EL25-49-000 · 2025-04-23 · Constellation Energy Generation, LLC

Exhibit 1 (Stockton)

PDF page 1

EXHIBIT 1
DECLARATION OF DR. PAUL STOCKTON

PDF page 2

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.

Large Loads Co-Located at Generating Facilities

Constellation Energy Generation, LLC.

v.

PJM Interconnection, L.L.C.
)

)

)
)
)
)
)
Docket No. EL25-49-000

Docket No. AD24-11-000

Docket No. EL25-20-000
      (Consolidated)

THE NATIONAL SECURITY IMPERATIVE FOR ARTIFICIAL INTELLIGENCE: Why the United States Cannot Afford a One- Size Fits All Solution for Powering Data Centers

Declaration of Dr. Paul Stockton, former Assistant Secretary of Defense for Homeland Defense and Americas’ Security Affairs

 April 23, 2025

PDF page 3

1

While broad agreement exists that artificial intelligence (AI) is crucial for US security, that consensus papers over key issues for determining how to connect and power the data centers that provide such AI services.1 In the Federal Energy Regulatory Commission’s (FERC) Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (February 20, 2025),2 FERC calls for assessments of “any national security implications associated with co-location arrangements,” including options for behind-the-meter nuclear power plants that serve data centers.3 This Declaration examines the specific ways in which AI data centers are becoming crucial for US defense in peacetime and war, the implications for co-located power, and broader security requirements for FERC to consider in its proceedings.

In the first round of filings, most of the PJM Interconnection, L.L.C. (PJM) Transmission Owners argued that all load needs to be interconnected to the utility-owned transmission grid, despite the fact that in some areas in PJM there are lengthy delays and even moratoriums on new large load utility interconnections. PJM, for its part, acknowledged its preference for a connection to the transmission grid that it operates, but also identified a number of additional options that could be explored for connecting large loads such as those used to power AI services for the Department of Defense (DOD). It appears that a number of these options may offer advantages in terms of the speed with which such plants can meet surging data center needs, and the resilience of the power supply certain configurations may provide over traditional interconnections.

This Declaration finds that given the extensive and accelerating dependence of US security on AI data centers, FERC must ensure that rules enable the quickest and most resilient options to connect and serve those data center loads, including rules that enable co-location arrangements, or other options to ensure a prompt connection to the transmission system, if that is what the load desires. The entities that own or operate the AI facilities should be given the choice to determine which configuration for interconnecting them is best for their needs, in close consultation with DOD and the other national security agencies that depend on their AI services. Neither FERC, PJM nor individual transmission owners should make that choice for them.

1 This Declaration employs the definition of AI provided by Exec. Order 14179 on AI and as set forth in 15 U.S.C. § 9401(3): AI is “a machine-based system that can, for a given set of human-defined objectives, make predictions, recommendations or decisions influencing real or virtual environments. Artificial intelligence systems use machine- and human-based inputs to (A) perceive real and virtual environments; (B) abstract such perceptions into models through analysis in an automated manner; and (D) use model inference to formulate options for information or action.” The term machine learning means “a set of techniques that can be used to train AI algorithms to improve performance at a task based on data.” 15 U.S.C. § 9401(3). In this Declaration, machine learning is treated as a subcomponent of AI.
2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (February 2025 Order).
3 Id. P 88(f)(vi).

PDF page 4

2
I. ARGUMENT SUMMARY

DOD relies on AI to help execute an immense, and rapidly growing, range of military missions. AI services provided by private sector data centers are crucial for meeting DOD’s requirements. Ensuring that the energy sector can keep pace with that growth, and connect new data centers quickly and provide the power that data centers need to support America’s defense, is especially important as China competes for primacy in AI. Co-locating existing power plants with data centers can often provide such connections and power years faster than interconnecting data centers for grid-provided service. That speed advantage should constitute a key factor in assessing the national security implications of co-location.

The resilience of power for data centers against enemy attack offers an additional security consideration, and one that has thus far been overlooked in proceedings on co-location. DOD uses AI every day to train autonomous drones and conduct other peacetime activities. But if a conflict breaks out in the Taiwan Strait or other region, DOD will rely on AI to support essential combat- related functions, including wartime intelligence analysis and the command, control, and coordination of US forces.

The distinction between data center defense support in peacetime versus war has profound implications for meeting their power requirements. In peacetime, any quick and reliable way to meet growing data center loads will do. In conflict, the US Intelligence Community assesses that China could conduct cyberattacks and potentially physical attacks against the US energy sector and other critical infrastructure systems.4 Given DOD’s dependence on AI data centers for combat support, those centers must have power supplies that are resilient against attacks by China or other potential adversaries.

FERC, the North American Electric Reliability Corporation (NERC), and their industry partners have greatly strengthened the cyber and physical security of the Bulk Power System (BPS). Those efforts improve the resilience of grid-provided power for data centers. They also bolster the resilience of service from co-located nuclear plants, by mitigating threats to the transmission lines those plants need for safe operations. Especially valuable: BPS critical infrastructure protection (CIP) standards make it far more difficult for China to create interconnection-wide blackouts than would otherwise be the case.

