EL25-49-000 · 2025-04-23 · Northern Virginia Electric Cooperative, Inc.

Comments of Northern Virginia Electric Cooperative, Inc

Text extracted from the eLibrary original (SHA-256 23e30613ddbee55f…). Download the original from the official source.

Contents · 7 sections
  1. I. BACKGROUND p. 3
  2. II. COMMENTS p. 6
  3. A. The Commission’s Jurisdictional Statement is Generally Correct, With Some p. 7
  4. B. PJM’s Existing Tariff is Just and Reasonable p. 8
  5. C. There are Characteristics of Behind-the-Meter Generation That Distinguish It p. 17
  6. D. If the Commission is Going to Incorporate Any National Security Concerns Into p. 19
  7. III. CONCLUSION p. 20

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

Co-located load is addressed by the Tariff, which allows co-located load to acquire transmission service consistent with the Commission’s cost-causation principle.
Read this passage Filed comments: Connecting load and generation

I. BACKGROUND

printed heading · Topic match: Connecting load and generation

P 74. 6 customer who must pay for them,’ and that costs must be allocated in a manner that is at least roughly commensurate with the benefits that entity receives.”18 The Commission also raised questions regarding the reliability and resource adequacy implications of co-location arrangements.19 The…
Read this passage Filed comments: Connecting load and generation

II. COMMENTS

printed heading · Topic match: Connecting load and generation

NOVEC has no particular objection to co-location arrangements in principle provided: (a) that the co-located load obtains and pays for Network Integration Transmission Service (“NITS”) or firm Point-to-Point Transmission Service (“PTP Service”); or (b) neither the co-located load nor the generator…
Read this passage Filed comments: Connecting load and generation

A. The Commission’s Jurisdictional Statement is Generally Correct, With Some

printed heading · Topic match: Connecting load and generation

NOVEC respectfully requests that the Commission take care not to intrude on matters of state jurisdiction in the event that, notwithstanding these comments to the contrary, the Commission decides that some modification of PJM’s Tariff is warranted.
Read this passage Filed comments: Connecting load and generation

B. PJM’s Existing Tariff is Just and Reasonable

printed heading · Topic match: Connecting load and generation

Co-located load arrangements make no mention of how this configuration will maintain or provide such reserves from the nuclear units serving the data center should those nuclear units not be available for some duration—those reserves will instead be provided by generators somewhere elsewhere on the…
Read this passage Filed comments: Connecting load and generation

C. There are Characteristics of Behind-the-Meter Generation That Distinguish It

printed heading · Topic match: Connecting load and generation

Unlike the co-located load which has been proposed up until now, BTMG and NRBTMG had or developed generation to supply the behind-the-meter load.
Read this passage Filed comments: Connecting load and generation

D. If the Commission is Going to Incorporate Any National Security Concerns Into

printed heading · Topic match: Connecting load and generation

Moreover, the Federal Power Act, in the context of sections 205 and 206, casts the Commission’s role as the arbiter of what is “just and reasonable.” Any consideration the Commission gives to national security must be as a component of a just and reasonable rate, and it cannot be a prime mover for…
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the Commission find that PJM’s existing Tariff is just and reasonable.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 23rd day of April, 2025. //s// Jessika D.