow for market power in the energy market even when a supplier fails PJM’s pivotal supplier test.99

97 See, e.g., Pub. Citizen v. FERC, 7 F.4th 1177, 1198 (D.C. Cir. 2021); FPA Section 203 Suppl. Pol’y Statement, 120 FERC ¶ 61,060, at PP 60, 65 (2007).
98 See, e.g., Commonwealth Edison Co., 91 FERC ¶ 61,036, at 61,133 & 61,133 n.42 (2000).
99 2024 PJM State of the Market at 9–10, 24–25, 30–32.

PDF page 34

34

IV. Consistent with Precedent, The Commission Should Assert Jurisdiction over Co-
Location Arrangements on PJM’s Transmission System.
The Commission’s Show Cause Order poses several questions about the extent of federal
jurisdiction over interconnection of customers to the electric grid.  Primarily, the order asks “whether the Commission must, should, or can exercise jurisdiction over the interconnection of co-location arrangements to the transmission system in interstate commerce as an element of transmission service, including where the purpose is to facilitate a retail sale.”100  PIOs appreciate the opportunity to share legal and technical perspectives on this important question.

A.  The Commission Must Not Disclaim Jurisdiction Over Interconnection
of Large Loads.
The introduction of large loads101 to the electric grid has potential to disrupt transmission system reliability, as observed recently by multiple grid operators.102  The Commission’s general position on its jurisdiction is that “[FERC] has not historically exercised jurisdiction over any and all transmission-level interconnections of retail load.”103  We interpret “any and all” to mean

100 Show Cause Order at P 73.
101 For context, the data center customer at issue in Docket No. ER24-2172 (regarding Susquehanna Nuclear, LLC) was proposed to utilize up to 960 MW.  Order Rejecting Amendments to Interconnection Service Agreement, 189 FERC ¶ 61,078 (Nov. 1, 2024), at P 10.
102 See Docket No. AD25-10, NERC Activities and Plans to Address Reliability Impacts from Large Load Integration (Apr. 17, 2025), Accession No. 20250418-3017, at 3-4 (an unanticipated 1,500 MW load loss in Loudoun County Virginia in July 2024 required “operators [to] have to take action to reduce the voltage to within normal operating levels”); Southern Company presentation to NERC Large Load Task Force (“LLTF”) (Nov. 14, 2024), https://www.nerc.com/comm/RSTC/LLTF/LLTF_Presentaions_November_14_2024.pdf, at 19 (“Large loads such as Data Centers could potentially impact Power Quality and System Stability”); Quanta Technology presentation to NERC LLTF (Nov. 14, 2024), id. at 38 (“Pulsating Loads in Data Center[s] … are a special type of nonlinear load: Large voltage and current signal variations introduce harmonics and potential instability concerns … Pulsed power loads can cause voltage sag or frequency fluctuations in connected power systems, dynamic overvoltage, interruption of other devices”); ERCOT presentation to NERC LLTF (Oct. 8, 2024), https://www.nerc.com/comm/RSTC/LLTF/LLTF_Kickoff_Presentations.pdf, at 34, 39 (“Some load types are reducing consumption during voltage disturbance events. When these loads are large, this behavior can cause a significant and unexpected frequency disturbance”; “In the 12 months ending February 2024, ERCOT experienced 255 five-minute SCED intervals where the change in Large Load consumption has exceeded the amount of procured Regulation[]”)
103 Show Cause Order at P 72.

PDF page 35

35

FERC has not exercised plenary authority over every transmission-level load interconnection, although there are cases where FERC and its regulated entities have sought to control

interconnections of load. For example, NYISO has a specific interconnection process to manage loads that are greater than 10 MW.104 NYISO’s definition of “Eligible Customers”105 appears to be based on language from FERC Order 888-A, which outlined the scope of unbundled

transmission service that may be covered in a federally sanctioned transmission tariff.106 The Commission’s historical forbearance, does not, however, establish as a matter of law

that FERC lacks jurisdiction over the general field of transmission-level load interconnections (contra the arguments107 of Southern California Edison108).  FPA Section 215, enacted109 in 2005, provides that:

104 NYISO OATT §§ 3.9.1 and 3.9.2.
105 Id.  at § 3.9.1 “Any Eligible Customer proposing to interconnect its Load with the NYS Power System shall submit its interconnection proposal to the ISO. The ISO, in cooperation with the Transmission Owner with whose system the Eligible Customer proposes to interconnect, shall perform technical studies to determine whether the proposed interconnection may degrade system reliability or adversely affect the operation of the NYS Power System”).
106 Order No. 888-A, 78 FERC ¶ 61,220 (Mar. 4, 1997), at 119-120 (“We therefore have modified section 1.11 [of the Commission’s pro forma tariff] to clarify that, with respect to service that we are prohibited from ordering by section 212(h) of the FPA (whether direct retail wheeling or ‘sham’ wholesale wheeling), otherwise eligible entities may obtain such service under the tariff only if it is pursuant to a state requirement that such service be provided or pursuant to a voluntary offer of such service.”
107 Docket No. EL25-20-000, Comments of Southern California Edison Company (“SoCal Edison”) (Dec. 23, 2024), Accession No. 20241223-5105, at 4 (“If FERC has jurisdiction over the interconnection of large (retail) loads, why would it have accepted the restrictive [CAISO tariff] provision [leaving non-wholesale load interconnections to the Local Regulatory Authority]? And, why would numerous state commissions be addressing large load interconnections and other terms of service for large loads?”). 108 SoCal Edison offers two additional arguments at page 6 of its Comments.  First, SoCal Edison cites S. Cal. Edison v. FERC, 603 F.3d 996, 1001 (D.C. Cir. 2010) to make the point that FERC may only regulate within its wholesale or transmission authority.  But that by itself does not defeat jurisdiction over transmission-connected load interconnections when the transmission is bundled with power sales, assuming reliability is implicated.  Second, SoCal Edison cites Order No. 2003-C, 111 FERC ¶ 61,401, at P 51, for the proposition that “interconnection jurisdiction is tied to the interconnection customer using OATT service.”  But the cited paragraph of Order No. 2003-C only addresses the question of interconnections to local distribution facilities, which is unlikely to be salient with respect to co-location arrangements, especially for large loads.  SoCal Edison characterizes the Order No. 2003-C paragraph as establishing that “interconnection jurisdiction is tied to the interconnection customer using OATT service,” but the Commission in that passage was referring to wholesale sellers utilizing the open access transmission tariff.  By definition, load cannot be part of a wholesale transaction.
109 Pub. Law 109-58 at § 1211 (creating new 16 U.S.C. § 824o).

