EL25-49-000 · 2025-04-23 · Vistra Corp.

Comments of Vistra Corp

Text extracted from the eLibrary original (SHA-256 a6500470c421fd3c…). Download the original from the official source.

Contents · 22 sections
  1. I. Summary of Proposal p. 8
  2. II. Background p. 9
  3. III. PJM’s Tariff is Unjust and Unreasonable and Unduly Discriminatory p. 11
  4. A. It Would be Unjust and Unreasonable and Unduly Discriminatory and p. 13
  5. B. PJM’s Recent Tariff Administration Demonstrates that the Tariff Lacks p. 19
  6. IV. FERC Must Direct a Replacement Rate to Remedy the Deficiencies in PJM’s Tariff p. 22
  7. A. Only A Few Narrow Elements of the Tariff Require Further Clarity p. 22
  8. B. Alternatively, Applying BTMG Netting Rules to Behind-the-Meter Load Would p. 31
  9. V. In General, the Necessary Study Rules Remain Just and Reasonable p. 33
  10. VI. PJM’s Answer Highlighted Additional Issues that the Commission Should Explore But p. 35
  11. A. The Commission Should Encourage PJM to Engage with Stakeholders to Explore p. 35
  12. B. There is a Regulatory Gap for Front-of-the-Meter Load Interconnection to the p. 36
  13. VII. Conclusion p. 39
  14. Attachment A p. 44
  15. I. Qualifications and Purpose of Affidavit p. 45
  16. II. Summary of Conclusions and Recommendations p. 46
  17. III. Co-Location is Not New p. 50
  18. IV. Rate Design, Use, Cost Causality, Billing Determinants p. 51
  19. V. The Current Tariff Does Not Prohibit Behind-the-Meter Co-Location p. 54
  20. VI. PJM's Answer Distorts Existing Option 3 (BTMG) p. 57
  21. VII. PJM’s Answer Offers No Coherent Way to Identify or Evaluate the Various Co- p. 62
  22. Attachment B p. 82

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 81.

Opening text

opening text · Topic match: Connecting load and generation

EL25-49 (filed Mar. 24, 2025) (“PJM Answer”). -3- proceeding.4 This proceeding can and must move quickly toward resolution to provide regulatory certainty by remedying the deficiencies in PJM’s tariff.
Read this passage Filed comments: Connecting load and generation

I. Summary of Proposal

printed heading · Topic match: Connecting load and generation

Specifically, Vistra’s proposed solution includes the following components:  Clarify that transmission owners must cooperate in the necessary study process.  Ensure that co-location configurations pay their fair share by (a) allocating the costs of upgrades identified in the necessary study…
Read this passage Filed comments: Connecting load and generation

II. Background

printed heading · Topic match: Connecting load and generation

EL25-20, at 7-9 (filed Nov. 22, 2024). -10- interconnection (i.e., behind-the-meter co-located load).24 Specifically, the Commission adopted the PJM guidance document’s definition of co-located load, which “refers to end-use customer load that is physically connected to the [generation] facilities…
Read this passage Filed comments: Connecting load and generation

III. PJM’s Tariff is Unjust and Unreasonable and Unduly Discriminatory

printed heading · Topic match: Connecting load and generation

Further, even aside from PJM’s newfound interpretation of its tariff, the record in this proceeding clearly demonstrates that PJM has been unable to administer its tariff to accommodate behind-the-meter co-located load in a just and reasonable and not unduly discriminatory manner.38 As a result, in…
Read this passage Filed comments: Connecting load and generation

A. It Would be Unjust and Unreasonable and Unduly Discriminatory and

printed heading · Topic match: Connecting load and generation

Entities that seek to develop such a configuration must, among other things, (1) negotiate and sign private, bilateral contracts between the load and the generator, (2) submit a request for a necessary study and sign a necessary study agreement, (3) wait for PJM to conduct the study, (4) negotiate…
Read this passage Filed comments: Connecting load and generation

B. PJM’s Recent Tariff Administration Demonstrates that the Tariff Lacks

printed heading · Topic match: Connecting load and generation

PJM’s Recent Tariff Administration Demonstrates that the Tariff Lacks Sufficient Clarity to Accommodate Behind-the-meter Co-located Load As noted above, until PJM filed its Answer in this proceeding, PJM had taken the position that its tariff permitted behind-the-meter co-location.70 However, the…
Read this passage Filed comments: Connecting load and generation

IV. FERC Must Direct a Replacement Rate to Remedy the Deficiencies in PJM’s Tariff

printed heading

FERC Must Direct a Replacement Rate to Remedy the Deficiencies in PJM’s Tariff When FERC finds that PJM’s tariff is unjust and unreasonable and/or unduly discriminatory or preferential, it must set a replacement rate that would render the tariff just and reasonable and not unduly discriminatory or…
Read this passage

A. Only A Few Narrow Elements of the Tariff Require Further Clarity

printed heading · Topic match: Connecting load and generation

We agree that a case can be made for some ancillary service cost allocation, but it must be supported by analysis that the co-location arrangement benefits or contributes to costs for particular ancillary services.95 For example, variances in the co-located load, which are seen by the grid as…
Read this passage Filed comments: Connecting load and generation

