Comments of BrightNight Power Marketing, LLC in response to FERC’s Order Instituting Proceeding Under Section 206 of the Federal Power Act etc. and Answers…
Text extracted from the eLibrary original (SHA-256 99b9d86b6fb4ce97…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
Any rates or charges applicable to co-located load must be just and reasonable by requiring co-located load to pay only for the grid services that it needs and benefits from, and ensures that co-located load does not directly or indirectly cross- subsidize other customers.Read this passage Filed comments: Connecting load and generation
I. BACKGROUND
printed heading · Topic match: Connecting load and generation
In response to challenges associated with the co-located load model, the Commission convened a technical conference on November 1, 2024, to examine the issues in Docket NO.Read this passage Filed comments: Connecting load and generation
II. COMMENTS
printed heading
II.Read this passage
A. Develop Pro Forma Co-location Interconnection Procedures and Agreements
printed heading · Topic match: Connecting load and generation
Furthermore, the resulting services and charges applicable to each of these configurations should impose charges on load and generation based only on the transmission services used and benefits received from the grid. 16 The benefits of standardized procedures and arrangements for co-located load…Read this passage Filed comments: Connecting load and generation
B. Rules Should Incentivize Co-Located Load to Bring Its Own Generation
printed heading · Topic match: Connecting load and generation
Rules Should Incentivize Co-Located Load to Bring Its Own Generation In its answer, PJM recognized that large load bringing its own generation has benefits.23 While large load should not be required to bring its own generation, BrightNight agrees that there are significant benefits when large load…Read this passage Filed comments: Connecting load and generation
III. CONCLUSION
printed heading
CONCLUSION BrightNight respectfully requests that the Commission consider these comments as it contemplates how to move forward on co-location issues in PJM.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Austin, TX, this 23rd day of April 2025.Read this passage