PDF page 36

36

On its own motion or upon complaint, the Commission may order compliance with
a reliability standard and may impose a penalty against a user or owner or operator
of the bulk-power system if the Commission finds, after notice and opportunity for
a hearing, that the user or owner or operator of the bulk-power system has engaged
or is about to engage in any acts or practices that constitute or will constitute a
violation of a reliability standard.110

Several months after the new legislation, the Commission found PJM’s existing resource
adequacy measures to be unjust and unreasonable, reasoning that a failure to “set prices adequate to ensure energy resources to meet its reliability responsibilities” would “result in multiple reliability criteria violations.”111  Similarly here, the Commission’s statutory mandate to ensure that transmission users, owners, or operators satisfy reliability criteria provides ample support for regulating the interconnections of large loads that – as discussed above – have usage

characteristics that can cause unacceptable disruption to the bulk power system.  To be clear, at minimum, Order 888-A already establishes112 FERC’s jurisdiction over interconnection for retail customers taking unbundled transmission service – which is true of many co-located customers receiving power at retail from the generator but also utilizing the transmission grid.113  But the outer limits of the Commission’s authority over load interconnection extend beyond the scope

110 16 U.S.C. § 824o(d)(3).
111 Initial Order on Reliability Pricing Model re PJM Interconnection, L.L.C., 115 FERC ¶ 61,079 (April 20, 2006), at PP 5, 11; see also Order Denying Rehearing and Approving Settlement Subject to Conditions, 117 FERC ¶ 61,331 (December 22, 2006) at PP 11-12 (describing past and projected reliability criteria violations related to resource deficits).
112 Cf. SoCal Edison Comments at 6 (admitting the same).
113 With regard to the Commission’s clarifying question in the Show Cause Order at P 73, “[I]f a co-located load is connected to the interstate transmission system only through the generator or if it is served by the generator at a transmission-level voltage, but using facilities that are not interconnected to the interstate transmission system, does that constitute a transmission interconnection in interstate commerce?”113 We believe the first of these scenarios should be treated as the end user taking unbundled retail transmission service directly from the transmission provider.  For the reasons stated by PJM in its Answer (pp. 42-45), any co-located user connected to a transmission- connected generator is itself almost certainly relying on the availability of transmission service.  As to the second scenario, we understand this to mean that the generator is interconnected to the interstate transmission grid, but provides power at transmission voltage to the co-located load facility through circuits that are not interconnected to the transmission grid.  In this case, the load is, again, still taking unbundled retail transmission service, since it is necessarily relying on the availability of transmission system services.

PDF page 37

37

asserted in Order 888-A, given the serious reliability implications of integrating large loads. Even where a load (including co-located loads) is taking bundled supply and transmission service from a utility, the Commission is already empowered to regulate the load’s interconnection to the transmission grid, if necessary to ensure reliability.

We share the perspectives above in the spirit of informing the Commission’s deliberations on these important issues, mindful that this proceeding is focused on co-located loads at the site of generators in the PJM system, and that any determinations the Commission renders on a just and reasonable transmission rate need only focus on the transmission interconnection of co- located loads.  Broader questions about interconnection of loads not co-located, or loads outside PJM, or loads interconnected to the distribution grid, can be examined more closely and determined in another proceeding of broader scope.

B. The Commission Must Plan for Wholesale Sales at Co-Located Facilities.
The Commission correctly notes that under the FPA, retail sales of electricity are a matter for exclusive state jurisdiction.114  This important observation is not the end of the legal analysis, because not all co-location arrangements between a generator and a large load customer will be direct retail sales.  The Commission must carefully consider its responsibilities when a co- located large load customer is not taking retail service.

In several PJM states, a merchant generator (that is, a generator not owned by an incumbent, vertically integrated utility) is prohibited by state law from offering retail supply to a customer.  In Kentucky, for example, incumbent electric utilities are assigned certified territories, and no supplier may attempt to furnish retail electric service to a customer inside the certified

114 Show Cause Order at P 60.

PDF page 38

38

territory of another retail electric supplier.115  The same is true in Indiana (wherein incumbent utilities’ territories are called “assigned service areas”).116  In West Virginia, a law enacted in 1998 authorized the Public Service Commission to determine whether deregulating electricity supply was in the public interest, and if so, to submit such a regulatory plan to the Legislature.117 Although the state commission made certain public interest findings, the West Virginia

Legislature did not ultimately authorize alternative retail suppliers.118  Finally, in Michigan, only 10 percent of an electric utility’s retail sales can be open to alternative retail electric suppliers.119 When the cap is met, customers wishing to take alternative retail supply shall enroll in a queue until new space for alternative supply is available under the 10 percent calculation.120  In 2024, the 10 percent cap in Michigan was fully subscribed, with thousands of customers representing over 2,000 MW waiting in the queue.121

Where a direct retail supply contract with a generator is banned, there could be self-
interested reasons why a large load customer would wish to locate next to a generator, including possible savings (which could be reflected in a special contract with the local utility) from

115 Ky. Rev. Stat. §§ 278.010, 278.016, 278.017, 278.018.  An exception in Kentucky is made where the Public Service Commission finds that the incumbent electric provider in a certified territory “has failed to render or propose to render adequate service,” in which case another supplier may be authorized to furnish retail service if the incumbent then fails to meet the need.  § 278.018(3). 116116 Ind. Code § 8-1-2.3-4.
117 W. Va. Code § 24-2-18.
118 It should be noted that a bill passed by both chambers of the West Virginia legislature as of this month (awaiting action by the Governor) would authorize merchant generators to provide power to co-located data centers within “microgrid districts,” although the bill still contemplates that the data center customer would remain a retail customer of the incumbent utility.  W. Va. Legislature, 2025 Regular Session, House Bill 2014 as enrolled (passed April 12, 2025), https://www.wvlegislature.gov/Bill_Text_HTML/2025_SESSIONS/RS/bills/hb2014%20sub1%20enr.pdf.
119 MCL § 460.10a(1)(a).
120 MCL §§ 460.10a(1)(g)-(i).
121 Mich. Pub. Serv. Comm’n, Status of Elec. Competition in Mich. (Feb. 1, 2025), at 5, https://www.michigan.gov/mpsc/-/media/Project/Websites/mpsc/regulatory/reports/elec- comp/2024_Electric_Competition_Status.pdf.

PDF page 39

39

avoiding congestion costs or line losses, or reducing the chance of weather-based outages.  This type of interest was observed recently in Indiana, where a cryptocurrency mining facility planned to locate its facility adjacent to the merchant Merom Generating Station, which would sell power at wholesale to a generation and transmission cooperative, while the crypto company would

purchase power at retail from the first cooperative’s member distribution cooperative.122
In a scenario where the co-located generator is providing power to a utility on a
wholesale basis but ultimately serving a co-located large load customer, the Commission likely has authority to review the transaction pursuant to its FPA Section 201 authorities (unless Market-Based Rate Authority or some other exception applies).  What’s more, there are scenarios where a co-location arrangement could be deliberately structured as a wholesale sale, but going through a special-purpose intermediary rather than the local utility, to avoid state jurisdiction – thus leaving a potential regulatory gap.123  The Commission should be clear in any order in this proceeding that it will exercise its powers to the fullest extent to review wholesale power agreements under the just and reasonable standard.

122 Order Authorizing Disposition of Jurisdictional Facilities re Hallador Power Company, LLC, 181 FERC ¶ 61,016 (Oct. 7, 2022); AboutBit to turn portion of Indiana power station into cryptocurrency mining facility, REjournals (May 18, 2022), https://rejournals.com/aboutbit-to-turn-portion-of-indiana-power-station-into-cryptocurrency- mining-facility.  Subsequently, it is not clear if the co-location arrangement contemplated in 2022 was finalized, but in the most recent investor relations call last month, the owner of Merom Generating Station stated that it is in negotiation with a “leading global data center developer.” https://s27.q4cdn.com/270326732/files/doc_financials/2024/q4/Hallador-Energy-Company-Q4-FY-2024-Earnings- Call-Transcript.pdf (March 17, 2025).
123 See PJM Answer at 28-29 (highlighting the O’Brien (Parlin) Cogeneration, Inc. matter from 1996 in Docket No. EG96-60 and in New Jersey state regulatory proceedings).  PJM also observed that even a direct retail sale between a co-located generator and the adjacent end user, if not involving a traditional utility, could fall outside state jurisdiction depending on the statutory scope of regulatory coverage.  Id. at 27-28.

