EL25-49-000 · 2025-04-23 · Northern Virginia Electric Cooperative, Inc.
Comments of Northern Virginia Electric Cooperative, Inc
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000
PDF page 2
2
Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
AD24-11-000
EL25-20-000
(Consolidated)
COMMENTS OF NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC.
Pursuant to paragraph 87 of the Federal Energy Regulatory Commission’s (“FERC” or
the “Commission”) February 20, 2025 Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (“Show Cause Order”), Northern Virginia Electric Cooperative, Inc. (“NOVEC”)1 respectfully submits these comments
addressing: “(1) whether the existing Tariff remains just and reasonable and not unduly discriminatory or preferential; and (2) if not, what changes to the Tariff should be implemented as replacement rates.”2 PJM Interconnection, L.L.C.’s (“PJM”) existing Open Access
1 NOVEC filed its intervention in Docket No. EL25-49-000 on March 4, 2025. NOVEC, Motion to Intervene, Docket No. EL25-49-000 (filed March 4, 2025) (Accession No. 20250304-5077).2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, P 87 (2025) (“Show Cause Order”) (“Interested entities may respond within 30 days of PJM’s and the Transmission Owners’ filings, addressing either or both of: (1) whether the existing Tariff remains just and reasonable and not unduly discriminatory or preferential; and (2) if not, what changes to the Tariff should be implemented as replacement rates.”). PJM and the Indicated PJM Transmission Owners filed their responses on March 24, 2025. Because NOVEC has filed these comments on April 23, 2025, it is timely.
PDF page 3
3
Transmission Tariff (“OATT” or “Tariff”) is just and reasonable, and not unduly discriminatory. Co-located load is addressed by the Tariff, which allows co-located load to acquire transmission service consistent with the Commission’s cost-causation principle. No Tariff changes are needed.
I. BACKGROUND
On March 22, 2024, PJM posted its since-rescinded Guidance on Co-Located Load (“Guidance Document”).3 The Guidance Document defines, and the Show Cause Order accepts for its purposes, co-located load as “end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on the Interconnection Customer’s side of the Point of Interconnection (‘POI’) to the PJM Transmission System (co-located Customer Facility).”4 Although the Guidance Document recommended that all co-located load be served by PJM transmission service, the Guidance Document also contemplated that a co-location arrangement could proceed without procuring firm transmission service, in which case the co- located generator would have to reduce its Capacity Interconnection Rights (“CIR”) to reflect the capacity designated to the co-located load.5 The implication of the removal of the CIR for the co- located load is that those megawatts (“MW”) would not be available to the capacity market.6 In Docket No. ER24-2172-000, PJM submitted an amended Interconnection Service Agreement (“ISA”) between PJM, Susquehanna Nuclear LLC (“Susquehanna”), and PPL Electric Utilities Corporation.7 The amended Susquehanna ISA would have implemented the Guidance Document’s option to proceed without firm transmission service as non-Network
3 PJM, PJM Guidance on Co-Located Load (March 22, 2024) (updated April 17, 2024), https://www.pjm.com/- /media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.pdf (“Guidance Document”).4 Guidance Document at 1; Show Cause Order at P 3 n.4.5 Show Cause Order at P 4; Guidance Document at 2-3.6 See Independent Market Monitor for PJM, Answer and Motion for Leave to Answer, Docket No. ER24-2172-000 at 4 (filed July 10, 2024) (Accession No. 20240710-5036) (“IMM Susquehanna Answer”).7 PJM, Amendment to Susquehanna ISA, Docket No. ER24-2172-000 (filed June 3, 2024) (Accession No. 20240603- 5012) (“Susquehanna ISA Filing”).
