EL25-49-000 · 2025-04-23 · Constellation Energy Generation, LLC
Exhibit 2 (Ming)
PDF page 1
EXHIBIT 2
TESTIMONY OF ZACHARY MING
PDF page 2
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
Testimony of Zachary Ming
Partner
Energy and Environmental Economics, Inc. (“E3”)
On behalf of
Constellation Energy Generation, LLC (“Constellation”)
April 23, 2025
PDF page 3
2
Table of Contents
1
Introduction … 3 2
Background … 8 3
Current Rate is Unjust and Unreasonable … 19
4
Ideal Rate Structures for Co-Location Configurations … 24
4.1
Transmission Charges … 27 4.2
Ancillary Service Charges … 42 4.3
Energy Charges … 44 4.4
Capacity Charges … 45 4.5
Non-PJM Charges … 48 4.6
Summary … 48 5
Assessment of PJM Proposed Rate Options … 52
6
Recommendations & Summary … 66
PDF page 4
3
Constellation
1
2
Transmission Tariffs for Co-Located Load
3
4
5
Testimony of Zachary Ming, Partner, Energy and Environmental Economics, Inc. 6
(“E3”)
7
1 Introduction
8
Q1.
PLEASE STATE YOUR NAME, OCCUPATION, AND BUSINESS
9
ADDRESS.
10
A1.
My name is Zachary Ming. My current position is Partner at Energy and 11
Environmental Economics (“E3”). My business address is 44 Montgomery Street 12
Suite 1500, San Francisco, California 94104.
13
Q2.
PLEASE STATE ON WHOSE BEHALF YOU ARE FILING TESTIMONY.
14
A2.
I am filing this testimony as an independent expert, and it represents my own 15
positions and perspectives. Constellation compensated for my testimony, but my 16
compensation did not depend on my conclusions.
17
Q3.
PLEASE DESCRIBE YOUR PROFESSIONAL BACKGROUND AND
18
EXPERIENCE.
19
A3.
I received a B.S. in Civil and Environmental Engineering (Atmosphere and Energy 20
program) with a Minor in Economics, and an M.S. in Management Science and 21
Engineering (Energy track), both from Stanford University. For over a decade I 22
have held various roles at E3, an energy consulting firm specializing in the 23
economics of the electricity system where I am currently a Partner. In addition to 24
PDF page 5
4
full-time consulting work at E3, I teach a graduate-level course at Stanford 1
University titled Electricity Economics.
2
Q4.
PLEASE DESCRIBE YOUR QUALIFICATIONS AS IT RELATES TO THE
3
TOPIC OF TRANSMISSION TARIFF DESIGN FOR CO-LOCATED
4
LOADS.
5
A4.
In my role as Partner, I oversee E3 projects across a number of areas including rate 6
design, system planning, marginal/avoided cost analysis, and resource adequacy. I 7
have authored several reports related to system planning that evaluate the role that 8
generation and transmission serve in reliably and cost-effectively meeting long- 9
term system needs, including Long-Run Resource Adequacy under Deep
10
Decarbonization Pathways for California1 and Net-Zero New England: Ensuring 11
Electric Reliability in a Low-Carbon Future.2 I have also developed the methods 12
that are used in both California and across the industry to quantify the transmission 13
benefits of co-locating generation and load.3 I have worked with utilities to develop 14
rate designs that accurately reflect the costs of the customers being served, 15
including for large loads in Nova Scotia and Alberta. I have testified before utility 16
Commissions in South Carolina on the topic of rate design4 and New Brunswick on 17
the topic of cost allocation.5 Most broadly, I lead an E3 team to support clients to 18
1https://www.ethree.com/wp-content/uploads/2019/06/E3_Long_Run_Resource_Adequacy_CA_Deep- Decarbonization_Final.pdf.2https://www.ethree.com/wp-content/uploads/2020/11/E3-EFI_Report-New-England-Reliability-Under- Deep-Decarbonization_Full-Report_November_2020.pdf.3https://www.ethree.com/wp-content/uploads/2025/02/2024-ACC-Documentation-v1b_clean.pdf.4 Docket Nos. 2023-15-E, 2023-16-E, and 2023-17-E.5 Matter No. 554.
PDF page 6
5
understand the current challenges facing the electricity system and to implement 1
solutions that are economic and reliable.
2
Q5.
HAVE YOU PREVIOUSLY TESTIFIED BEFORE THE FEDERAL
3
ENERGY REGULATORY COMMISSION (“FERC”)?
4
A5.
Yes, I have testified multiple times before FERC. My previous testimony has 5
covered various topics related to rate design and wholesale markets in PJM, 6
including the capacity market price cap,6 the participation of reliability must run 7
(“RMR”) units in the capacity market,7 and PJM’s filing to use marginal effective 8
load carrying capability (“ELCC”) as the basis for resource accreditation in the 9
capacity market.8 I have also testified to FERC on behalf of MISO in their proposal 10
to implement the direct loss of load (“DLOL”) methodology for resource 11
accreditation.9 Additionally, I have testified before state and provincial public 12
utility commissions in Oregon, Texas, South Carolina, Colorado, and New 13
Brunswick on topics relating to reliability, resource adequacy, market design, and 14
rate design.
15
Q6.
PLEASE PROVIDE A SUMMARY OF YOUR TESTIMONY.
16
A6.
