EL25-49-000 · 2025-04-23 · Maryland Office of People's Counsel, New Jersey Office of Ratepayer Advocate

Comments of the Maryland Office of Joint Consumer Advocates et al

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et. al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
Docket Nos. EL25-49-000

AD24-11-000

EL25-20-000
(Consolidated)

COMMENTS OF THE MARYLAND OFFICE OF JOINT CONSUMER
ADVOCATES
Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“Commission’s”) Rules of Practice and Procedure, 18 C.F.R. § 385.211, the Maryland Office of People’s Counsel (“MPC”) and the New Jersey Division of Rate Counsel (“Rate Counsel”) (together, the “Joint Consumer Advocates” or “JCA”), respectfully submit these comments in support of, in part, the March 24, 2025 filings of PJM Interconnection, L.L.C. (“PJM”) and the Indicated PJM Transmission Owners (“TOs”) answers to the Commission’s February 20, 2025 Order Instituting Proceeding under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (the “Show Cause Order”).

MPC filed a motion for leave to intervene in this proceeding on March 21, 2025, which the Commission accepted. MPC is the statutory representative of the residential

PDF page 2

2

ratepayers of utility services in Maryland. Pursuant to Maryland Public Utility Companies Code Annotated, Section 2-205(b), the People’s Counsel “may appear before any federal or state entity as necessary to protect the interests of residential . . . users of [gas, electricity or other regulated services].” Rate Counsel intervened in this proceeding on February 26, 2025, and is the statutory representative of ratepayers of utility services in New Jersey. Pursuant to N.J.S.A. 52:27EE-55, Rate Counsel may “represent the public interest in any federal proceeding, including but not limited to proceedings before . . . the Federal Energy Regulatory Commission.”

INTRODUCTION
The Commission’s existing pro forma open access transmission tariff (“OATT”), and PJM’s OATT-compliant tariff (“PJM Tariff”), already address co-located load in a just and reasonable manner. Either network integration transmission service (“network service”) or point-to-point transmission service (“point-to-point service”) can apply to co- located load arrangements under the PJM Tariff and render just and reasonable results when properly applied. Network service is the preferred designation to ensure co-located load is addressed in a just and reasonable manner, as such designation will reduce impacts on existing ratepayers and prevent negative externalities such as free-riding. Given the variables involved in point-to-point service, each application of point-to-point service would need to be individually evaluated to determine whether it can be applied in a just and reasonable manner. The JCA thus support, in part, the position of the Indicated Transmission Owners and PJM Interconnection, LLC.

PDF page 3

3

COMMENTS
I. PJM’s current tariff provisions on co-located load arrangements can
produce just and reasonable results.

A. Classifying co-located load as front-of-the-meter network service
minimizes risks to existing customers compared to other
configurations.
Co-located load is load from a large commercial or industrial customer such as a data center that has a contractual relationship with an adjacent generating facility for its supply of electricity. The PJM Tariff considers co-located load arrangements as network service or point-to-point service.1 Under these classifications, co-located load is studied to allocate the costs of reliability services, such as ancillary services, and for the impact the co-located load will have on the grid for planning purposes. Co-located load receiving network service is responsible to PJM for the costs associated with serving its load and would be included in PJM’s planning process.2

Classifying co-located load as front-of-the meter network service is thus preferrable from a reliability and cost causation standpoint. When such a large amount of load is “off-network” but still benefitting from the transmission system, a basic principle of cost allocation is frustrated—the principle that those who cause the costs and reap the benefits, bear responsibility for the costs.3 The appearance of co-located load on the grid could have the same effect as generation retirement, triggering transmission upgrades

1  PJM, Intra-PJM Tariffs, OATT, § 1 Definition of Network Load (providing that load shall be designated as Network Load or served by Point-to-Point service) (“PJM Tariff”).
2 Id.
3 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014) (Cost causation is a “matter of making sure that burden is matched with benefit.”).

PDF page 4

4

either directly to accommodate the co-located load or indirectly to accommodate future load that would otherwise have headroom on the existing transmission system but for the co-located load. Even though the costs of such upgrades would be allocated to all network service customers, if co-located load is located behind the meter, the entity co- locating its load would evade transmission rates. These transmission rates would pay for initial upgrades needed because of the co-location arrangement or future upgrades needed to serve all customers in the service territory. Other ratepayers, not the cost causers, would instead bear these costs, as described in the TO’s Answer.

