Comments of Invenergy Renewables LLC and Invenergy Thermal LLC
Text extracted from the eLibrary original (SHA-256 7a38aa79576d5a7d…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
Rather, it should seize this opportunity to articulate a new, proactive paradigm for jointly studying large-load interconnection requests as part of the generator interconnection queue, thereby ensuring that RTOs/ISOs engage in coordinated load, interconnection, and transmission planning that…Read this passage Filed comments: Reliability and curtailment
I. COMMENTS
printed heading
I.Read this passage
A. Large Loads Should be Studied in a Combined Queue with Generation and
printed heading · Topic match: Cost allocation
Folding large load requests into the interconnection queue will reduce guesswork and reduce speculative load interconnection requests.Read this passage Filed comments: Cost allocation
B. Co-Location Arrangements Must Include Safeguards to Ensure Other
printed heading · Topic match: Connecting load and generation
Moreover, to the extent the Commission approves New Option 6, it should adopt reasonable safeguards to ensure that other interconnection customers are not harmed by co-location arrangements, for instance by maintaining queue priority on a first-ready, first-served basis; preventing co-located load…Read this passage Filed comments: Connecting load and generation
C. PJM Should Include a Transition Process Until its New Co-Location Rules are
printed heading · Topic match: Connecting load and generation
Cir. 2007); Reform of Generator Interconnection Procs. & Agreements, Order No. 845, 163 FERC ¶ 61,043 at P 487 (2018) (explaining that SIS does not constitute queue jumping because SIS “does not compete for the same potential network upgrades that may be at issue in the normal interconnection…Read this passage Filed comments: Connecting load and generation
II. CONCLUSION
printed heading
CONCLUSION Invenergy respectfully requests that PJM and the Commission consider these comments in determining how PJM’s tariff could be amended to include just and reasonable rules for co- located load and generation.Read this passage
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that on this 23rd day of April, 2025, a copy of the foregoing document has been electronically served upon each person designated on the official service list in this proceeding. /s/ Kathryn Douglass Kathryn Douglass Crowell & Moring LLP 1601 Wewatta Street,…Read this passage