EL25-49-000 · 2025-04-23 · Vistra Corp.

Comments of Vistra Corp

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC

Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company

AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.

AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Docket Nos. EL25-49-000
EL25-49-001

PDF page 2

-2-
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company

Large Loads Co-Located at Generating Facilities

Constellation Energy Generation, LLC

v.

PJM Interconnection, L.L.C.

AD24-11-000

EL25-20-000
(Consolidated)

COMMENTS OF VISTRA CORP.

Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 Vistra Corp. (“Vistra”) hereby submits these comments on the Commission’s February 20, 2025 Order (“Show Cause Order”)2 and PJM Interconnection, L.L.C.'s (“PJM”) answer (“PJM Answer”)3 filed on March 24, 2025, in the above- captioned docket.  Vistra appreciates the Commission’s acknowledgement of the urgency of the issue, as reflected by its commitment to issue an order within 180 days of the initiation of this

1 18 C.F.R. § 385.211 (2024).
2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).
3 Answer of PJM Interconnection, L.L.C., Docket No. EL25-49 (filed Mar. 24, 2025) (“PJM Answer”).

PDF page 3

-3-
proceeding.4  This proceeding can and must move quickly toward resolution to provide regulatory certainty by remedying the deficiencies in PJM’s tariff.

PJM’s Answer provided a list of eight potential options to integrate new loads:
1. Load with a separate point of interconnection (“POI”) that is network load;
2. Co-located load that is at the same POI but separately metered that is network
load;
3. Existing behind-the-meter generation (“BTMG”) where the load is the
customer;
4. Co-located load with connection to grid with protections to avoid delivery of
system energy to serve the load;
5. Co-located load with connection to the grid to avoid delivery of system energy
to serve the load or receive back-up service from PJM with permission;
6. Co-located load that elects to be network load and brings own generation;
7. Co-located load that takes interruptible service (load willing to curtail in
advance of emergency procedures);
8. Co-located load that elects to be network load and that participates as demand
response.5
In evaluating these options, it is critical to recognize that co-location of large loads and generation facilities is not a new phenomenon in the PJM region.6  Despite accommodating such arrangements for many decades,7 PJM has pulled an about-face in this proceeding, now asserting that its tariff prohibits behind-the-meter co-located load (what PJM refers to as Options 4 and 5)— and that its tariff is nonetheless just and reasonable.8  PJM is wrong on both counts.  PJM’s actions in recent years demonstrate that it does not believe its tariff prohibits behind-the-meter co-location

4 See Show Cause Order at PP 87, 91.
5 PJM Answer, Exh. A.
6 Affidavit of Dr. Roy J. Shanker, PhD on Behalf of Vistra Corp., Attachment A, at PP 13-15 (“Dr. Shanker Aff.”).
7 See, e.g., Cogeneration Tech. & Dev. Co., 31 FERC ¶ 62,299, 63,449 (1985) (approving certification of a co- located co-generation facility in 1985); PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 (2004) (accepting BTMG tariff provisions).
8 See PJM Answer at 13-14 (explaining that fully isolated behind-the-meter co-located load is a “new potential option” for which “[t]ariff modifications would be needed based on the Commission’s November 1, 2024 Order in Docket No. ER24-2172.”).

PDF page 4

-4-
arrangements.9  In fact, as PJM’s own filings over the past few years—including as recently as last month—demonstrate, PJM has repeatedly applied the tariff’s necessary study provisions to facilitate behind-the-meter co-location configurations.10  However, other aspects of the tariff lack sufficient clarity on how to accommodate such arrangements on a non-discriminatory basis.11 PJM’s tariff, and PJM’s administration thereof, stand as an impediment to behind-the-meter co- location arrangements.  As a result, PJM’s tariff is unjust and unreasonable and unduly discriminatory with respect to behind-the-meter co-location arrangements.

Although PJM asserts that its tariff is just and reasonable because it accommodates front- of-the-meter load interconnection (i.e., Options 1 and 2), that assertion further highlights the tariff’s unlawfulness.  Requiring new large loads to interconnect through Options 1 and 2 would create a structural bias in favor of network transmission-served load and against competitive, bilateral supply arrangements between sophisticated buyers and market-based rate (“MBR”) sellers, depriving MBR sellers of their right to contract.12  The availability of one favored PJM alternative for co-location does not resolve the unduly discriminatory treatment that prevents other alternatives.  Attached to these comments, Vistra submits an affidavit from Dr. Roy J. Shanker, PhD, who provides a thorough evaluation of PJM’s Answer, including a detailed recounting of PJM’s BTMG program and a formal analysis of PJM’s Options 4 and 5 against a proper

9 See, e.g., PJM Interconnection, L.L.C., Amendment to ISA, SA No. 1442; Queue No. NQ-123, Docket No. ER24- 2172-000 (filed Jun. 3, 2024) (“Susquehanna ISA Filing”).
10 See PJM Interconnection, LG.L.C., Necessary Studies Agreement, Original Service Agreement No. 7476, Queue Position No. AA1-145, Docket No. ER25-1623-000, at Attach. 1 (filed Mar. 14, 2025) (“Doswell NSA”).
11 When discussing unduly discriminatory treatment, these comments refer both to (1) the fact that PJM’s Answer indicates that it is not allowing Options 4 and 5 at all, and also that (2) PJM’s proposed treatment of Options 4 and 5 is unduly discriminatory compared to its treatment of behind-the-meter generation.
12 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,117, at P 60 (2025) (explaining that resources may choose to “remain outside of the PJM capacity market.”).

PDF page 5

-5-
comparison case.13  Specifically, Dr. Shanker’s analysis illustrates that Options 4 and 5 produce either superior or neutral results compared to PJM’s Option 1 across all relevant evaluation factors.14

While the Commission’s rehearing order in Docket No. ER24-2172 (“Susquehanna ISA Rehearing Order”)15 indicates that the tariff permits Options 4 and 5, Vistra agrees with the Commission’s preliminary finding that the PJM tariff is unjust and unreasonable and unduly discriminatory because it does not contain provisions that address behind-the-meter co-located load with sufficient clarity or consistency.16  This lack of clarity, in turn, undermines PJM’s ability to implement its tariff in a just and reasonable, and nondiscriminatory manner.  Even putting aside PJM’s new position that its tariff does not allow behind-the-meter co-located load, the record in this proceeding demonstrates that PJM has recently been implementing, and continues to implement, its tariff in an unduly discriminatory or preferential manner—further highlighting the problems bred by the tariff’s lack of clarity on the rates, terms, and conditions of service associated with behind-the-meter co-location arrangements.

The Commission must proceed quickly to remedy the deficiencies in PJM’s tariff and to eliminate discriminatory treatment.  Vistra submits that the deficiencies in PJM’s tariff can be remedied quickly through a few targeted reforms that ensure that the tariff accommodates Option 4 and 5 configurations.  Alternatively, rather than direct those specific tariff revisions, the Commission could take an even more streamlined approach by clarifying that PJM’s existing retail

13 See Dr. Shanker Aff.
14 Id. PP 49-71.
15 PJM Interconnection, L.L.C., 191 FERC ¶ 61,025, at P 60 (2025) (“Susquehanna ISA Rehearing Order”).
16  Show Cause Order at P 74.

PDF page 6

-6-
BTMG netting provisions apply to new large co-located loads, either in front of or behind the generator.

It is critical for the Commission to direct PJM to accommodate Options 4 and 5 arrangements quickly to remedy the clear undue discrimination evidenced in the record.  However, PJM’s Answer highlighted a number of other issues that warrant further attention.  Beyond Option 4 and Option 5 configurations, PJM’s Answer identified other co-location configurations that PJM’s tariff does not yet accommodate, specifically Options 6-8 configurations.  Vistra supports further exploration of Options 6-8 to provide additional options and flexibility; there is significant interest in the industry to transact using these configurations.  As with Options 4-5, each of these configurations also could provide reliability and resource adequacy benefits.  However, they also appear likely to require more involved tariff modifications than those needed for Options 4 and 5. A triaging approach can help strike an appropriate balance between (a) resolving this proceeding with utmost speed, and (b) providing the flexibility to accommodate other beneficial co-location configurations.  Considering the possible outcomes of this proceeding illustrates the need for such a triaging approach.  On one extreme, PJM’s newfound approach of only allowing new large loads to interconnect under Options 1-2 would conclude this proceeding quickly, but it would also leave undue discrimination in place and result in significant litigation.  On the other extreme, the Commission could require PJM to implement tariff revisions to ensure its tariff accommodates all of Options 1-8, which would extend the length of this proceeding significantly.  The right balance is somewhere in the middle.  The Commission should act quickly to facilitate Options 4 and 5 in this proceeding, and direct PJM to conduct an expeditious stakeholder process regarding Options 6-8.  This approach remedies the immediate undue discrimination without sacrificing the benefits of accommodating other potential co-location configurations.

PDF page 7

-7-
PJM’s Answer also highlighted issues with the current processes for front-of-the-meter load interconnections to the transmission system (i.e., Options 1 and 2).  Vistra supports further exploration of those issues.  However, in keeping with the triage approach described above, the Commission should explore that issue in a separate proceeding.

The Commission need not wait until it has answers to every question raised in this proceeding to proceed to implement a replacement rate to remedy the clear undue discrimination against Options 4 and 5.  This proceeding cannot be expected to address every possible future concern with respect to co-location; this proceeding represents the beginning of the Commission’s efforts to adapt its regulatory framework to this growing trend of new large loads, not the end.  The evidentiary record before the Commission clearly demonstrates that the tariff is unlawful with respect to Option 4 and Option 5 configurations because PJM is actively hindering market participants’ ability to implement those configurations in a non-discriminatory fashion after having successfully navigated the tariff’s necessary study process.  The goal of this proceeding is to remedy the current deficiencies in the PJM tariff and, in doing so, to develop an initial framework to enable co-location arrangements to enter the system in a just and reasonable manner. As a practical matter, it is imperative that the Commission recognize that time is of the essence in removing unnecessary regulatory hurdles to deploying data center infrastructure, thereby fostering economic growth and national security benefits.  Thus, in deciding on an appropriate replacement rate, the Commission should not let the perfect be the enemy of the good. The Commission must recognize that the replacement rate adopted in this proceeding need not be the most just and reasonable rate.17  As with every aspect of the PJM tariff, the provisions relevant

17  See, e.g., Entergy Arkansas v. FERC, 109 F.4th 583, 594 (2024) (“FERC is not required to choose the best solution, only a reasonable one.”) (citing Petal Gas Storage, L.L.C. v. FERC., 496 F.3d 695, 703 (2007)).

PDF page 8

-8-
to co-location and the integration of large loads more broadly should be improved over time to enhance the efficiency of the market, maintain just and reasonable rates, and avoid or eliminate undue discrimination.  The refinement of any singular issue for co-location is no exception, but during the interim, PJM must not be allowed to prohibit behind-the-meter co-location altogether. The Commission should spur that process along by quickly resolving this proceeding, directing PJM to accommodate Option 4 and 5 configurations, and providing clear policy guidance to PJM on the topics it should engage with its stakeholders on next.

I. Summary of Proposal
In the below comments, Vistra suggests a specific replacement rate that the Commission could adopt quickly to ensure that the tariff accommodates Option 4 and 5 configurations in a just and reasonable and not unduly discriminatory manner.18  This proposal would ensure that co- location configurations that fit within Options 4 and 5 pay their fair share and that other customers are not harmed.  Specifically, Vistra’s proposed solution includes the following components:  Clarify that transmission owners must cooperate in the necessary study process.  Ensure that co-location configurations pay their fair share by (a) allocating the costs of upgrades identified in the necessary study process to the generator, (b) creating a new rate design to ensure that Option 4 and 5 configurations pay for ancillary services that they use, or perhaps benefit from, but do not pay for services that they do not use or benefit from, and (c) when Option 5 configurations draw power from the grid, apply netting provisions consistent with the retail BTMG program.

 Modify the pro forma ISA to include a co-location section that will govern the applicable data exchange and coordination requirements and formalize any

requirements regarding applicable protective schemes.
 Clarify that a secondary generator that provides occasional, interruptible backup service to a co-located load can also serve as a capacity resource because the generator will be available to PJM when needed.

18 As an alternative, Vistra also asserts that the Commission could remedy the current issues by clarifying that PJM’s retail BTMG program can apply to new, large loads.  See supra § IV.B.

PDF page 9

-9-
This framework provides a path forward to expeditiously facilitate Options 4 and 5 configurations in a just and reasonable and not unduly discriminatory way.

II. Background
In March 2024, as later revised in April 2024, PJM posted on its website a guidance document that explained PJM’s approach to behind-the-meter co-located load.19  On June 3, 2024, PJM filed a proposed amendment to the Susquehanna ISA to increase the amount of existing behind-the-meter load co-located with the Susquehanna nuclear facility, which is interconnected to PPL Electric Utilities Corporation’s transmission system.20  On September 30, 2024, Exelon filed a petition for declaratory order regarding the scope of the Commission’s jurisdiction over the interconnection of co-located load.21  On November 1, 2024, the Commission issued an order rejecting the proposed amendments to the Susquehanna ISA.22  On November 22, 2024, Constellation filed a complaint alleging that Exelon refused to review necessary studies to accommodate the addition of behind-the-meter co-located load at certain Constellation generating facilities.23

On November 1, 2024, the Commission hosted a technical conference on the co-location of large loads at generating facilities.  On February 20, 2025, the Commission issued the Show Cause Order.  For purposes of this proceeding, the Show Cause Order defined co-location arrangements to refer to configurations in which load is co-located behind a generator’s point of

19 PJM Guidance on Co-Located Load (March 22, 2024) (Updated April 17, 2024), available at https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.ashx.
20 See Susquehanna ISA Filing at 3.
21 Pet. for Declaratory Order of Baltimore Gas & Electric Company, et al., Docket No. EL24-149-000 (filed Sept. 30, 2024).
22 PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024).
23 Complaint of Constellation Energy Generation, LLC, Docket No. EL25-20, at 7-9 (filed Nov. 22, 2024).

PDF page 10

-10-
interconnection (i.e., behind-the-meter co-located load).24  Specifically, the Commission adopted the PJM guidance document’s definition of co-located load, which “refers to end-use customer load that is physically connected to the [generation] facilities of an existing or planned Customer [generation] Facility on the Interconnection Customer’s side of the Point of Interconnection to the PJM Transmission System.”25  The Commission required PJM to either (1) explain why its tariff remains just and reasonable and not unduly discriminatory without provisions addressing behind- the-meter co-location “with sufficient clarity or consistency,” or (2) explain what changes to the tariff would remedy the absence of such provisions.26  In other words, the Show Cause Order clearly indicated that the PJM tariff must accommodate behind-the-meter co-located load—either as currently filed or with revisions necessary to establish a replacement rate.27 On March 24, 2025, PJM filed its answer in this proceeding.  PJM’s Answer asserted that its tariff is just and reasonable because it permits what PJM refers to as Options 1 and 2—both of which contemplate load interconnecting in front-of-the-meter.28  PJM also noted the existence of Option 3 in its current tariff, but argued that it is not available to large loads.29  Despite the fact that PJM previously facilitated behind-the-meter load configurations, PJM’s Answer argued that the tariff prohibits behind-the-meter co-located load, which PJM refers to as Options 4 and 5.30 However, on March 14, 2025—a mere 10 days before PJM filed its Answer in this docket—PJM

24  Show Cause Order at P 3.
25 Id. P 3 n.4.
26  Id. P 2.
27  See id.
28  See PJM Answer at 9-11, 32.
29 Id. at 12-13. 30  See id. at 13-14 (explaining that fully isolated behind-the-meter co-located load is ‘a new potential option’ for which “[t]ariff modifications would be needed based on the Commission’s November 1, 2024 Order in Docket No. ER24-2172.”).

PDF page 11

-11-
filed a necessary study agreement to accommodate a behind-the-meter co-located load arrangement similar in nature to Option 4.31

On March 4, 2025, Vistra filed a motion for clarification, which asserted that additional clarity was needed regarding the implications of the Susquehanna ISA Order.32  On March 10, 2025, the Commission issued its order on rehearing in Docket No. ER24-2172, clarifying that the Susquehanna ISA Order should not be read to prohibit other entities from filing non-conforming interconnection agreements to facilitate behind-the-meter co-located load or to suggest that the Commission has prejudged any such filing.33

III. PJM’s Tariff is Unjust and Unreasonable and Unduly Discriminatory
Vistra agrees with the Commission’s preliminary finding that the PJM tariff is unjust and unreasonable and unduly discriminatory because it does not contain provisions that address behind-the-meter co-located load “with sufficient clarity or consistency.”34  PJM has effectively conceded this point.  Even though there are many existing behind-the-meter co-located load facilities in PJM (such as cogeneration facilities and retail BTMG), and even though PJM previously argued that its tariff permits behind-the-meter co-located load and implemented its tariff as if it permits such arrangements,35 PJM now asserts that its tariff does not permit behind- the-meter co-located load.36  To facilitate that litigation position, PJM’s Answer announced that it

31  See Doswell NSA.
32 Mot. for Clarification of Vistra Corp., Docket No. EL25-49 (filed Mar. 4, 2025).
33 Susquehanna ISA Rehearing Order at P 60 (“[W]e clarify that the Rejection Order does not prevent entities from filing non-conforming interconnection agreements to address matters related to a generator serving co-located load, or prejudge any such future filing.”).
34  See Show Cause Order at P 74.
35  See, e.g., Susquehanna ISA Filing.
36  See PJM Answer at 13-14 (explaining that fully isolated behind-the-meter co-located load is a “new potential option” for which “[t]ariff modifications would be needed based on the Commission’s November 1, 2024 Order in Docket No. ER24-2172.”).

PDF page 12

-12-
“rescinds its previously issued Guidance Document pending Commission guidance in this docket[.]”37  PJM’s misinterpretation of its tariff to adopt a blanket prohibition on behind-the- meter co-located load is manifestly unjust and unreasonable and unduly discriminatory. Further, even aside from PJM’s newfound interpretation of its tariff, the record in this proceeding clearly demonstrates that PJM has been unable to administer its tariff to accommodate behind-the-meter co-located load in a just and reasonable and not unduly discriminatory manner.38 As a result, in this proceeding, the Commission must ensure that PJM will accommodate behind- the-meter co-location configurations, and will do so in a just and reasonable and not unduly discriminatory manner.

Moreover, PJM’s Answer failed to adequately respond to the Show Cause Order’s
directives.  The Show Cause Order required PJM to (1) explain how its tariff is just and reasonable and not unduly discriminatory without provisions clearly addressing behind-the-meter co-located load, or to (2) propose tariff revisions to remedy that deficiency.  PJM’s Answer did neither.  If PJM now believes that its tariff does not accommodate behind-the-meter co-located load, then the Show Cause Order required PJM to propose tariff revisions to accommodate behind-the-meter co- located load.  PJM’s assertion that its tariff only permits front-of-the-meter load interconnection solutions, without providing tariff revisions to accommodate behind-the-meter configurations, is inadequate to comply with the Show Cause Order.  Deferring any progress to future stakeholder meetings was not responsive to the Commission’s directives and significantly hinders the urgent progress that is required to facilitate customer choices of co-located load configurations in PJM.

37
See id. at 33.
38  See Show Cause Order at P 75.

PDF page 13

-13-
A. It Would be Unjust and Unreasonable and Unduly Discriminatory and
Preferential to Prohibit Behind-the-Meter Co-located Load
PJM’s Answer asserts that its tariff “remains just and reasonable” because it “permits co- located loads to interconnect through existing load interconnection processes, albeit processes where the load is designated Network Load[.]”39  PJM’s Exhibit A makes clear that these “existing” options for large loads to interconnect (i.e., Options 1 and 2) both involve front-of-the- meter co-location.40  Vistra strongly disagrees with PJM’s argument that the availability of Options 1 and 2 would be sufficient to render PJM’s tariff just and reasonable and not unduly discriminatory.41  As discussed further below, requiring all new large loads to interconnect through Options 1 or 2 increases transmission costs for consumers and creates a structural bias in favor of transmission-served load while disadvantaging competitive, bilateral supply arrangements between sophisticated buyers and MBR sellers.  As discussed by Dr. Shanker, Option 4 and 5 alternatives can avoid some of the delays and potential cost impacts to other consumers that result from Options 1 and 2 without any adverse impacts to resource adequacy or reliability.42  In fact, Options 4 and 5 can actually accrue benefits to existing load by decreasing costs and enhancing reliability.43

PJM’s contention that Option 3 is not available to new large loads illustrates the undue discrimination that would occur if PJM failed to accommodate Options 4 and 5.  PJM’s retail BTMG program was designed to apply when a load and generator are co-located behind the same

39
See PJM Answer at 32.
40 See id., Exh. A.  However, PJM’s Answer does not address why it filed the amended Susquehanna ISA if it believed only Options 1 and 2 are permissible.
41  See PJM Answer at 9-13, 32.
42 See Dr. Shanker Aff. at PP 43, 54-59, 61-62, 70.
43 Id.

PDF page 14

-14-
meter.44  The BTMG netting approach “developed by PJM and its stakeholders reduces the cost to those market participants that rely to a lesser degree on the PJM integrated transmission system to serve load because they serve loads that utilize behind the meter generation.  As a result, entities that serve loads with behind the meter generation are allocated a fairer share of the costs associated with the operation of the PJM integrated transmission system, including costs for energy, capacity, ancillary services, and administrative fees.”45  Under this framework, retail BTMG loads are currently able to avoid transmission charges by using on-site generation or curtailing load during expected coincident peak events.  In doing so, these loads are permitted to net their usage of NITS to zero.  If Option 3 loads are permitted to net in this way, it is unduly discriminatory to prohibit behind-the-meter loads from engaging in exactly the same type of netting.  In fact, Option 4 configurations actually use the transmission system less than a retail BTMG configuration because protective systems ensure that the load never draws energy from the grid, whereas retail BTMG arrangements can draw from the grid at the discretion of the customer.46  Providing favorable netting provisions for Option 3 configurations while simultaneously failing to accommodate Option 4 and 5 configurations at all is even more unduly discriminatory.

Furthermore, PJM’s Answer illustrates how a prohibition on Option 4 and 5 configurations would unlawfully advantage transmission owners over competitive generation suppliers.  Options 1-3 are all facilitated by transmission owner load integration studies.47  These studies, and the processes by which they are facilitated, live in a regulatory gap.  Despite the fact that these

44  Dr. Shanker Aff. at PP 30-32.
45 Id. (citing PJM Interconnection, L.L.C., Submission of Revisions to Open Access Transmission Tariff, the Amended and Restated Operating Agreement, Etc., Docket No. ER04-608-000, at 1 (March 1, 2004)).
46 Id. P 37.
47  See PJM Answer at 6-7, 9-13.