PDF page 40

40

C. PJM Must Not Limit States’ Authority Over the Co-Located Generation
Mix.
The Commission also correctly notes that under the FPA,124 states retain authority over
the “mix” (that is, the portfolio characteristics) of a state’s generating fleet, as well as the locations and permission to operate for specific generating facilities.125  While generator interconnections to the transmission system are a matter of Commission jurisdiction, and the Commission through its FPA Section 215 authority may approve reliability standards for

generators, the Commission has no role to directly dictate, subsidize, discourage, or ban
particular generating projects or types of generating projects.  With these jurisdictional contours in mind, any FERC-jurisdictional tariff structure that may facilitate co-location arrangements must be neutral to technology type and not favor or disfavor any type of co-located generator, lest it encroach on a state’s desire to structure co-location arrangements according to a preferred mix, consistent with state authority under the FPA.

D.  The PJM Tariff Should Treat Co-Located Usage As Any Other
Consumption.
Recently, the Commission denied certain transmission owners’ proposal to clarify the
measurement of Network Load, on the grounds that the PJM Transmission Owners lack authority to propose those changes.126  Accordingly, the question of whether consumption by a co-located

124 “[S]uch Federal regulation, however, [is] to extend only to those matters which are not subject to regulation by the States.”  16 U.S.C. § 824(a).  “The Commission … shall not have jurisdiction, except as specifically provided in this subchapter and subchapter III of this chapter, over facilities used for the generation of electric energy[.]”  16 U.S.C. 824(b)(1).
125 Show Cause Order at 70.
126 Order Rejecting Tariff Revisions, Atlantic City Elec. Co., et al., Docket Nos. ER24-2888 to ER24-2894 (not cons.), 190 FERC ¶ 61,109 (Feb. 20, 2025), at PP 33-39.  Specifically, each of the Exelon Utilities, in a separate filing, proposed to add the following (in relevant part) tariff language to its rules on Network Integration Transmission Service: “For avoidance of doubt and to ensure compliance with the definition of 'Network Load,' all load [] that is electrically connected and synchronized when consuming power, regardless of the location of the physical interconnection to [] Transmission Facilities or whether that connection also uses facilities owned by a third party, shall either (a) be designated as Network Load by a Network Customer [] and subject to all associated charges

PDF page 41

41

end user should be defined as Network Load within the PJM tariff remains unaddressed by the Commission.  We recommend that any replacement rate related to co-location arrangements support the treatment of a co-located end user’s usage as Network Load rather than a special carve out for large loads, for at least two reasons.

First, assuming a generator is interconnected to the transmission system – either (1) directly at transmission voltage or (2) via transformers that step down transmission voltage to distribution level – a co-located end user will be using transmission grid services, including frequency and voltage regulation, in proportion to its usage from the co-located generator, which will rely on the grid.  This is so because, as PJM observed in its Answer to the Show Cause Order, conditions at existing data center co-location arrangements can “result in brief, but routine, imbalances between the load and the generation that would need to rely on the grid to balance.”127  And while “it is possible to develop a special protection scheme that could disconnect the load if the local generator trips […] PJM has observed these protection schemes can fail, and the load has taken service from the grid.”128  These new loads may, accordingly, give rise to a need for transmission upgrades to support the incremental services and energy withdrawals from the transmission system.

Because co-located usage relies on the transmission system,129 a co-located end user’s usage should be classified as Network Load to ensure that the costs of the transmission system

and services; or (b) where an Eligible Customer has elected not to designate a particular load at a discrete point of delivery as Network Load, the Eligible Customer is responsible for making separate arrangements [] for Point-To- Point Transmission Service for such non-designated load.”

127 PJM Answer at 45.
128 Id. at 44.
129 PIOs do not object to a proposed policy by PJM in the March 2024 “Guidance on Co-Located Load” (https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.pdf) suggesting that “If the co-located Customer Facility elects to be designated as Behind the Meter Generation (BTMG), it will be allowed to net the co-located load directly against the output of the co-located Customer

PDF page 42

42

are properly allocated to LSEs to the extent that a load share basis is used under the cost allocation tariff,130 and also so that PJM’s RTEP process131 takes appropriate consideration of usage that relies on the transmission grid to model system reliability.  If regional transmission planning fails to consider this consumption, necessary grid upgrades to remedy reliability risks may arise more acutely, requiring inefficiently expensive “piecemeal” upgrades paid for by a broad customer base.132

Additionally, separate from the question of whether co-located usage should count as Network Load for the PJM tariff, any replacement rate that the Commission may direct must not block utilities from attempting to physically measure co-located usage.  States retain authority over whether consumption by a co-located customer should count for purposes of (i) allocating transmission system charges to retail customers, (ii) allocating distribution system charges to retail customers, and (iii) charging retail customers for additional special riders that depend on customer usage.  These questions are squarely within a state’s jurisdiction and have also been the subject of recent state legislative debate.133  Even if the Commission does not agree with PIOs’ contention above that co-located usage should be Network Load within the meaning of PJM tariff rules, the tariff rules must not attempt to dictate to transmission owners that co-located

Facility.”  Importantly, Behind the Meter Generation is already defined in the Tariff as “a generation unit that delivers energy to load without using the Transmission System or any distribution facilities [].”  For any such engineering arrangement, the concerns described above about reliance on the transmission grid would, by definition, not obtain.  Notably, PJM proposed this as “Existing Option 3” in Exhibit A to its Answer of March 24.

130 PJM Open Access Transmission Tariff, § 34.1.
131 PJM Operating Agreement, Sch. 6, § 1.5.
132 Order 1920, 187 FERC ¶ 61,068 (May 13, 2024), P 128.
133 See, e.g., 104th Illinois General Assembly, House Bill 3758 (introduced Feb. 18, 2025), https://ilga.gov/legislation/104/HB/PDF/10400HB3758lv.pdf, at 410-413 (establishing certain requirements for how an electric utility shall meter the usage of a co-located customer); 89th Texas Legislature, Senate Bill 6 (introduced Feb. 12, 2025), https://capitol.texas.gov/tlodocs/89R/billtext/pdf/SB00006I.pdf#navpanes=0, at 2 (specifying how behind-the-meter retail customers shall pay retail transmission charges).

PDF page 43

43

usage may not be metered.  The Commission must not step outside its jurisdictional boundaries and interfere with a State’s valid regulatory authority over electric power consumption.

V. Conclusion
Given the scale and pace of data center load growth in PJM’s projections and, therefore, the high likelihood that generators and large loads will increasingly seek to implement co- location arrangements, the Commission should take action to ensure that PJM revises its existing tariff and related agreements for co-location arrangements (Options 1 and 2), consistent with our comments, to ensure that rates, terms, and conditions for Commission-jurisdictional services are just, reasonable and not unduly discriminatory or preferential.   We agree that large loads should remain ineligible for the behind-the-meter option (Option 3).  And, while we see limited to no utility with requiring PJM to implement new co-location arrangements (Options 4-8), if the Commission disagrees, we request that it require PJM to implement the provisions that mitigate the risks that we discuss above (e.g., unlawful cost shifts).