My testimony demonstrates that there are three fundamental configurations of co- 17
located load, each with different transmission system impacts and costs: 18
6 Docket EL25-46-000.7 Docket EL24-148.8 Docket ER24-99-000.9 Docket ER24-1638.
PDF page 7
6
• Firm: can take service from co-located generation but has the firm right to 1
draw from the grid when the co-located generation is not available 2
• Generator-contingent: can take service from co-located generation when 3
it is available but has no right to draw from the grid when co-located 4
generation is not available
5
• Interruptible: can be interrupted by PJM, regardless of whether the co- 6
located generator is online and available
7
8
Providing a rate design for each configuration that aligns with the impacts 9
and costs that it imposes on the transmission system is necessary to align with the 10
rate design principles of 1) fair apportionment of costs and 2) economic efficiency. 11
Because the current PJM tariff does not provide a clear mechanism for customers 12
to take service in any of these configurations, I conclude that it does not align with 13
rate design principles and is therefore unjust and unreasonable.
14
Using rate design principles and the transmission system impacts and costs, 15
I outline ideal rate structures that should be applied through various tariff 16
components (transmission, energy, capacity, ancillary services, etc.) for each of the 17
three fundamental co-location configurations.
18
PJM has proposed eight different rate design options that could potentially 19
be applied to co-located loads, including five new rate options “developed by PJM 20
in response to issues raised in the various predecessor co-located load 21
proceedings.”10 I demonstrate how each of these options can be generally mapped 22
10 PJM Filing, page 5.
PDF page 8
7
to one of the three fundamental configurations of co-located load that I outline 1
above. While the introduction of these options positively contributes to the 2
conversation, I demonstrate that the ideal rates I outline better align with rate design 3
principles for each of the three fundamental configurations of co-located load and 4
I show how the PJM options can be modified to align with these ideal rates. 5
Q7.
PLEASE PROVIDE AN OUTLINE OF YOUR TESTIMONY.
6
A7.
My testimony is organized as follows:
7
• In Section 2, I provide the background on rate design principles, discuss drivers 8
of transmission costs, and introduce and describe three distinct configurations 9
for co-located loads and their impact on transmission costs;
10
• In Section 3, I describe how the current PJM tariff does not provide a clear 11
mechanism or incentive for customers to interconnect in a lower cost co- 12
location configuration, does not align with rate design principles, and is 13
therefore unjust and unreasonable;
14
• In Section 4, I outline theoretically ideal rate structures for each of the three co- 15
location configurations based on well-established ratemaking principles and 16
objectives; and
17
• In Section 5, I evaluate the extent to which PJM’s eight proposed rate options 18
align with the three configurations and their corresponding ideal rate structures. 19
PDF page 9
8
2 Background
1
Q8.
PLEASE PROVIDE AN OVERVIEW OF THE CURRENT PJM OPEN-
2
ACCESS TRANSMISSION TARIFF (“TARIFF”).
3
A8.
The current tariff provides rates that are assessed to loads for transmission service, 4
ancillary services, energy, and capacity. The primary relevant service for which 5
loads take service is Network Integration Transmission Service (“NITS”). This 6
provides a mechanism for new load to interconnect to the transmission system and 7
purchase system energy. Loads are charged for transmission service based on their 8
contribution to their zone’s annual peak load, with specific calculation
9
methodologies that vary by transmission owner.11 Loads are charged for ancillary 10
services based on their monthly energy, monthly contribution to the zone’s annual 11
peak load, or monthly non-coincident peak demand depending on the specific
12
service.
13
Q9.
WHAT
RATE
DESIGN
PRINCIPLES
ARE
APPROPRIATE
TO
14
CONSIDER IN THE DEVELOPMENT OF A TRANSMISSION TARIFF?
15
A9.
The Bonbright rate design principles are well-established as the seminal standard 16
for establishing electric utility rates across North America.12 Underscoring their 17
relevance in PJM, FERC has cited these principles on numerous occasions.13
18
11 Common PJM Network Service Peak Load (“NSPL”) methods include 1 CP (customer load during single annual peak hour), 5 CP or 12 CP (average customer load over 5 or 12 annual peak hours).12 James C. Bonbright, Principles of Public Utility Rates, page 291, https://www.raponline.org/wp- content/uploads/2023/09/powellgoldstein-bonbright-principlesofpublicutilityrates-1960-10-10.pdf.13 For instance, Docket No. EL00-66-000 (Louisiana Public Service Commission & Council of the City of New Orleans v Entergy Corp) and AD06-2-000 (Assessment of Demand Response & Advanced Metering Report).
PDF page 10
9
Q10. WHICH SPECIFIC BONBRIGHT RATE DESIGN PRINCIPLES ARE
1
RELEVANT
TO
THE
ISSUE
OF
CO-LOCATED
LOAD
AND
2
GENERATION?
3
A10. There are two rate design principles that are most relevant to the development of 4
tariffs for co-located load and generation:
5
• Fair apportionment of costs: this principle establishes that costs should be 6
borne by the customers that cause the costs. Fair apportionment of costs 7
drives equity among customers.
8
• Economic efficiency: this principle discourages wasteful infrastructure 9
development and use while promoting all justified types and amounts of 10
use. Application of this principle yields an electricity system that serves 11
load at minimum total cost.
12
13
In addition, Bonbright also establishes that rates should be “free from 14
controversies as to improper interpretation” and “non-discriminatory.”14 Finally, 15
Bonbright also establishes several other principles that are less relevant to the topic 16
of co-located loads because all rate design proposals in this proceeding perform 17
similarly.15 For example, all rate options under consideration recover the total 18
revenue requirement.
19
14 James C. Bonbright, Principles of Public Utility Rates, page 291.15 Other rate design principles include recovery of the total revenue requirement, practicality, stability of rates and revenues, and simplicity and understandability.
PDF page 11
10
Q11. PLEASE DISCUSS THE CONCEPTS OF “GROSS” AND “NET” BILLING.