PDF page 4
4
Load, relieving the co-located load of having to obtain transmission service. Although several commenters filed pleadings raising questions about the propriety of the filing,8 the Commission rejected the Susquehanna ISA because “PJM has not demonstrated that the proposed non- conforming provisions in the Amended ISA are necessary deviations from the pro forma ISA due to specific reliability concerns, novel legal issues, or other unique factors.”9 On November 1, 2024, the Commission convened a technical conference in Docket No. AD24-11-000 “to discuss generic issues related to the co-location of large loads at generating facilities.”10 Contemporaneously with that effort, Constellation Energy Generation, LLC (“Constellation”) filed a complaint seeking to have PJM’s Tariff amended to incorporate the Guidance Document’s option to have a co-location arrangement without firm transmission service.11 The general thrust of Constellation’s complaint was that what Constellation calls “Fully Isolated Co-Located Load,” which it defines as “generation and end-use load co-located behind-the-meter in a configuration that includes protective relays to prevent the load from receiving power from the grid,”12 was not being served due to an asserted “gap” in the Tariff which allegedly renders the Tariff unjust and unreasonable.13
NOVEC, among many others that reacted to Constellation’s complaint, protested the complaint, explaining that it should be denied because: (1) it would relieve co-located loads of having to pay any transmission costs even though they rely on and benefit from the transmission system; (2) granting the complaint would facilitate the withdrawal of generation from PJM’s
8 See, e.g., Exelon Corporation, Protest, Docket No. ER24-2172-000 (filed June 24, 2024) (Accession No. 20240624- 5207); IMM Susquehanna Answer.9 PJM Interconnection, L.L.C., 189 FERC ¶ 61,078, P 85 (2024).10 Show Cause Order at P 5.11 Constellation, Complaint, Docket No. EL25-20-000 (filed Nov. 22, 2024) (Accession No. 20241122-5285) (“Constellation Complaint”). 12 Id. at 1.13 Id. at 9.
PDF page 5
5
energy and capacity markets, undermining both markets; and (3) the subject matter of co-located load has broad industry-wide implications that should be addressed in a general Commission rulemaking, not in a company-specific complaint proceeding (if any changes to the Tariff to address co-located load are going to be considered at all).14
In the Show Cause Order, the Commission observed that there had been a “surge” of interest in co-location arrangements which has presented “significant and novel issues.”15 The Commission consolidated the Constellation Complaint and the Commission’s technical conference with the Show Cause Order proceeding so that the records from those proceedings would form a part of the Show Cause Order’s proceeding’s record. The Commission first addressed the jurisdictional issues.16 Turning to the PJM Tariff, the Commission determined that it may be “unjust and unreasonable or unduly discriminatory or preferential because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements,” explaining that “[t]he absence of such provisions may leave entities unable to determine what steps they can or must take to effectuate co-location arrangements of various configurations and how to do so in a manner that is just and reasonable.”17 The Commission expressed concern that without a common understanding of how co-location arrangements in various configurations will be effectuated, “participants in a co-location arrangement may not be required to pay for wholesale services that they receive, as required by the cost causation principle, which provides that all Commission- jurisdictional rates and charges must ‘reflect to some degree the costs actually caused by the
14 See NOVEC, Protest, Docket No. EL25-20-000 (filed Dec. 18, 2024) (Accession No. 20241218-5285) (“NOVEC Protest”).15 Show Cause Order at P 65.16 Id. PP 66-73.17 Id. P 74.
PDF page 6
6
customer who must pay for them,’ and that costs must be allocated in a manner that is at least roughly commensurate with the benefits that entity receives.”18 The Commission also raised questions regarding the reliability and resource adequacy implications of co-location arrangements.19 The Commission posed a series of briefing questions to help it address the question as to whether the Tariff remains just and reasonable and, if not, what revisions to the Tariff would remedy those concerns.20
II. COMMENTS
NOVEC appreciates the Commission’s thoughtful approach to the question of co-location arrangements and respectfully submits these comments to supplement its protest in Docket No. EL25-20-000. NOVEC has no particular objection to co-location arrangements in principle provided: (a) that the co-located load obtains and pays for Network Integration Transmission Service (“NITS”) or firm Point-to-Point Transmission Service (“PTP Service”); or (b) neither the co-located load nor the generator to which it is tied are in any manner connected to the bulk electric system, either directly or via interconnection to distribution-level facilities that in turn interconnect with the bulk electric system.
To summarize NOVEC’s comments below, NOVEC first addresses the question of
jurisdiction. Next NOVEC explains why the specific configuration of the co-located load and the generator upon which that load is relying are of paramount importance to the Commission’s questions. Although there may be a variety of potential configurations, in the end the determination of whether co-located load or the supplier to such load should be required to obtain and pay for transmission service turns on whether the load and the generation serving it
18 Id. P 74 (quoting Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004); citing Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009)).19 See Show Cause Order at PP 83-86.20 Id. PP 87-88.