4 Office of the Director of Nat’l Intelligence (ODNI), Annual Threat Assessment of the U.S. Intelligence Community, Mar. 2025, p. 11, https://www.dni.gov/index.php/newsroom/reports-publications/reports-publications-2025/4058- 2025-annual-threat-assessment; ODNI, Annual Assessment of the U.S. Intelligence Community, Feb. 6, 2023, p. 10, https://www.dni.gov/files/ODNI/documents/assessments/ATA-2023-Unclassified-Report.pdf (ODNI 2023 Annual Threat Assessment).

PDF page 5

3
However, co-located power can offer significant resilience advantages against lesser (but still highly disruptive) events. Winter Storms Uri and Elliott help illuminate these potential benefits. In both storms, severe cold disrupted supplies of natural gas for power generation, requiring massive load shedding even though transmission systems were largely unaffected.5 Chinese attacks on natural gas pipelines – which do not have the robust physical and cyber security protection standards on par with those applied to the BPS – could create similar disruptions of gas- fired generation. The US Intelligence Community warns that China is specifically targeting gas pipelines for cyberattacks.6 If such attacks require Uri or Elliott-scale load shedding, AI data centers co-located with nuclear plants would have alternative mechanisms available for receiving power precisely when DOD and the Nation need them the most.

II. AI AND THE TRANSFORMATION OF NATIONAL DEFENSE

Secretary of Defense Pete Hegseth emphasizes that AI capabilities are disruptive and vital to DOD’s success in the future, and is prioritizing its use for monitoring cyberspace, countering transnational criminal organizations, testing and evaluating weapons, and other critical missions and support functions.7 Under the Department’s Data, Analytics, and Artificial Intelligence Adoption Strategy, the range of such AI applications is rapidly expanding. The strategy calls for an extensive range of AI applications to “enhance the warfighting capabilities of the Joint Force,” across the continuum “from the boardroom to the battlefield.”8

The scope and accelerating pace of DOD’s uses of AI are astonishing and little recognized beyond the Defense community – except, of course, by the private sector data center owners/operators who provide AI services to the military, including for highly classified missions. Meeting the power requirements for these data centers is crucial so that DOD can 1) train autonomous vehicles and conduct other AI functions in peacetime; 2) help DOD prevail during future conflicts; and 3) counter China’s drive for AI supremacy and its use of AI to help achieve military superiority over the United States.

5 FERC, NERC and Regional Entity Staff Report, Winter Storm Elliott Report: Inquiry into Bulk-Power System Operations During December 2022, Feb. 7, 2023, https://www.ferc.gov/media/winter-storm-elliott-report-inquiry- bulk-power-system-operations-during-december-2022 (FERC/NERC Winter Storm Elliott Report); FERC, NERC and Regional Entity Staff Report, The February 2021 Cold Weather Outages in Texas and the South Central United States, Nov. 16, 2021, https://www.ferc.gov/media/february-2021-cold-weather-outages-texas-and-south-central- united-states-ferc-nerc-and.
6 ODNI 2023 Annual Threat Assessment, p. 10.
7 Brandi Vincent, Trump’s defense secretary nominee pledges to prioritize AI investments, Defense Scoop, Jan. 14, 2025, https://defensescoop.com/2025/01/14/trump-pete-hegseth-defense-secretary-nominee-pledges-prioritize-ai- investments/.
8 DOD, Data, Analytics, and Artificial Intelligence Adoption Strategy, Nov. 2, 2023, p. 5, https://media.defense.gov/2023/Nov/02/2003333300/-1/- 1/1/DOD_DATA_ANALYTICS_AI_ADOPTION_STRATEGY.PDF (DOD Data, Analytics, and AI Strategy).

PDF page 6

4

A. Peacetime Defense Support

AI is now crucial for DOD efforts to help America prevail in future conflicts – and, even better, deter Chinese and other attacks on the US and its security partners in Asia and beyond. Prime examples of AI applications with significant power requirements include:

Autonomous system training. AI-controlled drones are not born smart. Their ability to dogfight and perform other missions depends on using extensive data sets (comprised of real world and simulated scenarios) to teach AI algorithms to autonomously navigate, identify targets, make tactical decisions, and react to adversary aircraft behavior. DOD and its industry partners continuously update these data sets to account for results of autonomous flights, evolving assessments of “wingman” requirements to support manned aircraft, and threat data.9 Massive AI training activities will also be required for the many thousands of air, sea and land-based autonomous vehicles that DOD will soon be deploying.10

Maintenance. At the opposite end of the glamour spectrum lies maintenance – mundane yet absolutely vital to keep drones and all other US weapons and platforms ready for war. Data center owners and operators are providing AI services to the armed forces to enable predictive maintenance. In particular, these solutions use AI algorithms and data analytics tools to monitor operations, detect anomalies, and predict possible defects or breakdowns in equipment before they happen.11