1
A11. A key issue at hand is whether co-located loads should pay for transmission service 2
based on “gross” or “net” load. A gross load construct would apply transmission 3
charges to the load-only portion of the co-located customer, while a net load 4
construct would subtract any generation from the load before applying charges. A 5
net load construct is consistent with measuring the actual energy flowing between 6
the entire co-location configuration and the transmission system as demonstrated 7
in the figure below. These concepts are discussed in more detail in later sections of 8
my testimony.
9
Figure 1: Graphical Depiction of Gross and Net Load for Co-Located Loads 10
11
Q12. PLEASE
PROVIDE
AN
OVERVIEW
OF
WHAT
CAUSES
12
TRANSMISSION COSTS.
13
A12. Transmission is built to allow for delivery of generation to loads. The sizing of the 14
transmission grid is primarily determined by the need to deliver generation to loads 15
PDF page 12
11
during peak demand. In its Electric Utility Cost Allocation Manuel, the National 1
Association of Regulatory Utility Commissioners (“NARUC”) states that 2
“investment in the transmission system is generally assumed to be driven by 3
increments in system peak load.” 16 FERC has similarly acknowledged this in 4
multiple ratemaking decisions; for instance, while defending a peak load-based 5
transmission cost allocation in Docket No. EL00-66-000, FERC stated that: 6
“A utility builds its bulk power facilities, i.e., generating units and transmission 7
lines, to meet the maximum or peak demand of its firm customers. Because the 8
utility incurs the cost of these facilities to meet the peak demand of its firm 9
customers, those customers should pay for the facilities. The peak responsibility 10
method accomplishes this by allocating the cost of the facilities among the firm 11
customers in the same proportion as each customer's demand bears to the system 12
peak.”17
13
From this first principle, it naturally follows that the integration of new 14
loads within an electricity system in a manner that does not increase peak demand 15
will result in lower transmission system costs than integration of new loads that do 16
increase peak demand. This notion is also well-supported in literature – for 17
example, a recent study authored by researchers at Duke University states that “[t]o 18
the extent a new load can temporarily reduce (i.e., curtail) its electricity 19
consumption from the grid during these peak stress periods, however, it may be 20
able to connect while deferring—or even avoiding—the need for certain 21
upgrades.”18
22
16 Page 128, https://www.pubmanitoba.ca/pdf/cos_review/exhibits/mipug-28.pdf.
17Order page 22, Docket No. EL00-66-000.18 Page 5, https://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf.
PDF page 13
12
Q13. HOW DOES THE RELATIONSHIP BETWEEN PEAK DEMAND AND
1
TRANSMISSION COSTS IMPACT RATE DESIGN?
2
A13. The fact that transmission costs are incurred by a need to serve peak demand is the 3
basis for demand charges, which are the industry-standard approach to recovering 4
transmission costs across the U.S. 19 Customers with higher coincident peak 5
demands20 on the transmission system cause a higher portion of total system costs 6
and are therefore allocated a higher share of total system costs. In PJM, the Network 7
Service Peak Load metric represents a customer’s contribution to peak load of the 8
transmission system and is used to allocate transmission service charges for 9
customers that take Network Service.21
10
The fact that these demand charges are nearly universal in the industry to 11
recover transmission costs is a direct reflection of the relationship between 12
transmission costs and peak demand. Put differently, if the size of a customer’s load 13
on the transmission system during the system peak were not indicative of the costs 14
this customer caused, then there would be no basis for differentiating charges based 15
on the size of a customer’s peak load.
16
19 https://pubs.naruc.org/pub.cfm?id=5378847A-2354-D714-5165-3DDAA31643D2.
20 Coincident peak demand is defined as a customer’s demand during the system peak.21https://www.pjm.com/markets-and-operations/billing-settlements-and-credit/guide-to-billing.
PDF page 14
13
Q14. CAN THE COST ASSOCIATED WITH EXPANSION OF THE
1
TRANSMISSION SYSTEM TO MEET INCREASES IN PEAK DEMAND
2
BE QUANTIFIED?
3
A14. Yes. The impact on transmission costs from peak load increases is quantified 4
through marginal cost analysis. 22 These methods quantify transmission cost
5
increases ($) for a given increase in peak load (MW), resulting in a $/MW value. 6
Similarly, avoiding or deferring an increase in peak load reduces transmission
7
system costs.
8
Q15. HOW ARE TRANSMISSION MARGINAL COST VALUES USED?
9
A15. Transmission marginal cost values are used in a multitude of ways in the industry, 10
including system planning, cost allocation, rate design, program compensation, and 11
more. 23 Another notable use of marginal costs is to quantify the benefits of
12
distributed energy resources, including energy efficiency, demand response, and 13
distributed generation. 24 These values are used to set program incentives,
14
compensation structures, and more.
15
22 For example, Section 20 https://www.raponline.org/wp-content/uploads/2023/09/rap-lazar-chernick- marcus-lebel-electric-cost-allocation-new-era-2020-january.pdf.
23 See summary of marginal cost allocation and pricing in Section 18 of Regulator Assistance Project’s Electric Cost Allocation for a New Era, https://www.raponline.org/wp-content/uploads/2023/09/rap-lazar- chernick-marcus-lebel-electric-cost-allocation-new-era-2020-january.pdf.
24 Examples include California Public Utilities Commission’s Avoided Cost Calculator, https://www.cpuc.ca.gov/dercosteffectiveness and New York State Public Service Commission’s Value of Distributed Energy Resources, https://www.nyserda.ny.gov/All-Programs/NY-Sun/Contractors/Value-of- Distributed-Energy-Resources.
PDF page 15
14
Q16. CAN EFFECTIVE RATE DESIGN ENABLE TRANSMISSION SYSTEM
1
COST REDUCTIONS?