PDF page 7
7
are both physically unconnected with either the bulk electric system or distribution facilities that connect to the bulk electric system. A co-location arrangement like the one advanced in the Susquehanna ISA or the Constellation Complaint did not involve such physically islanded load or generation and thus is not just and reasonable and is not permissible under the PJM Tariff. Such a configuration violates the Commission’s cost causation principles, undermines the Commission-approved PJM market structure, and is not fair to consumers. Third, given the historical cost-of-service arrangements for nuclear power plants that now, in part, make them attractive for these bilateral contracts, it would be unfair to dedicate such legacy generation to a single private customer after customers at large paid for such facilities and took the risks of construction since the time such resources were built. It is particularly troubling given the proposal and expectation that such units would remain interconnected to mitigate their weaknesses that require grid connection to operate -- thus deriving benefit from the grid -- but then be allowed to avoid paying for the benefits of grid interconnection. Fourth, NOVEC distinguishes behind the meter generation from co-location arrangements. Finally, NOVEC explains how the Commission may choose to integrate national security concerns into its decision-making processes.
A. The Commission’s Jurisdictional Statement is Generally Correct, With Some
Specifics as Applied to Virginia That Bear Consideration
NOVEC generally agrees with the Commission’s statement on jurisdiction. Whether and to what extent a co-location arrangement falls under state or federal jurisdiction depends on the aspect of the physical configuration of the co-located load being considered, as well as the contractual and tariff arrangements and the laws of the state in which it is located.21 Under
21 Id. P 68 (“As the comments described above illustrate, the boundaries between federal and state jurisdiction are not hermetically sealed. The application of these principles to the issue of co-location will often depend heavily on the specific facts and circumstances presented in particular situations.”) (internal citations omitted).
PDF page 8
8
NOVEC’s understanding of relevant state law, the co-location arrangements sought by Constellation in Docket No. EL25-20 would not be permissible in Virginia unless the supplier to the co-located load is authorized under state law to be a retail supplier in the geographic area in which the co-located load is located. Questions regarding the co-located load’s obligation or the supplying generator’s obligation to take and pay for transmission service in connection with their co-located arrangement is a matter of Commission jurisdiction.
NOVEC respectfully requests that the Commission take care not to intrude on matters of state jurisdiction in the event that, notwithstanding these comments to the contrary, the Commission decides that some modification of PJM’s Tariff is warranted. FERC has jurisdiction to address PJM’s Tariff and transmission service generally, but matters such as the authority to provide retail service are within each state’s jurisdiction. Any modification of PJM’s Tariff must not infringe on the states’ jurisdiction over retail service. Further, NOVEC submits that given the complications presented by these jurisdictional concerns, the Commission should not create a novel contractual arrangement in the PJM Tariff that allows co-located arrangements to bypass transmission service, local distribution utilities, and the capacity market. If it does, the Commission risks creating an uneven patchwork of co-location rules across PJM as some jurisdictions permit it and others do not.
B. PJM’s Existing Tariff is Just and Reasonable
Implicit in the Commission’s question as to whether the PJM Tariff is just and reasonable is whether the Tariff should permit co-located arrangements in configurations that relieve co- located load of transmission service costs or remove generation from the capacity and energy markets. On the contrary, the PJM Tariff is just and reasonable precisely because it does not permit that result. As discussed below, there are three reasons that support NOVEC’s position.
PDF page 9
9
1. Co-located load relies on the transmission system and should pay the
same costs as other transmission customers unless it and the supplying
generator are physically islanded.
“Fully Isolated Co-Located Load” is not fully isolated if any physical connection to the distribution or transmission grid exists with the co-located load or with the generator to which the co-located load is connected. If there is any physical tie at all, even if there is switchgear in place to isolate it, the co-location arrangement benefits from and relies upon the transmission system. The benefits of, and the need for, the transmission system is the very reason co-located loads seek to maintain that connection to the transmission system and do not island themselves.22
With respect to large generation assets interconnected to the grid, regardless of whether the unit is nuclear, fossil-fueled, or renewable, the grid necessarily responds to all power-quality issues caused by the generator or any load behind the generator, including but not limited to frequency response, reactive needs, transient issues, and voltage control. Co-located load is akin to parasitic load because the transmission grid cannot differentiate between energy that is injected into the market and energy that is injected to serve co-located load. Additionally, nuclear powered generation units are not operated as flexible or partially loaded assets but instead operate at full load between fueling cycles to maximize the value of their fuel rods. As such, nuclear powered generation assets depend upon other generators on the grid to provide all ancillary service and other power-quality needs.