PDF page 15

-15-
configurations involve interconnections directly to the transmission system, the studies, processes, and facilities associated with those interconnections are not currently subject to Commission regulation or oversight.48  As PJM’s Answer explained, the network upgrades identified in transmission owner load integration studies are placed in the supplemental projects category.49 PJM only reviews these projects under a bare minimum standard to ensure that they “do no harm” to the transmission system.50  As OPSI has previously explained, state regulators often do not have authority to review these supplemental projects.51  Stakeholders have little input in the supplemental project process, as “TOs are under no obligation to respond to stakeholder questions and comments or even acknowledge their receipt.”52  These projects are not subject to competitive bidding;53 rather, as PJM’s Answer explained, these projects are cost allocated to the transmission owners’ zone pursuant to the transmission owners’ cost allocation methodology.54  In other words, they go directly into the individual transmission owners’ rate base.  These projects thus receive cost recovery after PJM’s “do no harm” analysis, without any consideration of whether they represent efficient, cost effective, or prudent solutions.  Supplemental projects also constitute an

48  See infra, Section VI.B.
49  PJM Answer at 7.
50 PJM Answer at 7.
51  See, e.g., Comments of the Organization of PJM States, Docket No. RM21-17, at 6 (filed Aug. 17, 2020) (“Some retail regulators have extensive processes for reviewing [supplemental projects], and others do not. In the latter case, retail regulators often lack authority over the vast majority of these local projects, meaning that the local projects being proposed simply do not undergo a review at the retail level.”)
52  Id.
53  See, e.g., Appalachian Power Company, 170 FERC ¶ 61,196, at P 60 (2020) (“Supplemental Projects are not part of the RTEP process and thus are not part of the competitive window process.”).
54  PJM Answer at 17.

PDF page 16

-16-
outsized portion of transmission spending in PJM.55  Permitting front-of-the-meter load interconnections, which include little oversight or process, while simultaneously failing to accommodate behind-the-meter co-located load is unduly discriminatory.

PJM has provided no grounds that would excuse this discrimination.  Nor can it.  As the affidavit of Dr. Roy Shanker explains, neither reliability nor resource adequacy provide a reasoned basis to prohibit behind-the-meter co-located load like Options 4 and 5.  Dr. Roy Shanker explains that PJM’s analysis of the implications of these configurations is fundamentally flawed because PJM’s analysis rests on comparisons between the addition of behind-the-meter co-located load to a world in which the load does not exist.56  However, load growth will not simply disappear because one configuration is unavailable.57  Rather, the proper comparison case or counterfactual to a behind-the-meter co-located load configuration is one in which the load connects in front-of- the-meter in a manner similar to Option 1.  When compared against that counterfactual, behind- the-meter co-location actually provides significant benefits to the grid and to other market participants.  Dr. Roy Shanker’s affidavit includes a detailed analysis of Option 4 and Option 5 configurations compared to the appropriate comparison case to determine the actual implications of these behind-the-meter load configurations across a range of factors, including reliability, transmission costs for other customers, and capacity and energy prices.58  Across all factors, the

55  See Building for the Future Through Electric Regional Transmission Planning and Cost Allocation, Order No. 1920, 187 FERC ¶ 61,068, at P 109 (2024) (noting that in 2019, supplemental projects cost $3.75 billion while regionally planned projects cost $1.27 billion, and in 2020, supplemental projects cost $4.7 billion, while regionally planned projects cost $413 million).
56 See Dr. Shanker Aff. at P 43.
57 Id.
58 Id. at PP 49-72.  This finding is not intended to suggest a regulatory scheme must hold other customers harmless to be just and reasonable.  However, the fact that these configurations do hold other customers harmless demonstrates that there are no inappropriate cost shifts.

PDF page 17

-17-
impact of the addition of load in an Option 4 and 5 configuration was actually either neutral or beneficial for other market participants as compared to an Option 1 configuration.59 The Show Cause Order acknowledged that resource adequacy and reliability concerns “are not necessarily unique to co-location arrangements and that significant load growth more generally may raise many of the same concerns.”60  However, the Commission explained that its concern was the potential speed with which behind-the-meter co-located load can be added to the grid, and whether that creates a risk that these loads will not be adequately reflected in resource adequacy planning mechanisms.61  This concern can be alleviated, however, by considering the true development cycle of behind-the-meter co-located load.  These configurations do not appear on the grid overnight.  Entities that seek to develop such a configuration must, among other things,

(1) negotiate and sign private, bilateral contracts between the load and the generator, (2) submit a request for a necessary study and sign a necessary study agreement, (3) wait for PJM to conduct the study, (4) negotiate and sign an amended interconnection service agreement, (5) wait until any network upgrades needed to accommodate the change to the generator’s interconnection are built,

(6) obtain other appropriate permits, (7) submit advance orders for necessary equipment such as transformers and other long lead time equipment, and (8) construct the load facility and connect it to the generator.

Even after all of that, these large loads typically phase in over time rather than all at once. For instance, PJM recently filed a necessary study agreement that describes a campus that will initially contain two data halls with 60 MW gross demand, which will grow at a rate of one building

59 Id.
60  Show Cause Order at P 85.
61  Id.

PDF page 18

-18-
per year and reach a maximum gross peak load of 300 MW in year 5 (the “Doswell NSA”).62  In Vistra’s experience, this type of phase-in is typical of new large load facilities.  This provides ample time for the PJM capacity market to calibrate to respond to changes in the balance of supply and demand.  Further, as Dr. Shanker notes, the competitive results for capacity pricing and LMPs are virtually identical or even lower for the rest of PJM system customers when a configuration such as PJM Option 4 is compared to the proper counterfactual.63

Moreover, the concern that PJM must face the new challenge of ensuring that “a special protection scheme could be designed to never fail and cover all potential operating conditions” ignores the long history of special protection schemes (“SPS”) in the industry.  These are not new technologies.  Special protection schemes are often also referred to as remedial action schemes (“RAS”).64  In approving a NERC standard that governs these technologies, the Commission acknowledged “the diversity among the different types, functions, and placements of remedial action schemes across North America.”65  These schemes are commonly used, including in the interconnection context.66   Dr. Shanker references a list of such SPS and RAS already in operation by TOs within PJM.67  Moreover, the application of an SPS or RAS in a co-location arrangement is fairly simple—to keep the load from purchasing power from the grid—compared to the many

62  See Doswell NSA.
63 Dr. Shanker Aff. at PP 61-62.
64 See NERC, “Remedial Action Scheme” Definition Development, at 2 (Oct. 2014), available at https://www.nerc.com/pa/stand/prjct201005_2spclprtctnsstmphs2/faq_ras_definition_11102014_clean.pdf.
65 Remedial Action Schemes Reliability Standard, Order No. 837, 160 FERC ¶ 61,071, at P 30 (2017).
66 See, e.g., Midcontinent Independent System Operator, Inc., 177 FERC ¶ 61,233, at P 28 (2021); Southwest Power Pool, Inc., 177 FERC ¶ 61,091, at P 79 (2021).
67 Dr. Shanker Aff. at P 27 (citing PJM Manual 3: Transmission Operations, Attachment A (November 21, 2024), https://www.pjm.com/-/media/DotCom/documents/manuals/m03.pdf).

PDF page 19

-19-
other SPS and RAS schemes currently in effect.  Given this context, it is difficult to understand why PJM would view load isolation as atypically risky or unreliable.

Neither resource adequacy nor reliability concerns justify the failure to accommodate behind-the-meter co-located load.  Rather, the driving motivation behind the opposition to behind- the-meter co-located load appears to be the avoidance of competition for the financial benefits that transmission owners stand to gain from the increased rate base associated with requiring load to interconnect through Options 1 or 2.  As Dr. Shanker explains, Option 1 configurations result in interconnection upgrade costs going into the transmission owners’ rate base.68  To contrast, under an Option 4 configuration, interconnection upgrade costs are borne by the parties to the co-location arrangement; other customers pay none of these costs, and as a result, other customers’ NITS charges remain the same.69  Requiring all co-location to occur through front-of-the-meter load interconnection is unjust and unreasonable and unduly discriminatory because it creates a structural bias in favor of transmission-served load and against competitive, bilateral supply arrangements between sophisticated buyers and MBR sellers.

B. PJM’s Recent Tariff Administration Demonstrates that the Tariff Lacks
Sufficient Clarity to Accommodate Behind-the-meter Co-located Load
As noted above, until PJM filed its Answer in this proceeding, PJM had taken the position that its tariff permitted behind-the-meter co-location.70  However, the record demonstrates that PJM has been unable to administer those provisions in a just and reasonable and not unduly

68 Id. at P 59, Table 5.
69 Id.
70  See Show Cause Order at P 4 (explaining how the PJM Guidance Document addressed behind-the-meter co- located load).

PDF page 20

-20-
discriminatory manner because its tariff did not contain sufficiently clear rates, terms, and conditions of service.

The only aspect of the tariff that PJM has (sometimes) been able to administer successfully to accommodate behind-the-meter load arrangements over the last several years is the necessary study process.  As discussed in more detail below, that aspect of the tariff has produced multiple necessary study agreements and corresponding studies in support of co-location configurations similar to Option 4.  But beyond those limited successes, PJM has utterly failed to administer its tariff to successfully accommodate such arrangements.

The general structure of PJM’s process for studying and interconnecting Option 4 and 5 configurations makes sense.  After executing a necessary study agreement and filing it with the Commission, PJM coordinates with the generation owner and the relevant transmission owner to study the configuration through the necessary study process.  Through the necessary study, PJM analyzes whether any modifications to the transmission system are necessary to accommodate the proposed modification and provide a good faith estimate of the costs.  If the generator wishes to proceed, the interconnection parties negotiate a revised, non-conforming ISA to reflect the unique details of the configuration.71  While this general structure is sensible, the available evidence demonstrates that the tariff lacks sufficient detail to ensure that PJM can consistently implement it across the PJM region in a just, reasonable, and not unduly discriminatory manner. Across the recent co-location arrangements that have been pursued, different transmission owners “[took] different approaches to performing the steps necessary to accommodate a co-

71  See, e.g., Susquehanna ISA Filing; Susquehanna ISA Rehearing Order at P 60 (“[W]e clarify that the Rejection Order does not prevent entities from filing non-conforming interconnection agreements to address matters related to a generator serving co-located load, or prejudge any such future filing.”).

PDF page 21

-21-
location arrangement and in the transmission service that they are requiring entities to take.”72  For example, as illustrated by the record developed in the Constellation complaint docket, Exelon refused to work on Constellation’s request to co-locate load with its generators under this tariff framework.73  Specifically, Exelon refused to review the necessary studies for two Constellation generating facilities.74  On the other hand, PPL cooperated in both the necessary study process and in the amendment of the interconnection agreement for the proposed modification to the Susquehanna nuclear plant, both to initially facilitate the addition of behind-the-meter co-load and, later, to increase the amount of such load.75  These troubling dynamics have continued unabated during this proceeding: just ten days before it filed its Answer, arguing that its tariff does not permit co-location configurations, PJM submitted a filing with the Commission to accommodate a co- location configuration that appears to be an Option 4 configuration.76  And these are just the disparities that have seen the light of day through Commission proceedings.

Under these circumstances, it is obvious that the tariff is not being administered in a just, reasonable, and not unduly discriminatory manner.  However, as explained below, establishing a lawful replacement rate in this proceeding is not a heavy lift; it requires clarifying a small number of critical issues, which can be achieved through relatively light tariff revisions.

72  Show Cause Order at P 75.
73  Complaint of Constellation Energy Generation, LLC, Docket No. EL25-20, at 7-8 (filed Nov. 22, 2024) (explaining that Exelon reviewed a necessary study for one generating facility but later halted planned work on it, and Exelon refused to review the necessary study for the other two stations).
74 Id.
75 See Susquehanna ISA Filing.
76  Compare Doswell NSA with PJM Answer at 13-14.

PDF page 22

-22-
IV. FERC Must Direct a Replacement Rate to Remedy the Deficiencies in PJM’s Tariff When FERC finds that PJM’s tariff is unjust and unreasonable and/or unduly

discriminatory or preferential, it must set a replacement rate that would render the tariff just and reasonable and not unduly discriminatory or preferential.77  Below, Vistra presents two potential replacement rate options.  The first option involves targeted reforms to clarify four critical issues that must be addressed to allow PJM to effectively accommodate behind-the-meter load configurations.  In the alternative, the Commission could also remedy the undue discrimination concerns by simply clarifying that PJM’s existing retail BTMG netting rules apply equally to new large loads co-located with generation.  This approach would also remedy the deficiencies in PJM’s tariff and would do so using rules that PJM and the Commission already consider just and reasonable.

A. Only A Few Narrow Elements of the Tariff Require Further Clarity
Although PJM’s necessary study process effectively establishes the technical feasibility of a given behind-the-meter co-location arrangement,78 and PJM has applied this process repeatedly in recent years, according to PJM there currently is no path forward for such a project after it completes the necessary study process.  That contention appears inconsistent with the Commission’s order on rehearing of the Susquehanna ISA proceeding, which clarified that the Commission’s rejection of the Susquehanna ISA should not be read to indicate that other entities should not file non-conforming ISAs to address behind-the-meter co-located load.79  PJM’s contention even more fundamentally inconsistent with the fact that the Commission had already

77  See 16 U.S.C. § 824e.
78  See infra § V.
79 Susquehanna ISA Rehearing Order at P 30.

PDF page 23

-23-
approved the addition of some behind-the-meter co-located load at the Susquehanna facility in 2023 and 2024.80

Nonetheless, Vistra submits that, to provide a clear path forward, the tariff need only be revised to address four issues to allow Options 4 and 5 configurations:  (1) to require transmission owners to cooperate in the necessary study process, (2) determine the transmission and ancillary service charges that are appropriate for behind-the-meter co-located load, (3) incorporate surgical revisions to the pro forma ISA to address co-located load, and (4) develop a reasonable policy on the capacity treatment of secondary generators that only serve co-located load occasionally on an interruptible, backup basis.  The Commission can swiftly resolve this proceeding by establishing a replacement rate that addresses those four issues.

1. Transmission Owners Must Cooperate in the Necessary Study Process
As noted above, some transmission owners have cooperated in the necessary study process to allow behind-the-meter co-location configurations to move forward, whereas other transmission owners have refused to do so.  This issue can be easily remedied by a surgical tariff revision.  The tariff currently requires PJM to provide necessary study results.81  The relevant tariff language from Attach. O, App’x 2, Section 3.1 could be revised as indicated below:

The Interconnection Customer shall notify Transmission Provider
and Interconnected Transmission Owner of the proposed
modifications. and Transmission Provider shall provide, Within
sixty days of receipt of the relevant drawings and specifications (or
within such other time upon which the Interconnection Parties may
agree), Transmission Provider, with assistance from the
Interconnected Transmission Owner, shall provide an estimate
of any modifications to the Transmission System that would be
necessary to accommodate the proposed modification by

80
Susquehanna ISA Filing at 1-2 (“The Amended Susquehanna ISA . . . increase[s] from 300 [MWs] to 480 MW the amount of Co-Located Load under the ISA[.]”).

81 PJM Tariff, Attach. O, App’x 2, Section 3.1.

PDF page 24

-24-
Interconnection Customer and a good faith estimate of the costs
thereof.

This minor edit would ensure that transmission owners are required to cooperate in the necessary study process.

2. Co-located Load Should Pay its Fair Share—And No More
Any proposed solution to the tariff gaps identified in the Show Cause Order should ensure that co-located load pays its “fair share” for transmission and ancillary services and network upgrades.  However, co-located load should not be required to pay more than their “fair share.” As the Commission has explained, the cost causation principle requires that Commission- jurisdictional rates “reflect to some degree the costs actually caused by the customer who must pay for them”82 and allocate costs “in a manner that is at least roughly commensurate with the benefits that entity receives.”83  In keeping with the cost causation principle, transmission system charges for load served by co-located generation should be based on actual use of the transmission system.84  Being charged for services that are not actually received is not a “fair share” and is not “roughly commensurate with the benefits that entity receives.”

As the Commission acknowledged in the Order to Show Cause, the nature and degree of a co-located load’s transmission system use can vary dramatically depending on the details of the co-location configuration and how the co-located facilities are operated.85  There are many possible co-location arrangements.86  The cost causation principle requires that each of these arrangements

82  Show Cause Order at P 74 (quoting Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004)).
83  Id. (citing Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009)).
84 See PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 at P 28 (2004) (citing Occidental Chem. Corp. v. PJM Interconnection, L.L.C., 102 FERC ¶ 61,275 at P 14 (2003)).
85  Show Cause Order at P 74.
86  See PJM Answer, Exh. A; Dr. Shanker Aff. at P 41.

PDF page 25

-25-
be charged in a way that is “roughly commensurate” with the benefits that each receives from the system.87

In keeping with the cost causation principle, under an Option 4 or 5 configuration, the Commission could require the parties to the co-location arrangement to pay for any network upgrades needed to accommodate the addition of the behind-the-meter load.  This cost allocation would be consistent with the cost causation principle because such upgrades are designed to facilitate the co-location arrangement.  It also ensures that transmission costs for other customers do not increase (to contrast, in an Option 1 configuration, costs to other transmission customers could increase because the network upgrade costs are socialized).88

In a fully isolated behind-the-meter co-located load configuration (i.e., Option 4) the generator remains interconnected to the transmission system, but special protective schemes ensure that the load cannot draw power from the grid.  As Dr. Roy Shanker explained, this type of behind-the-meter co-located load will not draw power from the grid and therefore should not be considered network load.89  Applying the cost causation principle’s requirement for charges to be roughly commensurate with benefits, the correct charge for transmission service (as distinct from ancillary services) for a co-located load configuration that does not rely on the delivery of energy from the transmission system is zero.

However, it would be reasonable to create a penalty regime to address any unintended grid use in the rare case of a failure of the protective scheme that isolated the load.  Such a case would be rare indeed, given that there are already many significantly more complicated protective

87  Show Cause Order at P 74 (citing Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009)).
88 Dr. Shanker Aff. at P 59, Table 5.
89  Id. P 19.

PDF page 26

-26-
schemes active on the PJM system.90  Penalties for unintended grid usage are reasonable because they respond to use of the transmission system, rather than impose a baseline rate to configurations where the utility is providing no transmission service.  These penalties are conceptually similar to the unreserved use penalties that the Commission created in Order No. 890, which subject transmission customers to penalties for using transmission service that they did not reserve.91 With respect to ancillary services (as distinct from transmission service), under the current tariff, billing determinants for related ancillary services would be zero.92  However, Vistra acknowledges that it may be reasonable to charge a co-location configuration for some ancillary services, but again only to the degree that the co-location configuration benefits from those specific services.93  The rate design should be structured to allocate costs associated with the services that a particular generator receives from the grid in a way that is consistent with the cost causation principle.  The key to ensuring that ancillary service charges comport with the cost causation principle is to ensure that specific grid service charges are based on the extent to which the co- location arrangement actually contributes to additional costs and receives benefits from the PJM grid.  This matching of services and costs is a core component of the cost causation principle. Although the cost causation principle does not require “exacting precision,” it does require that costs be “roughly commensurate” with benefits received.94

90 Id. P 27.
91 See Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, FERC Stats. & Regs. ¶ 31,241, at P 834 (2007).
92 See Dr. Shanker Aff. at P 19.
93  See Show Cause Order at P 82 (“To the extent that certain co-location configurations benefit from or contribute to the need for certain ancillary services and black start services, it may be appropriate to allocation a portion of the costs of those services to those co-location arrangements, consistent with the cost causation principle”).
94  Sw. Power Pool, Inc., 137 FERC ¶ 61,075 at P 20 (2011) (citing KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992)).

PDF page 27

-27-
While PJM asserts that Option 4 configurations should pay for ancillary services, it has provided no analysis of which ancillary services benefit such co-location arrangements.  We agree that a case can be made for some ancillary service cost allocation, but it must be supported by analysis that the co-location arrangement benefits or contributes to costs for particular ancillary services.95  For example, variances in the co-located load, which are seen by the grid as changes in the co-located generator’s output, could be viewed as related to the need for regulation service.96 Co-location configurations with high load variation therefore can be considered to use regulation service.97  Charging the generator in such a configuration for regulation services could be reasonable under the cost causation principle.  Similarly, it may be appropriate to allocate such a configuration the costs of certain other ancillary services consistent with existing cost allocation principles.  It would be a reasonable exercise going forward to consider this type of question, and if necessary, adjust cost recovery.  But, any cost allocation would need to be based on analysis PJM has not yet provided.  Vistra urges the Commission to direct PJM to engage expeditiously in such analysis as part of a future compliance filing.  To effectuate any such identified cost responsibility, PJM could create a grid services rider in the ISA.98

Certain ancillary services are not appropriate for a fully isolated co-located load.  Ongoing charges for reactive power supply are not appropriate because, if the addition of the co-located load increases reactive supply needs, the network upgrades (like capacitor banks) to provide that

95 Dr. Shanker Aff. at PP 12, 20-21, Table 5.
96 See id. PP 12, 20.
97 See id.
98 See Integration of Variable Energy Resources, Order No. 764, 139 FERC ¶ 61,246, at PP 267-269 (2012) (declining to adopt proposed generic approach to recovery of generator regulation charges but confirming the rule “should not be interpreted as an unwillingness to consider individual proposals[.]”).

PDF page 28

-28-
reactive power would be borne by the parties to the co-location arrangement under this proposal.99 Ongoing charges for black start services are also likely not appropriate; as Dr. Roy Shanker explains, there has been no technical justification to support the assertion that co-located load receives comparable benefits from black start as network load.100  Rather, “the ability to isolate large loads so they cannot draw power from the system would act to sectionalize the grid and make black start more manageable.”101

As for a co-location arrangement that can sometimes take backup service from the grid (i.e., Option 5), during those periods when the configuration is drawing power from the grid, it may make sense to require such configurations to pay for point to point transmission service, NITS, or a new conditional, non-firm transmission service.  A conditional non-firm transmission service would be one in which PJM has no obligation to plan to provide service, nor expend costs in order to do so.102  Rather, the load would only take service when specifically permitted by PJM.103  When the load takes any such transmission service, it should be permitted to net against the generator’s output, consistent with the retail BTMG rules.  When the protective scheme is in place, an Option 5 configuration should be charged similar to an Option 4 configuration.

3. Surgical Changes to Pro Forma ISA Are Necessary and Sufficient to
Accommodate Behind-the-Meter Co-located Load
PJM’s Answer highlighted five items that would need to be added to the pro forma ISA to accommodate co-located load.  First, PJM indicated that it would require language formalizing the

99 See Dr. Shanker Aff. at P 64.
100 Id. P 66.
101 Id.
102 Id. P 69.
103 Id.

PDF page 29

-29-
special protection scheme or remedial action scheme that prevents the co-located load from drawing power from the grid.104  Second, the ISA may also need to include new data exchange requirements to ensure that appropriate communication and coordination occur.105  Third, the ISA should also specify the entity that owns the co-located load and contact information for the appropriate personnel.106  Fourth, the ISA may also specify whether the generator now functions as an electric distributor.107  Finally, PJM indicated that it would require the generator to affirm its continued rights, duties, and obligations under the ISA.108

While not highlighted in PJM’s Answer, the proposed amendments to the Susquehanna ISA also indicate that there may be a couple of additional items that are appropriate to include in these ISA revisions.  For example, the proposed Susquehanna ISA included details about coordinating the use of a secondary backup generator.109  It also included a process relating to the treatment of the generator’s capacity interconnection rights.  Specifically, Susquehanna was required to reduce the generator’s CIRs as load is incrementally added, and to purchase replacement capacity.110  Generic provisions on both items may be appropriate to include in the revised pro forma ISA, or elsewhere in the tariff.