2
A16. Yes. Developing rate designs in which costs incurred by customers mirror the costs 3
that are being imposed (or avoided) on the transmission system incentivizes loads 4
(and, similarly, distributed energy resources) to engage in behavior that reduces the 5
peak load on the transmission system – for example by shifting load, participating 6
in demand response, investing in energy efficiency, investing in distributed 7
generation, co-locating loads and generation, and more.
8
Q17. WHY IS INCENTIVIZING THIS BEHAVIOR BENEFICIAL?
9
A17. Without incentivizing behavior to reduce the system peak, this beneficial behavior 10
would simply not happen. This well-established concept has encouraged 11
policymakers to implement rate structures and designs precisely to incentivize 12
changes in behavior, recognizing that without price signals, loads have no incentive 13
to act in ways that reduces system costs.25
14
Q18. WHAT ARE THE IMPACTS OF REDUCING SYSTEM COSTS?
15
A18. Utilities recover their total revenue requirement from customers – a well- 16
established rate design principle. Therefore, reducing the total revenue requirement 17
has the impact of reducing total customer costs and improving affordability. 18
25https://www.esig.energy/wp-content/uploads/2023/03/ESIG-Retail-Pricing-dynamic-rates-E3-wp- 2023.pdf.
PDF page 16
15
Q19. PLEASE DEFINE “CO-LOCATED LOAD.”
1
A19. “Co-located load” refers to an electrical load that is electrically connected behind 2
the same point of interconnection as a generator, enabling it to be served directly 3
by the generator without the associated energy flowing over the transmission 4
system. An illustration of a standard load and co-located load configuration is 5
provided in the figure below.
6
Figure 2: Simplified Illustration of Standard and Co-Located Load Configurations 7
8
Q20. ARE THERE DIFFERENT POTENTIAL CONFIGURATIONS OF CO-
9
LOCATED LOADS WITH DIFFERENT TRANSMISSION SYSTEM
10
IMPACTS?
11
A20. Yes. There are a range of different potential configurations for co-located loads that 12
impact the transmission system differently. Broadly speaking, these can be 13
organized into three fundamental configurations of co-located load: 14
• Firm: This represents a co-located load configuration that uses co-located 15
generation when it is available but has the right to draw from the grid when 16
the co-located generation is not available.
17
PDF page 17
16
• Generator-contingent: This represents a configuration where co-located 1
load uses co-located generation when it is available but has no right to draw 2
from the grid when it is not. In other words, if the co-located generator is 3
available, the co-located load cannot be interrupted. However, if the co- 4
located generator is not available, the co-located load can be interrupted. 5
Therefore, the co-located load is contingent on the availability of the 6
generator.
7
• Interruptible: This represents a configuration where co-located load can 8
be interrupted by PJM at any time, regardless of whether the co-located 9
generator is online and available. Interruptions may be facilitated through 10
either load curtailment or additional backup generation, but it must be 11
enforceable and long-duration. This means that PJM must be certain that 12
the co-located load will interrupt whenever system conditions require 13
without any limit applied to the length of the interruption.
14
15
Both the “generator-contingent” and “interruptible” configurations can be 16
designed such that the co-located load can draw energy from the transmission 17
system on an as-available basis.
18
Q21. HOW DO THESE DIFFERENT POTENTIAL CONFIGURATIONS
19
IMPACT TRANSMISSION SYSTEM COSTS?
20
A21. The impact of a co-located load on the transmission system and corresponding costs 21
depends on its configuration. PJM acknowledges this in its statement that 22
“incremental load gives rise to incremental system costs. But the extent of those 23
PDF page 18
17
costs appears to vary based on the nature of the particular co-location 1
arrangement.”26 For any potential co-location configuration, cost impacts to the 2
transmission system are driven by the impact on grid power flows primarily during 3
the system peak. Different configurations have different transmission system 4
impacts:
5
• Firm: Under this configuration, the transmission system must be planned 6
and built to serve the co-located load, even if on-site generation is not 7
available. At the same time, it is not necessary to plan and build the 8
transmission system to serve the entirety of all co-located load, as the 9
natural diversity of loads and resources across the system make it 10
implausible that all co-located generation will be unavailable at the same 11
time (just as it is implausible that all PJM generation will be unavailable). 12
Using statistical methods that account for generator outage diversity, 13
planners can calculate the aggregate contribution toward the system peak 14
and corresponding transmission system requirements for firm loads with co- 15
located or behind-the-meter generation.
16
• Generator-contingent: Under this configuration, the transmission system 17
does not need to be sized to serve the co-located load during the peak period, 18
as the load is dependent on the on-site generator for supply and is not 19
entitled to be served from the grid when the generator is not available. At 20
the same time, the addition of co-located load in this configuration may 21
impact power flows that could potentially overload parts of the system, 22
26 Page 38, PJM Filing.
PDF page 19
18
meaning that transmission upgrades may still be necessary to ensure the 1
reliability of the system.
2
However, if the co-located load in this configuration is added in 3
certain areas of the transmission system (such as a local generation pocket 4
that requires exporting electricity) or in conjunction with an increase in 5
generation, there may be minimal if any required transmission system 6
upgrades. In fact, these co-located loads may even reduce potential 7
transmission system overloads and future potential upgrades.27
8
• Interruptible: Under this configuration, because PJM has the ability to 9
interrupt the co-located load to ensure transmission system reliability, there 10
is minimal, if any, impact to transmission system costs.28
11
12
For any energy that is withdrawn on an “as-available” basis in the 13
“generator-contingent” or “interruptible” configuration, this energy would only be 14
provided if the transmission system, as built, is capable of delivering it. This would 15
therefore not require any additional investment in transmission infrastructure. 16
27 Page 11, https://ferc.gov/libraries/pdf.js/web/viewer.html?file=https%3A%2F%2Fferc.gov%2Fsites%2Fdefault%2Ff iles%2F2024-10%2FCo-located%2520Load%2520Solution%2520Paper.pdf.28 Note that PJM would also have the ability to interrupt for issues related to resource adequacy.