PDF page 44

44

Dated: April 23, 2025

Respectfully submitted,
/s/ Christine Powell
Christine Powell, Deputy Managing Attorney /s/ Ada Statler

Ada Statler, Senior Associate Attorney Earthjustice Clean Energy Program

50 California Street, #500
San Francisco, CA 94111
cpowell@earthjustice.org
astatler@earthjustice.org

/s/ Nicholas J. Guidi
Nicholas J. Guidi, Senior Attorney /s/ Katherine L. Rogers

Katherine L. Rogers, Associate Attorney Southern Environmental Law Center

122 C Street NW, Suite 325
Washington, DC 20001
nguidi@selcdc.org
krogers@selcdc.org

Counsel for Appalachian Voices

/s/ Aaron Stemplewicz
Aaron Stemplewicz, Senior Attorney Earthjustice Clean Energy Program

1617 John F. Kennedy Blvd., Suite 2020 Philadelphia, PA 19103

astemplewicz@earthjustice.org
astemplewicz@earthjustice.org

/s/ Ted Kelly
Ted Kelly, Director and Lead Counsel /s/ Adam Kurland

Adam Kurland, Attorney
Environmental Defense Fund,
US Clean Energy
555 12th Street NW Suite 400
Washington, D.C. 20004
tekelly@edf.org
akurland@edf.org

/s/Michael Lenoff
Michael Lenoff, Senior Attorney
/s/ Nick Lawton
Nick Lawton, Senior Attorney
Earthjustice Clean Energy Program
1001 G St. NW, Suite 1000
Washington, DC 20001
nlawton@earthjustice.org

/s/ Jessica O’Neill
Jessica R. O’Neill, Managing Attorney PennFuture Litigation

1429 Walnut Street, Suite 701
Philadelphia, PA  19102
oneill@pennfuture.org

/s/ Megan Wachspress
Megan Wachspress
Sierra Club Environmental Law Program 2101 Webster St., Suite 1300

Oakland, CA 94612
megan.wachspress@sierraclub.org

/s/ Danielle C. Fidler
Senior Attorney
Clean Air Task Force, Inc.
114 State Street, 6th Floor
Boston MA 02109
dfidler@catf.us

PDF page 45

46

CERTIFICATE OF SERVICE

I hereby certify that the foregoing has been served in accordance with 18 C.F.R. § 385.2010 upon each party designated in the official service list compiled by the Secretary in this proceeding, by email.

/s/ Christine Powell
Christine Powell, Deputy Managing Attorney
Earthjustice Clean Energy Program
50 California Street, #500
San Francisco, CA 94111
cpowell@earthjustice.org

PDF page 46

EXHIBIT A

PDF page 47

1
2024 Load Forecast Adjustments
PJM Load Analysis Subcommittee – October 25, 2024

PDF page 48

2
Forecast Overview
o The era of datacenters has caused load growth to become:

▪More concentrated,
▪More disconnected from underlying economics, ▪And thus, more unpredictable.

o AEP is proactively addressing this by: ▪

Making our forecasts as transparent as possible, ▪

Relying on customer financial commitments more than predictive modeling to plan for new loads, ▪

Working to ensure that system costs for new loads are distributed fairly and sustainably.

Industrial
Data
Center
Crypto
Sector
Other
Indiana
Ohio
State
2025 – 2030 Load Adjustment Breakdown:

PDF page 49

3
Load Addition Criteria
Year 6
(2030) Year 20
(2045) 1) LOA Necessary
2) ESA Signed or in Progress
1) LOA’s or ESA’s as Available
2) 60% of Interconnection Queue with Land Control
Where Capacity is Constrained
Basis for load to be included in the forecast across time periods: Year 0

(2024) o In Years 6 and beyond we are outside the range of most signed agreements but still see substantial demand from customers awaiting sufficient transmission capacity for service.

o Capacity constraints have prevented AEP from signing agreements with customers, while the lack of signed agreements has prevented us from adding the necessary capacity to serve those customers. Including this unsigned load in the planning process allows AEP to end this circular reference, ultimately increasing the accuracy of the forecast and PJM’s overall planning processes.

o Within the first five years of the forecast, a project must, at a minimum, have a signed LOA, and an ESA in

progress to be included.
o An ESA becomes all-the-more important if the in-
service date falls within a year of the three-year
capacity planning window to ensure time to develop a
sufficient generation plan.

PDF page 50

4
Accounting for Unsigned Demand
12 GW
16 GW
35 GW
Criteria for including unsigned load additions into the long-term forecast: o Is an area capacity constrained?

o What loads in the interconnection queue already have land control and thus the ability and desire to sign an immediate ESA?

o What are the minimum tariff provisions relevant to the respective load?

Ohio Example:
Total Interconnection Queue
35 GW
% of Queue with Land Control
11.2 GW
60% Tariff Provision
6.7 GW
PJM Load Interconnection Queues at AEP

PDF page 51

5
Forecast Adjustment Summary
Cumulative Additions (MW)
2025
2026
2027
2028
2029
2030
Appalachian Power
41
421
421
421
421
421
Indiana & Michigan Power
721
1,489
2,076
2,565
3,265
6,045
Kentucky Power
3
3
3
3
3
3
AEP Ohio
1,509
2,726
3,423
3,969
4,443
11,421
Total AEP
2,274
4,639
5,924
6,958
8,122
17,890
0
5
10
15
20
2025
2026
2027
2028
2029
2030
Load Forecast Adjustments, GW
Industrial/Other
Crypto
Data Centers

PDF page 52

Dominion
Energy
Virginia
2024
20-Year
Data Center
Forecast
October 2024

PDF page 53

Dominion Energy Virginia - Market Overview

Virginia is home to the largest data center market in the world 

10 out of 53 customers account for 87% of YTD demand 

Forecasted 2024 billing demand:  3,562 MWs

2026 will experience higher than normal sales and demand growth as significant transmission infrastructure is energized, eliminating the temporary transmission constraint in Loudoun County, VA 

Customers are expanding beyond the traditional Northern Virginia market within Dominion Energy Virginia’s retail service territory 

New market entrants are competing for data center demand 

Capacity requests continue to increase
2

PDF page 54

Modeling Process
Forecast is based on 10+ years of metered data center customer information
1. Statistically modeled 7 largest or fastest growing customers and an 8th model of all remaining customers combined into one segment

2. Statistically model high billing demand forecast three ways for each customer segment (24 models)

a) Approach 1:  linear regression of billing demand
b) Approach 2:  polynomial regression of billing demand
c) Approach 3:  custom fit based on market/customer information
Note:  One of these three approaches is selected for each of the 8 customer segments
3. Validate/adjust statistical forecasts based on customer provided long-term forecasts (4 cloud customers)

4. Develop low billing demand forecast using industry aggregate statistical models (4 models)
5. Average high and low forecasts to derive the official billing demand forecast
6. Use load factor to model MWH sales based on high, official, and low forecast scenarios
7. Based on historical ratios, calculate coincident demand forecast from billing demand forecast