None of these changes require an overhaul of the ISA.  Rather, they can be accomplished through narrow, surgical changes, or the creation of a new, short appendix or schedule attached to the ISA.

104  PJM Answer at 52.
105  Id. at 60.
106  Id. at 61-62.
107  Id.
108  Id.
109 Susquehanna ISA Filing at 9
110 Id. at 6.

PDF page 30

-30-
4. Secondary, Interruptible Backup Units Should be Allowed to Participate
in the Capacity Market
The last issue that requires further clarity in PJM’s tariff is the ability of a secondary generation unit in a co-location arrangement to retain capacity resource status.  Resources that are committed to providing primary service to a co-located load clearly should not also sell that same capacity to PJM.111  However, there is disagreement over the extent to which a secondary unit that occasionally will provide back-up service to the co-located load should be able to participate in the capacity market.112  PJM suggests that non-network load can never be served by a capacity resource.113  However, this position ignores the existing retail BTMG provisions that allow a generator that designates a portion of its resource as BTMG to sell the rest of its resource as a capacity resource.114  Vistra submits that there is no justification for prohibiting a secondary unit from participating in the capacity market if the secondary unit’s service to the co-located load is interruptible.115

Allowing secondary backup resources to participate in the capacity market ensures that the market gets the greatest reliability benefit from these resources.  Ratepayers would enjoy access to additional capacity that would otherwise be underutilized, while the generation resource’s owner would put its resource to use and increase its contribution to the market.  In fact, these types of secondary backup units are more suited to capacity market participation than reliability must run

111 See Susquehanna ISA Filing at 6-7 (requiring the Susquehanna nuclear facility to obtain replacement capacity and reduce the capacity value of its units by the amount of incremental load added).
112  See Show Cause Order P 86.
113 See PJM Answer at 58 (“To the extent the co-located load is not considered Network Load and PJM does not have any resource adequacy obligation with respect to such load, such load may not be served by installed capacity associated with an Existing Capacity Resource.”).
114 Dr. Shanker Aff. at PP 38-39.
115 In this context, interruptible service means that the co-located load would not be supplied by the secondary unit. Rather, it would have the option to either cease consuming power or use an on-site backup generator.

PDF page 31

-31-
(“RMR”) resources, and the Commission recently approved the participation of certain RMR resources in the PJM capacity market.  Despite Vistra’s arguments that RMR units distort dynamic efficiency of the capacity market and do not face non-performance penalties, the Commission allows RMR resources to participate in the capacity market because they “can be reasonably expected to perform.”116  A secondary unit that occasionally serves co-located load on an interruptible basis can also be expected to perform when needed because PJM can recall it. Moreover, these secondary units could be held subject to capacity market non-performance penalties and do not distort dynamic efficiency in the capacity market.

Allowing units providing secondary service to participate in the capacity market while also subjecting those units to non-performance penalties would allow generators to meet a market need while ensuring that they are held accountable for their commitments to the market.  If PJM deems it necessary, it could also create a mechanism to address for how the second unit complies with its capacity must offer obligation when it is serving the co-located load.  Given these protections, resources that are made available to serve a co-located load on a secondary, interruptible basis when the primary resource is unavailable should not unreasonably be prevented from selling capacity.

B. Alternatively, Applying BTMG Netting Rules to Behind-the-Meter Load Would
Constitute a Just and Reasonable Replacement Rate
If the Commission decides not to proceed with the replacement rate described above, another possible avenue to remedy PJM’s failure to accommodate behind-the-meter co-located load would be to clarify that its existing retail BTMG provisions (i.e., Option 3) apply to new,

116  PJM Interconnection, L.L.C., 190 FERC ¶ 61,088, at P 47 (2025).

PDF page 32

-32-
large loads served behind-the-meter.  As Dr. Roy Shanker explains, this clarification is entirely consistent with the retail BTMG program.117

PJM’s Answer misrepresented pertinent facts about the BTMG program because it jumped back and forth between describing its retail and non-retail BTMG provisions.118  Non-retail BTMG involves netting for multiple customers—that are not necessarily co-located—spread over a muni or coop distribution system.119   Retail BTMG is the relevant program here because it applies where load is located “at the same electrical location as the BTMG, such that no transmission or distribution facilities are utilized to transmit energy from the BTMG to the load.”120  The same is true of behind-the-meter co-located load.

The retail BTMG program reflects the same principles and logic as behind-the-meter co- located load.121  The retail BTMG “netting approach developed by PJM and its stakeholders reduces the cost to those market participants that rely to a lesser degree on the PJM integrated transmission system to serve load because they serve loads that utilize behind the meter generation. As a result, entities that serve loads with behind the meter generation are allocated a fairer share of the costs associated with the operation of the PJM integrated transmission system, including costs for energy, capacity, ancillary services, and administrative fees.”122

117 Dr. Shanker Aff. at PP 30-37.
118 Id. P 31.
119 Id. P 30.
120  PJM Manul 14D, Appendix A, ¶ 3; Dr. Shanker Aff. at P 32.
121 Dr. Shanker Aff. at P 32.
122  Id. P 33 (citing PJM Interconnection, L.L.C., Submission of Revisions to Open Access Transmission Tariff, the Amended and Restated Operating Agreement, Etc., Docket No. ER04-608-000, at 1 (March 1, 2004)).

PDF page 33

-33-
Moreover, as Dr. Roy Shanker explains, behind-the-meter co-located load uses the transmission system less than many traditional retail BTMG configurations.123  Oftentimes, BTMG only serves a fraction of the co-located load; furthermore, such configurations can draw power from the grid.  To contrast, load that is co-located behind a generator’s meter is served entirely by the co-located generator, and either cannot draw any power from the transmission system (Option 4) or can only do so with express permission from PJM (Option 5).124 PJM’s justification for not allowing new co-location configurations to use its BTMG program is because PJM asserts that the BTMG construct was created for smaller loads.125 However, PJM provides no source for this assertion.126  In fact, as Dr. Shanker explains, this is inconsistent with his long experience with co-location arrangements in PJM.127  Moreover, PJM’s statements regarding the total cap on the BTMG program applies only to the non-retail BTMG program, not the retail BTMG program.128  PJM failed to provide a reasoned explanation for why new behind-the-meter co-located load cannot be treated as retail BTMG.  The Commission could quickly remedy the undue discrimination against behind-the-meter co-located load by simply clarifying that these types of new, large co-located loads can use PJM’s retail BTMG provisions.

V. In General, the Necessary Study Rules Remain Just and Reasonable
Regardless of which replacement rate the Commission directs PJM to adopt, the Commission should find that the necessary study process generally remains just and reasonable as

123  Id. P 36; see also Mot. for Leave to Answer and Answer of Vistra Corp., Docket Nos. ER24-2888-000 et al, at 6 (filed Nov. 19, 2024).
124 See Dr. Shanker Aff. at P 37.
125  PJM Answer at 13.
126 See Dr. Shanker Aff. at P 31.
127 Id.
128 Id.

PDF page 34

-34-
applied to the interconnection of co-located load behind-the-meter of an existing generator.  With the minor clarification that transmission owners must cooperate during the necessary study process, the overall structure will work well.129  Vistra agrees with PJM’s defense of the necessary study process.130  This process is well established; PJM has been completing necessary studies to facilitate behind-the-meter co-location for years.131  While, as PJM noted, there may be opportunities to enhance the transparency of the necessary study process, the basic structure of the study makes sense.132  The necessary study process ensures that PJM and the transmission owner have “an opportunity to perform studies to evaluate the potential reliability impact of a proposed addition or reduction of a co-located load configuration onto the PJM Transmission System, and determine what, if any, system reinforcements are required prior to the addition or reduction of the planned co-located load configuration.133  PJM explained that the “necessary study process is capable of incorporating and evaluating the impact of co-located arrangements” and that an additional queue “is not necessary.”134

In any event, PJM must continue to administer its necessary study process during the pendency of this proceeding.  The necessary study tariff provisions remains on file with the Commission, and the Federal Power Act requires that PJM continue to administer the currently

129 See supra § IV.A.1.
130 See PJM Answer at 56.
131 See Doswell NSA; PJM Interconnection, L.L.C., Original NSA, SA No. 6027; Queue No. NQ123, Docket No. ER21-1728 (filed Apr. 22, 2021); PJM Interconnection, L.L.C., Original NSA, SA No. 6265; Queue No. M04, Docket No. ER22-685-000 (filed Dec. 20, 2021).
132  PJM Answer at 48-49.
133 Id.
134 Id. at 56.

PDF page 35

-35-
effective tariff.135  PJM’s Answer appeared to rely on the rejection of the Susquehanna ISA as evidence that it cannot accommodate Option 4 or 5.136  However, the Commission’s order on rehearing of the Susquehanna ISA proceeding clarified that the Commission’s rejection of the Susquehanna ISA should not be read to indicate that other entities should not file non-conforming ISAs to address behind-the-meter co-located load.137  It is therefore clear that PJM can implement Options 4 and 5, though the reforms proposed above will help ensure PJM accommodates Options 4 and 5 in a just and reasonable and not unduly discriminatory manner.  In the meantime, PJM must be required to tender an amended ISA to any customers that have received the results of a necessary study under the current process, in line with the filed rate doctrine and the Commission’s typical practice of respecting the settled expectations of late-stage interconnection customers.138

VI. PJM’s Answer Highlighted Additional Issues that the Commission Should Explore But that Should Not Delay Expeditious Resolution of this Proceeding

A. The Commission Should Encourage PJM to Engage with Stakeholders to Explore
Tariff Reforms to Accommodate Options 6, 7, and 8
PJM’s Answer highlighted three other examples of potential co-location configurations that the tariff does not currently accommodate (Options 6, 7, and 8).  Vistra agrees with PJM that all three configurations appear beneficial to provide customers with additional options and to

135  See, e.g., Old Dominion Elec. Coop. v. FERC, 892 F.3d 1223, 1230 (D.C. Cir. 2018) (“The filed rate doctrine and the rule against retroactive ratemaking leave the Commission no discretion to waive the operation of a filed rate[.]”); Towns of Concord, Norwood, & Wellesley v. FERC, 955 F.2d 67, 71 (D.C. Cir. 1992). 136 PJM Answer at 14-15 (explaining that fully isolated behind-the-meter co-located load is ‘a new potential option’ for which “[t]ariff modifications would be needed based on the Commission’s November 1, 2024 Order in Docket No. ER24-2172.”).
137 Susquehanna ISA Rehearing Order at P 30.
138  See Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023, 184 FERC ¶ 61,054, at P 865 (2023) (allowing customers with an executed facilities study agreement to proceed with a facilities study and requiring transmission providers to tender an LGIA to interconnection customers that have received final facilities study reports).

PDF page 36

-36-
enhance operational flexibility.139  However, the record in the Commission’s various co-location proceedings to date contains far less information on these three options than it does for Options 4 and 5.  As pointed out by Dr. Shanker, Options 4 and 5 do not raise unique resource adequacy or reliability concerns; therefore, Options 6-8 are not required to address resource adequacy or reliability.140  These options may nonetheless provide beneficial avenues to facilitate new entry or flexibility.  Vistra believes that these options are worthy of further exploration but would benefit from further discussion with stakeholders.  The Commission should encourage PJM to initiate stakeholder proceedings to develop tariff revisions to implement these options as soon as possible. However, the Commission should not wait until those further tariff revisions are ready before directing PJM to adopt a replacement rate to remedy the clear deficiencies in PJM’s tariff that are already apparent in the record.  Furthermore, implementing Options 4 and 5 in the tariff now would make it easier to implement such additional options later.  For instance, the “bring your own generation” approach of Option 6 could contain significant overlap with Options 4 or 5.  A configuration that brings its own generation could design its facility into any potential layout. Once PJM has a framework in place for behind-the-meter co-location in addition to front-of-the- meter co-location, the only unique element that would be needed for Option 6 is a way to coordinate the generation and load interconnection processes.  As discussed further below, an excellent step in that direction would be to explore standardized interconnection procedures for front-of-the-meter load interconnections.

B. There is a Regulatory Gap for Front-of-the-Meter Load Interconnection to the Transmission System that the Commission Should Fill

139 See PJM Answer at 8.
140 See Dr. Shanker Aff. at P 52, 54-57, 69.

PDF page 37

-37-
As described above, PJM’s Answer highlighted a troubling regulatory gap and lack of transparency with regards to front-of-the-meter load interconnection.  Load interconnection to the transmission system (i.e., Options 1 and 2) currently occurs through transmission owner load integration studies.141  Unlike generator interconnections to the transmission system, there are currently no FERC-regulated standardized procedures setting forth the rates, terms, and conditions of service for load interconnections to the interstate transmission system.  As PJM’s Answer explained, the network upgrades identified in transmission owner load integration studies are designated as supplemental projects.142  PJM only reviews these supplemental projects under a bare minimum standard to ensure that they “do no harm” to the transmission system.143  As OPSI has previously explained, state regulators often do not have authority to review these supplemental projects.144  According to PJM, these projects are “cost allocated to the local Transmission Owners’ zone pursuant to individual Transmission Owners’ cost allocation frameworks.”145  In other words, these supplemental projects oftentimes are virtually unreviewed before they go directly into the transmission owners’ rate base.

The Commission has jurisdiction to close this regulatory gap.  The Show Cause Order asked a series of important questions regarding when load should be considered interconnected to the transmission system in interstate commerce.146  This is the right question because the

141 PJM Answer at 9-12.
142  Id at 7.
143 Id.
144  See, e.g., Comments of the Organization of PJM States, Docket No. RM21-17, at 6 (filed Aug. 17, 2020) (“Some retail regulators have extensive processes for reviewing [supplemental projects], and others do not. In the latter case, retail regulators often lack authority over the vast majority of these local projects, meaning that the local projects being proposed simply do not undergo a review at the retail level.”)
145  PJM Answer at 17.
146  Show Cause Order at P 73.

PDF page 38

-38-
Commission has jurisdiction when load interconnects to the transmission system in interstate commerce based on its exclusive authority over interstate transmission.147  The Commission regulates the terms of generator interconnections to the transmission system under this same authority.148

The Supreme Court has found that transmission facilities that are connected to the interstate grid operate in interstate commerce.149  Therefore, the operative question is when load is interconnected to the transmission system; if it is, then it is properly considered interstate commerce.  The answer is relatively straightforward:  load that can draw power directly from the transmission system (regardless of whether the load is co-located in front-of-the-meter or behind- the-meter or not co-located at all) should be considered interconnected to the transmission system.150  To contrast, load that is designed with protective schemes to prevent it from drawing power from the grid should not be considered interconnected to the transmission system because it will only receive power that flows over distribution facilities between the generator and the load. After concluding this show cause proceeding on behind-the-meter co-location

arrangements, the Commission should consider commencing a separate proceeding to explore the issue of front-of-the-meter load interconnection practices on a PJM-wide, or perhaps even nationwide, basis.  The Commission should exercise its authority over load interconnection to the

147 See id. P 72 (“[T]he Commission has exercised authority over the terms of certain interconnections to the transmission system”) (citing Standardization of Generator Interconnection Agreements & Procs., Order No. 2003, 104 FERC ¶ 61,103 (2003)).
148  See Order No. 2003, 104 FERC ¶ 61,103, at PP 18-20 (2003); order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, at P 6, order on reh’g, Order No. 2003-B, 109 FERC ¶ 61,287 (2004), order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401, at PP 51-52 (2005), aff’d sub nom. Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007).
149  New York v. FERC, 535 U.S. 1, 16 (2002); Fla. Power & Light Co., 404 U.S. 453, 466–67 (1972) (“[The Commission’s] alternative assertion that energy commingles in a bus is, in our opinion, sufficient to sustain [the Commission’s] jurisdiction.”))
150  See Dr. Shanker Aff. at P 19.

PDF page 39

-39-
transmission system to prevent undue discrimination and ensure that interconnection service is provided in a just and reasonable manner.  The Commission could fulfill this responsibility by issuing a notice of inquiry to explore the adoption of standardized load interconnection procedures. Standardized load interconnection procedures could help provide PJM more visibility into load that seeks to interconnect and the timing of such load, which can help alleviate the resource adequacy and load forecasting concerns.  However, similar to the discussion regarding behind-the- meter load interconnection, any such standardized load interconnection procedures should include a transition for any interconnection customers that are sufficiently far along in the process.

VII. Conclusion
Vistra urges the Commission to act quickly to provide a pathway to adequately
accommodate Options 4 and 5 configurations.  The Commission should confirm its preliminary finding that the PJM tariff is unjust and unreasonable and unduly discriminatory because it does not contain provisions that address behind-the-meter co-located load with sufficient clarity.  PJM’s new assertion that its tariff does not accommodate Options 4 and 5 demonstrates this point.  It would be manifestly unjust and unreasonable and unduly discriminatory not to accommodate behind-the-meter co-location given that PJM accommodates other co-location configurations. Moreover, PJM’s contention that new, large loads must interconnect through Options 1 or 2 creates a structural bias in favor of transmission-served load and against competitive, bilateral supply arrangements.  PJM provides no justification for this discrimination that can withstand scrutiny. In particular, Dr. Roy Shanker’s analysis demonstrates that Option 4 and 5 configurations provides significant benefits to the grid and other market participants when compared with PJM’s preferred Option 1.  Even putting aside PJM’s new position that its tariff prohibits Options 4 and 5, the recent history of its implementation demonstrate that its tariff does not contain the clarity necessary

PDF page 40

-40-
to ensure that it can actually facilitate such configurations.  In light of these facts, the Commission must confirm its preliminary finding and proceed to set a replacement rate to remedy these issues. Vistra herein suggests a replacement rate that the Commission could adopt quickly to ensure that the tariff accommodates Options 4 and 5 configurations in a just and reasonable and not unduly discriminatory manner.  This proposal would ensure that Options 4 and 5 configurations pay their fair share and that other customers are not harmed.  Vistra’s solution includes the following four elements.

First, the Commission should clarify that transmission owners must cooperate in the necessary study process.  This can be done through the surgical edit to Attach. O, App’x 2, Section 3.1 noted above.  This clarification is necessary given that some transmission owners have refused to participate in the necessary study process to facilitate Option 4 and 5 configurations. Second, the Commission could create a new rate design to ensure that Options 4 and 5 configurations pay their fair share.  First, the Commission can allocate costs of any facilities identified through the necessary study process to accommodate the new behind-the-meter load to the generator in the co-location arrangement.  The Commission could also create a grid services rider in the ISA to address ongoing costs.  In particular, this grid services rider could include penalties for any unintended grid usage in the rare case of a protective scheme failure.  Such penalties would be reasonable because they respond to actual use of the transmission system, rather than a baseline rate where the utility is providing no transmission service.  The rate design could also include some ancillary service charges.  PJM has rightly clarified that generators might be obligated to pay for some ancillary services, even under an Option 4 or 5 configuration.  However, to be consistent with the cost causation principle, it is critical that the Commission and PJM identify, with specificity, the actual services that co-location arrangements use.  Vistra urges the

PDF page 41

-41-
Commission to direct PJM to identify and apply a principled approach for evaluating whether, and to what extent, these configurations should pay for such services.  For example, it could be reasonable to charge co-location configurations for regulation services where the addition of a co- located load introduces more variability in the generator’s output.  For Option 5 configurations, it would be reasonable to impose some transmission service charges when the load draws power from the grid, subject to netting consistent with the retail BTMG program.

Third, the Commission should modify the pro forma ISA to include provisions specific to the addition of co-located load.  In particular, such provisions could include language formalizing any applicable protective schemes and data exchange requirements.  The provisions could also affirm the generators’ continued rights and duties, include details on coordinating the use of a secondary backup generator, and address the treatment of the generator’s capacity interconnection rights.

Fourth, the Commission should clarify that a secondary generator that provides occasional, interruptible backup service to a co-located load can also serve as a capacity resource.  If the backup service is interruptible, the generator will be available to PJM when needed, and there is no reason to exclude such a resource from capacity market participation.  Moreover, such resources could be subject to non-performance penalties to ensure they are held accountable for their commitment to the market.  Allowing interruptible secondary resources to participate in the capacity market ensures that the market gets the greatest reliability benefit from these resources. This framework provides a path forward to facilitate Options 4 and 5 configurations in a just and reasonable and not unduly discriminatory way.  After the Commission ensures that PJM accommodates Options 4 and 5 in this proceeding, the Commission should also turn its attention to other issues raised by PJM’s Answer.  In particular, the Commission should direct PJM to

PDF page 42

-42-
conduct an expedited stakeholder process to create tariff provisions to accommodate Options 6-8. The Commission should also explore the possibility of creating standardized load interconnection process that would govern load interconnection to the transmission system.

However, the sequence and timeline of these steps is important.  The Commission must remedy the undue discrimination that is already apparent in the record, and it must do so quickly. Time is of the essence in removing unnecessary regulatory hurdles to deploying data center infrastructure, thereby fostering economic growth and national security benefits.

Respectfully submitted,

/s/ J. Arnold Quinn
J. Arnold Quinn
SVP of Regulatory Policy

Andrew Weinstein
Vice President, FERC Market Policy

Vistra Corp.
325 7th Street NW
Suite 520
Washington, DC 20004
arnie.quinn@vistracorp.com
andrew.weinstein@vistracorp.com
__________________
Nicholas M. Gladd
Sarah Greenberg
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
ngladd@wsgr.com
sgreenberg@wsgr.com

Counsel for Vistra Corp.

Dated:  April 23, 2025

PDF page 43

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.

Dated: April 23, 2025
Washington, D.C.

/s/ Sarah Greenberg
Sarah Greenberg
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(202) 431-5231
sgreenberg@wsgr.com

PDF page 44

1

Attachment A

Affidavit of Dr. Roy J. Shanker, PhD

PDF page 45

2
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

AFFIDAVIT OF ROY J. SHANKER, PH.D.

I. Qualifications and Purpose of Affidavit
1. My name is Roy J. Shanker.  My address is P.O. Box 1480, Pebble Beach, California, 93953.  I have a bachelor’s degree from Swarthmore College and both a master’s degree and a doctorate degree from Carnegie-Mellon University.

