Comments of the Maryland Office of Joint Consumer Advocates et al
Text extracted from the eLibrary original (SHA-256 69c46c4ee4788619…). Download the original from the official source.
Contents · 6 sections
- INTRODUCTION
- I. PJM’s current tariff provisions on co-located load arrangements can
- A. Classifying co-located load as front-of-the-meter network service
- B. PJMs’ proposed new options four and five, with special protection
- II. The Commission should defer to state law control over how the costs of
- CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Cost allocation
MPC is the statutory representative of the residential 2 ratepayers of utility services in Maryland.Read this passage Filed comments: Cost allocation
INTRODUCTION
printed heading · Topic match: Cost allocation
INTRODUCTION The Commission’s existing pro forma open access transmission tariff (“OATT”), and PJM’s OATT-compliant tariff (“PJM Tariff”), already address co-located load in a just and reasonable manner.Read this passage Filed comments: Cost allocation
I. PJM’s current tariff provisions on co-located load arrangements can
printed heading · Topic match: Connecting load and generation
PJM’s current tariff provisions on co-located load arrangements can produce just and reasonable results.Read this passage Filed comments: Connecting load and generation
A. Classifying co-located load as front-of-the-meter network service
printed heading · Topic match: Connecting load and generation
When such a large amount of load is “off-network” but still benefitting from the transmission system, a basic principle of cost allocation is frustrated—the principle that those who cause the costs and reap the benefits, bear responsibility for the costs.3 The appearance of co-located load on the…Read this passage Filed comments: Connecting load and generation
B. PJMs’ proposed new options four and five, with special protection
printed heading · Topic match: Connecting load and generation
Forms of service tailored to specific co-located load will all but guarantee protracted litigation over intricate protective schemes that further muddy the regulatory waters, to the detriment of both ratepayers and co-located load customers.Read this passage Filed comments: Connecting load and generation
II. The Commission should defer to state law control over how the costs of
printed heading · Topic match: Connecting load and generation
Maryland recently passed legislation revising the definition of “retail electric customer” to include co-located load customers and specifying that a generating facility with co-located load can supply retail electricity in these instances.12 Once signed into law, this definitional revision will…Read this passage Filed comments: Connecting load and generation
CONCLUSION
printed heading · Topic match: Connecting load and generation
CONCLUSION Co-located load affects and benefits from the PJM grid.Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Lewis Assistant People’s CounselRead this passage