The impact on customers from treating services for co-located load as non- network service could be substantial. As Exelon warned in its comments in Docket No. EL25-20 and as the TO’s highlight in their answer, even a relatively small co-located load carveout of 480 megawatt (“MW”) from network service in the Southern Maryland Electric Cooperative (“SMECO”) territory—where the Calvert Cliffs nuclear facility is located—would result in the avoidance of over $53 million in charges per year.4 The financial impacts more than double if one gigawatt (“GW”) of load is not considered network service, allowing the co-located load customer to shift $112 million of annual avoided transmission charges onto other ratepayers. Even if some benefits were to accrue to non-cost causers, the ratepayer impact that such an arrangement would cause is too large to ignore. The PJM Tariff covering network service prevents this illegal cost shifting and should thus apply to co-located load.

4 See Answer of the Indicated PJM Transmission Owners to Order to Show Cause at 18–19 (hereinafter “TO Answer”).

PDF page 5

5

Although co-located load is located behind the point of interconnection, it is always electrically connected and synchronized to the transmission system; the generator cannot operate or supply the co-located load without that connection to the transmission system. As the TOs and the Union of Concerned Scientists (“UCS”) emphasize, it is economically and technically impossible to “fully isolate” co-located load from the transmission grid.5 Indeed, co-location with nuclear generation is being widely discussed, and nuclear industry standards require synchronization with the grid for stability, off-site power, and restoration. Co-location with baseload generation also poses reliability concerns, which are exacerbated if the co-located load is considered non-network load. As the Maryland Public Service Commission opined in its recent report on co-located load:

If [non]-network load co-locates with baseload generation, such as the Calvert Cliffs nuclear plant, significant quantities of existing capacity will be effectively removed from the grid and resource adequacy may be

degraded at an accelerated pace relative to connecting such load in
traditional ways. Baseload capacity of the type Calvert Cliffs provides could take years to plan, certificate, and build.6

Therefore, the Commission should clarify that co-located load is always network load, with a preference for network service, to prevent evasion of grid service charges and transmission grid upgrade charges to the detriment of other customers.

5 See TO Answer at 7–9; UCS Comments at 8.
6 Maryland Public Service Commission, Report on Co-Location, at 1 (2024).

PDF page 6

6

B. PJMs’ proposed new options four and five, with special protection
schemes, are misplaced and unnecessary.
The Commission should reject PJM’s suggested configurations that offer
protective schemes to co-located load that is non-network load—specifically new options four and five as detailed in Exhibit A to the PJM Answer. As the TOs underscore in their answer, inadvertently or directly creating a new class of service, especially non-network load, for co-located load is unnecessary and unduly preferential.7 PJM itself cautions against these options that involve complex special protection schemes to “prevent” withdrawal from the grid, conceding in its answer that such schemes in place at the Susquehanna Steam Electric Nuclear Power Facility — which has an interconnection agreement with a co-located data center —failed, causing the data center to instead rely on the PJM grid for its supply during an unplanned outage.8 Monitoring Analytics, the independent market monitor for PJM, also expressed concern over the issues of backup power for co-located load arrangements and emphasized it is “not possible for co-located load to be off the grid.”9 Moreover, as UCS notes, the variability of power demand from data centers creates “imbalances more quickly than generators can correct, resulting in [] voltage disturbances, thermal overloads and stability issues.”10 The risk that the protective measures in these complex options will fail is extremely high given that such variability affects multiple aspects of PJM service, such as ancillary services,

7 See TO Answer at 18–19.
8 See PJM Answer to Order to Show Cause at 39, FN 60.
9 Monitoring Analytics, Comments to the Maryland PSC Senate Bill 1 Co-location Study Administrative Docket PC 61, Sept. 24, 2024 at 2.
10 Comments of the Union of Concerned Scientists to Order to Show Cause at 14 (hereinafter “UCS Comments”).

PDF page 7

7

transmission capacity, and generation margin reserves. Allowing for an option that heightens the risk of these imbalances and miscalculations of reserves goes against PJM’s mission “to ensure the safety, reliability and security of the bulk electric system.”11 Finally, the TOs aptly point out that consistency is key to advance the goals of all relevant stakeholders, including co-located load customers. Forms of service tailored to specific co-located load will all but guarantee protracted litigation over intricate protective schemes that further muddy the regulatory waters, to the detriment of both ratepayers and co-located load customers. Therefore, the Commission should dismiss proposals for options four and five in Exhibit A to the PJM Answer and clarify that co- located load should be classified as network service under the PJM Tariff.