2. My resume, Attachment B hereto, summarizes my experience in numerous regulatory proceedings before state commissions and the Federal Energy Regulatory Commission (“FERC” or “Commission”).  As detailed therein, I have over 50 years of experience covering a broad range of issues in the electric utility/power generation/energy sectors for a broad range of clients. Prior to the creation of PJM Interconnection, L.L.C. (“PJM”) and the New York Independent System Operator, Inc. (“NYISO”), I was extensively involved in the development of on-site generation arrangements similar to the co-location issue under consideration in this docket.  In 1977, I was the Project Manager for New York’s first Energy Conservation Plan and New Jersey’s first Energy Master Plan, both of which involved understanding the status quo in terms of potential barriers or limitations related to on-site generation.

3. During the initial development of PJM and NYISO, I helped to formulate the underlying rationales for various elements of their market designs.  In PJM, I also participated extensively in the creation of net billing procedures for behind-the-meter generation (“BTMG”) in the 2003-

PDF page 46

3
2005 time period.  I also worked on subsequent adjustments to the BTMG paradigm.1 Throughout my 50 years of experience, I have participated extensively in stakeholder meetings and discussions concerning the underlying issues in this proceeding: co-location, net metering and behind-the-meter load.

4. On February 20, 2025, the Commission issued a Show Cause Order to address its concerns that PJM’s tariff is not just and reasonable with respect to the ability for a Network Resource to enter into an agreement to serve new behind-the-meter load.  The Show Cause Order contains an extensive list of questions to PJM regarding arrangements related to co-location arrangements and their interaction with the current tariff, and/or what potential tariff revisions may be necessary.

5. On March 24, 2025, PJM filed its response to the Show Cause Order (“PJM Answer or Response”).  I was asked by Vistra Corporation (“Vistra”) to review PJM’s Answer to the Show Cause Order and to review the existing tariff provisions as they relate to co-location arrangements.  In fulfilling this engagement, the below affidavit includes my assessment of the specific representations made by PJM.  It also presents a more general and organized approach to guide the Commission in its consideration of the questions it presented and appropriate context to evaluate various co-location arrangements.

II. Summary of Conclusions and Recommendations
6. As a starting point, the PJM Answer indicates that PJM is confused about the Commission’s inquiry.  PJM posits that there are only three existing ways within the current

1 This experience facilitated my correction of the misleading comments of PJM related to Behind the Meter Generation.  See PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 (2004); PJM Interconnection, L.L.C., 112 FERC ¶ 61,034 (2005); PJM Interconnection, L.L.C., 113 FERC ¶ 61,279 (2005); PJM Interconnection, L.L.C., Letter Order, Docket No. ER22-548-000 (January 31, 2022).

PDF page 47

4
tariff to implement the co-location of generation and load.  It also posits that there may be at least five additional ways to implement co-location.2  PJM appears to be saying that the current tariff is just and reasonable because of the three identified options and also suggests it is willing to discuss, going forward, modifications to existing tariff to address additional options.  All this seems contrary to the Commission’s directive, as stated above, which put upon PJM the obligation to explain why the tariff is not unjust and unreasonable or unduly discriminatory as it relates to co-location arrangements similar to arrangements like Options 4 and 5.  Further, PJM’s new position directly contradicts PJM’s own actions in executing and submitting to the Commission a modified Interconnection Service Agreement, coupled with identified necessary facilities for the proposed Talen/Susquehanna project (Docket ER24-2172), which appeared to be an Option 4 arrangement.  PJM’s position in its Answer also appears contradictory to its actions with respect to recently submitting a Necessary Study Agreement with LS Power for an isolated co-located load for a short-term arrangement again similar to Options 4 and 5.

7. Within this context, I reached the following conclusions.  First, in general there is nothing new about the concept of co-location.  These types of arrangements have existed from the very beginning of electrification.  I have been involved with these arrangements since prior to the implementation of PURPA in 1978.  The issues and concerns raised opposing such arrangements are old and oft repeated.  These issues do need to be addressed, but it is important to note that neither the concerns nor the remedies to those concerns are new or unusual.

8. Second, there does not appear to be any prohibition within the existing tariff with respect to the range of co-location options presented by PJM, and in particular, options 4 and 5.

2 As noted below, there are hundreds of alternative co-location options.  Some of those options are commercially superior to others in that they offer benefits compared to an appropriate comparison case.

PDF page 48

5
However, as described in Vistra’s comments, FERC should direct PJM to implement reforms to ensure that PJM will permit co-location in a just and reasonable and not unduly discriminatory manner.

9. Third, PJM misrepresents its own tariff with respect to its existing Option 3 (BTMG).  In discussing BTMG, PJM switches back and forth between discussing retail BTMG and non-retail BTMG.  Retail BTMG is the appropriate comparison for a behind-the-meter co-located load configuration.  Retail BTMG reflects an arrangement that allows behind the meter load to net its consumption against credits from PJM for the associated generation.  PJM’s Answer misrepresents the properties of the relevant existing program, retail BTMG, particularly with respect to any limitation on the total program level of participation (there is none) and the notion that the program was established for smaller loads (there are no such statements).

10. Fourth, PJM offers no organized approach to identifying and evaluating the various possible co-location configurations.  PJM did not provide an analytic foundation with respect to the use of a proper comparison case for each configuration of co-located generation and load to determine any differential impacts from the various options.  These omissions lead PJM to clearly incorrect conclusions regarding the properties of co-location arrangements.  In any potential replacement rate, the Commission should utilize an analytically sound basis to evaluate potential co-location arrangements to ensure they are treated fairly under the tariff.  Utilizing the proper comparison case for each co-location arrangement is critical to this analysis, because it will allow the Commission to properly evaluate the status quo, and any possible adjustments in order to assure the tariff is just and reasonable and not unduly discriminatory with respect to behind-the-meter co-location arrangements.

PDF page 49

6
11. Fifth, when we evaluate Options 4 and 5 appropriately, it is apparent that they present interconnection and load service arrangements that are either the same or superior in terms of planning reliability, LMP, capacity pricing, and billing results for existing load when compared to the appropriate comparison case.3  I recommend that the Commission direct PJM to ensure that market participants can enter into co-location arrangements that offer both benefits to the rest of system load or at minimum do not increase costs or adversely affect reliability for the rest of the system load when subjected to the proper comparison evaluations.

12. To facilitate that participation, FERC should direct PJM to implement the narrow set of tariff reforms identified by Vistra.  Those reforms would ensure that parties involved in a co- location arrangement pay their fair share.  Specifically, any incremental network upgrades that are identified as necessary to facilitate the addition of co-located load should be directly paid by the parties to the co-location arrangement.  With respect to transmission service, the co-located load should be eligible for netting consistent with the treatment of retail BTMG.  The reforms could also potentially include regulation service charges to the generator to the extent that high variances in the co-located load, seen by the grid as changes in generator output, is considered as using regulation services.  Other ancillary services that support PJM’s response to contingencies could be appropriate, but the specific allocation would need to be based on analysis has yet been provided by PJM or any other party.  Finally, those reforms also should include a recognition that a second unit that serves co-located load on an interruptible basis under PJM’s direction can serve as a capacity resource.

3 As noted in Vistra’s comments, this showing of all parties being in the same or better economic condition is not a necessary condition for a finding by the Commission that these alternatives are both just and reasonable.  However, the existence of this feature makes it clear that a contrary finding by the Commission could not be justified.

PDF page 50

7
III. Co-Location is Not New
13. My previous work history is particularly relevant to the repeated assertions about the “novelty” of the co-located load and generation business paradigms.  From time to time, since prior to the enactment of PURPA, I have been involved with both regulatory and business

transactions that would be classified as a form of co-location arrangements.
14. The ability for parties to operate in parallel with or independent from the grid under a wide variety of business and regulatory arrangements has existed for over a century.  Thomas Edison’s famous Pearl Street Generating station (1892) was in fact also a co-generation facility, providing energy for a steam loop.4  Hydro-electric generation at paper mills was very common.5 These arrangements continued against a backdrop of changing state and federal regulation, most notably the Public Utility Regulatory Policies Act of 1978 (“PURPA”).  Even prior to PURPA, I assisted in the co-location of new generation at an industrial site.6

15. The regulatory adjustments that occurred in the context of PURPA and PJM’s BTMG
paradigm are no different than the matters currently before the Commission.  The claims of “novelty” and “first impression” need not delay or obfuscate this iteration of co-location options being presented to the Commission.  Interestingly, the parties that oppose current behind-the-

4 Sonal Patel et al., History of Power: The Evolution of the Electric Generation Industry, Power Magazine, (October 1, 2022), https://www.powermag.com/history-of-power-the-evolution-of-the-electric-generation-industry/.
5 For example, in 1902, the Great Barrington Electric Light Company purchased a site on the Housatonic River at the north end of town.  This site, known as the Russell Water Power, was used in connection with the former Berkshire Woolen Mills at that location.  A combination hydroelectric and steam generating station was constructed there that used Stanley “S.K.C.” alternators.  This facility would have supplemented the power being obtained from the Alger’s Furnace hydroelectric station at Monument Mills. Thomas J. Blalock, In the Berkshires, Part 2, IEEE Power & Energy Magazine (Sept./Oct. 2012), https://magazine.ieee-pes.org/septemberoctober-2012/history- 4/#:~:text=In%201902%2C%20the%20Great%20Barrington,were%20known%20as%20McCormick%20turbines.
6 In 1977, I was engaged to help address regulatory issues related to the successful development of additional electric power generation at a petroleum coking facility.  This was done in cooperation with a local distribution company and private industrial entity.

PDF page 51

8
meter co-located load arrangements are almost the same as those who previously opposed the ability of Qualifying Facilities and co-located loads to net their own generation against purchases from the grid.  Their claims are remarkably similar to those made almost 50 years ago:  that generation combined with load running in parallel to the grid would harm the reliability of the grid, or service to existing customers would be somehow compromised, or that independent suppliers would not be reliable partners in the provision of power.7  When analyzed, these objections are wrong, and just as in the past, there are legitimate current mechanisms to pursue alternative competitive supply arrangements for electric consumers that are consistent with both reliability, overall cost impacts, and in this case, the existing PJM tariff.  In the case of co- location, some of those mechanisms can come with benefits to reliability and costs to existing customers when subject to the correct analyses.

IV. Rate Design, Use, Cost Causality, Billing Determinants
16. Another area of confusion relates to terminology related to the “taking” or “use” of Network Integration Transmission Service (“NITS”).8  It is worthwhile to explain the basics to inform the assessment of whether any particular co-location arrangement takes or uses NITS and what that means with respect to the specific cost recovery and charges.  The Commission typically seeks to assign costs to market participants (load and generation) in a fashion, to the

7 This is despite the fact that cogeneration and combined heat and power facility provide approximately 82,000 MW of power nationally in 3,700 locations with over a century of actual operations.  See Combined Heat and Power: A Clean Energy Solution 5, DOE & EPA (Aug. 2012), https://www.epa.gov/sites/default/files/2015- 07/documents/combined_heat_and_power_a_clean_energy_solution.pdf.
8 NITS to refer to all transmission services collectively rather than repeatedly referring to separate services such as point to point (PTP) service.

PDF page 52

9
extent possible, that considers and reflects who causes the costs and the related use of facilities or services.9

17. In doing so, it is typical to identify the cost “causer,” and then identify indicators of use (referred to as billing determinants) of the related facilities or services.  Costs are then spread over those billing determinants in total and assigned pro rata to customers based on their individual billing determinants.  As a simple example, the allocation of energy related LMP costs (i.e., payments to generators for energy) to customers would be based on the number of MWHs the customer consumes at a specific location and the LMP at that location.  In this example, the billing determinant is MWHs.  One has to be able to determine how many MWHs of power a customer consumed, and where and when, in order to then bill the customer for the energy.

18. This general paradigm continues to apply in the co-location context, including with respect to the “taking” of NITS and determination of what is “Network Load.”  In PJM, NITS related costs are broken out into various billing determinants.10  These billing determinants relate to PJM’s determination of the elements of use and cost causality associated with NITS, and the Commission’s determination that this was a just and reasonable allocation of costs.

19. These billing determinants reflect different types of use, and their total costs.  When combined with the allocated unit costs for these services, the billing determinants determine the charge for load directly connected to the PJM grid.  In certain co-location arrangements, like PJM Option 4, the load is not interconnected to the grid.  This load is not interconnected to the

9 See e.g. Southwest Power Pool, Inc., 137 FERC ¶ 61,075, at P 20 (2011) (“Under the cost causation principle, ‘it has been traditionally required that all approved rates reflect to some degree the costs actually caused by the customer who must pay them’ . . . the cost allocation mechanism must not be ‘arbitrary or capricious’ in light of the burdens imposed or benefits received.”) (citing KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1369 (D.C. Cir. 2004)).
10 See PJM Manual 29 at 14-16; PJM, Guide to Billing, available at https://www.pjm.com/markets-and- operations/billing-settlements-and-credit/guide-to-billing.

PDF page 53

10
transmission system because it cannot take power from the transmission system due to specific protective schemes reviewed and approved by PJM.  Rather, the load takes its service solely from the co-located generator (or through an intermediary).  The power this load takes only flows over the facilities between the generator and the load.  These facilities are all distribution facilities.  In such arrangements, only the generator is interconnected to the grid.  Under the current tariff, PJM has no billing determinants for generators with respect to NITS activity. There are similarly no billing determinants for load that is not interconnected to the PJM system. Thus, in terms of the ability to charge for such use and services, the current PJM tariff has determined that it is just and reasonable that these costs are recovered via load-based charges applied to load that is interconnected to the transmission system.  There is no basis for assigning these costs to load that is not interconnected and is “behind” a generator, and where only the generator is directly connected to the grid.

20. While this represents the status quo, a different perspective of cost causality might lead to other cost allocations and billing determinants for either load or generation that the Commission might deem just and reasonable.  For example, in a co-located arrangement, a 1 MWH increase in the load results in the decrease of 1 MWH of sales of energy from the generator to the grid (and vice versa for a decrease in co-located load).  Variances in the co-located load, which is only seen by the grid as changes in generator output, could be seen as related to the need for regulation service.  Thus, high load variation, (which appears to the grid as high generation variability) could be seen as using regulation services.  In turn, charging the generator for regulation services might be a reasonable causality and cost allocation approach for recovering costs related to regulation ancillary services.  Indeed, the Commission has previously considered

PDF page 54

11
imposing an ancillary charge on variable generation though decided a generic requirement was not necessary.11

21. As the last paragraph indicates, changing perspectives can suggest alternative cost allocation.  In the above regulation discussion, some portion of cost recovery would shift to generators.  To the extent that other ancillary services are reviewed in the similar context of a growing presence of arrangements such as the isolation of the load in Option 4, a different perspective on cost allocation may also be developed for those services.  For instance, another perspective could justify some cost allocation for other ancillary services.  This may differ from the status quo where these costs only are recovered by specific NITS billing determinants.  It would be a reasonable exercise going forward to consider this type of question and if necessary, adjust cost recovery.

V. The Current Tariff Does Not Prohibit Behind-the-Meter Co-Location
Arrangements
22. The fundamental attributes of behind-the-meter co-located load arrangements make it clear that there is no material regulatory impediment to a wide variety of co-location arrangements (nor should there be).  This can also be seen by decomposing the co-location process into its two basic components.

23. First, a generator that is interconnected with PJM chooses to stop selling parts of its energy and capacity into the PJM market.  This action will be reasonably reviewed consistent with the current tariff requirements.  For example, PJM will assure that necessary adjustments are made to the generator’s interconnection agreement and facilities.  After meeting these

11 See Integration of Variable Energy Resources, Order No. 764, 139 FERC ¶ 61,246, at PP 267-269 (2012) (declining to adopt proposed generic approach to recovery of generator regulation charges but confirming the rule “should not be interpreted as an unwillingness to consider individual proposals[.]”).

PDF page 55

12
requirements, there is no bar to this action in the tariff, that I am aware of, for making such sales. As conditioned above, a generator and its owner are free to sell to other parties under the PJM tariff.

24. Second, the generator then enters into a sale for power, either directly to the load at retail or to an LSE at wholesale.  If the generator is an Exempt Wholesale Generator (EWG), then the sale must be at wholesale.12  In those cases, the wholesale buyer would be a Load Serving Entity that, under state law, is permitted to purchase at wholesale and resell at retail.  Alternatively, a generator that is not an EWG could make a direct sale to a retail entity if it met the appropriate state regulatory requirements.  Again, none of these actions are prohibited by the PJM tariff.

25. Although tariff revisions would be needed if the Commission wishes to modify the status quo with regards to issues like charges for certain ancillary services, it is apparent from a review of the components of the co-location process that the current tariff permits these configurations. References to physical elements like synchronization or an expansive notion of use of the transmission system obfuscate the fact that the actions described above are already permissible.

26. Similarly, debates regarding the term “isolated” to describe electrical arrangements that are designed to prevent the co-located load from unintentionally drawing power from the grid obfuscate the fact that such electrical arrangements are already permissible.  While some parties

12 The Public Utility Holding Company Act of 2005 (“PUHCA 2005”) states that the term “exempt wholesale generator” will have the same meaning as that term had in section 32 of the Public Utility Holding Company Act of 1935 (“PUHCA 1935”).  42 U.S.C. § 16451(6) (2005).  Section 32(a)(1) of PUHCA 1935 defined an exempt wholesale generator as “any person determined by the Federal Energy Regulatory Commission to be engaged directly, or indirectly through one or more affiliates . . . , and exclusively in the business of owning or operating, or both owning and operating, all or part of one or more eligible facilities and selling electric energy at wholesale.”  15 U.S.C. § 79z-5a(a)(1) (1935) (repealed 2005).

PDF page 56

13
suggest these types of arrangements cannot be depended on, PJM itself approved the design of such an arrangement in the Susquehanna ISA.13

27. Moreover, PJM already has in place at least 14 Remedial Action Schemes (“RAS”) or Special Protection Schemes (“SPS”) that involve complicated switching or other transmission arrangements in real time to prevent adverse circumstances in the operation of the transmission system.14  As indicated in BPM Manual 7, Section 17, these types of arrangements are consistent with NERC standards.  The PJM manuals also describe the process for the use of automatic sectionalization, adjustments that can isolate dynamically faulted sections of the grid.15  For instance, in describing system operating limits, PJM acknowledges the role of “system reconfiguration through manual or automatic control or protection actions.”16  The notion of preventing a load from drawing power from the grid is fully within the scope of these types of existing configurations.  It seems incongruous that PJM would sponsor before the Commission an arrangement such as it submitted for Talen/Susquehanna if it did not believe that such actions were both permissible and reliable.

28. Debates regarding the term “synchronized” are also irrelevant as relating to the jurisdictional categorization of these facilities and the resulting NITS or PTP charges.  It is a natural property of an alternating current transmission and distribution system to synchronize in

13 See PJM Interconnection, L.L.C., Amendment to ISA, SA No. 1442; Queue No. NQ-123, Docket No. ER24- 2172-000 (filed Jun. 3, 2024).
14 See PJM Manual 3: Transmission Operations, Attachment A (November 21, 2024), https://www.pjm.com/- /media/DotCom/documents/manuals/m03.pdf.
15 See id. at § 1.9 (“Several PJM Transmission Owners use line and substation designs that automatically switch equipment in order to isolate faulted system elements (e.g., a line or a transformer) from unfaulted elements. Within the protection schemes for these system elements, sufficient fault detection and control capability is provided to automatically isolate the faulted element and then restore remaining equipment to service.”).
16 See PJM Manual 14 B, Attachment F.

PDF page 57

14
terms of frequency, voltage, phase and wave form.  The generator in a co-location arrangement must continue to be synchronized with the grid to be able to operate safely.  The same is true of all facilities, inclusive of retail BTGM and load on the system.

29. While that synchronization is necessary, it does not speak to the jurisdictional boundaries or related cost allocations.  The actual utilization of the facilities with respect to issues like reduction in voltage or geographic range or direction of power flow drive conclusions about whether facilities constitute transmission facilities that can implicate FERC-jurisdictional transmission charges.  In all instances, the power flowing over non-jurisdictional distribution facilities remain synchronized with the grid.

VI. PJM's Answer Distorts Existing Option 3 (BTMG)
30. Option 3 illustrates that PJM precedent acknowledges the different cost causality in transmission use and services based on the proximity of load to dedicated generation.  However, PJM’s Answer misstates pertinent details regarding the existing BTMG programs in the tariff. As described further below, it is critical to understand that PJM’s BTMG program comes in two forms:  retail BTMG and non-retail BTMG.  The below PJM graphic makes this distinction explicit in a very simple manner.17  Retail BTGM is referring to a single load co-located with a generator that does not utilize the transmission system. Non-real BTMG is referring to netting arrangements for multiple customers spread over the muni/coop distribution system with no

17 Theresa Esterly, PJM, Behind the Meter Generation Education, at 4, (June 1, 2023), available at https://www.pjm.com/-/media/DotCom/committees-groups/cifp-ra/2023/20230601/20230601-item-02b---behind- the-meter-generation-education.ashx.

PDF page 58

15
limitations on proximity to each other or the generator.

Figure 1:  PJM BTMG Programs
31. Understanding this distinction between retail and non-retail BTMG illustrates why PJM’s Answer appears to misstate the pertinent details of Option 3.  PJM’s Answer shuffles facts between the two programs.  For example, PJM’s Answer attempted to distinguish the BTMG program from Options 4 or 5 by stating that BTMG is limited with respect to total MWs and that it was only intended for small loads.18  First, the MW limitation that PJM references only applies to the total non-retail BTMG, which allows municipal and cooperative utilities to net at dispersed locations.  This limitation does not apply to retail BTMG, which is the arrangement of interest to the co-location discussion here.  Second, there is no source for PJM’s assertion that the retail co-

18 PJM Answer, Exh. A.

PDF page 59

16
located BTMG was intended only for small loads.19  In fact, while PJM encourages all BTMG generators to coordinate their interconnection, the requirement to coordinate only applies to generators above 10 MWs.20  So while there is a lower limit for review, there is no statement anywhere of an upper limit.  Moreover, PJM provides no inventory, or reporting of the total of the co-located retail BTMG or related parallel generation arrangements such as qualifying facilities (QFs).  This type of information on the quantity of retail BTMG and similar QF type arrangements would be helpful to the Commission.

32. The history of the BTMG provisions explains why retail BTMG is the relevant program to consider in this proceeding.  Both the retail and non-retail BTMG allow netting of generation against load requirements to reduce NITS or PTP services, including down to zero.  However, as PJM explained in its original retail BTMG filing, that program was intended “to implement market rules . . . [to] allow market participants to net operating behind the meter generation (or behind the meter generation expected to be operating in the case of the day ahead markets) against load at the same electrical location for the purposes of calculating charges for energy, capacity, transmission service, ancillary services, and PJM administrative fees.”21  This arrangement was intended to address generation and load at the same electrical location—which is what is now referred to as a co-location arrangement.  To contrast, non-retail BTMG was added to allow for netting of multiple customers—that are not necessarily co-located—behind a municipal or cooperative meter.