PDF page 20
19
3 Current Rate is Unjust and Unreasonable
1
Q22. HOW DOES THE CURRENT PJM TRANSMISSION TARIFF APPLY TO
2
CO-LOCATED LOADS?
3
A22. The current tariff does not provide sufficient clarity on how co-located loads should 4
be charged for transmission service, resulting in different interpretations and 5
applications of the tariff by different transmission owners within PJM. Several 6
transmission owners have interpreted the tariff as requiring all loads (co-located or 7
not) to be served under NITS, take firm service, and pay for transmission service 8
based on their full gross load, even if no electricity is being withdrawn from the 9
transmission system. For example, in its proposed revisions to its Open Access 10
Transmission Tariff (“OATT”), Exelon—through Atlantic City Electric 11
Company—states that “[s]ervice to such co-located load is Network Integration 12
Transmission Service (“NITS”) as defined in the PJM OATT.” 29 Other 13
transmission owners have interpreted the tariff as allowing co-located 14
configurations. For example, PSE&G has stated that “data centers should have the 15
option to select a configuration that best fits their particular circumstances and 16
needs – whether this is in front of the meter or a co-location arrangement.”30 PPL 17
also supported a co-location arrangement without requiring the co-located load to 18
take NITS service; in their proposed Interconnection Service Agreement (“ISA”) 19
with Susquehanna Nuclear, LLC, PPL states that “[t]he Co-Located Load is not 20
29 Transmittal, page 4, Docket No. ER24-2888-000.
30 Response of Public Service Electric and Gas Company to the Show Order Cause, page 1, EL25-49.
PDF page 21
20
Network Load, and it is intended that the Co-Located Load will never consume 1
capacity and/or energy from the PJM Transmission System, including the 2
Interconnected Transmission Owner’s transmission facilities.”31 Even PJM until 3
recently supported the notion that “[c]o-located must either be PJM Network Load 4
(with applicable firm transmission service or not PJM Network Load (load without 5
applicable firm transmission service.”32
6
Q23. IS THE TARIFF’S LACK OF CLARITY ALIGNED WITH RATE DESIGN
7
PRINCIPLES?
8
A23. No. One of Bonbright’s foundational rate design principles states that rates should 9
be “free from controversies as to improper interpretation.”33 The fact that different 10
transmission owners are interpreting the tariff differently is an obvious indicator of 11
the ambiguity of the existing tariff. Additionally, Bonbright states that rates should 12
be “non-discriminatory.” The fact that the possibility exists that some co-located 13
loads may be charged for transmission based on their gross behind-the-meter load 14
while others may be charged based on net withdrawal from the transmission system 15
purely based on the local transmission owner’s tariff interpretation is unduly 16
discriminatory and not aligned with this principle.
17
Q24. CONSIDERING THE AMBIGUITY PRESENT IN THE CURRENT
18
TARIFF, IS THE INTERPRETATION THAT REQUIRES CO-LOCATED
19
LOAD TO TAKE NITS SERVICE AND PAY TRANSMISSION CHARGES
20
31 Susquehanna ISA Amended, page 106, Docket No. ER24-2172-000.32 Page 4, https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co- located-load.pdf.33 James C. Bonbright, Principles of Public Utility Rates, page 291.
PDF page 22
21
BASED ON GROSS LOAD ALIGNED WITH PRECEDENT AND
1
TREATMENT OF OTHER LOADS IN PJM?
2
A24. No. Requiring all load to be served under NITS (or Point-to-Point service) and 3
assessing charges based on gross load is inconsistent with treatment of other loads 4
in PJM. Neither PJM nor any of its transmission owners (including the ones that 5
assert above that co-located load is network load) require full NITS service for load 6
served directly by behind-the-meter generation, whose transmission charges are 7
determined based on their net load served by the transmission system. 34 This 8
applies to both non-retail and retail behind-the-meter generation. While one 9
subcategory of behind-the-meter generation, called non-retail behind-the-meter 10
generation, is capped at 3,000 MW, 35 the amount of retail behind-the-meter 11
generation is much larger; PJM estimates that retail behind-the-meter solar capacity 12
across its footprint in 2025 totaled more than 10,000 MW.36
13
Q25. IS A TARIFF THAT REQUIRES CO-LOCATED LOAD TO PAY NITS
14
BASED ON GROSS LOAD CONSISTENT WITH THE PRINCIPLE OF
15
FAIR APPORTIONMENT OF COSTS?
16
A25. No. None of the configurations of co-located load (firm, generator-contingent, or 17
interruptible) impose the same costs on the transmission system as a NITS customer 18
that is directly connected to the transmission system. Charging customers that 19
34 Appendix A: https://www.pjm.com/-/media/DotCom/documents/manuals/m14d.pdf. 35 Id.
36 Page 2, https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/fact-sheets/distributed-energy- resources.pdf.
PDF page 23
22
impose different costs on the system in an equivalent manner is misaligned with 1
the principle of fair apportionment of costs and is inequitable.
2
Q26. IS A TARIFF THAT REQUIRES CO-LOCATED LOAD TO PAY NITS
3
BASED ON GROSS LOAD CONSISTENT WITH THE PRINCIPLE OF
4
ECONOMIC EFFICIENCY?