II. The Commission should defer to state law control over how the costs of the wholesale sale and transmission of electricity are allocated among

retail customers.
Maryland recently passed legislation revising the definition of “retail electric customer” to include co-located load customers and specifying that a generating facility with co-located load can supply retail electricity in these instances.12 Once signed into law, this definitional revision will enhance jurisdictional clarity for co-located load within Maryland. As the Commission notes, “states retain exclusive jurisdiction over the terms of retail sales, generally including the rate designs that determine how the costs of the wholesale sale and transmission of electricity assigned to a wholesale customer are

11 PJM, “Problem/Opportunity Statement”, July 26, 2023, accessible at, chrome- extension://efaidnbmnnnibpcajpcglclefindmkaj/https://www.pjm.com/-/media/DotCom/committees- groups/task-forces/rcstf/postings/problem-statement.pdf.
12 HB 1035 (the “Next Generation Energy Act”) is awaiting gubernatorial signature.

PDF page 8

8
allocated among that wholesale customer’s retail customers.”13 Further, the Commission explained that “the states also get to determine how the wholesale costs of providing electricity to those retail customers are recovered through retail rates. . . . irrespective of where the load interconnects (i.e., to the distribution system, the transmission system, or the generator itself).”14

In New Jersey, it is well-established precedent that the New Jersey Board of Public Utilities has the authority to regulate activities that are “clothed in the public interest,” and this includes the sale of “public-utility-type services to a limited market . . . .”15 The Commission should make clear in this proceeding that states have the

authority to allocate costs for “the wholesale sale and transmission of electricity assigned to a wholesale customer” and take no action that interferes with that authority. As the TOs note, the PJM Tariff ensures “all customers pay their fair share of the transmission network from which they benefit.” Maryland’s new legislation clarifies how state law advances the important goal of ensuring all customers pay their fair share of transmission system costs, including co-located load customers.

CONCLUSION
Co-located load affects and benefits from the PJM grid. Consequent policy
decisions about co-located load in PJM will thus have significant implications for all PJM customers, in Maryland, New Jersey, and in the PJM region at large. A straightforward

13 Order to Show Cause, EL25-49-000, et al., Feb. 20, 2025, P68.
14 Order to Show Cause, P69.
15 See In re in re S. Jersey Gas Co., 116 N.J. 251, 258 (1989) (affirming a final agency decision that a chemical company selling gas to a select group of large industrial users, is a “public utility” subject to the jurisdiction of the Board).

PDF page 9

9

approach that clarifies co-located load is network load that takes network service is the most cost-effective and equitable decision. Although point-to-point service may also be just and reasonable, implementation is more challenging and riskier for customers, requiring consideration on an individual basis. At minimum, the Commission should disallow non-network load configurations, while leaving undisturbed the states’ authority to allocate costs for wholesale sales and transmission, in determining the just and reasonable approach to co-located load.

Respectfully submitted,

DAVID S. LAPP

People’s Counsel

/electronic signature/
William F. Fields

Deputy People’s Counsel

Alexis H. Lewis

Assistant People’s Counsel

Office of People's Counsel

6 St. Paul Street, Suite 2102

Baltimore, Maryland 21202

(410) 767-8171

/s/ Emily Lam
Emily Lam, Esq.
T. David Wand, Esq.
Brian O. Lipman, Esq.

New Jersey Division of Rate Counsel
140 East Front Street, 4th Floor
P.O. Box 003
Trenton, NJ 08625
T (609) 984-1460
elam@rpa.nj.gov

PDF page 10

10

dwand@rpa.nj.gov
blipman@rpa.nj.gov

Dated:  April 23, 2025

PDF page 11

11

CERTIFICATE OF SERVICE

I HEREBY CERTIFY that, on this 23rd day of April 2025, the foregoing
“Comments of the Maryland Office of People’s Counsel” was either hand‐delivered, e‐ mailed or mailed first‐class, postage prepaid to all parties of record to this proceeding. Respectfully submitted,

/electronic signature/
Alexis H. Lewis

Assistant People’s Counsel