The reliance is clear from the proposed configurations. As the Indicated PJM
Transmission Owners (“Indicated PJM TOs”) explained in their answer to the Commission’s
22 See, e.g., NOVEC Protest at 10 n.35 (citing Large Loads Co-Located at General Facilities, Transcript, Docket No. AD24-11-000, at 113:11-17 (Dec. 3, 2024) (Accession No. 20241203-4000) (“And the final point that I would add is just that the grid has an immense reliability benefit that we are simply not interested in walking away from, and so we have every interest in getting the grid to be that reliability resource, and in that vein, at least from our perspective, we have no interest in diverting existing reliability grid connected resources away from the grid, thank you.”)).
PDF page 10
10
Show Cause Order, “all the arrangements being contemplated or requested as being
interconnected with and synchronized with the transmission and/or distribution grid and thus [are] not ‘fully isolated.’”23 Because of this reliance, it is just and reasonable to treat co-located load as Network Load or require it to procure PTP Service. PJM charges transmission customers on a formulary basis without regard for the distance between load and generation.24 Thus,
distance does not relieve one of the need to procure transmission service.
PJM itself recognized that the co-location arrangement is still electrically connected and
synchronized to the PJM Transmission System.25 It still uses various ancillary services at times to provide power quality products as identified in PJM’s response, including black start service.26 It is problematic to NOVEC that certain co-location arrangements would still require black start service but are proposing to avoid paying for it — the availability of black start service to co- location arrangements is indicative of the broader benefits provided by the transmission system during crisis. To the extent that a co-location arrangement is using the grid as a backup power supply, ancillary services, or other benefits, that is another way co-location arrangement relies on the transmission system. As the Indicated PJM TOs observed:
23 Indicated PJM Transmission Owners, Answer, Docket Nos. EL25-49-000, et al. at 9 (filed March 24, 2025) (Accession No. 20250324-5298) (“Indicated PJM TOs Answer”).
24 Id. at 10.25 Id. at 12.26 Id. at 12; see also Exelon, Comments, Docket No. EL25-20-000, Attachment 1, at P 14 (“For example, there is no reason to believe that the data center load will be immutably fixed and, indeed, all load typically varies over time to some degree. To the extent the load varies from second to second, minute to minute, or hour to hour, it will require load following services.”) (Dec. 12, 2024) (Accession No. 20241212-5263) (“Weaver Declaration”); id. at P 15 (“Likewise, the system needs to maintain adequate Operating Reserves (e.g., Spinning and Supplemental Reserves). Co-located load arrangements make no mention of how this configuration will maintain or provide such reserves from the nuclear units serving the data center should those nuclear units not be available for some duration—those reserves will instead be provided by generators somewhere elsewhere on the system to not only supply the location but to prevent the grid from collapse.”); id. at P 17 (“In addition, if the surrounding system was ever in a position of restoring the grid after a black out, it must rely on black start resources to support the restoration process. Nuclear units are incapable of providing black start services, so the co-located load must rely on black start services from other PJM resources on the grid to come back online.”); see also IMM Susquehanna Answer at 6 (“The co-located load will continue to rely on the grid for a range of ancillary services including frequency control, reactive, spinning reserves, reserves in general, black start, and PJM administrative functions.”); NOVEC Protest at 4-5.
PDF page 11
11
Moreover, in a recently submitted co-location arrangement and in the arrangements proposed and discussed in the Complaint, the co-located load depended upon
another nuclear unit at the same facility for its backup supply of real power—which is to say, a PJM capacity resource that is interconnected with, serves, and relies entirely upon the grid. The proposed backup arrangement, including any
“replacement capacity” mechanism, depends upon the delivery of energy from
other locations on the network through PJM’s transmission system.27
Co-location arrangements indisputably rely on the transmission system and its benefits. And, as the Indicated PJM TOs point out, all load, including co-located load, is used to plan the transmission system under the PJM Tariff.28 Co-location proposals that exempt co-located load from the costs of transmission service effectively give them free use of the transmission system and cause other load to subsidize that use. This is inconsistent with the Commission’s cost- causation principle; the Commission should not approve free-ridership. The existing PJM Tariff, which requires co-located load to procure transmission service, is just and reasonable because it matches the cost of the transmission system with the co-location arrangements’ benefit from and use of the transmission system. The Commission should not order changes to the PJM Tariff, or if it does to clarify the provision of co-location services, it should still require co-located load to acquire firm transmission service.