19 I have personal experience within PJM with parallel operations that were eligible to net, if desired, in excess of several hundred MWs. 20 PJM Manuals 14 G and 14 D.
21 PJM Interconnection, L.L.C., Submission of Revisions to Open Access Transmission Tariff, the Amended and Restated Operating Agreement, Etc., Docket No. ER04-608-000, at 1 (March 1, 2004) (“PJM Retail BTMG Filing”).

PDF page 60

17
33. The retail BTMG “netting approach developed by PJM and its stakeholders reduces the cost to those market participants that rely to a lesser degree on the PJM integrated transmission system to serve load because they serve loads that utilize behind the meter generation.  As a result, entities that serve loads with behind the meter generation are allocated a fairer share of the costs associated with the operation of the PJM integrated transmission system, including costs for energy, capacity, ancillary services, and administrative fees.”22  That “fairer share” can net all charges down to zero.

34. The Commission itself adopted and endorsed this perspective:
The Commission finds that . . . PJM’s proposed market rules [for
behind the meter generation and total netting] are just and
reasonable and will encourage qualifying entities with behind the
meter generation to reduce their use of the PJM transmission system
. . . . PJM’s total netting approach is consistent with our [prior]
decision [where] the Commission specifically found that “charges
for the use of PJM’s transmission system should be allocated to
network customers based on a network customer’s actual use of
PJM’s system, consistent with the principle of cost causation.”23

35. PJM also further explained that: “the new [retail BTMG] rules will permit an entity serving load with behind the meter generation that is operating and serving load at the same, single electrical location to net such generation against load for the purposes of calculating the charges for various services under the PJM agreements . . . . In the event there is more behind the meter generation than load or the behind the meter generation desires to sell all or part of the

22 Id. at 7 (footnote omitted).
23 PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at PP 27-28 (2004) (citing Occidental Chemical Corp. v. PJM Interconnection, L.L.C., 102 FERC ¶ 61,275 (2003)) (emphasis added).

PDF page 61

18
output of its generation into the PJM market, it may qualify as an Energy Resource or a Capacity Resource and sell energy into the PJM markets.”24

36. PJM’s Manuals continue to view retail BTMG in just this manner.  The following is from the current Manual 14 G:

Generating resources operating “behind the meter,” in isolation
from the PJM bulk power transmission system and which do not
intend to participate in the PJM wholesale energy market, need
only coordinate planning, construction and/or operation with the
host Transmission Owner.

Behind the Meter Generation (BtMG) is the output from
generation that offsets load and does not and cannot participate in
the wholesale market. Thus, in order to be considered BtMG,
power claimed as BtMG must deliver energy to load without using
the Transmission System or any distribution facilities (unless the
entity that owns or leases the distribution facilities has consented to
such use of the distribution facilities and such consent has been
demonstrated to the satisfaction of PJM).

37. It is clear that the retail BTMG program reflects the same general principles and logic as many of the proposed alternative co-location arrangements (such as Options 4 and 5).  The issue of discriminatory treatment thus must become front and center in the Commission’s deliberations.  It is also important to note that Option 4 configurations use the transmission system less than retail BTMG because “there are protection mechanisms in place to prevent delivery of energy from the grid to serve the load in the event the generation is offline.”25  Retail BTMG arrangements can draw from the grid; the net impact may vary at the discretion of the customer.

24 PJM Retail BTMG Filing at 4 (emphasis added).
25 PJM Answer at 13.

PDF page 62

19
38. With respect to the capacity status of the generator under the retail BTMG, the
Commission recognized that an appropriate portion of the generator (in excess of the load), can still be a Capacity Resource.26  However, PJM Indicated that in its Exhibit A that an Option 3 configuration cannot include Generation Capacity Status.  This directly contradicts the tariff provisions stating that so long as the capacity is in excess of the maximum load, that portion may be sold as a Capacity Resource. 27

39. This observation also informs PJM’s new claim that a secondary unit in a co-location arrangement cannot sell capacity.  As presented in an arrangement such as Talen’s, the co- located load receives the dedicated output of a single unit, the primary unit.  Should that primary unit not be available, a switching arrangement allows power supply from a secondary unit. However, the secondary unit is not dedicated to the co-located load.  It may only provide power to the co-located load with advanced permission from PJM.  PJM has full discretion to not provide that permission and/or interrupt the service.  There is no limitation from the co-location arrangement to limit the secondary unit from providing firm service as a Capacity Resource.

VII. PJM’s Answer Offers No Coherent Way to Identify or Evaluate the Various Co-
Location Options
40. PJM failed to present an organized and reasoned approach to identifying and defining possible co-location options and evaluating those options.  One of the first things I looked for

26 PJM Retail BTMG Filing at 4. 27 See e.g., PJM, Intra-PJM Tariff, A-B, OATT Definitions A-B (21.0.0) (“Behind The Meter Generation: ‘Behind The Meter Generation’ shall refer to a generation unit that delivers energy to load without using the Transmission System or any distribution facilities (unless the entity that owns or leases the distribution facilities has consented to such use of the distribution facilities and such consent has been demonstrated to the satisfaction of the Office of the Interconnection); provided, however, that Behind The Meter Generation does not include (i) at any time, any portion of such generating unit's capacity that is designated as a Generation Capacity Resource; or (ii) in an hour, any portion of the output of such generating unit that is sold to another entity for consumption at another electrical location or into the PJM Interchange Energy Market”) (emphasis added).

PDF page 63

20
when reviewing PJM’s Exhibit A was PJM’s characterization of the reliability of each option. For example, Options 1 and 2 state PJM’s preference as “Yes, Highest Reliability.”  PJM did not explain the basis for its conclusion that Options 1 and 2 provide the highest reliability.  Any such characterization is inherently based on a comparison between that configuration and a counterfactual case.  However, PJM did not provide any such description or comparison.  Nor did PJM analyze how energy or capacity prices would be impacted or whether how existing NITS customers’ billing determinants would be impacted.  PJM did not even provide a characterization of the reliability of Option 3; rather, it simply stated “Not for Large Loads.” PJM similarly did not provide a characterization of the reliability of Options 4 and 5, but simply noted that they are “Less preferred.”  This subjective evaluation was not supported by any formal analysis.

41. The first step in identifying the possible co-location options is to define the various relevant attributes or features of a co-location configuration.  The number of possible options would be the product of all the different possible values for each attribute identified.  This could result in several thousand options, although many may not be desirable or worth further discussion.  In table 1, I present what I identified as the key attributes.   Each attribute also indicates the number of possible options for each attribute (i.e., whether the generator is an EWG or not is a binary, so there are two possible options for that attribute).  The number of possible co-location alternatives is the product of multiplying all of the possible options for each attribute. Table 1:  Possible Attributes of Co-location Arrangements

Attribute28
Possible Options
Comment
New or Existing Load
(2) Key to most comparisons as incremental load
must be served
Direct or Isolated
Interconnection
(2) Ability of load to draw directly from the grid or
only from the generator

28 There may be other possible attributes, but I have limited my consideration to the most important attributes.

PDF page 64

21
Firm or Interruptible
Service to Load
(3) Commitment of generator to always service load
when operating, or interrupt by price at PJM
direction
Single or dual supplying
Generator(s)
(2) Potential for change in isolation or firmness of
supply after one generator fails
On Site Backup for Load
(2) Internal reliability and/or ability to support
general grid as subset
Supplying Generator
(Energy or Capacity)
(2) Implications for CIRs and system reliability as a
whole
Generator Economic or
Uneconomic/Retiring/New
(3) Whether the generator should be assumed to be
present going forward or retire
Dispatch Price/Must Run
(2) Direct impact on dispatch and LMP, co-located
dispatchable units inherently will lower LMPs
which market price is below generator offer price
Payment for Necessary
Facilities or Not
(2) Payment and Ownership of Necessary Facilities
May also create new property rights
Is the Generator an EWG
(2) Role of LSE in sale, or ability for direct sale

42. The next step would be to evaluate the possible options by establishing a proper comparison case (i.e., what would have happened “but for” the presence of the co-location arrangement).  How do the impacts compare to a case where the co-location proposal was not implemented?  This is the most crucial and difficult step.  While seemingly simple, proper comparison cases can be tricky and often offer surprising results.  Without the strength of a formal analytic comparison, important properties in decision making are missed.

43. Much of the confusion in the debate so far is due to various parties drawing comparisons from different assumptions that create different comparison cases (or in PJM’s Answer, no comparison case at all).  The most common one of these differences is the representation of the amount of load in the comparison case.  Without reason, many people assume that if there were no co-location, the co-located load would not exist.  There is no reason to make this assumption. There has been no indication that the load desiring to locate in PJM would “disappear” if there were no co-location arrangement.  Many parties are also pursuing options similar to PJM Option

PDF page 65

22
1,29 and one of the key elements for data centers seems to be speed to market, not just the electric supply arrangements alone.  There is no reason to believe that an appropriate comparison should not reflect the same level of load, in the same location, being served overall in a fashion that looks like PJM Option 1.

44. A very simple example shows how critical the right comparison is with respect to both the level and nature of load.  Several parties have raised concerns regarding the potential for common mode outages of data centers,30 possibly linked to a widespread internet failure that disrupts the operation of all data centers in a local area, such that all the data center load would drop off at the same time.  However, this concern is not about co-location, but about new large loads generally.  A comparison case would recognize the existence of the same loads regardless of whether they are co-located.  If the cause of load drop was indeed linked to the internet, that load drop would occur whether these data centers were directly connected as Network Load, or isolated behind the generator in a co-location arrangement.  The impact of the situation would be identical in terms of the system dealing with a large surge in generation as the load drops.  As discussed above, this indeed might be the basis for a modification in cost allocation for regulation services, but it is not specifically linked to the co-location arrangement.

45. The rest of the comparison case can be constructed by looking down at the relevant attributes and choosing comparable or contrasting attribute values for the comparison case consistent with an appropriate appraisal of differentiated attributes and impacts.

29 See, e.g., US utilities see uptick in data center deals, signaling booming demand, Reuters, (January 16, 2025), https://www.reuters.com/business/energy/us-utilities-signal-booming-demand-data-centers-ai-takes-root-2024-08- 12/.

30 See, e.g., Incident Review Considering Simultaneous Voltage-Sensitive Load Reductions, NERC (Jan. 8, 2025), https://www.nerc.com/pa/rrm/ea/Documents/Incident_Review_Large_Load_Loss.pdf.

PDF page 66

23
46. The third step is to evaluate the proposed configuration and the comparison case and assess any differences in defined criteria.  This step provides a basis for the Commission’s analytic decision-making.  Table 2 below lists relevant criteria, as informed by consideration of the background of this proceeding and related cases.  A proper comparison would assess the differences for each attribute between the specific co-location arrangement and its associated comparison case to draw conclusions about impacts of each possible arrangement. Table 2:  Proposed Evaluation Criteria

EVALUATION CRITERION
COMMENT/DESCRIPTION
Planning Reliability Rest of Pool /
Reserves
Is the planning reliability for the rest of the pool higher,
lower or the same in the co-location case v comparison
case.
NITS Payments by Existing
Customers
Are these higher, lower or the same for the existing
customers in the co-location case v comparison case.
(Enumerated by current tariff billing determinant categories
in comparison chart).
Payment for Transmission
Enhancements/Interconnection Costs
As defined by the cases themselves
Dispatch
How does system dispatch differ in the two cases
LMPs for Existing Customers
Are the LMPs higher, lower or the same of existing
customers in the co-location case v comparison case
Capacity Prices
Are the capacity prices higher, lower or the same of existing
customers in the co-location case v comparison case
Total Generation to Serve Load
How does the total generation to serve load differ in the two
cases (e.g. preventing a retirement would enhance
reliability)
Ancillary Services
How the addition of the co-located load impacts total cost
of ancillary services v. comparison case, and the extent to
which the co-location arrangement benefits from ancillary
services
Capacity Interconnection Rights
Who receives or relinquishes the rights and any value for
existing rights versus incremental rights
Incremental ARRs
Who receives or relinquishes the rights and any value for
existing rights versus incremental rights

47. Considering all possible combinations of all attributes yields hundreds or thousands of different possible co-location arrangements, not just the eight PJM discusses.  However, there are also a number of attributes or combinations of attributes that are “dominant,” in the sense that parties to the arrangement would be generally better off, and the arrangement would have either

PDF page 67

24
a positive or neutral impact on all other market participants.  For example, certain attributes in a configuration might be “dominant” if they ensure that the configuration does not change costs for current customers in a manner any different than the proper comparison case.  Among these “dominant” attributes includes features very similar to PJM’s Option 4 and 5.  Given that those features are the most salient part of this proceeding, the following section will focus on an evaluation of those two options, rather than all possible co-location arrangements.

48. In any further analyses of the appropriateness of other co-location arrangements the Commission should consider these types of dominant features (alone or in combination).  A more methodical review of the variations I have listed above may identify other arrangements for co-location that are win/win or a net neutral that can expedite the addition of new high priority loads.

VIII. Evaluation of PJM Options 4 and 5
49. The following sections evaluate Options 4 and 5.  For both configurations, Option 1 is generally the most appropriate comparison case.31  As discussed below, both Options 4 and 5 are “dominant” configurations that are comparatively superior to PJM Option 1 in terms of planning reliability, capacity costs, NITS cost impacts to other customers, network upgrade cost allocation, and LMPs.

a. Option 4 Evaluation v Comparison Case

50. PJM’s formulation of Option 4 is reproduced below in Table 3.

31 For Option 5, during the limited instances in which the configuration would draw from the transmission system, it becomes an interruptible load.  Therefore, during those limited times, the comparison case could also be an interruptible load that is otherwise similar to Option 1.

PDF page 68

25
Table 3:  PJM Option 4

51. Table 4 below lists the relevant attributes as compared to an Option 1 comparison case. As part of this evaluation, I have also included two possible supplying generators:  one a must run nuclear unit and the other a dispatchable combined cycle with a $30 per MWh dispatch energy offer.  This table does not include every possible attribute included in Table 1 above because not all attributes are relevant for every comparison.

Table 4: Attributes of PJM Option 4 versus PJM Option 1

 PJM OPTION 4
Isolated Co-Located Load Reference
Case
PJM OPTION 1
Comparison Case
Supplying
Generator
a) Existing 1,000 MW Nuclear
Facility that is economic today
a) The Same
b) The Same

PDF page 69

26

 PJM OPTION 4
Isolated Co-Located Load Reference
Case
PJM OPTION 1
Comparison Case
located in Dominion zone (high
capacity and availability factors)
b) Existing 400 MW CC with
$30/MWH dispatch cost
Direct or
Isolated Load
400 MW new data center, co-located and
sited behind the generator with back up.
High load factor.
400 MW new data center directly
connected to the grid in close proximity
to the generator
Firm or
Interruptible
Load
Firm while generator is online.  When
generator is offline, load is interrupted or
must use on-site backup generator.
Firm
NITS
Not taking NITS service (not receiving
energy and capacity from the grid), no
service billing determinants
NITS customer (either Load becomes its
own LSE or another LSE serves the load)
Capacity
Status of
Supplying
Generator
400 MW of CIRs are delisted, no new
load is served by the PJM system.
Generator may sell these CIRs. 100 MW
of New CIRs are created
No CIRs are delisted to serve new load,
400 MW of new load is added to the PJM
system demand. 100 MW of new CIRs
are created
52. While each of the individual components of the comparison are discussed below, the overall conclusion is that Option 4 is superior to the Option 1 comparison case.  All parties— including other market participants—are either better off or unaffected compared to the Option 1 comparison case (in which the new load connects directly to the grid).  This occurs because in general the new load is willing to pay a premium in order to be connected faster.  In doing so, they accept a lower quality of service and pay all the incremental costs (including those necessary to adjust their on-site reliability to an acceptable level).  This creates an opportunity to hold all other customers harmless and give those other customers potentially millions of dollars per year in terms of reliability benefits.

PDF page 70

27
53. Based on these attributes, the following section analyzes the two cases pursuant to the evaluation criteria provided above, namely:  (1) reliability and planning reserves, (2) NITS costs,

(3) interconnection costs, (4) impact on system dispatch, (5)  LMPs, (6) capacity prices, (7) total generation and load, (8) ancillary services, and (9) capacity interconnection rights / transmission rights.

54. Reliability and Planning Reserves.  An Option 4 configuration increases reliability for the rest of PJM compared to the Option 1 comparison case.  In terms of installed reserve margin (IRM) based on the ratio of Installed Capacity to System Coincident Peak, the Option 4 case is more reliable because the load increase is met by the same amount of generation decrease, with no adjustment for reserves (i.e., 400 MW of load will be served by 400 MW of ICAP from the generator, which is removed from the wholesale market).  The differing results for reserves makes sense because the co-located load has no ability to take power from the grid even if its co- located generator experiences a forced outage.  To contrast, in the Option 1 comparison case, the grid-connected load can take power from the grid even if the generator “next door” has an outage, so there is a need to include a reserve margin.

55. The same conclusion would apply under ELCC evaluations.  For the Option 4 case, whenever the generator is unavailable, load would also be decreased by the 400 MW.  As discussed earlier, the effect is an equal shift in the supply and demand curves with no adjustment for reserves.

56. To estimate of the cost impact, using an 18% installed reserve margin, then 72 MWs less capacity would be needed in the Option 4 case compared to the Option 1 case. (.18 x 400).  I estimate that at the pool wide accreditation rate of approximately 80%,32 and the most recent

32 PJM 2025/2026 Base Residual Auction Report, at 6 (July 30, 2024), https://pjm.com/-/media/markets- ops/rpm/rpm-auction-info/2025-2026/2025-2026-base-residual-auction-report.ashx.

PDF page 71

28
auction clearing price, 72 MW of additional capacity in the Dominion zone would cost approximately $9.3 million per year (.8 x 72 x $444 x 365).33

57. These conclusions directly contradict PJM’s characterization of Option 4.  However, PJM did not explain the basis for its conclusion regarding reliability.

58. NITS.  For the co-location case, because the co-location arrangement pays all incremental costs for interconnection and upgrades, NITS charges remain the same for the rest of PJM load.  In Option 1, total NITS related costs increase by at least the socialization of the necessary facilities costs, but the number of entities with billing determinants for these services will also increase, spreading these costs among more customers.  As a result, it is difficult to predict whether costs to existing customers will increase or decrease.  The ancillary service impacts are discussed further below.

59. Interconnection Costs and Other System Upgrades.  In Option 4, direct
interconnection costs would be borne by the co-located customer.  In the Option 1 comparison case, 90% of those costs could ultimately go into rate base for all customers.

60. Dispatch.  For the Option 4 co-located case with the nuclear unit, the dispatch of the system remains unchanged.  In the Option 4 co-located case where a combined cycle is the supplying generator, the dispatch will change.  In that situation, at all prices lower than the dispatch price of the combined cycle unit, the must run nature of the combined cycle unit will result in additional energy being available.  In comparison, in the Option 1 case, combined cycle units will be turned down or not committed at the lower prices.34

33 Id.
34 This is a simplification with respect to the operation of the CC unit.  No consideration was given to start-up, minimum or other operational requirements, but the general result is unchanged.

PDF page 72

29
61. LMPs.  In the Option 4 case in which the supplying generator is a must run nuclear unit, LMPs would be the same compared to the Option 1 comparison case.  In both cases, load, generation, and dispatch would be the same, resulting in the same LMPs.  However, in the Option 4 case where a $30/MWh dispatch price unit was running whenever it was available to serve the isolated load regardless of the market price LMP, LMPs would be lower compared to the Option 1 comparison case whenever the market LMP at that location would have been $30 or less and the 400 MW unit was still operating.  This occurs because the co-location arrangement turns a dispatchable unit into a must run unit, always operating when available to serve the co- located load.  As a result, there is effectively more energy available into the market at a price of zero at all price levels below the assumed $30.  Using elasticity data, supply curve information and load duration information from the State of the Market report for 2024, this type of change in dispatch for 400 MW reduced costs to other market participants by millions of dollars annually, but PJM has ignored these types of benefits and not estimated them in reaching its conclusions.

62. Capacity Prices.  In the Option 1 comparison case, the demand curve would shift to the right, and capacity prices would increase.  In the Option 4 co-located case, the demand curve does not change from before the addition of the load, but the supply curve is shifted to the left and capacity prices increase.  In either case, the addition of new load raises capacity prices with all other factors held constant in both cases.  However, prices would increase more in the Option 1 comparison case because it requires more planning reserves than the Option 4 co-located load case.  This relates to the fact that the co-located load is receiving a form of less reliable service; if the amount of load is the same, and the reliability for a portion of load is lower, the rest of the system is either more reliable or requires less capacity to achieve the same reliability.  The net

PDF page 73

30
benefit would depend on the shape and clearing location of the demand curve but would apply to all of the capacity cleared either in the RTO, or just the LDA if prices separated.

63. Total generation and load.  As appropriate for an accurate comparison, the total generation and load were equivalent in both the co-location and comparison cases.

64. Reactive Requirements.  In the Option 4 co-location case, the generator’s reactive capability is unchanged from before the load energized; to the extent that the increase in load identifies necessary facilities such as capacitor banks, the co-location arrangement will pay for these facilities.  Thus, requirements will be met without additional cost to the rest of the system. In the Option 1 comparison case, the total reactive generator capability will remain the same, but the cost of related facilities would be socialized.  The empirical result of whether the incremental cost of the additional facilities, coupled with the increased billing determinants of the increased load, increase or decrease the individual bills of the rest of load.

65. Regulation.  The regulating capability of the system is unchanged in the co-location case.  Any variation in load would be expected to be the same in both cases, however in the co- location case, the load variation occurs behind the generator and is seen as a movement up or down in generator output.  To date, PJM has not indicated that the regulation requirements for the system would change for the co-location case.35  Thus, regulation costs for the rest of the system load would be the same in the comparison and co-location cases.

66. Black Start.  There should be no differences, or only beneficial improvements for the black start process (with no costs to other customers) between the Option 4 co-location case and Option 1 as the comparison case.  As there are no related billing determinants for the co-located

35 It has been reported that there have been common mode outages of data center loads.  This could change total regulation requirements.  But in a proper comparison, as noted above, the loads and the resulting changes would be the same in both cases.

PDF page 74

31
load, there would be no change in any charges to the rest of the system load between the two cases.  Many parties have asserted that co-located load receives comparable benefits to network load from black start and thus should pay for this type of service.  However, I have not seen any technical justification for this assertion.  In my view, the ability to isolate large loads so that they cannot draw power from the system would act to sectionalize the grid and make black start more manageable.  I am not aware of any work done by PJM or others to quantify this benefit to the rest of load, so the proper comparison at this point would be that there are no differences.