5
A26. No. Requiring all co-located loads to take firm NITS (or Point-to-Point service) 6
based on gross load stands in direct conflict with the principle of economic 7
efficiency for two reasons. First, if all load is charged equivalently regardless of its 8
impact on the transmission system, load will have no incentive to seek 9
configurations that could lower transmission system costs, and they therefore will 10
not. This will cause total costs to rise due to inefficient and ultimately unnecessary 11
investments in the transmission system. Serving all load in a manner that does not 12
minimize costs stands directly in conflict with the principle of economic efficiency. 13
Secondly, unnecessary and inefficient costs may slow down – or even discourage 14
– the interconnection of new beneficial load, which would hinder the interests of 15
the United States. Dr. Paul Stockton states “[t]hat speed advantage should constitute 16
a key factor in assessing the national security implications of co-location.”37 This 17
would additionally forego opportunities for these new loads to contribute to the 18
costs of the grid above and beyond the costs they are imposing on the grid, as I 19
demonstrate in the subsequent section, which would ultimately increase costs for 20
other ratepayers.
21
37 Constellation Answer, Docket Nos. EL25-49-000, et al., Exh. 1, Affidavit of Paul Stockton at 2.
PDF page 24
23
Q27. WHAT IS YOUR OVERALL ASSESSMENT OF THE CURRENT TARIFF?
1
A27. The current tariff does not provide clarity to transmission owners regarding how 2
co-located loads should be treated, which does not align with the principle that rates 3
should be “free from controversies as to improper interpretation.” Additionally, the 4
interpretation of some transmission owners to require co-located load to be served 5
under NITS and charged for transmission on a gross load basis while 6
simultaneously allowing other loads to net their transmission charges using behind- 7
the-meter generation also conflicts with the principle of “non-discrimination.” 8
Furthermore, failing to provide an option for loads to interconnect and use 9
the system in a lower cost co-location configuration impacts not just how costs are 10
allocated between customers but how system costs are incurred. Loads without an 11
incentive to interconnect and use the system in a lower cost way impose higher 12
transmission costs on the system, if they even materialize at all. Recognizing that 13
producers and consumers respond to incentives is one of the most fundamental 14
principles of economics, and indeed the concept that the entire PJM competitive 15
market is based on.
16
The failure of the current tariff to provide a clear, non-discriminatory, fair 17
and equitable, and economically efficient rate for co-located loads that impose 18
lower transmission system costs is unjust and unreasonable.
19
PDF page 25
24
4 Ideal Rate Structures for Co-Location Configurations
1
Q28. PLEASE PROVIDE AN OVERVIEW OF A JUST AND REASONABLE
2
RATE DESIGN FRAMEWORK FOR CO-LOCATED LOADS.
3
A28. A just and reasonable rate design framework for co-located loads would provide 4
different rate options for each of the three different configurations of co-located 5
load based on the cost impacts that are caused by the load: “firm,” “generator- 6
contingent,” and “interruptible.” Each rate design would adhere to the principles 7
of:
8
▪ Fair apportionment of costs: rates should be designed in a manner 9
such that co-located loads with lower impacts on the transmission 10
system should be responsible for a lower proportion of transmission 11
costs. Notably, PJM’s statement that “whether the transmission system 12
needs to be planned to be able to serve these large loads if they are co- 13
located and operate behind the meter of a generator will be instructive 14
to the question of transmission cost allocation”38 is aligned with this 15
principle.
16
▪ Economic efficiency: rates should encourage loads to site and
17
configure in an economically optimal manner that, all else equal, results 18
in lower transmission system costs.
19
38 Page 8, Bresler, Overview of Large Co-Located Load Issues, FERC Technical Conference, November 2024
PDF page 26
25
These rates would also be implemented in a manner that is clear in interpretation 1
and non-discriminatory.
2
Q29. WHY IS IT IMPORTANT TO OFFER MULTIPLE OPTIONS FOR RATE
3
DESIGNS FOR CO-LOCATED SERVICE?
4
A29. The existence of multiple options for co-located loads to interconnect under 5
different arrangements is, itself, foundational to economically efficient tariff 6
design. Large customers seeking interconnection as co-located loads will have a 7
range of expectations and preferences for the level of reliability of service, and 8
providing multiple options enables those customers to evaluate trade-offs between 9
reliability and cost. To the extent that each individual rate design is aligned with 10
principles of fair apportionment of costs and economic efficiency, those choices 11
will also promote lowest cost outcomes for the system as a whole. This result can 12
only be achieved if co-located loads can tailor their requests for service to match 13
their needs and values. In contrast, the current tariff, which a number of 14
transmission owners interpret as requiring all co-located customers to subscribe to 15
a firm service, will invariably result in some customers paying higher costs to fund 16
transmission upgrades that are not needed to provide the level of service they desire. 17
This concept is illustrated in the figure below.
18
PDF page 27
26
Figure 3: Efficiency of Multiple Rate Options
1
2
Q30. WHAT TARIFF COMPONENTS DO YOU CONSIDER IN THE
3
DEVELOPMENT OF A JUST AND REASONABLE RATE DESIGN?
4
A30. I consider multiple tariff components in the development of a just and reasonable 5
rate design for each co-location configuration. Each of these components may be 6
structured differently depending on co-location configuration. I address each of the 7
following tariff components in a standalone subsection below.
8
• Transmission
9
• Ancillary services
10
• Energy
11
• Capacity
12
• Non-PJM charges
13
PDF page 28
27
4.1 Transmission Charges
1
Q31. PLEASE PROVIDE AN OVERVIEW OF HOW TRANSMISSION
2
CHARGES SHOULD BE IDEALLY APPLIED TO THE THREE
3
DIFFERENT CONFIGURATIONS OF CO-LOCATED LOAD.