3

PDF page 55

Modeling Methodology
4
Forecast Modeling
Statistical
Assessments
Sensitivities
Comparison of
Modeling Approaches
Customer Intelligence
Signed Contracts
Customer Provided
Forecasts
Customer Provided
Growth Intelligence
Geographical Areas of
Future Growth
Market Research
Land Purchase
Intelligence
Industry Changes
Comparison of Data
Center Markets
Validation
Customer Specific
Load Ramps
Customer Provided
Forecasts
Signed Contracts
Dominion LSE
Data Center
Forecast
Submission to PJM

PDF page 56

5
462
532
636
753
931
1,113
1,421
1,808
2,302
2,767
3,183
3,562
 -
 500
 1,000
 1,500
 2,000
 2,500
 3,000
 3,500
 4,000
2013A
2014A
2015A
2016A
2017A
2018A
2019A
2020A
2021A
2022A
2023A
2024F
Billing Demand (MW)
Historical Demand Growth

PDF page 57

6
3,562 3,882
4,504
5,033
5,630
6,253
6,903
7,579
8,283
9,014
9,751
10,515
11,306
12,085
12,820
13,401
14,000
14,618
15,254
15,907
16,577
17,265
 -
 2,000
 4,000
 6,000
 8,000
 10,000
 12,000
 14,000
 16,000
 18,000
2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Billing Demand (MW)

2024 Data Center Forecast

PDF page 58

7
5,597
7,157
7,575
7,880
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
8,012
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
5,835
3,183 3,562 3,882
4,504 5,033 5,630
6,253
6,903
7,579
8,283
9,014
9,751
10,515
11,306
12,085
12,820 13,401 14,000
14,618
15,254
15,907
16,577
17,265
 -
 2,000
 4,000
 6,000
 8,000
 10,000
 12,000
 14,000
 16,000
 18,000
2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Billing Demand (MW)

Contracts in Hand – July 2024
Electric Service Agreements (ESA)
Construction Letters of Authorization (CLOA)
2024 Demand Forecast
7,570 MWs of Substation Engineering Letters of Authorization (SELOA) under contract.

PDF page 59

Questions?
8

PDF page 60

Approach to Large Load Adjustments
Oct 25, 2024

PDF page 61

2
Processes
Forecasting vets
potential load
expansions.
Determines amount
of additional load to
include in the
forecast
Teams monitor
customer expansion
expectations and/or
impacts and adjust
forecasts if needed
Large Account
Management group
works with
customers to plan
for new loads or
load expansions
Economic
Development
works through
leads on
potential new
customer growth
opportunities

PDF page 62

3
Summary
• Over the last 2 years, Duke Energy Ohio-Kentucky has worked with many prospective customers regarding plant expansions and new large loads

• Economic Development / Large Account Management / Load Forecasting work together to identify these new loads and determine impact on forecast

• Focus has been on expansions that are >20 MW’s
• The 4 additions that have been identified are expected to ramp up over the next 5 years
• Work continues with customers regarding possible additions in the future

PDF page 63

4
Additions Detail
§ Large Load Additions in MW’s (at “full load” expectations) § For Comparison purposes:

§ DEO Peaks ~ 4,300 MW’s
§ DEK Peaks ~ 850 MW’s

PDF page 64

5
Warehouse Facility Load Shape

PDF page 65

6
Food Processing Load Shape

Food Processing Facility

PDF page 66

7
Metals / Steel Load Shape

PDF page 67

Duquesne Light Company 2024 Large Load Adjustment October 2024 Load Analysis Subcommittee Meeting 1

PDF page 68

Large Load Adjustment Methodology
• Customers seeking to interconnect new loads or increase their loading submit a request for service to Duquesne Light.

• Duquesne Light analyzes requests for new service and develops estimates to interconnect the customer.
• Duquesne Light updates its load forecast upon commitment from the customer to proceed with the interconnection project.

• Duquesne Light submits a load adjustment to PJM for any loads that may not be captured as part of PJM’s load forecasting efforts.

2

PDF page 69

Requested Adjustment
3
• Duquesne Light is requesting a 20 MW load increase for years 2026-2035.
−The load increase is for a construction project that is expected to last approximately ten years. −The load is forecasted to be a constant 20 MW.

PDF page 70

[No extractable text on this page.]

PDF page 71

October 25, 2024
2025 Large Load Adjustment
Proposal - Exelon
Exelon Load Forecasting

PDF page 72

Agenda
• Exelon Load Forecasting and Large Load Adjustment process summary (Slide 3)
• ComEd Data Center Landscape (Slide 4)
• Large Load Adjustment Assumptions and Forecast Overview (Slide 5) 2

PDF page 73

• Exelon’s Load Forecasting team covers the BGE, ComEd, Peco, ACE, DPL, and PEPCO zones
• Forecasts are derived from industry standard econometric models and techniques incorporating standard drivers of load
• Load forecasts have traditionally not included discrete data centers/large load adjustment given steady historical growth
• Recent rapid growth in in-service customers and growth in new projects (number of requests and request size) drove discrete adjustments to recent internal forecast

• Exelon’s forecast data considered in-service data centers (BGE, ComEd), new confirmed data center projects (BGE, ComEd, PECO) and electric vehicle battery manufacturing (ComEd)

Exelon Load Forecasting Process and Overview
Exelon Load Forecasting and Large Load Adjustment Overview
Key Teams
•
Economic Development
•
Transmission Planning
•
Load Forecasting
Key Data
•
In-service billed demand
•
Capacity requests and ramp
schedules for new projects
Key Steps
•
2024 PJM Load Report “deep dive”
•
Leverage internal best practices
•
Incorporate historical data as guide
Key Result
•
Forecast assumptions exclude less
certain projects
•
Historical trend and economic data
analysis
•
Load driver growth evaluation
•
M-3 status
Large Load Intelligence Gathering
Forecast Assumptions Development
Large Load Forecast Evaluations
3

PDF page 74

-
 100
 200
 300
 400
 500
 600
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
(YTD Aug)
MW
~9% CAGR
~20% CAGR
Significant but stable growth in data centers historically; recent data highlights emergent growth trends

ComEd Data Center Landscape
4

PDF page 75

• Forecast Criteria: Threshold/requirement for including data center/high-density load projects in load forecast and adjustment proposal

• Forecast includes projects with signed engineering agreements/financial deposits
• M-3 Status: All transmission projects were submitted through local plan or are anticipated to be submitted by year end
• Ramp Assumption: incremental load increases to final capacity
• 8-year ramp new projects from in-service date based on historical experience with large load customer ramps
• Utilization Rate Assumption: % of requested customer capacity assumed to be realized after ramp period
• Varies by zone reflecting project specific detail
Key Forecast Criteria/Assumptions
Large Load Adjustment Assumptions and Forecast
Large Load Forecast Adjustment Overview
2029 Load Forecast (2.6 GW)*
•
BGE: 0.1 GW
•
ComEd: 2.2 GW
•
PECO: 0.2 GW
Capacity Requests (8 GW)*
•
BGE: 0.5 GW
•
ComEd: 7.0 GW
•
PECO: 0.4 GW
Large Load Forecast Request Adjustment of 2.6 GW in 2029
Key Assumptions
•
Ramp
•
Utilization Rate
* Includes in-service and new projects meeting forecast criteria; amounts may not sum due to rounding * 2029 load forecast adjustment represents year-end GW

5

PDF page 76

Thank you

PDF page 77

[No extractable text on this page.]