2. Certain of the proposed co-location arrangements have involved the
removal of significant generation from PJM’s markets, which would
cause an unreasonable and unsustainable increase in costs for customers
even as the load causing those cost increases benefits from the markets’
planning functions.
The Commission should be very concerned about the potential impacts to reliability and resource adequacy of certain types of co-location arrangements. If co-location arrangements like the configuration advanced by the Constellation Complaint are permitted, they will present reliability challenges. The Indicated PJM TOs explained that a Reliability, Availability and
27 Indicated PJM TOs Answer at 14 (internal citations omitted).28 Id. at 14-17.
PDF page 12
12
Serviceability (“RAS”) system operation “may fail, thrusting the full burden of the co-located load onto the grid to continue operating if the co-located generation is offline for any reason.”29 The Commission recognized the possibility that “if the generator were to trip offline, then load could appear instantaneously on the grid and cause serious grid level events at the scale of a data center.”30 The potential size of the co-located load only emphasizes the reliability risk — the Susquehanna ISA contemplated 480 MW being withdrawn from the grid which, under emergency conditions, could appear on the grid.31 Not only will 480 MW of generating capacity be withheld from the market as a result of dedicating that capacity to a single customer (the co- located load), in the event of an outage of the supplying generation, the PJM system could be called upon to now serve that load even though it now has 480 MW less capacity in its arsenal to help it do so. If the Commission were to adopt a regime that significantly subsidizes co-location arrangements by relieving such load or their suppliers of the obligation to procure firm transmission service, there is every reason to believe that they would increase in both size and frequency.
Any increase in frequency, if it means a withdrawal from the supply stack PJM can call upon, also presents a reliability concern. Reliability is assured by having adequate generation. In the event of a weather event like Winter Storm Elliott, where some generation becomes unable to operate, will co-location arrangements evoke Animal Farm, where some load, specifically co- located, is “more equal” than other load? NOVEC recognizes that the Commission considered this question in its briefing questions when it asked: “Under what circumstances can PJM direct the operators of co-location arrangements to shed such load if deemed necessary to preserve
29 Id. at 10.30 Show Cause Order at P 83.31 Susquehanna ISA Filing at 1-2.
PDF page 13
13
system reliability during a declared emergency?”32 If required to take NITS or firm PTP Service, the question will be answered — the susceptibility to cutoff for the co-located load would be the same as that of any other NITS or firm PTP Service customer.
With respect to resource adequacy, NOVEC is gratified that PJM has rescinded the
Guidance Document.33 Co-location arrangements organized along those lines present real
resource-adequacy risks,34 and as PJM notes, is not permissible under the PJM Tariff without authorization.35 As NOVEC explained in its protest, “[t]he latest clearing prices for capacity in the Dominion Zone marked a 15-fold increase from the prior delivery year.”36 The capacity
market has been constrained by lack of supply, which has already hindered its operation.37 PJM needs greater supply — as NOVEC’s Vice President – Power Supply, Mr. Jaramillo, remarked to the Virginia State Corporation Commission: “trends towards increasing levels of non-
dispatchable generation…may leave PJM wholesale electricity markets unable to provide the
market-based generation NOVEC currently utilizes to meet the needs of its [data center]
customers” and, even if generation is available, “increased costs in power markets may adversely impact all customers.”38 The capacity market sets prices based in part on supply: less supply
32 Show Cause Order at Briefing Questions, (e)(vi).
33 PJM Interconnection, L.L.C., Answer, Docket Nos. EL25-49-000, et al. at 33-34 (March 24, 2025) (Accession No. 20250324-5313) (“PJM Answer”).34 See, e.g., NOVEC Protest at 7-9; PJM Answer at 57 (“Depending on the configuration, co-location has the same implications for resource adequacy as load that is not co-located. These implications then impact the quantities of resources available to clear in the market and the resulting prices paid by customers.”) (emphasis added).35 PJM Answer at 57-58 (“All Generation Capacity Resources must offer their full Accredited Unforced Capacity into the capacity market, unless PJM has granted an exception to the must-offer requirement pursuant to the existing rules in Tariff, Attachment DD, section 6.6. While there is an exception from the must-offer requirement where the Capacity Market Seller ‘has entered into a unit-specific bilateral transaction for service to load located outside the PJM Region,’ there is no exception allowing Capacity Resources to not offer capacity bilaterally committed to serve load in the PJM Region.”) (internal citations omitted).36 NOVEC Protest at 8 (citing NOVEC, Opening Remarks of Gilbert D. Jaramillo, Case No. PUR-2024-00144 at 5:3- 6 (Dec. 9, 2024) (available at: https://www.scc.virginia.gov/docketsearch#caseDocs/145480) (“Jaramillo Remarks”).37 See Governor Josh Shapiro and the Commonwealth of Pennsylvania, Complaint, Docket No. EL25-46-000 (filed Dec. 30, 2024) (Accession No. 20241230-5225).38 Jaramillo Remarks at 5:3-9.