67. Capacity Interconnection Rights/Transmission Rights.  If the generator in the Option 4 co-location case sells or releases the CIRs in the same quantity as the firm co-located load, there is no difference between the Option 4 co-located case and the Option 1 comparison case. In the Option 1 comparison case, there would be the same potential CIRs that now exist because the generator would still be entirely a Capacity Resource with the CIRs.  In the Option 4 co- location case, the firm load on the system is reduced compared to Option 1, and the CIRs held by the generator are reduced by the same amount.  By releasing their CIRs, those CIRs would become available to new generation to purchase.  Furthermore, in the Option 4 co-location case, the addition of facilities (the necessary study additions), may very likely result in new CIRs that will be available in the same area.  These additional CIRs will be created in both the co-located and comparison case, but the only difference is who is paying for these upgrades.  In the Option 1 comparison case, these types of costs are socialized and any incremental CIRs are given away based on queue priorities, with IARRs effectively just increasing the feasible set of rights available under the current allocation process.  This type of comparison is complicated, as part of the incremental CIR availability may be related to an increase of load in a generation pocket, and not to any transmission related facilities.

PDF page 75

32
68. Most of these findings are also reiterated in the following Table 5, which specifically compares Options 1 and 4 as it relates to the overall rate impacts as dictated by the billing determinants in PJM’s current rate design.

Table 5:  Comparison of Rate Impacts of Option 4 versus Option 1
Category
PJM OPTION 4
Isolated New Load
Dedicated Existing Generation
COMPARISON CASE
(PJM OPTION 1)
New Load Included
NITS
payments
The total cost, number and total
load of customers making NITS
payments will remain the same.
Billing determinants for this load
remain the same, and no new
socialized costs are added to
transmission rate base. Thus,
individual charges to current
customers will not change from
prior to the co-location.
Total NITS related costs may increase.
The specifics depend on the total costs
socialize for upgrades needed for the new
load.  The amount of load taking NITS
service will also increase and the increased
NITS charges will be spread across a larger
amount of coincident peak load.  The net
impact on customer rates is the result of the
two offsetting effects and could result in
either a net increase or decrease in unit
charges to existing customers.
Interconnection
Costs

The co-located load/generator
pay all interconnection costs:
$200 million in the case
assumption.
$200 million,36 of which $180 million may
be socialized to existing customers and rate
based (socialized costs approximated at
90%).37

Total costs increase, unit cost changes
depend on the level of additional billing
determinants added.
Transmission
enhancements
All necessary enhancements to
bring the co-located load online
are paid for by the supplying
generator and co-located load.
No change in total costs borne
Enhancement costs are socialized as well
as some portion of interconnection.  There
would be an increase in billing
determinants due to the increased load on
the system. The net effect will depend on

36 The dollar figure is an estimate based on recent load additions.  See Transmission Expansion Advisory Committee: PPL Supplemental Projects, at 4 (Apr. 2, 2024), https://www.pjm.com/-/media/committees- groups/committees/teac/2024/20240402/20240402-item-08---ppl-supplemental-projects.ashx (identifying $244 million supplemental project); see also Transmission Expansion Advisory Committee: AEP Supplemental Projects, at 7 (June 4, 2024), https://www.pjm.com/-/media/committees-groups/committees/teac/2024/20240604/20240604- item-05---aep-supplemental-projects.ashx (identifying $155.69 million supplemental project).
37 In a recent Illinois Commerce Commission docket, ComEd explained that the average cost to interconnect a large load customer is $11,899,297, and the large load customer paid $981,392 on average.  This indicates that the large load customer typically pays under 10% of the total cost to interconnect.  See Commonwealth Edison Company’s Response to Constellation Energy Generation LLC’s Data Request, Ill. Commerce Comm’n, Docket No. 22-0486 (May 30, 2024), https://www.icc.illinois.gov/docket/P2023-0055/documents/352947/files/617782.pdf.

PDF page 76

33
Category
PJM OPTION 4
Isolated New Load
Dedicated Existing Generation
COMPARISON CASE
(PJM OPTION 1)
New Load Included
and unit costs for transmission to
other customers.  An assumed
$30 million upgrade from the
necessary study result.  The
enhancements may create
incremental transmission related
rights for the parties paying for
the upgrades.
the specifics of the size of the new load
and the cost of enhancements.  The case
assumes the same enhancement costs as the
Option 4.  The enhancements may create
incremental transmission related rights and
would be allocated consistent with current
PJM procedures.
Reliability
and planning
reserves
The Fully Isolated Co-Located
Load case is more reliable for
the remainder of the system
because the co-located load
increase is met by the same
amount of generation decrease,
with no adjustment for reserves.
Load is not served by system
resources if co-located
generation is not available.
PJM would need to adjust installed
capacity to reflect the need for additional
planning reserves. Assuming an Installed
Reserve Margin (“IRM”) is approximately
18%38 the 400 MW of additional load
would require approximately 472 MW of
additional capacity for comparable
reliability in terms of the IRM.  This
increases costs to remaining load by ~$95
million NPV
Operating reserves
Current allocation of operating
reserves and synchronized and
non-synchronized reserves is
based on load share at different
times, but in all cases would still
result in a zero allocation to the
co-located load because it is not
taking service from the grid; it is
isolated, and not included in any
load or peak share.  This case
would not increase costs of these
reserves to existing load.  May
be appropriate to allocate some
reserves consistent with existing
cost allocation principles.
If the new load did not change the
operating reserve total charges, these
would now be spread over a larger set of
billing determinants and unit costs should
be lower.  If there were a change in
operating reserve charges the unit costs to
existing load could be higher or lower.
PJM scheduling,
system control and
dispatch control
There is no increase in these
total costs.  Unit costs for
Total costs would remain unchanged, but
unit costs would decrease due to the

38 PJM 2025/2026 Base Residual Auction Report, at 6 (July 30, 2024), https://pjm.com/-/media/markets- ops/rpm/rpm-auction-info/2025-2026/2025-2026-base-residual-auction-report.ashx. Comparisons can similarly be made to Accredited UCAP, Forecast Pool Requirement and Expected Unserved Energy. In this case, the high accreditation for the generation and high load factor use of IRM should closely approximate the Accredited UCAP results.

PDF page 77

34
Category
PJM OPTION 4
Isolated New Load
Dedicated Existing Generation
COMPARISON CASE
(PJM OPTION 1)
New Load Included
existing load would be
unchanged.
increase in billing determinants from the new load.

Physical dispatch of
the system inclusive
of the new load
The nuclear units will run as
usual and total load will be met
in the same manner in the two
cases.

For CC units, they would be
dispatched all the time.
The nuclear units will run as usual and total load will be met in the same manner in the two cases.

For CC units, they would only be
dispatched when economic.
Locational marginal
prices (LMPs)
LMPs will be the same in both
cases assuming the comparison
case load is electrically adjacent to the nuclear interconnection

point to the grid.

As noted, for dispatchable co-
location supply LMPs would be
lower for all prices below the
dispatch price.  PJM has not
estimated these savings.
LMPs will be the same in both cases assuming the comparison case load is electrically adjacent to the nuclear interconnection point to the grid.

As noted, if the supplying generator is dispatchable, prices would be higher for all periods when prices are below the dispatch price of that unit.

Capacity prices
Lower than Option 1.  The
supply curve will shift to the left reflecting the 400 MW reduction

and prices will increase.  But
because of the lack of network
reserves for this load, the
increase would be less than the
comparison case
Higher than Option 4.  The demand curve will shift to the right including both the 400 MW plus reserves and prices will increase.  The increase in prices would be more than in the co-located load case. Total generation

available to serve
total load
Total amount of generation is
unchanged.  All the same
resources are available to serve
the same total load in both cases. Total amount of generation is unchanged. All the same resources are available to serve the same total load in both cases. Reactive power

supply and costs
Total reactive capability from
generators is the same in both
cases.  Costs of any network
upgrades for reactive supply to
address the increased load would
be borne by the co-located load
arrangement.
Total reactive capability from generation would remain the same.  To the extent that the new load requires network

enhancements, these costs would be socialized and related total costs and charges increase.  The unit cost increase would depend on the cost of the

enhancements and change in billing determinants for reactive supply.

PDF page 78

35
Category
PJM OPTION 4
Isolated New Load
Dedicated Existing Generation
COMPARISON CASE
(PJM OPTION 1)
New Load Included
Regulation
If the total amount of regulation
stays the same, unit charges to
existing customers remain
unchanged.  If common mode
load drop increased regulation
requirements, they would
increase by the same amount for
both cases.  However, the Option
4 case would not otherwise pay
for such additional regulation
service.
If total amount of regulation increased, would increase by the same amount for

both cases.  Unit charges would be
expected to decrease reflecting the increase in billing determinants from the new load if the regulation requirement stayed

constant.  The unit cost impact may be an increase or decrease if the regulation

requirement is increased.
Black start
The total cost for black start
should remain unchanged as
well as the unit costs for the rest
of load.  Sectionalizing the new
load by isolation may improve
black start capability at no cost
to other customers.
The total costs for black start should
remain unchanged but the unit cost and
charges to load would decrease based on
the increased load and billing determinants. However, the black start process may be

less flexible than the co-location case as the new load cannot be isolated.

Capacity
interconnection
rights (CIRs)
The nuclear unit would have to
sell or release 400 MW of CIRs.
They then would become
available for use by new or
expanded existing generation.  It
is possible that the transmission
enhancements coupled with the
load increase would create new
CIR capability.
The nuclear unit would retain all its CIRs and new load interconnection studies

would include the increased load.  If new CIRs are created by the socialized

enhancements, incremental CIRs are given away for free via the queue.

PJM monitoring
and administration
Total costs would be expected to
stay the same or decrease.  The
unit costs to existing load would
stay the same or slightly
decrease.
Total costs would stay the same and the
unit costs would decrease based on the
increased load and billing determinants.

b. Option 5 Evaluation v Option 1 Comparison Case
69. As described by PJM Option 5 “is the same configuration as Option 4 above, but with the potential for the load to receive back-up service with PJM’s advanced authorization.”39  Given

39 PJM Answer at 15 (emphasis added).

PDF page 79

36
the similarities between Options 4 and 5, there is little difference in the analysis, particularly because the back-up service that Option 5 can take from PJM is conditional and non-firm.  PJM has no obligation to plan for providing this back-up in any manner, nor expend costs beyond those that it would have for PJM Option 4.  One might conclude that the co-located load benefits in some manner from this, but it is difficult to specify exactly what that benefit may be as it is fully conditional on PJM’s determination in a specific incident.  It is irrational to assume PJM would serve such interruptible load to the detriment of firm load.  As commented above, these observations also resolve the debate regarding the ability of a secondary unit to sell its capacity in the market.  So long as PJM has the ability to call the output (curtail the co-located load) when supply is from a unit other than the primary generator, the secondary unit is not differentiated in its obligations from any other Capacity Resource in PJM and can sell its capacity.

70. The reliability of PJM Option 5 is therefore exactly the same as Option 4 and is superior to the Option 1 comparison case when the primary unit is operating.  When the secondary unit is operating, because the load in interruptible, the reliability would be the same as in the comparison case or better.40  The conclusions on comparisons between Option 5 and its comparison case in the other categories discussed above are also the same, except that the Option 5 configuration would pay some transmission and ancillary service charges when pulling from the grid.  This could be analogous to the current type of charges for retail BTMG when the net use exceeds zero.

40 Because the nature of service changes based on the availability of the primary generation unit, it could be argued that the comparison case could change as well when the primary unit is unavailable.  But changing the comparison case to reflect the interruptibility of the co-located load results in the planning reliability being either the same or better in the co-location case.

PDF page 80

37
71. PJM does not explain why this Option is “less preferred.”  Further, PJM suggests that this arrangement could lead to an increase in the coincident peak and thus reserve requirements.  It is unclear why this is the case, given that PJM would decide, at its sole discretion, whether or not to provide additional services.

72. There is one potential source of difference between Options 4 and 5, which is difficult to quantify, but makes little difference, and is eliminated in the proper comparison.  If PJM decided to provide back-up service, it would receive payment for those services through LMP payments. LMPs during that period would be higher than otherwise, but not higher than the proper comparison case.  However, it is difficult to predict this result because it is unknown how often PJM would agree to provide back-up service.  Again, consideration of the right comparison case makes these types of differences disappear.

73. This concludes my affidavit.

PDF page 81

[No extractable text on this page.]

PDF page 82

Roy J. Shanker

Page 1

Attachment B

Resume of
Dr. Roy J. Shanker, PhD

PDF page 83

Roy J. Shanker
Page 2

QUALIFICATIONS
AND
EXPERIENCE OF

DR. ROY J. SHANKER

EDUCATION:

Swarthmore College, Swarthmore, PA
A.B., Physics, 1970

Carnegie-Mellon University, Pittsburgh, PA
Graduate School of Industrial Administration
MSIA Industrial Administration, 1972
Ph.D., Industrial Administration, 1975

Doctoral research in the development of new non-parametric multivariate techniques for data analysis, with applications in business, marketing and finance.

EXPERIENCE:

1981 -
Independent Consultant
Present
P.O. Box 1480

Pebble Beach, CA 93953

Providing management and economic consulting services in
natural resource-related industries, primarily electric
and natural gas utilities.

1979-81        Hagler, Bailly & Company

2301 M Street, N.W.

Washington, D.C.

Principal and a founding partner of the firm; director of electric utility practice area.  The firm conducted economic, financial, and technical management consulting analyses in the natural resource area.

1976-79        Resource Planning Associates, Inc.

1901 L Street, N.W.

Washington, D.C.

PDF page 84

Roy J. Shanker
Page 3
Principal of the firm; management consultant on resource problems, director of the Washington, D.C. utility practice.  Direct supervisor of approximately 20 people.

1973-76        Institute for Defense Analysis

Professional Staff

400 Army-Navy Drive

Arlington, VA

Member of 25 person doctoral level research staff

conducting economic and operations research analyses of military and resource problems.

RELEVANT EXPERIENCE:

2024

270—On behalf of PJM Power Providers. EL24-148-000.  Testimony regarding reliability must run designation and price formation for energy and capacity in the context of the development of the PJM Reliability Pricing Model.

269—On behalf of Constellation Energy Generation LLC, Before the Federal Energy Regulatory Commission Dockets No. ER24-2172-000 Affidavit addressing the proper comparison of impacts of co-located load behind a generator to Network Load or behind the meter generation in the PJM Interconnection markets. Conclusions addressing the specific business configuration of interest.

268—On behalf of Constellation Energy Generation LLC, Before the Federal Energy Regulatory Commission Dockets No. El24-2888 et al. Affidavit addressing the proper comparison of impacts of co-located load behind a generator to Network Load or behind the meter generation in the PJM Interconnection markets. Conclusions addressing the specific business configuration of interest.

267—On behalf of Kiewit Power Constructors. AAA CASE NO. 01-23- 0000-2706. Analyses of the proper comparison of alternatives to estimate damages related to the performance of an electric generator during Winter Storm Elliott.

2023

266—On behalf of the PJM Power Providers. Before the Federal Energy Regulatory Commission. Docket No. EL 23-19-000 and Docket ER23-729

PDF page 85

Roy J. Shanker
Page 4
Affidavit regarding the calculation of the Capacity Emergency Transfer Objective and model properties and how they interact with the Reliability Requirements for a Locational Deliverability Area. Explanation of the role of offer options in degrading information in the Capacity Auctions.

265—On Dr. Shanker’s own behalf. Before the Federal Energy Regulatory Commission, Docket EL23-13. Answer ing statements to intervenors regarding Dr. Shanker’s complaint.

2022

264—On Dr. Shanker’s own behalf. Before the Federal Energy Regulatory Commission, Docket EL23-13. An FPA Section 206 complaint for violating its Tariff via over accreditation of certain Variable Capacity Resoruces.

263—On Dr. Shanker’s own behalf. Before the Federal Energy Regulatory Commission, Docket RM22-14. Comments and reply comments regarding the Notice of Proposed Rulemaking Improvements to Generator Interconnection Procedures and Agreements.

262—On behalf of the Energy Trading Institute. Before the Federal Energy Regulatory Commission, Docket No. ER22-797. Affidavit in support of PJM LLC proposals for modifications to the Auction Revenue Rights/Financial Transmission Rights Market. Preparation of extensive general regulatory and PJM history regarding the formation of such rights over time.

2021

261—On behalf of the PJM Power Producers Group (P3) before the Federal Energy Regulatory Commission Docket No. ER21-2582-000. Affidavit addressing PJM’s proposed modification of the Minimum Offer Price Rule and problems related to the economic justification of the proposed narrowing of the applicability of the rule.

260—On behalf of LS Power Associates L.P. before the Federal Energy Regulatory Commission Docket No. ER21-2043. Affidavit discussing PJM’s revised Effective Load Carrying Capability proposal, its limitations and associated PJM responses to previous comments regarding its initial proposal.

259—On behalf of Indicated Suppliers before the Federal Energy Regulatory Commission in Dockets No. EL19-47-000 and EL19-63-000 comments regarding the PJM proposed modification to its Market Seller

PDF page 86

Roy J. Shanker
Page 5
Offer Cap in the Reliability Planning Model Base Residual Auction for Capacity Resources.

258—Written post conference comments in Federal Energy Commission Docket No. AD21-10. Discussion of the appropriate scope and range of actions for the Commission with respect to the PJM Minimun Offer Price Rate. Similar considerations of the legal scope of the Commission under the Federal Power Act.

257—Invited Speaker before the Federal Energy Energy Regulatory Commission Docket No. AD21-10. Comments before the Commissioners related to the role of subsidies and their impact in terms of the determination of satisfaction of just and reasonable rates under the Federal Power Act.

256—On behalf of LS Power Associates L.P. before the Federal Enegy Regulatory Commission Docket No. ER21-278-001. Affidavit discussing PJM’s Effective Load Carrying Capability proposal, its limitations and associated PJM responses to the Commission’s deficiency notice.

2020

256—On behalf of Cricket Valley Energy Center and Empire Generating Company before the Federal Energy Commission Docket EL21-7. Affidavit addressing the appropriate design of offer price floors in the NYISO Capacity market and associated mitigation and extension of the related rules to the entire state.

255—Invited speaker and written submission before the Federal Energy Regulatory Commission Docket AD20-14. Comments about the legal issues under the Federal Power Act relevant to the implementation of carbon pricing within the wholesale regional transmission organizations.

254—On behalf of Shell Energy North America before the Federal Energy Regulatory Commission, Docket EL20-49. Affidavit addressing bilateral trading of FTRs, associated agreements and the interaction with PJM’s FTR Center reporting and Tariff.

2019

253—On behalf of White Oak Power Constructors before the United States District Court for the Eastern District of Virginia (Richmond Division). Expert report on proper calculation of damages and costs associated with the delay in commercial operations of a new electric power generation facility.

PDF page 87

Roy J. Shanker
Page 6
252—On behalf of the Public Service Companies before the Federal Energy Regulatory Commission, Docket ER19-1486. Affidavit regarding the PJM proposed operating reserve demand curve and other modifications to the reserve products market. Comments on missing elements within the proposal.

251—On behalf of  Indicated Parties, (Calpine, Vestra, and Electric Power Supply Association) before the Federal Energy Regulatory Commission. Docket EL19-63. Affidavit regarding the complaint of the Joint Consumer Advocates regarding PJM’s market seller offer cap, the potential exercise of market power in the capacity market and appropriate market design adjustments under the Capacity Performance paradigm.

250—On behalf of  Indicated Parties, (Calpine, Vestra, and Electric Power Supply Association) before the Federal Energy Regulatory Commission. Docket EL19-47. Affidavit regarding the appropriate adjustment of penalties and the Market Seller Offer Cap within the PJM Capacity Performance paradigm.

249—Supreme Court of the United States. Brief of Energy Economists as Amici Curiae in Support Of Petitioners, Nos. 18-868 & 18-879. Discussion of the impact of subsidies in electric energy market structures and the relationship of the instant cases where a Writ of Certiorari is being sought to previous Supreme Court precedent regarding state actions that effect Federal Energy Regulatory Commission jurisdictional rates.

2018

248—On behalf of PJM Power Providers (P3). Federal Energy Regulatory Commission. Docket EL18-178. Affidavit addressing the appropriate mechanisms to address state/public policy subsidies in the PJM Reliability Planning Model capacity construct. Related comments with respect to a “Clean” Minimum Price Offer Rule.

247—On behalf of Calpine Corporation, Eastern Generating and CPV Power Holdings. Federal Energy Regulatory Commission. Docket No. EL18-169. Affidavit addressing the the establishment of a “clean” Minimum Offer Price Rule for capacity offers in the PJM markets.

246—On behalf of DC Energy LLC and Vitol Inc. Federal Energy Regulatory Commission. Docket No. ER18-1334. Affidavit on the CAISO proposals to limit source and sink pairs in its annual and monthly CRR auctions, as well as comments addressing appropriate coordination of transmission outage and constraint information.

PDF page 88

Roy J. Shanker
Page 7
245—On behalf of the PJM Power Providers. Federal Energy Regulatory Commission Docket No. ER18-1314-000. Affidavit on the PJM proposed mitigation alternatives for addressing out of market subsidies either by Repricing or a modified Minimum Offer Price Rule.

244—On behalf of Joint Commentors. Federal Energy Regulatory Commission Docket EL18-34. Participation in the preparation of comments addressing PJM’s proposed fast start pricing modifications and related price formation issues.

243—On behalf of the PJM Power Providers Group. Federal Energy Regulatory Commission Dockets EL17-32 and EL17-36. Pre-Technical Conference Comments and participant technical conference regarding seasonal capacity products and specific related reliability and forecasting questions from Commission Staff.

(2018) Non-public reports regarding potential market manipulation within ISO NE markets.

2017

242—On behalf of the PSEG Companies. Federal Energy Regulatory Commission Docket No. ER13-535-000. Affidavit regarding

implementation of Court of Appeals remand to FERC of the PJM capacity market Minimum Offer Price Rule.

241-- In the United States Court of Appeals for the Second Circuit. Case No. 17-2654.Co-writer/sponsor of the Brief of Energy Economists as Amici Curiae in Support of Plaintiffs-Appealants-Reversal. Comments regarding the impacts of subsidies on the operation of organized electric markets.

240—In the United States Court of Appeals for the Seventh Circuit. No. 17-2433.Co-writer/sponsor of the Brief of Energy Economists as Amici Curiae in Support of Plaintiffs-Appealants. Comments regarding the impacts of subsidies on the operation of organized electric markets.

239—Invited speaker Federal Energy Regulatory Commission technical session, Docket AD17-11. Comments on the appropriate incorporation of state policies in wholesale electric markets. Submission of post technical session comments.

238—On behalf of PJM Power Providers. Federal Energy Regulatory Commission Dockets EL17-36 and EL17-32  addressing the current Capacity Performance design and criticisms related to the exclusion of an inferior seasonal capacity product. Explanation of how PJM establishes its adequacy targets and whether or not the asserted criticisms were valid.

PDF page 89

Roy J. Shanker
Page 8

2016

237- On behalf of DC Energy, Vitol, Intertia Power, Saracen Energy East. Federal Energy Regulatory Commission Dockets EL16-6, ER16-121. Submission of post technical session statement regarding PJM FTR market “netting” proposal.