PDF page 78

Large Load Adjustment 2024
Presented by E. B. Stein
10/25/2024
ATSI and APS Zones*

PDF page 79

Approach

10/25/2024
Load Analysis Subcommittee
2
Large Load Adjustment 2024

PDF page 80

Process
■*ATSI and APS Zones only
– Other FE zones do not have load increases requiring a Large Load Adjustment disclosure at this time ■Begin with weather normalized peak forecast

– Based on historical data for FE Electric Companies
– Use forecast peak data where provided by Municipalities and Cooperatives
– Effects of economic and societal behavioral changes captured here (for FE electric companies)
– EV Growth, Electrification, Industrial Output, Customer changes, Energy Efficiency, Distributed Energy Resources, Etc.

■Customer interconnection requests are an independent addition to the forecast
– These become PJM Large Load Adjustments
– Introduced a scoring system to reduce subjectivity of including in the forecast
– Based on a series of questions describing where in process project is
– Score greater than or equal to 5 is included in PJM LLA submittal
■Continuous Improvement
– FE has a committed forecasting operation empowered to keep step with industry trends and requirements
– FERC Order 1920, State requirements
10/25/2024
Load Analysis Subcommittee
3

PDF page 81

ATSI

10/25/2024
Load Analysis Subcommittee
4
Large Load Adjustment 2024

PDF page 82

ATSI Zone Quick Information
■The ATSI Zone covers two states – Ohio and Pennsylvania ■The FirstEnergy Electric Companies

– Ohio Edison
– Toledo Edison
– Cleveland Electric Illuminating Company
– FE Pennsylvania Electric Company (Penn Power District only)
– Total retail customers: Roughly 2.2 Million
■Several Municipalities and Cooperatives are served through the following:
– American Municipal Power
– Buckeye Power
– Cleveland Public Power
10/25/2024
Load Analysis Subcommittee
5

PDF page 83

ATSI Zone Large Load Adjustment Summary
10/25/2024
Load Analysis Subcommittee
6

PDF page 84

ATSI Zone – Summer Peak MW
10/25/2024
Load Analysis Subcommittee
7
W/N = Weather Normalized

PDF page 85

APS

10/25/2024
Load Analysis Subcommittee
8
Large Load Adjustment 2024

PDF page 86

APS Zone Quick Information
■The APS Zone covers four states –Pennsylvania, Maryland, Virginia and West Virginia ■The FirstEnergy Electric Companies

– Monongahela Power
– Potomac Edison (WV & MD)
– FE Pennsylvania Electric Company (West Penn Power District only)
– Total retail customers: Roughly 1.5 Million
■Several Municipalities and Cooperatives are served through the following:
– Old Dominion Electric Cooperative (VA)
– Front Royal
– Chambersburg
– Letterkenney
– Mont Alto
– Tarentum
– Hagerstown
– Thurmont
10/25/2024
Load Analysis Subcommittee
9
– Williamsport
– HREA
– New Martinsville
– Philippi
– Allegheny Electric
Cooperative

PDF page 87

APS Zone Large Load Adjustment Summary
10/25/2024
Load Analysis Subcommittee
10

PDF page 88

APS Zone – Summer Peak MW
10/25/2024
Load Analysis Subcommittee
11
W/N = Weather Normalized

PDF page 89

10/25/2024
Load Analysis Subcommittee
12
Large Load Adjustment 2024

PDF page 90

NOVEC Data Center Load Forecast
PJM Load Analysis Subcommittee
October 25, 2024

PDF page 91

• NOVEC has requested that PJM incorporates an adjustment in the upcoming 2025 PJM Load Forecast to reflect data center growth in NOVEC service territory

• NOVEC 2024 Data Center Forecast Timeline:
✓Aug 1:
Forecast Finalized
✓Aug 2:
Distributed internally
✓Sep 2:
Submitted to Dominion Energy Transmission Planning
✓Sep 9:
Submitted to PJM Load Analysis Team
✓Sep-Oct: Responded to inquiries from PJM staff
❑Oct 25: Present at PJM LAS
❑Nov-Dec: Prepare written document for PJM Load Forecast Overview

PDF page 92

• Goal: Present on NOVEC’s load forecast adjustment request as required by PJM Manual 19 Attachment B

• Agenda:
• Brief background on NOVEC
• Data center activity in Northern Virginia
• NOVEC’s forecasting methodology
• NOVEC 2024 Data Center Load Forecast
• Comparison of 2024 vs 2023 forecasts
• Q&A
• Key takeaways:
• NOVEC has a sound, defensible process for producing data center load forecasts
• NOVEC’s data center forecast should be incorporated as an adjustment in the 2025 PJM Load Forecast

Agenda

PDF page 93

About NOVEC
• NOVEC: Northern Virginia Electric Cooperative

• Largest US electric distribution
cooperative by KWH sales
• Service Territory: 651 square miles of primarily suburban/exurban

• Customer Mix: residential, small
commercial, critical government facilities, data centers, and other large power

• Meters: Approx. 180,000 (~275 per square mile)

PDF page 94

NOVEC Data Centers
• NOVEC serves 50+ data centers
with approx. load of 1000 MW
• Contribution:
• Energy: 64% (Oct. 23-Sep. 24)
• Summer Peak: 51% (Jul. 24)
• Winter Peak: 51% (Jan. 24)
• Key hotspots: Loudoun and Prince
William

PDF page 95

Rapid Load Growth for NOVEC
6

PDF page 96

• Key terms:
• Contracted capacity – nameplate capacity of the building’s electric service
• Metered demand – building’s actual usage
• Utilization rate – metered demand as a percentage of contracted capacity Data Center 101

7

PDF page 97

Data Center Developments
20
MVA
40
MVA
40 MVA
40 MVA
100
MVA
100
MVA
100
MVA
SUB
SUB
100
MVA
100
MVA
100
MVA
SUB
100
MVA
100
MVA
100
MVA
SUB
100
MVA
100
MVA
100
MVA
Building
Campus
70
MVA
70 MVA
70 MVA
SUB
70
MVA
Campus + Dedicated
Substation
Mega-Campus + Multiple
Dedicated Substations

PDF page 98

• Two phases:
1. Ramping – load increases over time while building is filled out
2. Maturity – building is fully constructed, load remains relatively stable over time
• Key features:
• Daily/weekly/annual seasonal patterns
• Weather sensitivity (cooling only)
• Very high load factor
• Heterogeneity: every customer, campus, and building is unique
Data Center Load Profile

PDF page 99

• NOVEC utilizes a bottom-up forecasting approach for data centers
• Forecast load on individual buildings
• Aggregate building loads to campus, substation, region, system
• Phase one: identify all data centers in NOVEC service territory
• Phase two: produce metered load forecast for each building Methodology Overview

PDF page 100

• NOVEC identifies all current and upcoming data center projects within our service territory

• Includes: active, under construction, or planned projects highly likely to be successfully developed

• NOVEC’s analysis includes:
• Collecting a detailed site plan
• Identifying the electric infrastructure that will serve each project Phase one: Planning

PDF page 101

• NOVEC generates a metered load forecast for each building identified in the planning phase

• Econometric models were developed and are used by NOVEC staff to predict building-level utilization rates (metered demand/contracted capacity) conditional on:

• Calendar factors (day of week/day of year)
• Weather factors (cooling degree days)
• Past behavior at the customer, campus, and/or building-level when available
• Building-level forecasts are aggregated to
campus/substation/region/system as needed
Phase two: Forecasting