4
A31. For each of the three configurations of co-located load, I describe a transmission 5
charge that is consistent with principles of 1) fair apportionment of costs and 2) 6
economic efficiency, recognizing the impacts that each arrangement will have on 7
the system.
8
• Firm: Co-located loads with firm service would be assessed charge equal 9
to the greater of 1) standard NITS applied to the load’s net usage and 2) a 10
standby charge based on a customer-designated firm load subscription level. 11
The standby rate would be discounted relative to the NITS rate to reflect the 12
customers’ reduced impact on the transmission system. These customers 13
would have the right to draw power from the transmission system up to their 14
subscribed level if co-located generation is unavailable.
15
• Generator-contingent: Co-located loads with generator-contingent service 16
would be subject to a one-time system impact charge for any transmission 17
upgrades identified as necessary to preserve transmission system reliability 18
at the time of their interconnection. To the extent that energy is allowed to 19
be drawn from the system on an as-available basis, this would be assessed 20
a discounted $/MWh transmission charge.
21
• Interruptible: No standby or one-time system impact charges for 22
transmission service would be applied to co-located loads that are 23
PDF page 29
28
interruptible, reflecting the fact that such loads should have no impact on 1
the transmission system design, as PJM would have the ability to curtail 2
those loads when system conditions require (even if the co-located 3
generator is available) to manage transmission system reliability. Any 4
energy that is drawn from the system on an as-available basis would be 5
assessed a discounted $/MWh transmission charge.
6
Q32. PLEASE PROVIDE MORE DETAIL ON THE TRANSMISSION CHARGE
7
FOR A FIRM CO-LOCATION CONFIGURATION.
8
A32. Consistent with FERC precedent and non-discriminatory treatment with behind- 9
the-meter generation, the starting point for a co-located load configuration should 10
be a net billing construct that measures the actual energy flowing between the entire 11
co-location configuration and the transmission system. To the extent that the entire 12
configuration is drawing energy during the coincident peak hours, the co-located 13
load should be charged for any net draw from the transmission system at full NITS 14
rate, which is consistent with all NITS customers.
15
However, there is a high likelihood that the co-located generator will be 16
available during the coincident peak hours, meaning that the co-located load is 17
unlikely to be withdrawing energy during coincident peak hours. For this reason, 18
conventional NITS charges based on net system energy withdrawals may not fully 19
capture the costs associated with designing the transmissions system to ensure the 20
co-located load could be served (including during coincident peak load hours) even 21
if the on-site generation is unavailable.
22
PDF page 30
29
Because of this, the appropriate rate for a firm co-located load customer is 1
a standby charge to reflect the fact that the transmission system must be built to a 2
certain extent to serve the load on a firm basis. The standby charge would be applied 3
not to any specific metered gross or net usage but rather a customer-designated firm 4
load subscription level of what the customer could draw from the transmission 5
system.
6
The appropriate $/MW standby charge rate would be discounted relative to 7
NITS to reflect the diversity of co-located generation and that most will be available 8
during the coincident peak, which means that the transmission system does not need 9
to be designed assuming that all co-located generation is unavailable at the same 10
time. This concept is well-established in the industry, for example, a 11
Standby/Capacity Reservation Charge Best Practices and Review prepared for the 12
Pennsylvania Public Utility Commission states that “standby rate design should not 13
assume that all forced outages of on-site generators occur simultaneously, or at the 14
same time as the utility peak.” 39 Further, the Pennsylvania Public Utility 15
Commission supports discounting standby charges relative to firm charges based 16
on its statement “it is reasonable and just to pro-rate distribution charges for standby 17
customers.”40
18
39 Page 12, https://www.puc.pa.gov/Electric/pdf/CHPWG/Standby_Cap_Res_Best_Practices_Review- 071618.pdf.
40 Page 12, https://hunterstonconsulting.com/Hunterston%20Consulting%20- %20Where%20Things%20Stand%20on%20Standby%20Aug%202019.pdf.
PDF page 31
30
Q33. HOW WOULD A DISCOUNT BE DETERMINED?
1
A33. Such a discount should be calculated through a study conducted by PJM that 2
reflects the cost of serving these customers, which is aligned with best practices for 3
developing standby rates.41 Other important best practices include that rate should 4
be simple and transparent and reflect the specific attributes of the co-located 5
generator in question. This could be accomplished through discounts that are a 6
function of the 1) type of resource, i.e. nuclear, solar, storage, etc. and 2) resource- 7
specific performance data, such as historical forced outage rates of the generation 8
with which the load is co-located. Such an approach would not be dissimilar from 9
the PJM capacity accreditation process that accredits resources based on their 10
technology “class” combined with an individual “resource performance 11
adjustment.”42 The discounts resulting from these calculations can be meaningful. 12
For example, the Pennsylvania Public Utility Commission approved a discounted 13
rate of $2.50/kW relative to the utility proposed $8/kW for Duquesne Light 14
Company based on the rationale that “it is reasonable and just to pro-rate 15
distribution charges for standby customers.”43
16
Q34. IS THERE PRECEDENT IN PJM FOR SUCH DISCOUNTED STANDBY
17
CHARGES RELATIVE TO FULL REQUIREMENTS SERVICE?
18
A34. Yes, multiple utilities offer discounted standby service in PJM. For example, 19
Exelon subsidiary Delmarva Power offers a “Standby Service” applicable to 20
41 Page 24, https://betterenergy.org/wp-content/uploads/2021/04/best-practices-for-standby-rates-for- combined-heat-and-power.pdf.42https://www.pjm.com/-/media/DotCom/documents/manuals/m21a.pdf.43 Page 12, https://hunterstonconsulting.com/Hunterston%20Consulting%20- %20Where%20Things%20Stand%20on%20Standby%20Aug%202019.pdf.