236-On behalf of DC Energy, Vitol, Intertia Power, Saracen Energy East. Federal Energy Regulatory Commission Dockets EL16-6, ER16-121. Participant in two Technical Session Panels addressing PJM FTR market design and deficiency in the pending proposal to remove netting in the market settlement.

2015

235- On behalf of the Electric Power Supply Associaton. Federal Energy Regulatory Commission Dockets EL15-70, 71, 72, 82. Affidavit regarding MISO capacity market design and also addressing use of opportunity costs in offers.

234-On behalf of the Electric Power Supply Associaton. Federal Energy Regulatory Commission Dockets EL15-70, 71, 72, 82. Discussant in technical session addressing the establishment of opportunity costs as the basis for capacity reference pricing in the MISO Planning Resource Auctions.

233-On behalf of Dominion Virginia Power. Federal Energy Regulatory Commission Docket ER15-1966. Affidavit regarding changing economic incentives for suppliers associated with the modification of PJM’s calculation of Lost Opportunity Costs.

232-On behalf of “Indicated Suppliers” Federal Energy Regulatory Commission Docket No. EL15-64-000. Testimony addressing the appropriateness of proposed changes to the NYISO buyer side mitigation exemptions.

231-On behalf of Hydro Quebec, Energy Services U.S. Federal Energy Regulatory Commission Docket No. ER15-623. Affidavit addressing the consistent treatment of energy imports under PJM’s Capacity Performance proposal.

230-Before the Supreme Court of the United States, No. 14-995, On Petition for a Writ of Certiorari to the United States Court of Appeals for the Third Circuit. Brief of electrical engineers, scientists and economists as amici curiae in support of petitioners. Metropolitan Edison et al. versus

PDF page 90

Roy J. Shanker
Page 9
Pennsylvania Public Utility Commission et al., http://www.americanbar. org/content/dam/aba/publications/supreme_court_preview/briefs_2015_20 16/14-840_Borlick_et_al.pdf.

2014

229-On behalf of Benton County Wind Farm. United States District Court Southern District of Indiana, Indianapolis Division, Civil Action No. 1:13- cv-1984-SEB-TAB. Expert Reports addressing custom and practice in electric power purchase agreements.

228-On behalf of FirstEnergy Services. FERC Docket EL14-55. Affidavit related to the appropriate characterization of Demand Response in Capacity Markets reflecting performance as the reduction of retail energy consumption.

227-Federal Energy Regulatory Commission. Docket RM10-17. On my own behalf, a statement regarding the ability of the PJM capacity and energy markets to clear in the transition from any determination that demand response would be excluded jurisdictionally from wholesale markets. This could in turn result in a more appropriate representation of retail demand response.

226-Illinois Commerce Commission. Matter: No. 13-0657. On behalf of Commonwealth Edison Company. Testimony regarding the operation of the PJM regional transmission expansion planning process in general and particularly with regards to the preservation of long-term transmission rights (Stage 1A Auction Revenue Rights), and the consequences that occur when such mandated rights are infeasible.

225-Federal Energy Regulatory Commission. Docket ER14-1579. On behalf of H-P Energy. Affidavit explaining importance of property rights and associated contracts within the PJM transmission planning process, particularly as they pertain to Upgrade Construction Service Agreements.

2013

224-Federal Energy Regulatory Commission. Docket No. ER14-456. On behalf of NextEra Energy to analyze a proposed modification to the PJM Tariff allowing for “easily resolved constraints” to be address by transmission upgrades without any analyses of benefits.

223-Federal Energy Regulatory Commission. Docket No. ER14-504. Affidavit on behalf of PJM Power Producers addressing the interaction between the PJM adequacy planning processes and the formulation of

PDF page 91

Roy J. Shanker
Page 10
saturation constraints on Limited and Extended Summer Demand Response products.

222-Federal Energy Regulatory Commission. Docket AD13-7. Invited speaker on the Commission’s technical session regarding capacity markets in RTO’s. Comments addressed basic principles of market design, market features, and consequences of market failures and deviations from design principles.

221-Federal Energy Regulatory Commission. Docket No. EL13-62 on behalf of TC Ravenswood LLC. Two affidavits addressing the treatment of reliability support services agreements and associated capacity in the NYISO capacity market design.

2012

220-Federal Energy Regulatory Commission. Docket No. ER12-715-003. On behalf of First Energy Services Company. An affidavit and testimony addressing the appropriateness of the application of a proposed new MISO tariff provision after the fact to a withdrawing MISO member.

219-Federal Energy Regulatory Commission. Docket ER13-335. On behalf of Hydro Quebec U.S. Affidavit addressing appropriate application of ISO-NE Market Rule 1/ Tariff with respect to the qualification of  new external capacity to participate in the Forward Capacity Market.

218-Federal Energy Regulatory Commission. Docket IN12-4. On behalf of Deutsche Bank Energy Trading. Affidavit regarding a review of specific transactions, related congestion revenue rights, and deficiencies in CAISO tariff implementation during periods when market software produces multiple feasible pricing solutions.

217-Federal Energy Regulatory Commission. Docket No. ER12-715-003. On behalf of FirstEnergy Services Company.  Affidavit regarding implementation of the MISO Tariff with respect to the determination of appropriate exit fees and charges related to certain transmission facilities.

216-Federal Energy Regulatory Commission. Docket No. IN12-11. On behalf of Rumford Paper Company. Affidavit regarding free riding behavior in the design of demand response programs, and its relationship to accusations of market manipulation.

215-Federal Energy Regulatory Commission. Docket No. IN12-10. On behalf of Lincoln Paper and Tissue LLC. Affidavit regarding relationship of demand response behavior and value established in Order 745 to

PDF page 92

Roy J. Shanker
Page 11
claimed market impacts associated with accusations of market manipulation.

214-Federal Energy Regulatory Commission. Docket No. AD12-16-000. On behalf of PJM Power Providers, testimony regarding deliverability of capacity between the MISO and PJM RTO’s and associated basic adequacy planning concepts.

213-United States Court Of Appeals, District of Columbia Circuit. Electric Power Supply Asociation, et al (Petitioners) v. Federal Energy Regulatory Commission et al (Respondents) Nos. 11-1486. Amici Curiae brief regarding the appropriate pricing of demand reduction services in wholesale markets vis a vis the FERC determinations in Order 745.

212-United States Supreme Court. Metropolitan Edison Company and Pennsyvalnia electric Company (Petitioners), Pennsylvania Public Utility Commission (Respondent) (No. 12-4) Amici Curiae brief regarding the nature of physical losses in electric transmission and relationship to proper marginal cost pricing of electric power and the marginal cost of transmission service.

2011

211-Federal Energy Regulatory Commission Docket No. ER12-513-000. On behalf of PJM Power Providers, testimony regarding the establishment of system wide values for the net cost of new entry related to modifications of the Reliability Planning Model.

210-Federal Energy Regulatory Commission Docket No. EL11-56-000, on behalf of First Energy Services. Affidavit regarding the appropriateness of proposed transmission cost allocation of Multi-Value Projects to an exiting member of the Midwest Independent System Operator.

209-Federal Energy Regulatory Commission Docket No. ER11-4081-000, on behalf of “Capacity Suppliers”. Affidavit addressing correct market design elements for Midwest Independent System Operator proposed resource adequacy market.

208-Public Utility Commission of Ohio, Case Nos. 11-346-EL-SSO,11- 348-EL-SSO,Nos. 11-349-EL-AAM, 11-350-EL-AAM, on behalf of First Energy Services. Testimony regarding the interaction between the capacity default rates for retail access under the PJM Fixed Resource Requirement and the PJM Reliability Planning Model valuations.

207-Federal Energy Regulatory Commission Dockets No. ER11-2875, EL11-20, Staff Technical Conference on behalf of PJM Power Providers,

PDF page 93

Roy J. Shanker
Page 12
addressing self supply and the Fixed Resource Requirement elements of PJM’s capacity market design.

206-New Jersey Board of Public Utilities, Docket Number EO11050309 on behalf of PSEG Companies. Affidavit addressing the implications of markets and market design elements, and regulatory actions on the relative risk and trade-offs between capital versus energy intensive generation investments.

205-Federal Energy Regulatory Commission Docket No. ER11-2875. Affidavit and supplemental statement on behalf of PJM Power Providers addressing flaws in the PJM tariff’s Minimum Offer Price Rule regarding new capacity entry and recommendations for tariff revisions.

204-Federal Energy Regulatory Commission Docket No. EL11-20. Affidavit on behalf of PJM Power Providers addressing flaws in the PJM tariff’s Minimum Offer Price Rule regarding new capacity entry.

203-Federal Energy Regulatory Commission  Docket Nos. ER04-449. Affidavit and supplemental statement on behalf of New York Suppliers addressing the appropriate criteria for the establishment of a new capacity zone in the NYISO markets.

2010

202-New Jersey State Assembly and Senate. Statements on behalf of the Competitive Supplier Coalition addressing market power and reliability impacts of proposed legislation, Assembly Bill 3442 and Senate Bill 2381.

201-Federal Energy Reglatory Commission. Docket ER11-2183. Affidavit on behalf of First Energy Services Company addressing default capacity charges for Fixed Resource Requirement participants in the PJM Reliability Pricing Model capacity market design.

200-Federal Energy Regulatory Commission. Docket ER11-2059 Affidavit on behalf of First Energy Services Company addressing deficiencies and computational problems in the  proposed “exit charges” for transmission owners leaving the MISO RTO related to long term transmission rights.

199-Federal Energy Regulatory Commission Docket RM10-17. Invited panelist addressing metrics for cost effectiveness of demand response and associated cost allocations and implications for monopsony power.

198-Federal Energy Regualtory Commission Consolidated Dockets ER10- 787-000, EL10-50-000, and EL10-57-000. Two affidavits on behalf of the

PDF page 94

Roy J. Shanker
Page 13
New England Power Generators Association regarding ISO-NE modified proposals for alternative price rule mitigation and zonal definitions/functions of locational capacity markets.

197-Federal Energy Regulatory Commission Docket No. ER10-2220-000. Affidavit on behalf of the Independent Energy Producers of New York. Addressing rest of state mitigation thresholds and procedures for adjusting thresholds for frequently mitigated units and reliability must run units.

196-Federal Energy Regulatory Commission Docket PA10-1. Affidavit on behalf of Entergy Services related to development of security constrained unit commitment software and its performance.

195-Federal Energy Regulatory Commission Docket No. ER09-1063-004. Testimony on behalf of the PJM Power Providers Group (P3) regarding the proposed shortage pricing mechanism to be implemented in the PJM energy market. Reply comments related to a similar proposal by the independent market monitor.

194-PJM RTO. Statement regarding the impact of the exercise of buyer market power in the PJM RPM/Capacity market. Panel discussant on the issue at the associated Long Term Capacity Market Issues Sympossium.

193-Federal Energy Regulatory Commission Docket No. ER10-787-000. Affidavit on behalf of New England Power Generators Association addressing proper design of the alternative price rules (APR) for the ISO- NE Forward Capacity Auctions. Second affidavit offered in reply. Supplemental affidavit also submitted

192-Federal Energy Regulatory Commission Docket No. RM10-17-000. Affidavit on behalf of New England Power Generators Association addressing proper pricing for demand response compensation in organized wholesale regional transmissiom organizations.

191-Federal Energy Regulatory Commission Docket No. RM10-17-000, Affidavit on my on behalf regarding inconsistent representations made between filings in this docket and contemporaneous materials presented in the PJM stakeholder process.

2009

190-Federal Energy Regulatory Commission Docket No. ER09-1682. Two affidavits on behalf of an un-named party regarding confidential treatment of market data coupled with specific market participant bidding, and associated issues.

PDF page 95

Roy J. Shanker
Page 14
189-American Arbitration Assoication, Case No. 75-198-Y-00042-09 JMLE, on behalf of Rathdrum Power LLC. Report on the operation of specific pricing provision of a tolling power purchase agreement.

188-Federal Energy Regulatory Commission. Docket No. IN06-3-003. Analyses on behalf of Energy Transfer Partners L.P. regarding trading activity in physical and financial natural gas markets.

187-Federal Energy Regulatory Commission. Docket No. ER08-1281- 000. Analyses on behalf of Fortis Energy Trading related to the impacts of loop flow on trading activities and pricing.

186-American Arbitration Association. Report on behalf of PEPCO Energy Services regarding several trading transactions related to the purchase and sale of Installed Capacity under the PJM Reliability Pricing Model.

185-Federal Energy Regulatory Commission Docket No. EL-0-47. Analyses on behalf of HQ Energy services (U.S.) regarding pricing and sale of energy associated with capacity imports into ISO-NE.

184-Federal Energy Regulatory Commission Docket No.  ER04-449 019, Affidavit on behalf of HQ Energy Services (U.S.) regarding the implementation of the consensus deliverability plan for the NYISO, and associated reliability impacts of imports.

183-Federal Energy Regulatory Commission Docket ER09-412-000, ER05-1410-010, EL05-148-010. Affidavit and Reply Affidavit on behalf of PSEG Companies addressing proposed changes to the PJM Reliability Pricing Model and rebuttal related to other parties’ filings.

2008

182-Pennsylvania Public Service Commission. En Banc Public Hearing on "Current and Future Wholesale Electricity Markets", comments regarding the design of PJM wholesale market pricing and state restructuring.

181-Maine Public Utility Commission. Docket No. 2008-156. Testimony on behalf of a consortium of energy producers and suppliers addressing the potential withdrawal of Maine from ISO New England and associated market and supplier response.

180-Federal Energy Regulatory Commission. Docket No. EL08-67-000. Affidavit on behalf of Duke Energy Ohio and Reliant Energy regarding criticisms of the PJM reliability pricing model (RPM) transitional auctions.

PDF page 96

Roy J. Shanker
Page 15

179-Federal Energy Regulatory Commission. Docket AD08-4, on behalf of the PJM Power Providers. Statement and participation in technical session regarding the design and operation of capacity markets, the status of the PJM RPM market and comments regarding additional market design proposals.

178-Federal Energy Regulatory Commission. Docket ER06-456-006, Testimony on behalf of East Coast Power and Long Island Power Authority regarding appropriate cost allocation procedures for merchant transmission facilities within PJM.

2007

177-FERC Docket No. EL07-39-000. Testimony on behalf of Mirant Companies and Entergy Nuclear Power Marketing regarding the operation of the NYISO In-City Capacity market and the associated rules and proposed rule modifications.

176-FERC Dockets: RM07-19-000 and AD07-7-000, filing on behalf of the PJM Power Providers addressing conservation and scarcity pricing issues identified in the Commission’s ANOPR on Competition.

175-FERC Docket No. EL07-67-000. Testimony and reply comments on behalf of Hydro Quebec U.S. regarding the operation of the NYISO TCC market and appropriate bidding and competitive practices in the TCC and Energy markets.

174-FERC Docket Nos. EL06-45-003. Testimony on behalf of El Paso Electric regarding the appropriate interpretation of a bilateral transmission and exchange agreement.

2006

173-United States Bankruptcy Court for the Southern District of New York. Case No. 01-16034 (AJG). Report on Behalf of EPMI regarding the properties and operation of a power purchase agreement.

172-FERC Docket No. EL05-148-000. Testimony regarding the proposed Reliability Pricing Model settlement submitted for the PJM RTO.

171-FERC Docket No. ER06-1474-000, FERC. Testimony on behalf othe PSEG Companies regarding the PJM proposed new policy for including “market efficiency” transmission upgrades in the regional transmission expansion plan.

PDF page 97

Roy J. Shanker
Page 16
170-FERC Docket No. EL05-148-000,  FERC. Participation in Commission technical sessions regarding the PJM proposed Reliability Pricing Model.

169-FERC Docket No. EL05-148-000,  FERC. Comments filed on behalf of six PJM market participants concerning the proposed rules for participation in the PJM Reliability Pricing Model Installed Capacity market, and related rules for opting out of the RPM market.

168-FERC Docket No. ER06-407-000. Testimony on behalf of GSG, regarding interconnection issues for new wind generation facilities within PJM.

2005

167-FERC Docket No. EL05-121-000, Testimony on behalf of several PJM Transmission Owners (Responsible Pricing Alliance)  regarding alternative regional rate designs for transmission service and associated market design issues.

166-FERC Technical Conference of June 16, 2005. (Docket Nos. PL05-7- 000, EL03-236-000, ER04-539-000). Invited participant. Statement regarding the operation of the PJM Capacity market and the proposed new Reliability Pricing Model Market design.

165-American Arbitration Association Nos. 16-198-00206-03 16-198- 002070.On behalf of PG&E Energy Trading. Analyses related to the operation and interpretation of power purchase and sale/tolling agreements and electrical interconnection requirements.

164-Arbitration on behalf of Black Hills Power, Inc. Expert testimony related to a power purchase and sale and energy exchange agreement, as well as FERC criteria related to the applicable code and standards of conduct.

2004

163-Federal Energy Regulatory Commission Docket No. EL03-236-003. Testimony on behalf of Mirant companies relating to PJM proposal for compensation of frequently mitigated generation facilities.

162-Federal Energy Regulatory Commission. Docket No. ER03-563-030. Testimony on behalf of Calpine Energy Services regarding the development of a locational Installed Capacity market and associated generator service obligations for ISO-NE. Supplemental testimony filed 2005.

PDF page 98

Roy J. Shanker
Page 17

161-Federal Energy Regulatory Commission.  Docket No. EL04-135-000. Testimony on behalf on the Unified Plan Supporters regarding implications of using a flow based rate design to allocate embedded costs.

160-Federal Energy Regulatory Commission. Docket No. ER04-1229- 000. Testimony on behalf of EME Companies regarding the allocation and recovery of administrative charges in the NYISO markets.

159-Federal Energy Regulatory Commission. Dockets No. EL01-19-000, No. EL01-19-001, No. EL02-16-000, EL02-16-000. Testimony on behalf of PSE&G Energy Resources and Trade regarding pricing in the New York Independent System Operator energy markets.

158-Federal Energy Regulatory Commission. Invited panelist regarding performance based regulation (PBR)  and wholesale market design. Comments related to the potential role of PBR in transmission expansion, and its interaction with market mechanisms for new transmission.

157-Federal Energy Regulatory Commission. Docket No. ER04-539-000 Testimony on behalf of EME Companies regarding proposed market mitigation in the energy and capacity markets of the Northern Illinois Control Area.

156-Federal Energy Regulatory Commission. Standardization of Generator Interconnection Agreements and Procedures Docket No. RM02- 1-001, Order 2003-A, Affidavit on Behalf of PSEG Companies regarding the modifications on rehearing to interconnection crediting procedures.

155-Federal Energy Regulatory Commission. Dockets ER03-236- 000,ER04-364-000,ER04-367-000,ER04-375-000. Testimony on behalf of the EME Companies regarding proposed market mitigation measures in the Northern Illinois Control Area of PJM.

154-Federal Energy Regulatory Commission. Dockets PL04-2-000, EL03- 236-000. Invited panelist, testimony related to local market power and the appropriate levels of compensation for reliability must run resources.

2003

153-American Arbitration Association. 16 Y 198 00204 03. Report on behalf of Trigen-Cineregy Solutions regarding an energy services agreement related to a cogeneration facility.

152-Federal Energy Regulatory Commission. Docket No. EL03-236-000. Testimony on behalf of EME Companies regarding the PJM proposed

PDF page 99

Roy J. Shanker
Page 18
tariff changes addressing mitigation of local market power and the implementation of a related auction process.

151-Federal Energy Regulatory Commission. Docket No. PA03-12-000. Testimony on behalf of Pepco Holdings Incorporated regarding transmission congestion and related issues in market design in general, and specifically addressing congestion on the Delmarva Peninsula.

150-Federal Energy Regulatory Commission. Docket Nos. ER03-262-007, Affidavit on behalf of EME Companies regarding the cost benefit analysis of the operation of an expanded PJM including Commonwealth Edison.

149-Supreme Court of the State of New York, Index No. 601505/01. Report on behalf of Trigen-Syracuse Energy Corporation regarding energy trading and sales agreements and the operation of the New York Independent System Operator.

148-Federal Energy Regulatory Commission. Docket No. ER03-262-000. Affidavit on behalf of the EME Companies regarding the issues associated with the integration of the Commonwealth Edison Company into PJM.

147-Federal Energy Regulatory Commission. Docket No. ER03-690-000. Affidavit on behalf of Hydro Quebec US regarding New York ISO market rules at external generator proxy buses when such buses are deemed non- competitive.

146-Federal Energy Regulatory Commission. Docket RT01-2-006,007. Affidavit on behalf of the PSEG Companies regarding the PJM Regional Transmission Expansion Planning Protocol, and proper incentives and structure for merchant transmission expansion.

145-Federal Energy Regulatory Commission. Docket No. ER03-406-000. Affidavit on behalf of seven PJM Stakeholders addressing the appropriateness of the proposed new Auction Revenue Rights/Financial Transmission Rights process to be implemented by the PJM ISO.

144-Federal Energy Regulatory Commission. Docket No. ER01-2998- 002. Testimony on behalf of Pacific Gas and Electric Company related to the cause and allocation of transmission congestion charges.

143-Federal Energy Regulatory Commission. Docket No. RM01-12-000. On behalf of six different companies including both independent generators, integrated utilities and distribution companies comments on the proposed resource adequacy requirements of the Standard Market Design.

PDF page 100

Roy J. Shanker
Page 19
142-United States Bankruptcy Court, Northern District of California, San Francisco Division, Case No. 01-30923 DM. On behalf of Pacific Gas and Electric Dr. Shanker presented testimony addressing issues related to transmission congestion, and the proposed FERC SMD and California MD02 market design proposals.

2002

141-Arbitration. Testimony on behalf of AES Ironwood regarding the operation of a tolling agreement and its interaction with PJM market rules.

140-Federal Energy Regulatory Commission. Docket No. RM01-12-000. Dr. Shanker was asked by the three Northeast ISO’s to present a summary of his resource adequacy proposal developed in the Joint Capacity Adequacy Group. This was part of the Standard Market Design NOPR process.

139-Federal Energy Regulatory Commission. Docket No. ER02-456-000. Testimony on behalf of Electric Gen LLC addressing comparability of a contract among affiliates with respect to non-price terms and conditions.

138-Circuit Court for Baltimore City. Case 24-C-01-000234. Testimony on behalf of Baltimore Refuse Energy Systems Company regarding the appropriate implementation and pricing of a power purchase agreement and related Installed Capacity credits.

137-Federal Energy Regulatory Commission. Docket No. RM01-12-000. Comments on the characteristics of capacity adequacy markets and alternative market design systems for implementing capacity adequacy markets.

2001

136-Federal Energy Regulatory Commission.  Docket ER02-456-000. Testimony on behalf of Electric Gen LLC regarding the terms and conditions of a power sales agreement between PG&E and  Electric Generating Company LLC.

135-Delaware Public Service Commission. Docket 01-194. On behalf of Conectiv et al. Testimony relating to the proper calculation of Locational Marginal Prices in the PJM market design, and the function of Fixed Transmission Rights.