PDF page 14
14
means the price increases. Co-location arrangements premised on generators removing themselves from the capacity market will only exacerbate the long-standing structural problems affecting PJM’s markets, as well as looming supply shortages.
Moreover, it seems to NOVEC that, in significant part, the lack of supply arising from congestion in the interconnection queue, as-yet unresolved failures to act on existing interconnection approvals, and retiring thermal generation is the impetus for the interest in co- location arrangements. Those supply problems affect all load, and it is discriminatory to afford some load a lifeboat in the form of co-location while the remaining load must address the consequences made worse by that lifeboat.
However, there are co-location configurations that can maintain the integrity of the capacity market and are thus just and reasonable. The Indicated PJM TOs have already explained that co-location is permitted under the PJM Tariff so long as the co-location arrangement procures the necessary firm transmission service. In its answer, PJM discussed various co- location configurations that are already permitted by the PJM Tariff and observed that “the capacity market was designed with such bilateral intra-PJM arrangements in mind, allowing sellers to offer such contracted capacity as ‘self supply’ into RPM Auctions.”39 Thus, generation associated with co-location arrangements is able to enter into bilateral agreements with co- located load even as it satisfies its obligation to offer into the capacity market.
3. It is unfair, and thus not just and reasonable, to consecrate legacy
generation units funded by ratepayers to the exclusive service of private
entities to the detriment of the public served by PJM’s markets.
The Commission asked for comments on its question: “Finally, for generation units paid for originally by consumers in base rates prior to restructuring, is it fair and/or just and
39 PJM Answer at 58.
PDF page 15
15
reasonable if these units are taken out of the system’s supply stack and devoted exclusively to serving co-location arrangements with one or a few large customers?”40 This is a legitimate question for the Commission to ask, one that neither PJM nor the Indicated PJM TOs chose to address in detail.41 As Chairman Christie emphasized in his comments at the February 2025 Open Meeting, large load customers should be served, but it has to be done in a way that is fair.42
The Susquehanna ISA and many other potential targets for co-location are nuclear power
plants. They serve an important role in PJM’s energy and capacity markets and the PJM’s
Independent Market Monitor (“IMM”) has described them as “baseload power.”43 For the most part, nuclear power plants have the distinction of mostly having been built between 1970 and 1990, prior to the restructuring of the electric industry in the PJM region. Thus, the plants were largely constructed by or for vertically integrated utilities who funded the projects from cost-of- service rates collected by captive retail customers. This meant that it was retail customers who bore the enormous risks associated with the construction of nuclear power plants, where billions can be spent with nothing to show for it in the end. For an example, the Commission can refer to the expansion of the V.C. Summer nuclear plant which foundered after billions of ratepayer dollars were spent.44 Even a successful construction of a nuclear power plant can generate
40 Show Cause Order at Briefing questions, (f)(vii).
41 PJM Answer at 72 (“This question goes further and asks about whether customers have an ongoing entitlement to units remaining as capacity resources based on their previous regulatory status prior to restructuring. Whether a specific cost is eligible for recovery is for stakeholders, the Commission, and/or appropriate state or local entities to decide.”); Indicated PJM TOs Answer at 21-22.42 See February 20, 2025 Open Meeting, https://www.ferc.gov/news-events/events/february-20-2025-open-meeting- 10022024 at 9:07-9:50.43 IMM Susquehanna Answer at 6; see also id. at 2 (“How will load be met if multiple base load generators are effectively removed from the market? What will the impact be on power flows given that the grid is built in significant part to deliver nuclear energy to load? What will be the impact on energy prices and capacity prices?”).44 Peter Maloney, Death of a nuke build: Summer abandonment leaves ratepayers holding the bag, UtilityDive (Aug. 4, 2017) (Available at: https://www.utilitydive.com/news/death-of-a-nuke-build-summer-abandonment-leaves- ratepayers-holding-the-bag/448597/).