9 Training autonomous systems is a key focus of the DOD’s Defense Innovation Unit and the Pentagon’s Chief Digital and Artificial Intelligence Office (CDAO). Jon Harper, Pentagon Contemplating AI Hub for Replicator Initiative; Hill briefings Underway, DefenseScoop, Jan. 24, 2024, https://defensescoop.com/2024/01/24/replicator- ai-hub-cdao-lawmaker-briefings-aditi-kumar/. On training the Air Force’s unmanned Collaborative Combat Aircraft to serve as “loyal wingmen” that will fly alongside crewed fighters, see Chris Gordon, America’s First Unmanned Fighters are Here: YFQ-42 and YFQ-44, Air & Space Forces Magazine, Mar. 3, 2025, https://www.airandspaceforces.com/americas-first-unmanned-fighters-yfq-42-yfq-44/.
10 DOD, Defense Innovation Official Says Replicator Initiative Remains on Track, Jan. 26, 2024, https://www.defense.gov/News/News-Stories/Article/Article/3657609/defense-innovation-official-says-replicator- initiative-remains-on-track/; Admiral Steve Koehler, Commander, U.S. Pacific Fleet, West 2025 Address, Jan. 28, 2025, https://www.cpf.navy.mil/Newsroom/News/Article/4048491/west-2025-keynote-address/DOD; DOD, Deputy Secretary of Defense Hicks Announces First Tranche of Replicator Capabilities Focused on All Domain Attritable Autonomous Systems, May 6, 2024, https://www.defense.gov/News/Releases/Release/Article/3765644/deputy- secretary-of-defense-hicks-announces-first-tranche-of-replicator-capabil/; Congressional Research Service, The Army’s Robotic Combat Vehicle (RCV) Program, Jan. 16, 2025, https://crsreports.congress.gov/product/pdf/IF/IF11876/13.
11 See, e.g., Liz Martin, Amazon Web Services (AWS), The U.S. Air Force Improves Aircraft Readiness with AI and Predictive Maintenance Solutions, Dec. 14, 2023, https://aws.amazon.com/blogs/publicsector/the-us-air-force- improves-aircraft-readiness-with-ai-and-predictive-maintenance-solutions/.

PDF page 7

5
Defense Manufacturing and the Defense Industrial Base. The examples of peacetime AI applications highlighted above primarily focus on DOD activities. However, the DOD makes very few of its own weapons. It depends on the defense industrial base (DIB) to manufacture products for national defense. With DOD’s support, defense companies are rapidly adopting AI tools to design, develop, and produce the next generation of US weaponry. Especially important, the DOD Office of Industrial Base Resilience is driving the integration of AI into defense systems, and is collaborating with the DIB to rapidly adopt AI for defense applications and maintain the Nation’s tactical advantage.12 The DIB’s adoption of AI drastically increases the total defense-related uses of data centers. More than 100,000 DIB companies and their subcontractors perform under contract to the DOD.13

Defense Intelligence. Project Maven exemplifies the emerging value of AI for intelligence applications. Maven provides image-processing AI capabilities that have become some of the military’s most in-demand tools for intelligence and targeting. In US Central Command alone, 13,000 Maven accounts are already in frequent use. The National Geospatial-Intelligence Agency (NGA) now plans to expand its total user base ten-fold. The problem, according to NGA director Vice Admiral Frank Whitworth: the explosive growth in computer requirements to operate intelligence-related AI functions.14 Of course, these computational requirements (and the electricity loads they require) are greater still if we include the broader intelligence community essential for national security, including the booming uses of AI by the Central Intelligence Agency.15

B. Combat Support in Future Conflicts

AI is driving a tidal wave of change in how DOD will operate in future conflicts. Those changes will greatly improve our warfighting capabilities, but also heighten why our adversaries (China in particular) will gain by disrupting electric service to US data centers. Key AI-enabled advances critical to supporting combat activities include:

12 DOD, Defense Industrial Base Adoption of Artificial Intelligence for Defense Applications; Notice of Availability, 89 Fed. Reg. 44,964, May 22, 2024, https://www.federalregister.gov/documents/2024/05/22/2024- 11195/defense-industrial-base-adoption-of-artificial-intelligence-for-defense-applications-notice-of.
13 Cybersecurity and Critical Infrastructure Agency (CISA), The Defense Industrial Base Sector, https://www.cisa.gov/topics/critical-infrastructure-security-and-resilience/critical-infrastructure-sectors/defense- industrial-base- sector#:~:text=The%20Defense%20Industrial%20Base%20partnership,Department%20of%20Defense%2C%20and %20government%2D.
14 Sydney Freedberg, Jr., ‘Success begets challenges’: NGA struggles to meet rising demand for Maven AI, Breaking Defense, Sept. 3, 2024, https://breakingdefense.com/2024/09/success-begets-challenges-nga-struggles-to-meet- rising-demand-for-maven-ai/.
15 CIA, Creating the Future of Intelligence with DDI, https://www.cia.gov/stories/story/creating-the-future-of- intelligence-with-ddi/.

