EL25-49-000 · 2025-04-23 · Invenergy Renewables LLCInvenergy Thermal LLC

Comments of Invenergy Renewables LLC and Invenergy Thermal LLC

PDF page 1

DCACTIVE-79938279.1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.

)
Docket No. EL25-49-000

)
Large Loads Co-Located at Generating Facilities
)
Docket No. AD24-11-000

)
Constellation Energy Generation, LLC

)
Docket No. EL25-20-000
v.

)
PJM Interconnection, L.L.C.

)
(Consolidated)

COMMENTS OF INVENERGY RENEWABLES LLC AND INVENERGY THERMAL
LLC

Invenergy Renewables LLC and Invenergy Thermal LLC (collectively, “Invenergy”)
respectfully submit these comments in response to the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) February 20, 2025, Order to Show Cause1 and PJM Interconnection, L.L.C.’s (“PJM”) March 24, 2025, answer in the above-captioned proceeding.2

As the Commission has acknowledged, data centers, advanced manufacturing, and
electrification are spurring significant load growth. By 2028, data centers alone will account for up to 12% of national electricity consumption, exceeding even relatively recent load forecasts.3 As a result, the Commission and regional transmission organizations are reexamining existing policies to ensure they can satisfy these new demands. PJM, the Midcontinent Independent

1 PJM Interconnection, L.L.C. et al, 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).
2 PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al., Answer oof PJM Interconnection, L.L.C. (Mar. 24. 2025).
3 2024 United States Data Center Energy Usage Report at 52, Lawrence Berkeley National Laboratory (Dec. 2024), available at https://www.energy.gov/articles/doe-releases-new-report-evaluating-increase-electricity-demand-data- centers; Mooney, M., 2025 Preliminary PJM Load Forecast, Load Analysis Subcommittee (Dec. 9, 2024), available at https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2024/20241209/20241209-item- 03---2025-preliminary-pjm-load-forecast.ashx;

PDF page 2

DCACTIVE-79938279.1

2

System Operator, Inc. (“MISO”), and the Southwest Power Pool, Inc. (“SPP”), for instance, have all proposed upending long-standing interconnection procedures for short-term, and Invenergy would argue sometimes illusory, benefits.4 But regardless of the merits of those individual proposals, they share a common feature: they are reactive, rather than proactive. They do not improve load forecasting, facilitate needed transmission deployment, or establish generally- applicable market rules that facilitate long-term investment to accommodate new, large loads. This Show Cause proceeding is a needed first step to address these broader issues, but as Invenergy sets forth below, the Commission should not stop upon adopting rules for co-located large loads. Rather, it should seize this opportunity to articulate a new, proactive paradigm for jointly studying large-load interconnection requests as part of the generator interconnection queue, thereby ensuring that RTOs/ISOs engage in coordinated load, interconnection, and transmission planning that enhances resource adequacy and reliability, while efficiently deploying generation and allocating scarce transmission where it is most needed. The Commission should also consider other, economical alternatives for addressing load growth. Therefore, in addition to adopting an integrated planning process, the Commission should ensure that RTOs/ISOs properly value and compensate merchant transmission for its reliability and economic benefits.5 While Invenergy acknowledges this issue is outside the scope of this proceeding, it encourages the Commission to adopt policies that better facilitate merchant transmission as part of its holistic consideration of how to address large load growth. With regard to this Show Cause proceeding, Invenergy offers the following high-level

4 See, e.g., PJM’s Reliability Resource Initiative and MISO’s Expedited Resource Adequacy Study, a version of which SPP is also considering.  PJM Interconnection, L.L.C., 190 FERC ¶ 61,084 (2025); Midcontinent Indep. Sys. Operator, Inc., Expedited Resource Addition Study Filing, Docket No. ER25-1674-000 (filed Mar. 17, 2025).
5 See Invenergy Transmission LLC, Request for Technical Conference Concerning Interregional HVDC Merchant Transmission, Docket No. AD22-13-000 (July 19, 2022).

PDF page 3

DCACTIVE-79938279.1

3

principles that should guide co-location policy.
I.   COMMENTS

A. Large Loads Should be Studied in a Combined Queue with Generation and
Transmission Interconnection.

PJM, in its response to the Show Cause Order,6 proposes to continue its bifurcated approach to studying co-located loads and generation, wherein network load interconnection requests are studied under Attachment M-3 and co-located generator modifications are studied in the generator interconnection and necessary study process,7 while non-network loads will only employ the necessary study used for generator interconnections. Invenergy respectfully encourages the Commission and PJM to dispense with this bifurcated process and to instead jointly study large load and generator interconnection requests. Doing so would more efficiently use the transmission system and decrease ratepayer costs.

