Comments of Public Interest Organizations in response to PJM Interconnection, L.L.C.’s 03/24/2025 Answer to FERC’s 02/20/2025 Order
Text extracted from the eLibrary original (SHA-256 e9fdc9937aa7678e…). Download the original from the official source.
Contents · 29 sections
- II. PJM’s OATT, the Amended and Restated Operating Agreement of PJM, and the Reliability
- A. PJM’s Existing Study Processes to Identify and Allocate Costs for Transmission
- B. The Load Forecasting Provisions in PJM’s Practice Manual 19 Lack Controls and
- III. Any Replacement Rate that Enables Co-location Arrangements Involving the Use of
- A. Co-Location Arrangements Must Pay for the Transmission and Ancillary Services from
- B. The Commission Must Ensure that Co-Location Arrangements With Existing Capacity
- C. Co-Location Arrangements Should Not Receive Preferential Interconnection
- D. The Commission Must Ensure that PJM Conducts Rigorous Reliability Review of Co-
- E. The Commission Should Fix its Market Power Mitigation Rules to Address the Increased
- IV. Consistent with Precedent, The Commission Should Assert Jurisdiction over Co-Location
- A. The Commission Must Not Disclaim Jurisdiction Over Interconnection of
- I. Introduction
- II. PJM’s OATT, the Amended and Restated Operating Agreement of PJM, and the
- A. PJM’s Existing Study Processes to Identify and Allocate Costs for
- B. The Load Forecasting Provisions in PJM’s Practice Manual 19 Lack
- III. Any Replacement Rate that Enables Co-location Arrangements Involving the Use
- A. Co-Location Arrangements Must Pay for the Transmission and Ancillary
- B. The Commission Must Ensure that Co-Location Arrangements With
- C. Co-Location Arrangements Should Not Receive Preferential
- D. The Commission Must Ensure that PJM Conducts Rigorous Reliability
- E. The Commission Should Fix its Market Power Mitigation Rules to
- IV. Consistent with Precedent, The Commission Should Assert Jurisdiction over Co-
- A. The Commission Must Not Disclaim Jurisdiction Over Interconnection
- B. The Commission Must Plan for Wholesale Sales at Co-Located Facilities.
- C. PJM Must Not Limit States’ Authority Over the Co-Located Generation
- D. The PJM Tariff Should Treat Co-Located Usage As Any Other
- V. Conclusion
- Summary
- Summary
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 70, 77.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection L.L.C. ) ) ) Docket No.Read this passage
Table of Contents
printed heading
Table of Contents I.Read this passage
II. PJM’s OATT, the Amended and Restated Operating Agreement of PJM, and the Reliability
printed heading
II.Read this passage
A. PJM’s Existing Study Processes to Identify and Allocate Costs for Transmission
printed heading · Topic match: Connecting load and generation
A.Read this passage Filed comments: Connecting load and generation
B. The Load Forecasting Provisions in PJM’s Practice Manual 19 Lack Controls and
printed heading
B.Read this passage
III. Any Replacement Rate that Enables Co-location Arrangements Involving the Use of
printed heading
III.Read this passage
A. Co-Location Arrangements Must Pay for the Transmission and Ancillary Services from
printed heading
Co-Location Arrangements Must Pay for the Transmission and Ancillary Services from Which They Benefit. ................................................................................................................. 25Read this passage
B. The Commission Must Ensure that Co-Location Arrangements With Existing Capacity
printed heading · Topic match: Reliability and curtailment
The Commission Must Ensure that Co-Location Arrangements With Existing Capacity Resources Do Not Unjustly Shift Costs of Maintaining Resource Adequacy. ......................... 26Read this passage Filed comments: Reliability and curtailment
C. Co-Location Arrangements Should Not Receive Preferential Interconnection
printed heading
C.Read this passage
D. The Commission Must Ensure that PJM Conducts Rigorous Reliability Review of Co-
printed heading
The Commission Must Ensure that PJM Conducts Rigorous Reliability Review of Co- Location Arrangements. ............................................................................................................ 30Read this passage
E. The Commission Should Fix its Market Power Mitigation Rules to Address the Increased
printed heading
E.Read this passage
IV. Consistent with Precedent, The Commission Should Assert Jurisdiction over Co-Location
printed heading
IV.Read this passage
A. The Commission Must Not Disclaim Jurisdiction Over Interconnection of
printed heading
EL25-49-000 COMMENTS OF PUBLIC INTEREST ORGANIZATIONS Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (FERC or Commission) Rules of Practice and Procedure,1 Appalachian Voices, Clean Air Task Force, Earthjustice, the Environmental Defense Fund, PennFuture, and the Sierra Club,…Read this passage
I. Introduction
printed heading · Topic match: Cost allocation
While options 1-2 are favorable since they require that load acquire network service, the status quo provisions are not sustainable in the face of a huge influx of these arrangements and need for substantial changes to the study processes, large load forecast process, and cost allocation.14 As…Read this passage Filed comments: Cost allocation
II. PJM’s OATT, the Amended and Restated Operating Agreement of PJM, and the
printed heading
PJM’s OATT, the Amended and Restated Operating Agreement of PJM, and the Reliability Assurance Agreement Among Load Serving Entities in PJM’s Region are Unjust, Unreasonable, and Unduly Discriminatory and Preferential.Read this passage
A. PJM’s Existing Study Processes to Identify and Allocate Costs for
printed heading · Topic match: Connecting load and generation
Under PJM’s existing Tariff, there is high risk that co-located load underpays for the upgrades it triggers by only taking sole responsibility for costs arising in the Necessary Study Process (to the extent an existing generator passes the costs on to the co-located load, that is).Read this passage Filed comments: Connecting load and generation
B. The Load Forecasting Provisions in PJM’s Practice Manual 19 Lack
printed heading · Topic match: Reliability and curtailment