PDF page 8

6

Command and Control. Autonomous vehicles again serve as the poster child for AI. The US Air Force is planning to deploy a fleet of more than 1,000 unmanned warplanes, the first of them operating by 2028.16 With thousands more Navy, Army and Marine autonomous vehicles operating in all warfare domains, managing the integrated operation of all of these assets against enemy forces (themselves AI-enabled) will be immensely difficult.17 DOD’s Combined Joint All- Domain Command & Control (CJADC2) initiative is structured to meet this challenge.  With the help of AI, the program was originally designed to produce “the warfighting capability to sense, make sense, and act at all levels and phases of war, across all domains, and with partners, to deliver information advantage at the speed of relevance.”18

Decision Support. DOD’s AI strategy calls for the development of additional ways to achieve “decision advantage” over enemy commanders, via 1) battlespace awareness and understanding;

2) adaptive force planning and application; 3) fast, precise, and resilient attack structures; and 4) other applications of AI to combat and combat support functions.19

The advantages that AI offers for decision support is driving the rapid expansion of their use. A comprehensive analysis of these services found that “artificial intelligence promises to help military commanders make sense of vast amounts of data at superhuman speeds. The military has a strong motivation to take advantage of AI, and among the most interested within the armed forces are commanders charged with making operational decisions in war. These commanders must continuously ‘observe, orient, decide, and act’ on a fast-paced and multidimensional battlefield where decisions are life-and-death.”20 To meet these needs, Palantir, Scale AI, Anduril, and other AI companies and their associated commercial data centers are rapidly scaling up their decision support and situational awareness services to DOD.21

Decision support applications are already moving into surprising realms. Air Force Gen. Anthony J. Cotton, Commander of the Strategic Air Command, declared “AI will enhance our decision-

16 Tara Copp, AI-Controlled Fighter Jet Takes Air Force Secretary on Historic Ride, AP News, May 3, 2024, https://apnews.com/article/artificial-intelligence-fighter-jets-air-force-6a1100c96a73ca9b7f41cbd6a2753fda.

17 Section II.C of this Declaration examines the emerging AI warfighting capabilities of China and other potential adversaries.
18 DOD, Summary of the Joint All-Domain Command & Control (JADC2) Strategy, Mar. 2022, p. 2, https://media.defense.gov/2022/Mar/17/2002958406/-1/-1/1/SUMMARY-OF-THE-JOINT-ALL-DOMAIN- COMMAND-AND-CONTROL-STRATEGY.pdf.
19 DOD Data, Analytics, and AI Strategy, p. 5.
20 Emelia Probasco, et al., AI for Military Decision-Making: Harnessing the Advantages and Avoiding the Risks, Center for Security and Emerging Technology, Apr. 1, 2025, p. 5, https://cset.georgetown.edu/wp- content/uploads/CSET-AI-for-Military-Decision-Making.pdf.
21 Id. pp. 11-12.

PDF page 9

7
making capabilities” for nuclear command and control. Cotton also stated that growing threats, an overwhelming flow of sensor data, and increasing cybersecurity concerns are driving the need for AI to keep American forces a step ahead of those seeking to challenge the US. Accordingly, AI and other advanced systems “can inform us faster and more efficiently.”22 Applications of equivalent uses of AI for decision support are accelerating across US Combatant Commands around the globe.23

Undersea warfare and beyond. In every warfare domain, AI and machine learning (ML) tools are transforming the way our armed forces will engage the enemy.24 For example, the Navy relies on commercially provided ML models to support underwater target threat detection by unmanned underwater vehicles. DOD’s Defense Innovation Unit is now partnering with ML vendors to provide a pipeline to track, modify, and redeploy ML algorithms for underwater target threat detection.25

Equivalent AI-enabled progress is underway for surface warfare, air and land operations under the Thunderforge program and other DOD initiatives. DOD’s Defense Innovation Unit notes that in addition to Thunderforge’s peacetime applications, the effort “marks a decisive shift toward AI- powered, data-driven warfare, ensuring that US forces can anticipate and respond to threats with speed and precision” across all realms of combat.26

C. Countering China’s Drive for Primacy

The defense missions summarized above highlight the imperative to ensure that as DOD increases its dependence on AI, the data centers that provide those AI services will have the power they need. The imperative for the energy sector to serve these growing loads is magnified by an

22 Cotton also stated that as the Command adopts AI tools, “we must always maintain a human decision in the loop to maximize the adoption of these capabilities and maintain our edge over our adversaries.” Greg Hadley, AI ‘Will Enhance’ Nuclear Command and Control, Says STRATCOM Boss, Air & Space Forces Magazine, Oct. 28, 2024, https://www.airandspaceforces.com/stratcom-boss-ai-nuclear-command-control/.
23 Jon Harper, Combatant Commands to Get New Generative AI Tech for Operational Planning, Wargaming, DefenseScoop, Mar. 5, 2025, https://defensescoop.com/2025/03/05/diu-thunderforge-scale-ai-combatant- commands-indopacom-eucom/.
24 Machine learning is a subfield of AI that gives computers the ability to learn without explicitly being programmed. Sara Brown, Machine Learning Explained, MIT, Apr. 21, 2021, https://mitsloan.mit.edu/ideas-made- to-matter/machine-learning-explained.
25 DOD, Defense Innovation Unit, DoD Successfully Deploys Commercial AI Infrastructure to Support Underwater Target Detection, June 16, 2024, https://www.diu.mil/latest/dod-successfully-deploys-commercial-ai-infrastructure- to-support-underwater.
26 Hayden Field, Scale AI Announces Multimillion-Dollar Defense Deal, a Major Step in US Military Automation, CNBC, Mar, 5, 2025, https://www.cnbc.com/2025/03/05/scale-ai-announces-multimillion-dollar-defense-military- deal.html.

