EL25-49-000 · 2025-04-23 · BrightNight Power Marketing, LLC

Comments of BrightNight Power Marketing, LLC in response to FERC’s Order Instituting Proceeding Under Section 206 of the Federal Power Act etc. and Answers…

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC

Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company

AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc.

AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.

AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
               Docket Nos. EL25-49-000

PDF page 2

2

Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana,
Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company

Large Loads Co-Located at Generating Facilities

Constellation Energy Generation, LLC

v.

PJM Interconnection, L.L.C.

AD24-11-000

EL25-20-000
(Consolidated)

COMMENTS OF BRIGHTNIGHT POWER MARKETING, LLC

BrightNight Power Marketing, LLC (“BrightNight”)1 submits these Comments in
response to the Commission’s Order Instituting Proceeding Under Section 206 of the Federal Power Act (“FPA”) and Consolidating with Other Proceedings2 and the answers filed by PJM Interconnection, L.L.C. (“PJM”) and individual and groups of PJM Transmission Owners (“PJM TOs”).3  BrightNight appreciates the opportunity to share its on-the-ground perspective on co-

1 BrightNight is filing these comments pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”), 18 C.F.R. § 385.211, having intervened in Docket No. EL25-49-000 on March 12, 2025.
2 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).  In the Show Cause Order, the Commission directed PJM and the PJM Transmissions to either explain why the existing PJM governing documents are just and reasonable and not unduly discriminatory or preferential without provisions specifically addressing co-located load arrangements or explain what changes would remedy the Commission’s concerns. Id. at P 87.
3 PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Answer of PJM Interconnection, L.L.C. (Mar. 24, 2025) (“PJM Answer”); PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Answer of the Indicated PJM Transmission Owners (Mar. 24, 2025) (“Indicated PJM Transmission Owners Answer”); PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Response of Public Service

PDF page 3

3

location issues.  BrightNight works with all types of customers around the United States to design, develop, and operate safe, reliable, large-scale, power projects.  BrightNight is an active developer of renewable and other types of generation projects and is in discussions with data centers interested in co-locating with hybrid renewable generation.  There is significant potential in the co-location model to (i) meet the ever-increasing energy needs of data centers while (ii) supporting reliability and reducing congestion on the grid and (iii) ensuring that data center load pays its fair share of costs.  To successfully achieve these interrelated goals, the industry must have regulatory certainty without foreclosing flexible commercial approaches.  Because PJM’s current open access transmission tariff is not sufficiently clear about the rules that apply to co- located load arrangements, BrightNight supports the Commission establishing pro forma rules, not only for PJM but rules that could apply more broadly, for evaluating and serving co-located load and generation that provide certainty for participants but include flexibility so as to not unnecessarily stifle innovative arrangements.  Any rates or charges applicable to co-located load must be just and reasonable by requiring co-located load to pay only for the grid services that it needs and benefits from, and ensures that co-located load does not directly or indirectly cross- subsidize other customers.  Additionally, BrightNight supports an expedited or fast-tracked study process for co-located load and generation.

I. BACKGROUND

As technology has advanced to seamlessly connect people and systems across industries, the need for large, external facilities that store and process large amounts of digital data, e.g.,

Electric and Gas Company (“PSEG”) (Mar. 24, 2025) (“PSEG Answer”); PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Answer of the Dayton Power and Light Company D/B/A AES Ohio (Mar. 24, 2025); PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Answer of Allegheny Electric Cooperative, Inc. (Mar. 24, 2025); PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Answer of NextEra Energy Transmission MidAtlantic, Inc. (Mar. 24, 2025); PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Answer of Silver Run Electric, LLC (Mar. 24, 2025).

PDF page 4

4

data centers, has increased.  Data centers require a significant amount of electricity to operate servers and cooling systems.  The dramatic increase in data center demand is expected to result in significant load growth on an electric system that had been forecasting flat load growth.  The Department of Energy’s 2024 Report on U.S. Data Center Energy Use estimates that data center load growth has tripled over the past decade and will double or triple again by 2028.4  In response to long wait periods to interconnect and obtain service from the grid, data center developers are exploring solutions that include co-locating with generation but are running into barriers.

In response to challenges associated with the co-located load model, the Commission convened a technical conference on November 1, 2024, to examine the issues in Docket NO. AD24-11-000 (“Co-location Technical Conference”).5  Later that same month, Constellation Energy Generation, LLC (“Constellation”) filed a complaint under Section 206 of the FPA, arguing that PJM’s Tariff is unjust and unreasonable and unduly discriminatory because it does not contain rules or guidance for generators to follow when interconnecting to provide service to a fully isolated co-located load.6  Constellation explained that, while nothing in the PJM Tariff prohibits fully isolated co-located load arrangements, utilities have relied upon ambiguities in the rules to thwart competition by delaying or significantly increasing the costs of such

4
DOE Press Release, DOE Releases New Report Evaluating Increase in Electricity Demand from Data Centers (Dec. 20, 2024), available at https://www.energy.gov/articles/doe-releases-new-report-evaluating- increase-electricity-demand-data-centers.