B. Alternatively, Applying BTMG Netting Rules to Behind-the-Meter Load Would

printed heading · Topic match: Connecting load and generation

Roy Shanker explains, behind-the-meter co-located load uses the transmission system less than many traditional retail BTMG configurations.123 Oftentimes, BTMG only serves a fraction of the co-located load; furthermore, such configurations can draw power from the grid.
Read this passage Filed comments: Connecting load and generation

V. In General, the Necessary Study Rules Remain Just and Reasonable

printed heading · Topic match: Connecting load and generation

With the minor clarification that transmission owners must cooperate during the necessary study process, the overall structure will work well.129 Vistra agrees with PJM’s defense of the necessary study process.130 This process is well established; PJM has been completing necessary studies to…
Read this passage Filed comments: Connecting load and generation

VI. PJM’s Answer Highlighted Additional Issues that the Commission Should Explore But

printed heading

PJM’s Answer Highlighted Additional Issues that the Commission Should Explore But that Should Not Delay Expeditious Resolution of this Proceeding
Read this passage

A. The Commission Should Encourage PJM to Engage with Stakeholders to Explore

printed heading · Topic match: Reliability and curtailment

Shanker, Options 4 and 5 do not raise unique resource adequacy or reliability concerns; therefore, Options 6-8 are not required to address resource adequacy or reliability.140 These options may nonetheless provide beneficial avenues to facilitate new entry or flexibility.
Read this passage Filed comments: Reliability and curtailment

B. There is a Regulatory Gap for Front-of-the-Meter Load Interconnection to the

printed heading · Topic match: Cost allocation

Shanker Aff. at P 19. -39- transmission system to prevent undue discrimination and ensure that interconnection service is provided in a just and reasonable manner.
Read this passage Filed comments: Cost allocation

VII. Conclusion

printed heading · Topic match: Connecting load and generation

Moreover, PJM’s contention that new, large loads must interconnect through Options 1 or 2 creates a structural bias in favor of transmission-served load and against competitive, bilateral supply arrangements.
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated: April 23, 2025 Washington, D.C. /s/ Sarah Greenberg Sarah Greenberg Wilson Sonsini Goodrich & Rosati 1700 K Street NW Fifth Floor Washington, DC 20006 (202) 431-5231 sgreenberg@wsgr.com 1
Read this passage

Attachment A

printed heading

Shanker, PhD 2 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION AFFIDAVIT OF ROY J.
Read this passage

I. Qualifications and Purpose of Affidavit

printed heading

I have a bachelor’s degree from Swarthmore College and both a master’s degree and a doctorate degree from Carnegie-Mellon University. 2.
Read this passage

II. Summary of Conclusions and Recommendations

printed heading · Topic match: Connecting load and generation

Further, PJM’s new position directly contradicts PJM’s own actions in executing and submitting to the Commission a modified Interconnection Service Agreement, coupled with identified necessary facilities for the proposed Talen/Susquehanna project (Docket ER24-2172), which appeared to be an Option 4…
Read this passage Filed comments: Connecting load and generation

III. Co-Location is Not New

printed heading · Topic match: Connecting load and generation

My previous work history is particularly relevant to the repeated assertions about the “novelty” of the co-located load and generation business paradigms.
Read this passage Filed comments: Connecting load and generation

IV. Rate Design, Use, Cost Causality, Billing Determinants

printed heading · Topic match: Cost allocation

Southwest Power Pool, Inc., 137 FERC ¶ 61,075, at P 20 (2011) (“Under the cost causation principle, ‘it has been traditionally required that all approved rates reflect to some degree the costs actually caused by the customer who must pay them’ . . . the cost allocation mechanism must not be…
Read this passage Filed comments: Cost allocation

V. The Current Tariff Does Not Prohibit Behind-the-Meter Co-Location

printed heading · Topic match: Connecting load and generation

If the generator is an Exempt Wholesale Generator (EWG), then the sale must be at wholesale.12 In those cases, the wholesale buyer would be a Load Serving Entity that, under state law, is permitted to purchase at wholesale and resell at retail.
Read this passage Filed comments: Connecting load and generation

VI. PJM's Answer Distorts Existing Option 3 (BTMG)

printed heading · Topic match: Connecting load and generation

Thus, in order to be considered BtMG, power claimed as BtMG must deliver energy to load without using the Transmission System or any distribution facilities (unless the entity that owns or leases the distribution facilities has consented to such use of the distribution facilities and such consent…
Read this passage Filed comments: Connecting load and generation

VII. PJM’s Answer Offers No Coherent Way to Identify or Evaluate the Various Co-

printed heading · Topic match: Connecting load and generation

As part of this evaluation, I have also included two possible supplying generators: one a must run nuclear unit and the other a dispatchable combined cycle with a $30 per MWh dispatch energy offer.
Read this passage Filed comments: Connecting load and generation

Attachment B

printed heading · Topic match: Reliability and curtailment

Testimony regarding reliability must run designation and price formation for energy and capacity in the context of the development of the PJM Reliability Pricing Model. 269—On behalf of Constellation Energy Generation LLC, Before the Federal Energy Regulatory Commission Dockets No.
Read this passage Filed comments: Reliability and curtailment