PDF page 10

8
additional factor: China’s drive for AI preeminence, and the broader strategic competition between China and the United States that AI will help shape in the defense realm and beyond.

President Trump warns that “the release of DeepSeek AI from a Chinese company should be a wake-up call” for US industry, and that “we need to be laser focused on competing.”27 China is already employing DeepSeek and other AI tools to improve its cyberattack capabilities and overwhelm US defenses.28 Moreover, DOD warns that “China is a global leader in AI technology and aims to overtake the West in AI [research and development] by 2025 to become the world leader in AI by 2030.”29 China’s leaders believe that “advances in AI and autonomy are central to intelligentized warfare,” in which AI integrates and leverages vast amounts of data to conduct cyberattacks against US infrastructure and other targets with unprecedented speed, precision, and effectiveness.30

China views DeepSeek as a major step forward in its AI-enabled military capabilities and, more broadly, a breakthrough that reshapes the balance of power in the US-China AI competition. US strategists Tye Graham and P.W. Singer, reviewing Chinese defense publications on DeepSeek, note that Chinese military analysts laud DeepSeek’s ability to improve intelligent decision-making in combat scenarios, optimize weapons systems, and improve real-time battlefield analysis.31 Companies that provide AI services to DOD are carefully tracking these Chinese advances as well. Dan Tadross, Head of Public Sector at Scale AI, testified to the US Senate Armed Services Committee in March 2025 that “AI is made up of three main pillars—compute, data, and algorithms. More than one year ago, the United States was clearly ahead on all three. However, today that is no longer the case. Advancements from China, most notably with the launch of Deepseek, have shown that they have closed the gap.”32 And while China currently constitutes our

27 David Ingram, Trump Says China’s DeepSeek ‘Should be a Wake Up Call’ for American Tech Companies, NBC News, Jan. 27, 2025, https://www.nbcnews.com/tech/innovation/trump-china-deepseek-ai-wake-call-rcna189526.
28 Tye Graham and Peter Singer, To China, DeepSeek is more than an app—it's a strategic turning point, Defense One, Feb. 21, 2025, https://www.defenseone.com/ideas/2025/02/china-sees-deepseek-strategic-turning- point/403159/?oref=d1-hp-voices-module. 29 DOD, Military and Security Developments Involving the People’s Republic of China, 2023, p. 169, https://media.defense.gov/2023/Oct/19/2003323409/-1/-1/1/2023-MILITARY-AND-SECURITY- DEVELOPMENTS-INVOLVING-THE-PEOPLES-REPUBLIC-OF-CHINA.PDF.
30 Id.
31 Tye Graham and Peter Singer, To China, DeepSeek is more than an app—it's a strategic turning point, Defense One, Feb. 21, 2025, https://www.defenseone.com/ideas/2025/02/china-sees-deepseek-strategic-turning- point/403159/?oref=d1-hp-voices-module.
32 Statement by Dan Tadross, Head of Public Sector, Scale AI, to Sen. Armed Services Comm., Subcomm. Hearing on Cybersecurity, Mar. 25, 2025, https://www.armed-services.senate.gov/imo/media/doc/tadross_testimony.pdf.

PDF page 11

9
only competitor for global AI primacy, other nations are acquiring advanced AI capabilities that will strengthen their cyberattack capabilities, including Russia,33 Iran,34 and North Korea.35

D. The Need for Speed

DOD’s growing reliance on AI in peacetime and war, combined with China’s efforts to overtake US progress, provide compelling reasons for FERC to facilitate the rapid connection of data centers and to continue its efforts to ensure power sources are incented and rapidly deployed. Speed is of the essence for national security.

President Trump has pointed the way to a promising option to achieve such speed: have data centers rely on power generators sitting “right next” to them.36 The President noted that co-located data center projects can go forward on a “very rapid basis” compared to other options.37 That speed offers a significant advantage over grid-connected alternatives for data center power, which can take as many as 7 years or longer to build the necessary transmission infrastructure and meet other project requirements.38 Some transmission owners argue that their preferred grid-connection options should be the only connection option available.39 However, limiting data center development to only grid-connected options may simply take too long to implement in many