Under PJM’s existing rules, PJM’s standardized interconnection procedures only apply to generation and transmission interconnection, but PJM uses the Attachment M-3 process for load interconnections. Attachment M-3 establishes a local planning process in which PJM and transmission owners process load interconnection requests and plan local upgrades and supplemental projects in response to identified load needs.8  While Attachment M-3 has been used to incorporate large load additions into the PJM system, it was originally intended as a transmission planning process for supplemental projects, not as a process to interconnect large loads. As a result, it has several characteristics that make it unsuitable for large load

6 Show Cause Order at P 88, subsection d.
7 PJM Answer at 8, 48-49.
8 PJM Open Access Transmission Tariff (“PJM Tariff”), Attachment M-3.  See also PJM Answer at 6-7 (explaining the “traditional load interconnection processes” includes the “Transmission Owner retail load integration study” to identify local upgrades based on local transmission owner planning criteria and PJM’s “Do No Harm study” to evaluate supplemental project’s impact on the transmission system).

PDF page 4

DCACTIVE-79938279.1

4

interconnection.
First, Attachment M-3 does not consider transmission solutions outside of a particular transmission owner’s footprint, artificially excluding potentially less-expensive solutions. Second, because load additions are primarily studied under local transmission owner study processes using a different set of study assumptions, models and timelines, than generator interconnection studies, the load and generator study processes may each identify network upgrades that would not be necessary were these processes combined, resulting in overbuilding of the PJM system at significant expense. Third, because of the independent study processes, large load additions may not get factored into generator interconnection studies in a timely manner, or could be factored in but then never materialize. This creates significant opacity and risk for generators, thereby stifling development that might occur were generation developers provided more clarity on planned load interconnections.

Finally, there is little, if any, transparency on how M-3 studies are conducted, or the timeline for completing such studies.  Large load interconnection customers are already facing interconnection delays as a result of this uncertainty, and the lack of transparency is creating opportunities for undue discrimination that will decrease competition and raise systemwide costs. These defects, however, can be remedied by adopting a joint study process that requires large loads – those over 50 MW or interconnecting to facilities at voltages greater than 115kV – be studied along with generation and transmission interconnection requests. Combining load interconnection with generation and transmission into a standardized study process would promote transparency and ensure that network upgrades identified and allocated to interconnection customers correctly reflect the expected topology of the system.  It would also address a number of concerns raised in the Show Cause Order because transmission use, co-

PDF page 5

DCACTIVE-79938279.1

5

location impacts on the transmission system, and cost allocation would be addressed in a single study process.9

Moreover, if load and generation have not already identified one another, a common interconnection queue can match appropriate generation to the load, mitigating the uncertainty that can result from uncertain load forecasting. While PJM notes that large load aggregations could be included in regional transmission planning as part of the yearly load-forecasting process,10 it is unclear how often this occurs or what aggregation would trigger planning for large load additions in regional planning.  Load forecasts also are just that, a forecast, and may never materialize. Folding large load requests into the interconnection queue will reduce guesswork and reduce speculative load interconnection requests.

Invenergy recognizes that incorporating large load interconnections into the generation queue across the PJM footprint will involve stakeholder and state engagement.  In crafting these rules, Invenergy makes the following suggestions:

• Large load interconnection requests should be part of the standard interconnection queue with assigned queue positions. This will increase transparency for load and developers, while also ensuring equitable treatment of load and generation as they interconnect to the transmission system.

• PJM could establish commercial readiness criteria or security deposits for large load interconnection requests akin to those required for generator interconnection requests, thereby reducing speculative large load interconnection requests and incentivizing large loads to materialize.

• Like generator interconnection requests, large load interconnection requests could withdraw from the queue if they are no longer viable, with appropriate penalties to offset the harm to other interconnection customers.

Given that PJM is currently completing its interconnection queue transition process, these

9 E.g., Show Cause Order at P 88, subsection d (questioning whether PJM’s existing queue processing and study processes address the impacts of co-location, including whether PJM adequately considers reliability impacts on the transmission system, and whether cost allocation changes are needed to mitigate transmission system impacts).
10 PJM Answer at 7-8.

PDF page 6

DCACTIVE-79938279.1

6

new rules could reasonably commence with New Cycle # 1, which is projected to begin April 2026.  In the interim, PJM’s Tariff should be amended to include at least co-located loads in the standard generator interconnection procedures. Studying co-located load and generators together will reduce the chance of overbuilding the system and ensure costs for network upgrades are assigned consistent with the Commission’s cost allocation policies.