5 Large Loads Co-Located at Generating Facilities, Docket No. AD24-11-000, Notice of Commissioner-Led Technical Conference (Aug. 2, 2024).  The Commission requested that interested parties file post-technical conference comments, but took no further action in the docket until the Show Cause Order.
6 Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Docket No. EL25-20-000, Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC at 1 (Nov. 22, 2024) (“Constellation Complaint”).

PDF page 5

5

arrangements.7  Constellation asked the Commission to require PJM to incorporate into its Tariff sections from PJM’s Guidance on Co-located Load.8

On February 20, 2025, the Commission issued the Show Cause Order opening a new docket, Docket No. EL24-49-000, and consolidated the new docket with the Constellation Complaint docket, Docket No. EL25-20-000, and the technical conference docket exploring co- located large loads and generators, Docket No. AD24-11-000.  Based on the Constellation Complaint and Co-location Technical Conference, the Commission found that PJM’s Tariff appears to be unjust, unreasonable, unduly discriminatory or preferential, and directed PJM and PJM Transmission Owners to either:

(1) show cause as to why the [PJM Tariff], the Amended and
Restated Operating Agreement of PJM, and Reliability Assurance
Agreement Among Load Serving Entities in the PJM Region . . .
remains just and reasonable and not unduly discriminatory or
preferential without provisions addressing with sufficient clarity or
consistency the rates, terms, and conditions of service that apply to
co-location arrangements; or (2) explain what changes to the Tariff
would remedy the identified concerns if the Commission were to
determine that the Tariff has in fact become unjust and
unreasonable or unduly discriminatory or preferential and,
therefore, proceeds to establish a replacement Tariff.9
PJM and PJM Transmission Owners filed answers and responses.  PJM took the position that the PJM Tariff is just and reasonable, although it conceded that there is room for improvements and clarifications.10  It asked the Commission to provide guidance so that it can move forward.11  PJM included in its answer eight potential co-location arrangements and

7 Id.
8 Id. at 2.
9 Show Cause Order, 190 FERC ¶ 61,115 at P 2.
10 PJM Answer at 4.
11 Id.

PDF page 6

6

summarized what it sees as each arrangement’s key attributes, impacts on the grid, necessary studies, rates, operational considerations, and service options.12  PJM expressed a preference for certain options and less of a preference for other options.13    Indicated PJM Transmission Owners urged the Commission to find that the existing PJM Tariff is just and reasonable and declare that all co-located loads should be treated as load in front of the meter and designated as Network Load.14  PSEG, a transmission owner who filed separately from other transmission owners, framed the question before the Commission as defining what benefits a particular co- located load and generation configuration receives from the grid and setting charges and rates accordingly.15

II. COMMENTS
A. Develop Pro Forma Co-location Interconnection Procedures and Agreements
The comments across the three dockets show that Commission guidance is needed, and it is needed now.  Data center developers, generation developers, and system planners cannot make long-term decisions without understanding what co-location arrangements the Commission will accept.  Ideally, Commission guidance would come in the form of pro forma procedures and agreements governing co-location arrangements.  Standardizing procedures and agreements would give developers and planners certainty, reduce opportunities for undue discrimination or

12 PJM Answer at Exhibit A.
13 Id.
14 Indicated PJM Transmission Owners Answers at 2.
15 PSEG Answer at 1-2.

PDF page 7

7

preference, reduce disputes, and, hopefully, expedite the development of data centers and needed generation.16

While standardization is beneficial, it is equally important that the Commission build into any pro forma procedures and agreements flexibility to allow for different co-location configurations and arrangements.  Not all large loads are the same, so not all co-location configurations will be the same either.17  This could be accomplished by allowing different paths that lead to different studies and services for different types of co-location configurations.  The type of co-location arrangement can then lead to different charges.18  A pro forma process and agreements should allow for at least the following three configurations: (i) load and generation are fully islanded from the electric grid, with no service from the grid; (ii) flexible loads or demand response loads; and (iii) loads that will require backup grid service, such as a behind the meter arrangement, with associated studies and costs for each.  Furthermore, the resulting services and charges applicable to each of these configurations should impose charges on load and generation based only on the transmission services used and benefits received from the grid.