PDF page 102

• Forecast generated August 2024
• Incorporates projects identified and vetted through 2024-07-31
• Econometric models estimated with metered load data through 2024-07-31
• NOVEC requests PJM incorporate this forecast as an adjustment to the upcoming 2025 PJM Load Forecast

NOVEC Data Center Forecast
August 2024 Forecast Vintage

PDF page 103

Actual
Forecast
Jul
2020
Jul
2021
Jul
2022
Jul
2023
Jul
2024
Jul
2025
Jul
2026
Jul
2027
Jul
2028
Jul
2029
Data Centers (#)
29
33
37
47
55
74
97
118
138
167
Yr-Yr Change
5
4
4
10
8
19
23
21
20
29
Contracted
Capacity (MVA)
866
1,131
1,380
1,794
2,347
3,513
5,153
6,784
8,266
10,927
Yr-Yr Change
230
265
249
414
553
1,166
1,640
1,631
1,482
2,661
Coincident Peak
Load (MW)
298
432
545
808
1,049
1,408
2,204
3,170
4,480
5,861
Yr-Yr Change
55
134
113
263
241
359
796
966
1,310
1,381
Near-term Forecast
August 2024 Forecast Vintage

PDF page 104

Long-term Forecast
August 2024 Forecast Vintage

PDF page 105

• Updates for the 2024 Forecast:
1. New projects added
• Net impact: substantial increase in long-term contracted capacity/peak load levels
2. Updates to existing project timelines
• Net impact: modest reduction in near-term growth
3. Re-trained load models with latest metered load readings
• Net impact: negligible change in projected utilization rates
Forecast Updates: 2023 vs 2024

PDF page 106

Forecast Updates: 2023 vs 2024

PDF page 107

• Goal: Present on NOVEC’s load forecast adjustment request as required by PJM Manual 19 Attachment B

• Key takeaways:
• NOVEC has a sound, defensible process for producing data center load forecasts
• NOVEC’s data center forecast should be incorporated as an adjustment in the 2025 PJM Load Forecast

• NOVEC Forecast Adjustment Timeline:
✓Sep 9:
 Submitted to PJM Load Analysis Team
✓Sep-Oct:  Responded to inquiries from PJM staff
✓Oct 25:  Present at PJM LAS
❑Nov-Dec: Prepare written document for PJM Load Forecast
Summary

PDF page 108

ODEC Large Load
Adjustments
Brandon Newbill – Senior Manager, Power Supply Planning October 25, 2024

PDF page 109

About ODEC
Old Dominion Electric Cooperative is a member-owned,
not-for-profit wholesale generation and transmission electric cooperative. ODEC supplies power for 11 not-for-profit retail distribution cooperatives in Virginia, Maryland and Delaware, serving 1.5 million people.

PDF page 110

ODEC’s Membership Territories
3

PDF page 111

ODEC Historical
Data Center Load
4

PDF page 112

Historical Data Center Load - Demand (MW) 5

 -
 100
 200
 300
 400
 500
 600
 700
 800
 900
 1,000
1/1/2022
3/1/2022
5/1/2022
7/1/2022
9/1/2022
11/1/2022
1/1/2023
3/1/2023
5/1/2023
7/1/2023
9/1/2023
11/1/2023
1/1/2024
3/1/2024
5/1/2024
7/1/2024
9/1/2024
11/1/2024
1/1/2025
3/1/2025
5/1/2025
7/1/2025
9/1/2025
11/1/2025
1/1/2026
3/1/2026
5/1/2026
7/1/2026
9/1/2026
11/1/2026
1/1/2027
3/1/2027
5/1/2027
7/1/2027
9/1/2027
11/1/2027
1/1/2028
3/1/2028
5/1/2028
7/1/2028
9/1/2028
11/1/2028
1/1/2029
3/1/2029
5/1/2029
7/1/2029
9/1/2029
11/1/2029
1/1/2030
3/1/2030
5/1/2030
7/1/2030
9/1/2030
11/1/2030
MW
Data Center Complex
Forecasted Peak vs. Actual Peak by Month Forecasted

Actual
2022 average = 125% actual vs. forecast 2023 average = 118% actual vs. forecast 2024 average = 81% actual vs. forecast (YTD)

PDF page 113

Historical Data Center Load - Energy (MWh) 6

 -
 100,000
 200,000
 300,000
 400,000
 500,000
 600,000
1/1/2022
3/1/2022
5/1/2022
7/1/2022
9/1/2022
11/1/2022
1/1/2023
3/1/2023
5/1/2023
7/1/2023
9/1/2023
11/1/2023
1/1/2024
3/1/2024
5/1/2024
7/1/2024
9/1/2024
11/1/2024
1/1/2025
3/1/2025
5/1/2025
7/1/2025
9/1/2025
11/1/2025
1/1/2026
3/1/2026
5/1/2026
7/1/2026
9/1/2026
11/1/2026
1/1/2027
3/1/2027
5/1/2027
7/1/2027
9/1/2027
11/1/2027
1/1/2028
3/1/2028
5/1/2028
7/1/2028
9/1/2028
11/1/2028
1/1/2029
3/1/2029
5/1/2029
7/1/2029
9/1/2029
11/1/2029
1/1/2030
3/1/2030
5/1/2030
7/1/2030
9/1/2030
11/1/2030
Energy (MWh)
Data Center Complex
Forecasted Load vs. Actual Load by Month Forecasted

Actual

PDF page 114

ODEC Large Load Forecast
7

PDF page 115

ODEC Large Load Forecast (3,212 MWs) – Project Status 8

 -
 500
 1,000
 1,500
 2,000
 2,500
 3,000
 3,500
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
2042
2043
2044
2045
Load (MW)
ODEC Large Load Forecast - Project Status
In-Service
Construction
Design
Study

PDF page 116

ODEC Large Load Forecast – Type of Data Center 9

 -
 500
 1,000
 1,500
 2,000
 2,500
 3,000
 3,500
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
2042
2043
2044
2045
Load (MW)
ODEC Large Load Forecast - Type of Data Center Hyperscale

Co-Locator
TBD - Developer

PDF page 117

ODEC Large Load Forecast – Contract Agreements
10
 -
 500
 1,000
 1,500
 2,000
 2,500
 3,000
 3,500
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
2042
2043
2044
2045
Load (MW)
ODEC Large Load Forecast - Contracts in Place
LOA + ED&C + ESA
LOA + ED&C
LOA Only
LOA = Letter of Agreement
ED&C = Engineering, Design, and Construction (Procurement) ESA = Electric Service Agreement

PDF page 118

ODEC Large Load Forecast
Methodology
11

PDF page 119

ODEC Large Load Forecast Methodology
1. ODEC reviews delivery point load requests monthly
2. To prepare for the annual PJM large load adjustment submission, ODEC meets with its member distribution cooperatives to review each individual delivery point request to discuss project specifics

▪Determine financial commitments made by the end use customer
▪Identify contracts that are in place
▪Discuss other quantitative/qualitative factors to forecast the likelihood of the project
3. Using the information identified in step 2, ODEC selects the projects to include in the submission to PJM

▪30% (~950 MW) of ODEC’s total submission are projects currently in-service or under construction

▪Additional projects were included that met the qualifications outlined in PJM Manual 19b ▪ODEC’s submission to PJM represents approximately 25% (in terms of MWs) of the delivery point requests already submitted or are anticipated to be submitted soon