33 Annie Fixler, Russia’s AI-Powered Cyberattacks Threaten to Outpace Western Defenses, Foundation for Defense of Democracies, Feb. 20, 2025, https://www.fdd.org/analysis/policy_briefs/2025/02/20/russias-ai-powered- cyberattacks-threaten-to-outpace-western-defenses/.
34 Steven Stalinsky, Iran’s Dangerous Push to Become an AI Superpower, Middle East Media Institute, Feb. 11, 2025, https://www.memri.org/reports/irans-dangerous-push-become-ai-superpower.
35 Hyuk Kim, North Korea’s Artificial Intelligence Research: Trends and Potential Civilian and Military Applications, 38 North, Jan. 23, 2024, https://www.38north.org/2024/01/north-koreas-artificial-intelligence- research-trends-and-potential-civilian-and-military-applications/.
36 The White House, Remarks by President Trump at the World Economic Forum, Jan. 23, 2025, https://www.whitehouse.gov/remarks/2025/01/remarks-by-president-trump-at-the-world-economic-forum/.
37 Id.
38 See, e.g., Josh Saul, Data Centers Face Seven Year Wait for Dominion Power Hookups, Bloomberg, Aug. 19, 2024, https://www.bloomberg.com/news/articles/2024-08-29/data-centers-face-seven-year-wait-for-power-hookups- in-virginia; Christopher Tozzi, Why Data Center Grid Connections are Slowing Down – And How to Fix it, Data Center Knowledge, Mar.17, 2025, https://www.datacenterknowledge.com/energy-power-supply/why-data-center- grid-connections-are-slowing-down-and-how-to-fix-it; Robert Walton, AI, data center electricity demand could drive advanced nuclear investment: NERC head Jim Robb, Utility Dive, June 6, 2024, https://www.utilitydive.com/news/ai-data-center-electricity-demand-advanced-nuclear-investment-Robb/718181/ (“it takes me about four years to build a substation,” according to David Schleicher, Northern Virginia Electric Cooperative CEO); Tom Robb, Elk Grove Mayor Meets With ComEd on Substations for Data Centers, Journal & Topics, Mar. 14, 2024, https://www.journal-topics.com/articles/elk-grove-mayor-meets-with-comed-on-substations- for-data-centers/ (Mayor of Elk Grove, Illinois, “expressed frustration with ComEd, saying the electricity utility was ‘dragging their feet’ in building substations to support the growing data center industry”); Comments of Talen Energy Corporation re Co-Located Load: Market, Economic, and Ratemaking Principles, Docket No. AD24-11, Oct. 10, 2025, fn. 43 (describing delays of 7 to 10 years to establish new load connections for several PJM transmission owners).
39 Answer of the Indicated PJM Transmission Owners, Docket No. EL25-49, Mar. 24, 2025, Att. A p. 21.

PDF page 12

10
situations to meet rapidly growing defense requirements because it requires transmission owners to build out infrastructure that would not be necessary if the data center instead co-locates with a generator. DOD and the AI data centers should have all options available to accelerate the connection of those centers, especially expedient ones, so that the DOD and its AI partners can determine the quickest path forward. FERC should ensure rules that make all such options available to DOD and should act quickly to do so.

Measures to accelerate data center connections should also account for DOD’s dependence on private sector facilities. It would be mistaken to imagine that because AI services are so critical to national defense, DOD relies entirely on its own data centers sited on military bases or other defense installations, and that somehow the DOD powers these centers with its own generation resources. The opposite is true. Both DOD-owned data centers and their private sector counterparts that provide AI service to the DOD overwhelmingly depend on grid-provided power, co-located nuclear plants, or other commercial solutions. Moreover, DOD’s utilization of private sector data centers is rapidly growing, including highly classified AI support functions.40 Rules to facilitate the rapid connection of data centers must enable options that meet all such urgent requirements for power.

III. POWER RESILIENCE

In addition to accelerating the availability of expedient data center connection options given its importance to America’s defense, rules on data center connections should also enable DOD and its data center partners to benefit from the increased resilience that locating at or near nuclear plants can provide in future conflicts.

Reliable electric service is necessary for day-to-day operations of data centers in peacetime. However, given the importance of data centers to support US warfighting, and the risk that China will attack the grid and natural gas infrastructure in future conflicts, connections to data centers must also be resilient: that is, be able to “prepare for and adapt to changing conditions and recover rapidly from operational disruptions,” including from “deliberate attacks, accidents, or naturally occurring threats or incidents.”41

40 See, e.g., Adam Mazmanian, Microsoft Deploys Air-Gapped AI for Classified Defense, Intelligence Customers, Nextgov/FCW, May 7, 2024, https://www.nextgov.com/artificial-intelligence/2024/05/microsoft-deploys-air- gapped-ai-classified-cloud/396354/.
41 US Dep’t of Energy (DOE), Resilience, https://www.directives.doe.gov/terms_definitions/resilience.

PDF page 13

11
A. Intensifying Threats and US Resilience Initiatives

The March 2025 Annual Threat Assessment of the US Intelligence Community states that “China has demonstrated the ability to compromise U.S. infrastructure through formidable cyber capabilities that it could employ during a conflict with the United States.”42 In particular, “if Beijing believed that a major conflict with Washington was imminent, it could consider aggressive cyber operations against U.S. critical infrastructure and military assets. Such strikes would be designed to deter U.S. military action by impeding U.S. decision-making, inducing societal panic, and interfering with the deployment of U.S. forces.”43

This US Intelligence Community assessment provides additional context for responding to FERC’s February 2025 request for analysis of the national security implications associated with co-location arrangements.44 As noted in Section II.B above, AI data center services play a vital and rapidly growing role in supporting US combat decision-making, command and control, and other missions essential for deploying and operating US forces. Given the US Intelligence Community’s assessment of Chinese conflict objectives, strengthening the resilience of power flows to data centers is crucial to help counter those goals and reinforce deterrence against Chinese attacks.