B. Co-Location Arrangements Must Include Safeguards to Ensure Other
Interconnection Customers are Not Harmed.

PJM in its Answer identifies numerous avenues for adding large co-located loads. One of those proposals, “New Option 6,” would permit large loads interconnecting as Network Load to bring its own generation to PJM. PJM explains that it might consider mechanisms to process these types of interconnection requests more quickly.11 While Invenergy welcomes improvements that expedite the interconnection process, any such changes must be adopted on a non-discriminatory, queue-wide basis, and not only for preferenced generators. Moreover, to the extent the Commission approves New Option 6, it should adopt reasonable safeguards to ensure that other interconnection customers are not harmed by co-location arrangements, for instance by maintaining queue priority on a first-ready, first-served basis; preventing co-located load from getting priority access to available transmission system headroom; and ensuring that PJM’s processing of co-location interconnection requests does not deprive PJM of the resources needed to process the interconnection queue. Such limitations would be in keeping with the Commission’s long-standing policy against queue jumping.12

11 PJM Answer at 17 (explaining that PJM could accelerate interconnection studies of new generation, enhance provisional interconnection service options at discrete study points to accelerate generation’s ability to reach commercial operation, and that states could remove barriers to entry by assuming cost responsibility for transmission upgrades pursuant to the State Agreement Approach to encourage large load development in their jurisdictions).
12 See, e.g., Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ 61,103, at P 35 (2003), reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, reh’g, Order No. 2003-B, 109 FERC ¶

PDF page 7

DCACTIVE-79938279.1

7

C. PJM Should Include a Transition Process Until its New Co-Location Rules are
Effective.

While this Show Cause proceeding could result in new rules accommodating additional
co-location configurations and should include a combined interconnection process for load and generation, properly issuing new rules takes time and benefits from a robust stakeholder process. Therefore, while new comprehensive rules are developed, PJM should implement a

transition process so that large loads customers can move forward with co-location arrangements in the short-term if they so choose. To reduce study timelines and avoid significant modifications to the PJM system while new rules are being fashioned, large-load customers should be allowed to pursue behind-the-meter configurations with new generating facilities in development and without being considered network load, and protections should be required to prevent that load from accessing the grid.  To the extent such protections are not available, behind-the-meter load should be charged commensurate with its expected transmission system use, but less than fully network load.

61,287 (2004), reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff’d sub nom. Nat’l Ass’n of Regulatory Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007); Reform of Generator Interconnection Procs. & Agreements, Order No. 845, 163 FERC ¶ 61,043 at P 487 (2018) (explaining that SIS does not constitute queue jumping because SIS “does not compete for the same potential network upgrades that may be at issue in the normal interconnection queue.”), order on reh'g, Order No. 845-A, 166 FERC ¶ 61,137, order on reh'g, Order No. 845-B, 168 FERC ¶ 61,092 (2019); Southwest Power Pool, Inc. 181 FERC ⁋ 61,269 at P 17 (2022) (accepting a proposal that “prevent[s] a [SIS] customer from using any interconnection service capacity that might otherwise go to a different interconnection customer in the queue.”); Southwest Power Pool, Inc., 147 FERC ⁋ 61,201 at P 124 (2014) (finding that SPP’s proposal could “increase the level of uncertainty” faced by an interconnection customer, “change the nature of the available capacity at a given time,” and potentially “induce multiple restudies of lower-queued interconnection requests.”); Xcel Energy Operating Co., 107 FERC ¶ 61,313, at PP 2, 22, 26 (2004) (finding that variations to the pro forma LGIP and LGIA proposed to accommodate a state resource planning process “must not disadvantage or delay other Interconnection Requests not involved in the solicitation”).

PDF page 8

DCACTIVE-79938279.1

8

II. CONCLUSION

Invenergy respectfully requests that PJM and the Commission consider these comments in determining how PJM’s tariff could be amended to include just and reasonable rules for co- located load and generation.

Respectfully submitted,

April 23, 2025
/s/ Tyler O’Connor
Tyler O’Connor
Kathryn Douglass
Crowell & Moring LLP
1001 Pennsylvania Avenue, NW
Washington, DC  20004
202-624-2500
toconnor@crowell.com
kdouglass@crowell.com

William Borders
Executive Vice President, Legal & Chief
Compliance Officer
Invenergy
One South Wacker Drive, Ste. 1500
Chicago, IL 60606
wborders@invenergy.com

Counsel for Invenergy Renewables LLC
and Invenergy Thermal LLC

PDF page 9

DCACTIVE-79938279.1
CERTIFICATE OF SERVICE
I hereby certify that on this 23rd day of April, 2025, a copy of the foregoing document has been electronically served upon each person designated on the official service list in this proceeding.

/s/ Kathryn Douglass
Kathryn Douglass
Crowell & Moring LLP
1601 Wewatta Street, Ste. 815
Denver, CO 80202
kdouglass@crowell.com