16 The benefits of standardized procedures and arrangements for co-located load and generation are similar to those the Commission found for generator interconnection.  See, e.g., Order No. 2003 at PP 8-12. See Standardization of Generator Interconnection Agreements & Procs., Order No. 2003,104 FERC ¶ 61,103 at PP 8-12 (2003), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, order on reh’g, Order No. 2003-B, 109 FERC ¶ 61,287 (2004), order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff’d sub nom. Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007).
17 See Large Loads Co-located at Generating Facilities, Docket No. AD24-11-000, Post-Workshop Comments of the Solar Energy Industries Association at 4 (Dec. 9, 2024) (“SEIA Post-Technical Conference Comments”), citing Kormos Pre-filed Presentation, The Co-Located Load Solution at 2.  PJM identified eight potential co-location configurations that have different needs and impacts on the grid.  PJM Answer at Exhibit A.
18 Data center developers have agreed that they should pay for the benefits they receive from the grid.  See Large Loads Co-located at Generating Facilities, Docket No. AD24-11-000, Post-Workshop Comments of the Data Center Coalition at 5 (Dec. 9, 2024) (“Consistent with established and sound utility ratemaking principles, DCC’s co-location principles support all load paying their fair share of costs for benefits and services received from the grid, including transmission, energy, and ancillary services costs.” (citation omitted)); Large Loads Co-located at Generating Facilities, Docket No. AD24-11-000, Post-Workshop Comments of Google LLC at 5 (Dec. 9, 2024) (At Google, we are not seeking to avoid paying our fair share of these costs . . ..”).

PDF page 8

8

In this respect, BrightNight generally supports the PSEG approach and strongly disagrees with the ‘one-size fits all configurations’ approach put forward by indicated PJM Transmission Owners.  Co-located load should be charged just and reasonable rates and not forced to subsidize other customers.

BrightNight also supports the Co-Location Interconnection Service Agreement concept proposed by the Solar Energy Industries Association (“SEIA”) in its post-technical conference comments in Docket No. AD24-11-000.19  SEIA urged the Commission to adopt a pro forma but flexible approach for co-location arrangements, particular fully islanded load and generation; flexible loads or demand responsive load; and loads that require back-up gride service.20  SEIA suggested that the Commission define the problem and impact of various types of co-location arrangements and develop a pro forma agreement considering different arrangements.21  As stated, “The pro forma agreement would provide flexibility in its terms to accommodate various types of co-location arrangements, including load receiving firm transmission service or load that does not receive full transmission service.  Included in the pro forma agreement would be provisions for System Protection Facilities in place to prevent the unexpected withdrawal of power from the grid, and penalties for failure of these protection facilities.”22  The Commission can use the record created in this proceeding to establish a pro forma agreement for co-locating loads and generation in the PJM region that set the baseline for other regions and transmission providers to use.

19
SEIA Post-Technical Conference Comments at 5-6.
20 Id. at 4.
21 Id. at 3-5.
22 Id. at 5-6.

PDF page 9

9

B. Rules Should Incentivize Co-Located Load to Bring Its Own Generation
In its answer, PJM recognized that large load bringing its own generation has benefits.23 While large load should not be required to bring its own generation, BrightNight agrees that there are significant benefits when large load brings new generation with it, particularly if that generation is co-located with the large load.  Large load bringing new generation promotes resource adequacy and avoids new constraints or congestion on the transmission system. In its answer, PJM discusses ways to incentivize large loads to bring their own generation, including expedited interconnection studies.24  SEIA outlined a process that incentivizes load to bring its own generation in its Post-Technical Conference Comments.25  An expedited or fast-tracked interconnection process appears to be appropriate.  PJM should be required to net the large load and generation, resulting in faster study time and less impact on the transmission system and load forecast.  It could be handled similarly to the surplus interconnection process, where the load and generation configuration can be screened for potential material impacts to the native transmission system or adjoining systems.  If there are material impacts that cannot be resolved among the affected systems, then the load and generation will be shifted to the typical interconnection and transmission service request processes.  BrightNight encourages the Commission, PJM, and other stakeholders to incorporate in the pro forma co-location procedures incentives for large loads to bring co-located generation.

23 PJM Answer at 16-18, Exhibit A.
24 Id. at 17.
25 SEIA Post-Technical Conference Comments at 6-7.

PDF page 10

10

III. CONCLUSION
BrightNight respectfully requests that the Commission consider these comments as it contemplates how to move forward on co-location issues in PJM.

April 23, 2025

     Respectfully Submitted,

By: /s/ Radha Soorya
Radha Soorya, Ph.D.
Senior Vice President Transmission
BrightNight Power, LLC
515 N. Flagler Drive, Suite P200
West Palm Beach, FL 33401
Telephone: 850-460-0697
E-mail: radha.soorya@brightnightpower.com

By: /s/ Duane K. Duclaux
Duane K. Duclaux
General Counsel
BrightNight Power, LLC
515 N. Flagler Drive, Suite P200
West Palm Beach, FL  33401
Telephone: 850-502-6492
E-mail:  duane@brightnightpower.com

Christina R. Switzer
Engleman Fallon, PLLC
823 Congress, Ave., Suite 300-67
Austin, TX 78701
Telephone: 202-464-1334
E-mail: cswitzer@efenergylaw.com

Counsel for BrightNight Power Marketing, LLC

PDF page 11

11

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

 Dated at Austin, TX, this 23rd day of April 2025.

By: /s/ Christina Switzer
823 Congress, Ave., Suite 300-67
Austin, TX 78701
Telephone: 202-464-1334
E-mail: cswitzer@efenergylaw.com