4. ODEC uses the load ramp provided by the member (by way of the end use customer) and assumes monthly smoothing

5. ODEC meets with member cooperatives and TOs to verify that projects are not double counted 12

PDF page 120

1
PPL Service Territory
Data Center Load Growth
PJM Load Analysis Subcommittee
October 25, 2024
George Khoury

PDF page 121

2
Company Profile
PPL Electric Utilities
•
Headquartered in
Allentown, PA
•
Serves 1.5 million
customers in 29
Pennsylvania counties
•
Operates 50,000 miles of
power lines
Louisville Gas and Electric
and Kentucky Utilities
•
Headquartered in
Louisville, KY
•
Serves 1.3 million customers
in almost 100 counties
across Kentucky and Virginia
•
More than 8,000 megawatts
of generation capacity
Rhode Island Energy
•
Headquartered in
Providence, RI
•
Serves 770,000
customers across RI
•
Over 9,000 miles of
power and gas lines

PDF page 122

3
Company Profile
• More than 6,700 employees
• Serve more than 3.5 million customers in the U.S.
• Operate and maintain over 90,000 miles of electric and gas lines
• 36 billion kilowatt-hours of electricity delivered in 2021 (LG&E and KU and PPL EU)
• PPL’s service area in Pennsylvania and Kentucky covers nearly 20,000 square miles
• Over the past decade, we have invested more than $20 billion in new infrastructure and technology to create a smarter, more reliable and resilient energy grid.

• Thanks to our investments in smart grid technology, >1M outages avoided since 2015
• Company goal to reach net-zero carbon emissions by 2050
• Consistently recognized as an industry leader in customer satisfaction

PDF page 123

4
PPL Historical and Forecasted Loads

PDF page 124

5
PPL Interconnection Process
INITIAL STUDY
SIGNED
AGREEMENT
DEVELOPMENT
PHASE
CONSTRUCTION
•
Since Aug 2023, PPL has received over 35,000 MW of large load interconnection requests •

Approximately 20% of the requested load developed into a Signed Agreement.
•
All Signed Agreements are presented at the TEAC as soon as the contractual agreement was completed.

PDF page 125

6
Methodology & Process
• To ensure an accurate representation of datacenter load within PPL territory, only those with a Signed Agreement are typically included in the Load Forecast.

• Majority of the requested loads with a Signed Agreement have been presented at the previous TEAC meetings.

• The solutions presented for the requested loads ensure the ability to meet the load ramp schedule and to reuse or uprate the facilities based on additional loads being added to the area.

• It is our goal to have accurate and realistic load projections that reflect the locations of the load and high probability of execution.

• PPL continues to engage with PJM to ensure that all our customers have sufficient capacity to meet their energy and reliability needs.

PDF page 126

7
Load Ramp Schedule
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
2025
2026
2027
2028
2029
2030
2031
2032-2045
Cumulative Load (MW)
Year
Load Ramp

PDF page 127

8
George Khoury -  Transmission Planning LGKhoury@pplweb.com

Sean Zimmerman – Load and Settlement Specialist SZimmerman@pplweb.com

Colleen Kester – Interconnection Affairs CKester@pplweb.com

Contact Information

PDF page 128

PSE&G Load Forecast
Adjustment Request
10/25/2024
Presentation for the PJM Load Analysis Subcommittee

PDF page 129

2 2
2025 Load Adjustment request
PSE&G Requests Adjustment to the
2025 PJM Load Forecast for PS Zone

An accurate load forecast is crucial to ensuring grid reliability in the near-term and long-term. 

PSE&G requests adjustments to PJM’s 2025 load forecast to improve the accuracy of the load forecast.


PJM’s forecast must reflect evolving energy demand trends driven by New Jersey data centers growth and ports electrification/expansion.

Data Center Load Growth: Significant increases are being experienced due to expansion of the existing data centers, new data center load requests, and the feasibility study requests.

Port Electrification: Major projects to electrify operations at ports will drive new energy demands.

PDF page 130

3 3
2025 Load Adjustment request
Data Centers Load Forecast
PSE&G currently has 39 data center sites with a summer peak demand of 343MW. Data centers are significant users of on-peak electricity, since they are more energy intensive than the average commercial activity, data centers are not captured by the PJM econometric based load forecast model framework.

Expansions of existing data centers, new data center load requests, and feasibility study requests from data center customers, are driving an increase in load forecast. For each new load and feasibility study request, PSE&G assessed a likelihood percentage (confidence level: 0% to 100%) using the factors below:

This approach factors in the likelihood of realization of Data Center projects. o

Customer readiness
o
Construction complexity
o
Equipment lead time / availability
o
Site control
o
Overall customer commitment, etc.

PDF page 131

4 4
Existing and Projected Data Center Load
2025 Load Adjustment request
PSE&G developed a 20-year forecast through 2045 comprised of: 

Expansion and New Data Center load requests: At various stages of completion. The analysis assumes an average completion likelihood of 95% for new data centers.


Feasibility Study requests: Assumes an average completion likelihood of 40%. 

Estimate: An extrapolation of continued Data Center growth from 2035-2045. Existing

(MW)
Expansions of
Existing (MW)
New Load
Requests
(MW)
Feasibility
Study Requests
(MW)
 Estimate
(MW)
Total
(MW)
2024
343
343
2025
343
29
10
8
390
2026
343
65
70
78
556
2030
343
145
330
377
1196
2035
343
168
330
456
39
1337
2040
343
168
330
456
143
1441
2045
343
168
330
456
247
1545

PDF page 132

5 5
Port Electrification
2025 Load Adjustment request
The Clean Ports Program in the Inflation Reduction Act includes $3 billion in funding to plan, purchase or install zero-emission port equipment or technology at the nation’s ports1. The electrification of ports is seen as a key way to reduce air pollutants and address public health and environmental impacts on surrounding communities.


The Port Authority of New York and New Jersey (PANYNJ) has begun planning to electrify the Ports of Newark, Elizabeth and Bayonne to achieve the goal of net zero carbon emissions by 20502.


This load increase is not captured by the PJM Load Forecasting Model’s economic drivers. 1: United States Environmental Protection Agency, “Clean Ports Program”, https://www.epa.gov/inflation-reduction-act/clean-ports-program 2: Squires, Anna,” NREL Leads the Charge to Electric Trucks at Port of New York and New Jersey”, National Renewable Energy Laboratory, January 30, 2023 3: Includes requests from South Jersey Port in Camden, NJ

3

PDF page 133

6
you
Thank

PDF page 134

Rappahannock Electric
Cooperative (REC)
2024 Data Center Forecast
1

PDF page 135

Modeling Methodology
Considerations:
•
There is no currently no metered data center load in REC’s service territory •

REC requested Dominion Energy Virginia’s assistance with the forecast •

The forecast does not assume continued growth in the long-term given the newness of the market.  This assumption will be revisited annually. Modeling Process:

•
Modeled demand curve based on Dominion’s aggregate load shape. •

Applied REC and customer provided information to validate curve. 2

PDF page 136

3
0
61
169
300
454
631
830
1,052
1,297
1,564
1,854
2,167
2,502
2,762
2,963
3,119
3,240 3,333 3,333 3,333 3,333 3,333
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Billing Demand (MW)

Rappahannock Electric Cooperative
2024 Data Center Forecast

PDF page 137

Questions?
4