Operator Corp, 133 FERC ¶ 61,224 at P 159 & n.138 (2010) (“While, presently, we find it acceptable to place the mentioned details used to determine policy-driven elements in the Business Practice Manual, if, once drafted, a party is concerned that these provisions could significantly affect rates…Read this passage Filed comments: Reliability and curtailment
III. Any Replacement Rate that Enables Co-location Arrangements Involving the Use
printed heading · Topic match: Connecting load and generation
Additionally, we reiterate that the unjust and unreasonable practices identified in 68 See PJM Answer at 13-20 (New Option 4: Co-located load with connection to the grid with protections to avoid delivery of system energy to serve the load; New Option 5: Co-located load with connection to the grid…Read this passage Filed comments: Connecting load and generation
A. Co-Location Arrangements Must Pay for the Transmission and Ancillary
printed heading · Topic match: Cost allocation
We agree with the Commission’s findings in the Show Cause Order that the PJM Tariff may be unjust, unreasonable, unduly discriminatory or preferential insofar as the Tariff fails to ensure that co-location arrangements follow cost causation principles for transmission and ancillary services.69…Read this passage Filed comments: Cost allocation
B. The Commission Must Ensure that Co-Location Arrangements With
printed heading · Topic match: Cost allocation
EL25-49-000, (Apr. 10, 2025), Accession No. 20250411-5520. 74 PJM Answer at 36. 75 See Comments of Suzanne Glatz and Abraham Silverman (quoting Order No. 2003-A at P 12, “neither Energy Resource Interconnection Service nor Network Resource Interconnection Service guarantees delivery service”). 27…Read this passage Filed comments: Cost allocation
C. Co-Location Arrangements Should Not Receive Preferential
printed heading · Topic match: Connecting load and generation
ER24-2045 (June 20, 2024), Accession No. 20240620-5242 (documenting PJM’s badly backlogged interconnection queue and substantial delays in processing interconnection requests). 86 See, e.g., Final Brief of Respondent-Intervenors Interconnection Reform Advocates, at 39-44, Advanced Energy United et…Read this passage Filed comments: Connecting load and generation
D. The Commission Must Ensure that PJM Conducts Rigorous Reliability
printed heading · Topic match: Connecting load and generation
The Commission Must Ensure that PJM Conducts Rigorous Reliability Review of Co-Location Arrangements.Read this passage Filed comments: Connecting load and generation
E. The Commission Should Fix its Market Power Mitigation Rules to
printed heading
The Show Cause Order asks for a variety of information on how co-location arrangements may require changes to the PJM Tariff and the rules governing PJM’s capacity, energy, and ancillary services markets.95 One such area pertains to market power and manipulation.Read this passage
IV. Consistent with Precedent, The Commission Should Assert Jurisdiction over Co-
printed heading
Primarily, the order asks “whether the Commission must, should, or can exercise jurisdiction over the interconnection of co-location arrangements to the transmission system in interstate commerce as an element of transmission service, including where the purpose is to facilitate a retail sale.”100…Read this passage
A. The Commission Must Not Disclaim Jurisdiction Over Interconnection
printed heading · Topic match: Connecting load and generation
The Commission Must Not Disclaim Jurisdiction Over Interconnection of Large Loads.Read this passage Filed comments: Connecting load and generation
B. The Commission Must Plan for Wholesale Sales at Co-Located Facilities.
printed heading · Topic match: Retail and wholesale authority
The Commission must carefully consider its responsibilities when a co- located large load customer is not taking retail service.Read this passage Filed comments: Retail and wholesale authority
C. PJM Must Not Limit States’ Authority Over the Co-Located Generation
printed heading · Topic match: Retail and wholesale authority
With these jurisdictional contours in mind, any FERC-jurisdictional tariff structure that may facilitate co-location arrangements must be neutral to technology type and not favor or disfavor any type of co-located generator, lest it encroach on a state’s desire to structure co-location arrangements…Read this passage Filed comments: Retail and wholesale authority
D. The PJM Tariff Should Treat Co-Located Usage As Any Other
printed heading · Topic match: Connecting load and generation
“The Commission … shall not have jurisdiction, except as specifically provided in this subchapter and subchapter III of this chapter, over facilities used for the generation of electric energy[.]” 16 U.S.C. 824(b)(1). 125 Show Cause Order at 70. 126 Order Rejecting Tariff Revisions, Atlantic City…Read this passage Filed comments: Connecting load and generation
V. Conclusion
printed heading · Topic match: Cost allocation
Conclusion Given the scale and pace of data center load growth in PJM’s projections and, therefore, the high likelihood that generators and large loads will increasingly seek to implement co- location arrangements, the Commission should take action to ensure that PJM revises its existing tariff and…Read this passage Filed comments: Cost allocation
CERTIFICATE OF SERVICE
printed heading · Topic match: Connecting load and generation
Including this unsigned load in the planning process allows AEP to end this circular reference, ultimately increasing the accuracy of the forecast and PJM’s overall planning processes. o Within the first five years of the forecast, a project must, at a minimum, have a signed LOA, and an ESA in…Read this passage Filed comments: Connecting load and generation
Summary
printed heading
Summary • Over the last 2 years, Duke Energy Ohio-Kentucky has worked with many prospective customers regarding plant expansions and new large loads • Economic Development / Large Account Management / Load Forecasting work together to identify these new loads and determine impact on forecast •…Read this passage
Summary
printed heading
ODEC reviews delivery point load requests monthly 2.Read this passage