Ongoing improvements to the cybersecurity of the BPS help strengthen that resilience. FERC, NERC, and BPS entities deserve enormous credit for developing and implementing CIP standards that strengthen the grid’s resilience against cyber and physical threats. These ongoing security improvements to the BPS strengthen the resilience of grid-provided power for data centers. Those improvements also benefit co-located nuclear plants by mitigating threats to the transmission lines that plants need to safely operate.

Natural gas pipeline systems and other gas infrastructure owners and operators are also taking significant, urgently needed steps to strengthen the cyber resilience of their systems. The US Transportation Security Administration (TSA) has issued a series of performance-based cybersecurity mandates for these systems, including that owners/operators establish and implement TSA-approved cybersecurity implementation and incident response plans.45 On a

42 ODNI, 2025 Annual Threat Assessment, p. 9.
43 Id. pp. 11-12.
44 February 2025 Order, P 88(f)(vi).
45 US Transportation Security Admin., SD Pipeline-2021-02E: Pipeline Cybersecurity Mitigation Actions, Contingency Planning, and Testing, July 26, 2024, https://www.tsa.gov/sites/default/files/tsa-security-directive- pipeline-2021-02e-and-memo-508c.pdf. For a comprehensive list of cybersecurity measures for pipelines, see US Transportation Security Admin., Security Directives and Emergency Amendments, https://www.tsa.gov/sd-and-ea.

PDF page 14

12
voluntary basis, many system operators also adopt cybersecurity guidelines that go over and above TSA’s mandates.46

Nevertheless, these requirements are far less comprehensive and detailed than the BPS CIP standards for cybersecurity established by FERC and NERC. Given this disparity between these standards for the grid versus natural gas systems, the US must continue to account for the risk that China will adopt an indirect strategy to disrupt electric service to data centers and other critical customers, by striking the flow of natural gas on which 43% US power generation depends.47

This threat is more than hypothetical. In 2023, the US Intelligence Community warned that “China almost certainly is capable of launching cyber attacks that could disrupt critical infrastructure services within the United States, including against oil and gas pipelines” and other targets.48 China has continued to upgrade its capabilities to attack this infrastructure ever since. Indeed, with the gap between increasingly stringent BPS security mandates and the equivalent standards for natural gas infrastructure, the risks of gas-focused strategies to disrupt electric service to critical customers

– including data centers – will intensify.

Accordingly, from a national security perspective, it makes sense for FERC rules to enable data center operators to choose from a diverse set of resilient power options. Some operators (and their DOD customers) may decide that grid-connected power best meets their needs. Others may want to prioritize resilience against attacks on natural gas systems designed to disrupt the grid, and decide instead to rely on co-located or proximate generation. The section that follows highlights the potential advantages of co-location.

B. Uri, Elliott, and Power Resilience for Defense-Critical Data Centers

Extreme weather events provide “real world” examples of how disruptions of natural gas supplies for generation can degrade electric service, even when transmission systems are largely unaffected. Winter Storms Elliott and Uri offer prime examples. In both storms, severe cold disrupted supplies of natural gas for power generation. The resulting generation outages, de-rates, and failures to start required grid operators to conduct large scale load shedding operations to maintain the grid’s reliability – including shedding firm load.49

46 Natural Gas Ass’n, Natural Gas Cybersecurity Guidelines & Standards Portfolio, https://www.aga.org/wp- content/uploads/2022/11/ong_cybersecurity_guidelines_and_standards_002.pdf; Interstate Natural Gas Ass’n of America (INGAA), Commitments to Pipeline Security, https://ingaa.org/wp-content/uploads/2019/02/34310.pdf.
47 US Energy Information Agency, EIA Publishes its First Energy Sector Forecasts Through 2026, Jan. 14, 2025, https://www.eia.gov/pressroom/releases/press564.php.
48 ODNI, 2023 Threat Assessment, p. 10.
49 FERC/NERC Winter Storm Elliott Report, pp. 5-6.

PDF page 15

13
Moreover, even as severe cold disrupted gas generation and electric service to key customers, nuclear power plants kept providing much-needed power. During Winter Storm Elliott, 31 nuclear reactors in operation across PJM’s service territory produced more than 96 percent of their potential power output during the storm.50 A key enabler: unlike gas generators, nuclear power plants typically have many months of fuel stored on site, and that fuel is impervious to disruptions by severe weather or adversary attacks.