PDF page 16
16
enormous cost overruns.45 The risk to retail customers was real, and the inability to assign that risk to retail customers in many areas of the country because of organized wholesale markets corresponds to the general end of the construction of utility-scale nuclear power plants in the United States.
Since the restructuring of the electric industry, most nuclear power plants have largely been depreciated.46 Prior to restructuring, this would have benefited customers through lower rates, because depreciation is a significant contribution to rate base and thus the cost of service. If the Constellation Complaint were to be granted and co-location arrangements were to be allowed under that or a similar paradigm, it would shift all of the remaining benefit of that generation to the co-located load and away from other load that paid for that facility, all while also shifting transmission costs away from co-located load and onto the remaining load.47 Although NOVEC agrees in principle that owners of generation assets should be able to seek to maximize the beneficial ownership of those assets, the Commission has the responsibility to reject proposals that are not just and reasonable because the Federal Power Act is a consumer- protection statute.48 This is why NOVEC’s comments here are focused on incumbent generation, as distinct from new generation that is being or was developed to serve the co-located load and has not been participating in the market. NOVEC supports the development of new generation.
45 Jeff Amy, Georgia nuclear rebirth arrives 7 years late, $17B over cost, Associated Press (May 25, 2023) (Available at: https://apnews.com/article/georgia-nuclear-power-plant-vogtle-rates-costs- 75c7a413cda3935dd551be9115e88a64).46 As an example of customers having already paid for nuclear power plants, many nuclear plant owners were provided accelerated recovery of the nuclear plants through a stranded cost mechanism. While this process and the methodology for calculating the amount of accelerated cost recovery varied among the states, the result was that retail customers paid higher rates to fund such stranded cost recovery.47 NOVEC will also note that, to the extent that the nuclear generators received subsidies from federal or state governments, those were also borne by retail customers in the form of taxes.48 Xcel Energy Services, Inc. v. FERC, 815 F.3d 947, 952 (D.C. Cir. 2016) (“It is long-established that the ‘primary aim [of the FPA] is the protection of consumers from excessive rates and charges.’” (quoting Mun. Light Bds. of Reading & Wakefield v. FPC, 450 F.2d 1341, 1348 (D.C. Cir. 1971), cert. denied, 405 U.S. 989 (1972))).
PDF page 17
17
It is to the Commission’s credit that it appreciates the potential unfairness of the situation and asked the question. The Commission has periodically observed how the legacy of the pre- restructuring period has created inequities and the possibility of unjust and unreasonable results. For example, in Opinion No. 494, the Commission found that the costs of legacy transmission facilities which were built to serve the transmission systems of individual companies and their customers could not be allocated to the entire PJM region under the Commission’s cost- causation principles.49 The instant situation is the inverse, but it implicates the same principle. In this case, customers paid for the benefits of these legacy units, but the approval of certain co- location arrangements that allow generation to withdraw from the capacity market would have the effect of shifting the benefits to private entities. Cost causation considers both costs and benefits of the service involved.50
NOVEC respectfully urges the Commission to consider the legacy costs that retail customers bore before allowing private parties to dedicate the remaining benefits of existing generation to co-located load. The Commission should not permit any co-location paradigm that removes nuclear generation from the capacity market because it is not just and reasonable given customers’ investments and risk-bearing that helped make those plants now attractive to load that would now like to co-locate.
C. There are Characteristics of Behind-the-Meter Generation That Distinguish It From Co-Location Arrangements That Warrant Distinct Treatment
The Commission asked commenters to address how co-located loads are disparate from Behind The Meter Generation (“BTMG”) as defined in PJM’s Tariff or Non-Retail Behind The
49 PJM Interconnection, L.L.C., Opinion No. 494, 119 FERC ¶ 61,063, P 42 (2007).50 Old Dominion Electric Cooperative v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018) (“For decades, the Commission and the courts have understood this requirement to incorporate a ‘cost-causation principle’—the rates charged for electricity should reflect the costs of providing it…We often frame this principle as one that ensures ‘burden is matched with benefit,’ so that FERC ‘generally may not single out a party for the full cost of a project, or even most of it, when the benefits of the project are diffuse.’”) (internal citations omitted).