134-Federal Energy Regulatory Commission. Docket No. IN01-7-000 On behalf of Exelon Corporation . Testimony relating to the function of Fixed

PDF page 101

Roy J. Shanker
Page 20
Transmission Rights, and associated business strategies in the PJM market system.

133-Federal Energy Regulatory Commission. Docket No. RM01-12-000. Comments on the basic elements of RTO market design and the required market elements.

132-Federal Energy Regulatory Commission. Docket No. RT01-99-000. On behalf of the One RTO Coalition. Affadavit on the computational feasibility of large scale regional transmission organizations and related issues in the PJM and NYISO market design.

131-Arbitration. On behalf of Hydro Quebec. Testimony related to the eligibility of power sales to qualify as Installed Capacitywithin the New York Independent system operator.

130-Virginia State Corporation Commission. Case No. PUE000584. On behalf of the Virginia Independent Power Producers. Testimony related to the proposed restructuring of Dominion Power and its impact on private power contracts.

129-United States District Court, Northern District of Ohio, Eastern Division, Case: 1:00CV1729. On behalf of Federal Energy Sales, Inc. Testimony related to damages in disputed electric energy trading transactions.

128-Federal Energy Regulatory Commission. Docket Number ER01- 2076-000. Testimony on behalf of Aquila Energy Marketing Corp and Edison Mission Marketing and Trading, Inc. relating to the implementation of an Automated Mitigation Procedure by the New York ISO.

2000

127-New York Independent System Operator Board. Statement on behalf of Hydro Quebec, U.S. regarding the implications and impacts of the imposition of a price cap on an operating market system.

126-Federal Energy Regulatory Administration. Docket No. EL00-24-000. Testimony on behalf of Dayton Power and Light Company regarding the proper characterization and computation of regulation and imbalance charges.

125-American Arbitration Association File 71-198-00309-99. Report on behalf of Orange and Rockland Utilities, Inc. regarding the estimation of damages associated with the termination of a power marketing agreement.

PDF page 102

Roy J. Shanker
Page 21

124-Circuit Court, 15th Judicial Circuit, Palm Beach County, Florida. On behalf of Okeelanta and Osceola Power Limted Partnerships et. al. Analyses related to commercial operation provisions of a power purchase agreement.

1999

123-Federal Energy Regulatory Commission. Docket No. ER00-1-000. Testimony on behalf of TransEnergie U.S. related to market power associated with merchant transmission facilities. Also related analyses regarding market based tariff design for merchant transmission facilities.

122-Federal Energy Regulatory Commission. Docket RM99-2-000. Analyses on behalf of Edison Mission Energy relating to the Regional Transmission Organization Notice of Proposed Rulemaking.

121-Federal Energy Regulatory Commission. Docket No. ER99-3508- 000. On behalf of PG&E Energy Trading, analyses associated with the proposed implementation and cutover plan for the New York Independent System Operator.

120-Federal Energy Regulatory Commission. Docket No. EL99-46-000. Comments on behalf of the Electric Power Supply Association relating to the Capacity Benefit Margin.

119-New York Public Service Commission, Case 97-F-1563. Testimony on behalf of Athens Generating Company describing the impacts on pricing and transmission of a new generation facility within the New York Power Pool under the new proposed ISO tariff.

118-JAMS Arbitration Case No. 1220019318 On behalf of Fellows Generation Company. Testimony related to the development of the independent power and qualifying facility industry and related industry practices with respect to transactions between cogeneration facilities and thermal hosts.

117-Court of Common Pleas, Philadelphia County, Pennsylvania. Analyses on behalf of Chase Manhattan Bank and Grays Ferry Cogeneration Partnership related to power purchase agreements and electric utility restructuring.

PDF page 103

Roy J. Shanker
Page 22
1998

116-Virginia State Corporation Commission. Case No. PUE 980463. Testimony on behalf of Appomattax Cogeneration related to the proper implementation of avoided cost methodology.

115-Virginia State Corporation Commission. Case No. PUE980462 Testimony on behalf of Virginia Independent Power Producers related to an applicaton for a certificate for new generation facilities.

114-Federal Energy Regulatory Commission. Analyses related to a number of dockets reflecting amendments to the PJM ISO tariff and Reliability Assurance Agreement.

113-U.S. District Court, Western Oklahoma. CIV96-1595-L. Testimony related to anti-competitive elements of utility rate design and promotional actions.

112-Federal Energy Regulatory Commission Dockets No. EL94-45-001 and QF88-84-006. Analyses related to historic measurement of spot prices for as available energy.

111-Circuit Court, Fourth Judicial Circuit, Duval County, Florida. Analyses related to the proper implementation of a a power purchase agreement and associated calculations of capacity payments. (Testimony 1999)

1997

110-United States District Court for the Eastern District of Virginia, CA No. 3:97CV 231. Analyses of the business and market behavior of Virginia Power with respect to the implementation of wholesale electric power purchase agreements.

109-United States District Court, Southern District of Florida, Case No. 96-594-CIV, Analyses related to anti-competitive practices by an electric utility and related contract matters regarding the appropriate calculation of energy payments.

108-Virginia State Corporation Commission. Case No. PUE960296. Testimony related to the restructuring proposal of Virginia Power and associated stranded cost issues.

107-Federal Energy Regulatory Commission. Dockets No. ER97-1523- 000 and OA97-470-000, Analyses related to the restructuring of the New

PDF page 104

Roy J. Shanker
Page 23
York Power Pool and the implementation of locational marginal cost pricing.

106-Federal Energy Regulatory Commission Dockets No. OA97-261-000 and ER97-1082-000 Analyses and testimony related to the restructuring of the PJM Power Pool and the implementation of locational marginal cost pricing.

105-Missouri Public Service Commission. Case No. ET-97-113. Testimony related to the proper definition and rate design for standby, supplemental and maintenance service for Qualifying facilities.

104-American Arbitration Association. Case 79 Y 199 00070 95. Testimony and analyses related to the proper conditions necessary for the curtailment of Qualifying Facilities and the associated calculations of negative avoided costs.

103-Virginia State Corporation Commission. Case Number PUE960117 Testimony related to proper implementation of the differential revenue requirements methodology for the calculation of avoided costs.

102-New York Public Service Commission. Case 96-E-0897, Analyses related to the restructuring of Consolidated Edison Company of New York and New York Power Pool proposed Independent System Operator and related transmission tariffs.

1996

101-Florida Public Service Commission. Docket No. 950110-EI. Testimony related to the correct calculation of avoided costs using the Value of Deferral methodology and its implementation.

100-Federal Energy Regulatory Commission Dockets No. EL94-45-001 and QF88-84-006.  Testimony and Analyses related to the estimation of historic market rates for electricity in the Virginia Power service territory.

99-Circuit Court of the City of Richmond Case No. LA-2266-4. Analyses related to the incurrence of actual and estimated damages associated with the outages of an electric generation facility.

98-New Hampshire Public Utility Commission, Docket No. DR96-149. Analyses related to the requirements of light loading for the curtailment of Qualifying Facilities,  and the compliance of a utility with such requirements.

PDF page 105

Roy J. Shanker
Page 24
97-State of New York Supreme Court, Index No. 94-1125. Testimony related to system planning criteria and their relationship to contract performance specifications for a purchased power facility.

96-United States District Court for the Western District of Pennsylvania, Civil Action No.  95-0658.  Analyses related to anti-competitive actions of an electric utility with respect to a power purchase agreement.

95-United States District Court for the Northern District of Alabama, Southern Division. Civil Action Number CV-96-PT 0097-S. Affadavit on behalf of TVA and LG&E Power regarding displacement in wholesale power transactions.

1995

94-American Arbitration Association. Arbitration No. 14 198 012795 H/K. Report concerning the correct measurement of savings resulting from a commercial  building cogeneration system and associated contract compensation issues.

93-Circuit Court City of Richmond. Law No. LX-2859-1. Analyses related to IPP contract structure and interpretation regarding plant compensation under different operating conditions.

92-Federal Energy Regulatory Commission. Case EL95-28-000. Affidavit concerning the provisions of the FERC regulations related to the Public Utility Regulatory Policies Act of 1978,  and relationship of estimated avoided cost to traditional rate based recovery of utility investment.

91-New York Public Service Commission, Case 95-E-0172, Testimony on the correct design of standby, maintenance and supplemental  service rates for qualifying facilities.

90-Florida Public Service Commission, Docket No. 941101-EQ. Testimony related to the proper analyses and procedures related to the curtailment of purchases from Qualifying Facilities under Florida and FERC regulations.

89-Federal Energy Regulatory Commission, Dockets ER95-267-000 and EL95-25-000. Testimony related to the proper evaluation of generation expansion alternatives.

1994

88-American Arbitration Association, Case Number 11 Y198 00352 94 Analyses related to contract provisions for milestones and commercial

PDF page 106

Roy J. Shanker
Page 25
operation date and associated termination and damages related to the construction  of a NUG facility.

87-United States District Court, Middle District Florida, Case No. 94-303 Civ-Orl-18. Analyses related to contract pricing interpretation other contract matters in a power purchase agreement  between a qualifying facility and Florida Power Corporation.

86-Florida Public Service Commission Docket 94037-EQ. Analyses related to a contract dispute between Orlando Power Generation and Florida Power Corporation.

85-Florida Public Service Commission Docket 941101-EQ.  Testimony and analyses of the proper procedures for the determination and measurement for the need to curtail purchases from qualifying facilities.

84-New York Public Service Commission Case 93-E-0272, Testimony regarding PURPA policy considerations and the status of services provided to the generation and consuming elements of a qualifying facility.

83-Circuit Court for the City of Richmond. Case Number LW 730-4. Analyses of the historic avoided costs of Virginia Power, related procedures and fixed fuel transportation rate design.

82-New York Public Service Commission, Case 93-E-0958 Analyses of Stand-by, Supplementary and Maintenance Rates of Niagara Mohawk Power Corporation for Qualifying Facilities .

81-New York Public Service Commission, Case 94-E-0098. Analyses of cost of service and rate design  of Niagara Mohawk Power Corporation.

80-American Arbitration Association, Case 55-198-0198-93, Arbitrator in contract dispute regarding the commercial operation date of a qualifying small power generation facility.

1993

79-U.S. District Court, Southern District of New York Case 92 Civ 5755. Analyses of contract provisions and associated commercial terms and conditions of power purchase agreements between an independent power producer and Orange and Rockland Utilities.

78-State Corporation Commission, Virginia. Case No. PUE920041. Testimony related to the appropriate evaluation of historic avoided costs in Virginia and the inclusion of gross receipt taxes.

PDF page 107

Roy J. Shanker
Page 26

77-Federal Energy Regulatory Commission. Docket ER93-323-000. Evaluations and analyses related to the financial and regulatory status of a cogeneration facility.

76-Federal Energy Regulatory Commission. Docket EL93-45-000; Docket QF83-248-002. Analyses related to the qualifying status of cogeneration facility.

75-Circuit Court of the Eleventh Judicial Circuit, Dade County, Florida. Case No. 92-08605-CA-06.  Analyses related to compliance with electric and thermal energy purchase agreements. Damage analyses and testimony.

74-Board of Regulatory Commissioners, State of New Jersey. Docket EM 91010067. Testimony regarding the revised GPU/Duquesne 500 MW power sales agreement and associated transmission line.

73-State of North Carolina Utilities Commission. Docket No. E-100 Sub
67. Testimony in the consideration of rate making standards pursuant to Section 712 of the Energy Policy Act of 1992.

72-State of New York Public Service Commission. Cases 88-E-081 and 92-E-0814. Testimony regarding appropriate procedures for the determination of the need for curtailment of qualifying facilities and associated proper production cost modeling and measurement.

71-Pennsylvania Public Utility Commission. Docket No. A-110300f051. Testimony regarding the prudence of the revised GPU/Duquesne 500 MW power sales agreement and associated transmission line.

1992

70-Pennsylvania Public Service Commission. Dockets No. P-870235,C- 913318,P-910515,C-913764. Testimony regarding the calculation of avoided costs for GPU/Penelec.

69-Public Service Commission of Maryland. Case No. 8413,8346. Testimony on the appropriate avoided costs for Pepco, and appropriate procedures for contract negotiation.

1991
68-Board of Regulatory Commissioners, State of New Jersey. Docket EM- 91010067. Testimony regarding the planned purchase of 500 MW by GPU from Duquesne Light Company.

PDF page 108

Roy J. Shanker
Page 27
67-Public Service Commission of Wisconsin. Docket 05-EP-6. State Advance Plan. Testimony on the calculation of avoided costs and the structuring of payments to qualifying facilities.

66-State Corporation Commission, Virginia. Case No. PUE910033. Testimony on class rate of return and rate design for delivery point service. Northern Virginia Electric Cooperative.

65-State Corporation Commission, Virginia. Case No. PUE910048 Testimony on proper data and modeling procedures to be used in the evaluation of the annual Virginia Power fuel factor.

64-State Corporation Commission, Virginia. Case No. PUE910035. Evaluation of the differential revenue requirements method for the calculation of avoided costs.

63-Public Service Commission of Maryland. Case Number 8241 Phase II. Testimony related to the proper determination of avoided costs for Baltimore Gas and Electric.

62-Public Service Commission of Maryland. Case Number 8315. Evaluation of the system expansion planning methodology and the associated impacts on marginal costs and rate design, PEPCO.

1990

61-Public Utility Commission, State of California, Application 90-12-064. Analyses related to the contractual obligations between San Diego Gas and Electric and a proposed QF.

60-Montana Public Service Commission. Docket 90.1.1 Testimony and analyses related to natural gas transportation, services and rates.

59-State Corporation Commission, Virginia. Case No. PUE890075. Testimony on the calculation of full avoided costs via the differential revenue requirements methodology.

58-District of Columbia Public Service Commission. Formal Case 834 Phase II. Analyses and development of demand side management programs and least cost planning for Washington Gas Light.

57-State Corporation Commission, Virginia. Case No. PUE890076. Analyses related to administratively set avoided costs. Determination of optimal expansion plans for Virginia Power.

PDF page 109

Roy J. Shanker
Page 28
56-State Corporation Commission, Virginia. Case No. PUE900052. Analyses supporting arbitration of a power purchase agreement with Virginia Power. Determination of expansion plan and avoided costs.

55-Public Service Commission of Maryland. Case Number 8251. Analyses of system expansion planning models and marginal cost rate design for PEPCO.

54-State Corporation Commission, Virginia. Case No. PUE900054. Evaluation of fuel factor application and short term avoided costs.

53-Federal Energy Regulatory Commission. Northeast Utilities Service Company Docket Nos. EC90-10-000, ER90-143-000, ER90-144- 000,ER90-145-000 and El90-9-000. Analyses of the implications of Northeast Utilities and Public Service Company of New Hampshire merger on electric supply and pricing.

52-Public Service Commission of Maryland. Re: Southern Maryland Electric Cooperative Inc. Contract with Advanced Power Systems, Inc. and PEPCO.

51-Puerto Rico Electric Power Authority, Office of the Governor of Puerto Rico. Independent evaluation for PREPA of avoided costs and the evaluation of competing QF's.

50-State Corporation Commission, Virginia. Case No. PUE890041. Testimony on the proper determination of avoided costs with respect to Old Dominion Electric Cooperative.

1989

49-Oklahoma Corporation Commission.  Case Number  PUD-000586. Analyses related to system planning and calculation of avoided costs for Public Service of Oklahoma.

48-Virginia State Corporation Commission.  Case  Number PUE890007. Testimony relating to the proper determination of avoided costs to the certification evaluation of new generation facilities.

47-Federal Energy Regulatory Commission.  Docket RP85-50. Analyses of the gas transportation rates, terms and conditions filed by Florida Gas Transmission.

46-Circuit Court of the Fifth Judicial Circuit, Dade County, Florida.  Case No. 88-48187.  Analyses related to compliance with electric and thermal energy purchase agreements.

PDF page 110

Roy J. Shanker
Page 29

45-Florida Public Service Commission.  Docket 880004-EU. Analysis of state wide expansion planning procedures and associated avoided unit.

1988

44-Virginia State Corporation Commission.  Case No. PUE870081. Testimony on the implementation of the differential revenue requirements avoided costmethodology recommended by the SCC Task Force.

43-Virginia State Corporation Commission.  Case No. PUE880014. Testimony on the design and level of standby, maintenance and supplemental power rates for qualifying facilities.

42-Virginia State Corporation Commission.  Case No. PUE99038. Testimony on the natural gas transportation rate design and service provisions.

41-Montana Public Service Commission.  Docket 87.8.38. Testimony on Natural Gas Transmission Rate Design and Service Provisions.

40-Oklahoma Corporation Commission.  Cause Pud No. 00345. Testimony on estimation and level of avoided cost payments for qualifying facilities.

39-Florida Public Service Commission.  Docket No.8700197-EI. Testimony on the methodology for establishing non-firm load service levels.

38-Arizona Corporation Commission.  Docket No. U-1551-86-300. Analysis of cost-of-service studies and related terms and conditions for material gas transportation rates.

1987

37-Virginia State Corporation Commission.  Case No. PUE870028. Analysis of Virginia Power fuel factorapplication and relationship to avoided costs.

36-District of Columbia Public Service Commission.  Formal Case No. 834 Phase II.  Analysis of the theory and empirical basis for establishing cost effectiveness of natural gas conservation programs.

35-Virginia State Corporation Commission.  Case No. PUE860058. Testimony on the relationship of small power producers and cogenerators to the need for power and new generation facilities.

PDF page 111

Roy J. Shanker
Page 30

34-Virginia State Corporation Commission.  Case No. PUE870025. Testimony addressing the proper design of rates for standby, maintenance and supplement power sales to cogenerators.

33-Florida Public Service Commission.  Docket No. 860004 EU. Testimony in the 1986 annual planning hearing on proper system expansion planning procedures.

1986

32-Florida Public Service Commission.  Docket No. 860001 EI-E. Testimony on the proper methodology for the estimation of avoided O&M costs.

31-Florida Public Service Commission.  Docket No. 860786-EI. Testimony on the proper economic analysis for the evaluation of self- service wheeling.

30-U.S. Bankruptcy Court, District of Ohio.  Testimony on capabilities to develop and operate wood-fired qualifying facility.

29-Public Utility Commission, New Hampshire Docket No. DR-86-41. Testimony on pricing and contract terms for power purchase agreement between utility and QFs. (Settlement Negotiations)

28-Florida Public Service Commission, Docket No. 850673-EU. Testimony on generic issues related to the design of standby rates for qualifying facilities.

27-Virginia State Corporation Commission.  Case No. 860024. Generic hearing on natural gas transportation rate design and tariff terms and conditions.

26-Virginia State Corporation Commission. Commonwealth Gas Pipeline Corporation.  Case No. 850052. Testimony on natural gas transportation rate design and tariff terms and conditions.

25-Bonneville Power Administration.  Case No. VI86. Testimony on the proposed Variable Industrial Power Rate for Aluminum Smelters.

24-Virginia Power.  Case No. PUE860011.  Testimony on the proper ex post facto valuation of avoided power costs for qualifying facilities.

PDF page 112

Roy J. Shanker
Page 31
23-Florida Public Service Commission.  Docket No. 850004 EU. Testimony on proper analytic procedures for developing a statewide generation expansion plan and associated avoided unit.

1985

22-Virginia Natural Gas.  Docket No. 85-0036.  Testimony and cost of service procedures and rate design for natural gas transportation service.

21-Arkansas Louisiana Gas.  Louisiana Docket No. U-16534. Testimony on proper cost of service procedures and rate design for natural gas service.

20-Connecticut Light and Power.  Docket No. 85-08-08.
Assist in the development of testimony for industrial natural gas transportation rates.

19-Oklahoma Gas and Electric.  Cause 29727.  Testimony and system operations and the development of avoided cost measurements as the basis for rates to qualifying facilities.

18-Florida Public Service Commission.  Docket No. 840399EU. Testimony on self-service wheeling and business arrangements for qualifying facilities.

17-Virginia Electric and Power Company.  General Rate application No. PUE840071.  Testimony on proper rate design procedures and computations for development of supplemental, maintenance and standby service for cogenerators.

16-Virginia Electric and Power Company.  Fuel Factor
Proceeding No. PUE850001.  Testimony on the proper use of the PROMOD model and associated procedures in setting avoided cost energy rates for cogenerators.

15-New York State Public Service Commission.  Case No. 28962. Development of the use of multi-area PROMOD models to estimate avoided energy costs for six private utilities in New York State.

14-Vermont Rate Hearings on Payments to Small Power Producers.  Case No. 4933.  Testimony on proper assumptions, procedures and analysis for the development of avoided cost rates.

PDF page 113

Roy J. Shanker
Page 32
1984

13-Northern Virginia Electric Cooperative.  Case No. PUE840041. Testimony on class cost-of-serviceprocedures, class rate of return and rate design.

12-BPA 1985 Wholesale Rate Proceedings.  Analysis of Power 1985 Rate Directives.  Testimony on theory and implementation of marginal cost rate design.

11-Virginia Electric Power Company.  Application to Revise Rate Schedule 19 -- Power Purchases from Cogeneration and Small Power Production Qualifying Facilities.  Case No. PUE830067.  Testimony on proper PROMOD  modeling procedures for power purchases and

properties of PROMOD model.

10-Northern Virginia Electric Cooperative.  Case No. PUE840041. Testimony on class cost-of-service procedures, class rate of return and rate design.

9-BPA 1985 Wholesale Rate Proceedings.  Analysis of Power 1985 Rate Directives.  Testimony on the theory and implementation of marginal cost rate design, financial performance of BPA; interactions between rate design, demand, system expansion and operation.

1983

8-Northern Virginia Electric Cooperative.  Case No. PUE830040. Testimony on class cost-of-service procedures, class rate of return and rate design.

7-Vermont Rate Hearings to Small Power Producers.  No.4804. Testimony on proper use and application of production costing analyses to the estimation of avoided costs.

6-BPA Wholesale Rate Proceedings.  Testimony on the theory and implementation of marginal cost rate design; financial performance of BPA; interactions between rate design, demand, system expansion and operation.

5-Idaho Power Company, PUC-U-1006-185.  Analysis of system
planning/production costing model play of hydro regulation and associated energy costs.

PDF page 114

Roy J. Shanker
Page 33
1982

4-Generic Conservation Proceedings, New York State.  Case No. 18223. Testimony on the economic criteria for the evaluation of conservation activities; impacts on utility financial performance and rate design.

3-PEPCO, Washington Gas Light.  DCPSC-743.  Financial evaluation of conservation activities; procedures for cost classification, allocation; rate design.

2-PEPCO, Maryland PSC Case Nos. 7597-I, 7597-II, and 7652. Testimony on class rates of return, cost classification and allocation, power pool operations and sales.

1981

1-Pacific Gas and Electric.  California PSC Case No. 60153.  Testimony on rate design; class cost-of-service and rate of return.

Previous testimony before the District of Columbia
Public Service Commission, Maryland PSC, New York Public Service Commission, FERC; Economic Regulatory Administration