Of course, the ability of nuclear plants to sustain their operations in severe weather events depends on the continued availability of transmission system ties to enable their safe operation. The same will be true in future conflicts. It is prudent to assume that, to disrupt US military operations, China will attack both natural gas infrastructure and the BPS on which data centers and other defense- critical assets depend. Thanks to the security initiatives taken by FERC and its partners, US transmission systems may be able to keep operating in the face of such attacks, just as they did in Uri and Elliott. That survivability could help nuclear power plants sustain service to co-located data centers even if large scale load-shedding is underway in the surrounding grid. And of course, the resilience of nuclear-provided power is further enhanced by their compliance with the stringent, continuously upgraded cyber and physical security standards established by the US Nuclear Regulatory Commission.51

IV. CONCLUSION: ALTERNATIVE PATHS TO POWER RESILIENCE

Not all data center owners and operators will assess their needs for resilient power in the same way. And over time, new technologies may become available to provide resilient power beyond those that exist today, including the deployment of small modular reactors. As FERC assesses the security considerations involving co-location arrangements it should consider the following:

• Data center owners and operators should have the latitude to select power sources and interconnection configurations that best meet the requirements of their particular applications, including power resilience for military and other mission-critical use cases. One size will not fit all. Rules affecting large load interconnections should preserve that latitude.

• That said, accelerating the pace with which new sources of power can meet data center loads will remain absolutely vital to national security. The advantages of alternatives to traditional utility grid connections in this regard are compelling, and should be weighted accordingly by FERC as it moves forward in this proceeding.

50 Matt Crozat, Nuclear Saves the Holiday Season, Nuclear Energy Institute, Jan. 26, 2023, https://www.nei.org/news/2023/nuclear-saves-the-holiday-season.
51 US Nuclear Regulatory Comm’n, Cybersecurity, https://www.nrc.gov/security/cybersecurity.html.

PDF page 16

14

Let me conclude by offering my thanks to the Commissioners for including national security considerations in FERC’s proceedings on co-location arrangements. The extent of DOD’s extraordinary (and growing) dependence on AI data centers is only beginning to be recognized outside the defense realm. By factoring the resulting imperatives for speed and resilience in serving data center loads, the Commission has the opportunity to advance America’s security in uniquely valuable ways.

PDF page 17

[No extractable text on this page.]

PDF page 18

Attachment A to Stockton Declaration

PDF page 19

PAUL N. STOCKTON
PROFESSIONAL BIOGRAPHY
Dr. Stockton leads Paul N Stockton LLC, a strategic advisory firm in Santa Fe, NM. He helps private sector and government leaders strengthen the resilience of US infrastructure. He also chairs the Board of Directors of Analytic Services, Inc., the Homeland Defense and Defense Support to Civil Authorities subcommittee of DOD’s Reserve Forces Policy Board, and the Grid Resilience for National Security subcommittee of DOE’s Electricity Advisory Committee.

As Assistant Secretary of Defense for Homeland Defense and Americas’ Security Affairs from 2009-2013, Dr. Stockton led the development of DOD’s Strategy for Mission Assurance and strengthened defense partnerships with Canada, Mexico, and other Western Hemisphere nations. He guided Defense support in response to Superstorm Sandy and other catastrophes. Dr. Stockton also served as Executive Director of the US Council of Governors, and led Department policy initiatives on continuity planning and antiterrorism/force protection.

After leaving DOD, Dr. Stockton provided grid regulators with innovative metrics and cost recovery criteria in Resilience for Black Sky Days (2014). His recent studies on the electric system include Resilience for Grid Security Emergencies: Opportunities for Industry-Government Collaboration (June 2019), Strengthening the Cyber Resilience of the North American Energy Systems (September 2020), and Securing the Grid from Supply-Chain Based Attacks (September 2020). He is the co-editor of Blackstart Power Restoration for a Greener Grid (2004) and is currently drafting Surfing the Wave: Resilience Strategies for the Decentralizing Grid. Dr. Stockton supports resilience initiatives in other infrastructure sectors as well. Strengthening the Cyber Resilience of America’s Water Systems: Industry-Led Regulatory Options (August 2021) examines new opportunities to counter intensifying threats. In addition, he has helped FEMA and DHS assess and mitigate risks of cascading failures across infrastructure sectors, and served as contributing editor to the 4th Edition of the National Response Framework. Dr. Stockton also analyzes options to counter the Chinese use of information operations (IOs) and cyberattacks to influence US decision-making in confrontations over Taiwan or other conflicts. Defeating Coercive Information Operations in Future Crises (2021) analyzes these threats and proposes strategies to defeat them.

Dr. Stockton holds a PhD from Harvard University and a BA from Dartmouth College. He was twice awarded the Department of Defense Medal for Distinguished Public Service, DOD's highest civilian award. DHS also awarded Dr. Stockton its Distinguished Public Service Medal. After leaving DOD, Dr. Stockton served as Managing Director of Sonecon LLC. Prior to becoming Assistant Secretary, he was a Senior Research Scholar at Stanford’s Center for International Security and Cooperation, an Associate Provost of the Naval Postgraduate School, a Legislative Assistant for Senator Daniel Patrick Moynihan, and served as the founding director of the Center for Homeland Defense and Security.

Dr. Stockton is a Senior Fellow of the Johns Hopkins University’s Applied Physics Laboratory. He also serves on the Science and Technology and Strategic Advisory Committees of the Idaho National Laboratory.