PDF page 18
18
Meter Generation (“NRBTMG”).51 There are differences that merit the distinct treatment. Unlike the co-located load which has been proposed up until now, BTMG and NRBTMG had or
developed generation to supply the behind-the-meter load. In contrast, the co-located proposal here would not be relying on generation already dedicated to or that is built specifically to serve that load, but would instead repurpose existing generation from the capacity supply stack. The additional generation provides greater flexibility to customers and PJM, not less.
In addition, the scale and subsequent impact to PJM of co-located load (which consists of energy intensive customers) relative to the scale and impact of BTMG should be taken into account. The Susquehanna ISA alone involved 480 MW. In fact, NRBTMG is currently capped
under the PJM Tariff at 3,000 MW to ensure that it “does not detrimentally affect system
operations.”52 NRBTMG is designed to make contributions to grid reliability during emergency conditions as well, whereas certain co-location arrangements would remove any obligation of the generation to support the grid as well as potentially exacerbate the emergency conditions or their underlying causes.53 Moreover NRBTMG fails to operate as required to support the grid during those occasions, the NRBTMG’s netting eligibility is reduced, which incentivizes efficient operation and availability.5451 Show Cause Order at Briefing Questions, (a)(iv).52 American Municipal Power, Inc., Limited Answer, Docket No. ER24-2889-000, et al., at 6 (filed Oct. 18, 2024) (Accession No. 20241018-5201); see also PJM Tariff, § 34.3; PJM Manual 14D: Generator Operational Requirements, at Appendix A, PP 56, 66.53 PJM Tariff, Schedule 15 (“A Non-Retail Behind The Meter Generation resource that has output that is netted from load for the purposes of determining the DCPZ of a Network Customer pursuant to Tariff, Part III, section 34 shall be required to operate at its full output the first ten times between November 1 and October 31, that Maximum Generation Emergency conditions occur in the zone in which the Non-Retail Behind The Meter Generation resource is located.”).54 Id. (“… for each instance a Non-Retail Behind The Meter Generation resource fails to operate, in whole or in part, as required in section 1 above, the amount of operating Non-Retail Behind The Meter Generation from such resource that is eligible for netting will be reduced pursuant to the following formula….”).
PDF page 19
19
D. If the Commission is Going to Incorporate Any National Security Concerns Into Its Analysis, It Needs to Explicitly Define National Security and Consider
Countervailing National Security Interests
The Commission encouraged “parties to address any national security implications associated with co-location arrangements, including with respect to the specific issues discussed in this show cause order, and what actions, if any, the Commission should take in response.”55 NOVEC has several observations to offer. As a concept, “national security” has not been well defined in this proceeding. As Constellation used it in its complaint, national security is implicated because the failure to speedily adopt co-located loads will delay the development of artificial intelligence (“AI”) because data center generation will not be able to interconnect fast enough otherwise. But national security in the general sense is broader than AI: other industries are vital to national security — in particular, large industrial concerns. The price increases that co-located load could cause have the potential to harm their interests. Could that constitute a countervailing national security interest? One would think. One would also wonder about the existing data centers: they serve a vital function — does a cost increase to their operation harm their long-term viability and threaten national security? In an even broader sense, does the increase in costs to customers harm the general prosperity of the United States? If the Commission chooses to consider national security, it should consider it more systematically. Moreover, the Federal Power Act, in the context of sections 205 and 206, casts the Commission’s role as the arbiter of what is “just and reasonable.” Any consideration the Commission gives to national security must be as a component of a just and reasonable rate, and it cannot be a prime mover for the Commission in assessing rates.
55 Show Cause Order at Briefing Questions, (f)(vi).
PDF page 20
20
III. CONCLUSION
WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the Commission find that PJM’s existing Tariff is just and reasonable.
Respectfully submitted,
//s// Alan I. Robbins
Alan I. Robbins
Debra D. Roby
Thomas B. Steiger III
Washington Energy Law LLP
900 17th Street. N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9313
Email: arobbins@washingtonenergylaw.com
droby@washingtonenergylaw.com
tsteiger@washingtonenergylaw.com
Counsel to the Northern Virginia Electric
Cooperative, Inc.
Dated: April 23, 2025.
PDF page 21
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this consolidated proceeding.
Dated at Washington, D.C. this 23rd day of April, 2025.
//s// Jessika D. Dziechciowska
Jessika D. Dziechciowska
Energy Practice Analyst
Washington Energy Law LLP
900 17th Street, N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9308
Email: jdziechciowska@washingtonenergylaw.com