PDF page 32
31
customers whose power is normally supplied through on-site generation. The rates 1
are discounted by 20% relative to standard service.44
2
Q35. HOW WOULD THE STANDBY CHARGE INTERACT WITH THE NITS
3
CHARGE APPLIED TO THE NET DRAW OF THE CO-LOCATION
4
CONFIGURATION DURING THE COINCIDENT PEAK?
5
A35. The transmission charges to the customer in a firm configuration should be the 6
greater of the standby charge or net load NITS charges. This ensures that firm 7
customers that avoid net usage from the system during the coincident peak 8
contribute to the costs they impose on the system but are not charged more than 9
other firm customers. This construct has the additional benefit of incentivizing 10
avoidance of net usage during the coincident peak through strategies such as 11
performing maintenance and nuclear refueling outside of summer months. This has 12
the impact of reducing coincident peak and transmission system costs. 13
Q36. PLEASE PROVIDE MORE DETAIL ON THE ONE-TIME SYSTEM
14
IMPACT
CHARGE
FOR
A
GENERATOR-CONTINGENT
CO-
15
LOCATION CONFIGURATION.
16
A36. As described in Section 2, a co-located load whose ability to use electricity is 17
contingent upon the availability of on-site generation would not impose the costs 18
in the same manner as a firm load, as PJM would have no obligation to serve the 19
44 Pdf Page 166, Rider “S”, https://www.delmarva.com/cdn/assets/v3/assets/blt47b6e332b18fb457/bltefc1a0bec7ba2be7/67ed6ee63c65 952497e53e9c/2025-03-05_MASTER_MD_DPL_Tariff_Book_1.pdf?branch=prod_alias.
PDF page 33
32
load from the grid. For this reason, a rate design that charges this load equivalently 1
to a firm configuration is inappropriate.
2
However, a generator-contingent configuration may impact grid power
3
flows in a way that requires transmission system upgrades as quantified through a 4
study process (either a “necessary study” or additional studies45) that evaluates 5
generation interconnection modification. This study process would identify any 6
transmission reinforcements or network upgrades needed to resolve reliability 7
violations due to the addition of co-located load in this configuration and quantify 8
the cost of these modifications as part of the study results. The appropriate rate 9
design for a generator-contingent co-located load customer is a one-time system 10
impact charge based on the cost of these transmission system reinforcements and 11
upgrades.
12
Q37. HOW DOES YOUR PROPOSAL TO ALLOCATE A ONE-TIME SYSTEM
13
IMPACT
CHARGE
TO
CUSTOMERS
USING
GENERATOR-
14
CONTINGENT SERVICE ALIGN WITH RATE DESIGN PRINCIPLES?
15
A37. The construct I describe for generator-contingent service provides a natural 16
incentive for loads to co-locate with existing generators in locations where requisite 17
transmission reinforcements or network updates upgrades associated with the 18
generator interconnection modification would be lower or perhaps non-existent at 19
45 Pages 4-5. “The necessary studies (emphasis added) process provides PJM an opportunity to perform studies to evaluate the potential reliability impact of a proposed addition or reduction of a co-located load configuration on the PJM Transmission System, and determine what, if any, system reinforcements are required prior to the addition or reduction of the planned co-located load configuration […] Transmission Owner may require additional studies (emphasis added) based on the planned co-located load configuration, and such studies may result in additional study costs. https://www.pjm.com/- /media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.pdf.
PDF page 34
33
all, much like how current interconnection charges incentivize generators to do the 1
same. Similarly, when new loads are co-located with new or increased generation, 2
the co-location of new load and generation could provide for lower system impact 3
charges if transmission reinforcements or network upgrades are minimal. Both 4
outcomes adhere to the principle of economic efficiency by reducing transmission 5
system costs through more efficient siting and by substituting lower cost generation 6
for transmission system upgrades where feasible.
7
This construct also ensures that other network loads are not allocated any 8
costs associated with the interconnection or modification of a generator, which is 9
consistent with prior FERC orders.46 Finally, this charge appropriately recognizes 10
any costs due to changes to the configuration of a generator should be borne by the 11
generator and not other ratepayers.
12
Q38. HOW WOULD A SYSTEM IMPACT CHARGE BE ASSESSED IN A
13
SITUATION
WHERE
NO
REQUIRED
TRANSMISSION
14
REINFORCEMENTS OR NETWORK UPGRADES ARE IDENTIFIED?
15
A38. In the case where a co-located load taking generator-contingent service does not 16
require transmission reinforcements or network upgrades, no system impact charge 17
would be assessed. There are several possible scenarios where such an outcome 18
may occur. For example, if the co-located load is interconnecting in certain areas 19
of the transmission system (such as a local generation pocket that requires exporting 20
46 For example, FERC Order 2003-B states that “This order reaffirms that an important objective of the Commission's pricing policy is the protection of the Transmission Provider's existing Transmission Customers, including native load, from subsidizing Network Upgrades required to interconnect merchant generators.”
PDF page 35
34
electricity), the co-located load may actually reduce congestion and defer or 1
eliminate future transmission system investments. In this case, the co-located load 2
would not be assessed a system impact charge. Another potential scenario is when 3
a co-located load interconnects in a part of the system that has some level of excess 4
transmission capacity that can accommodate the new load without any near-term 5
additional investment. In this case, not assigning a system impact charge is 6
consistent with how generators are charged for their use of the system on a first- 7
come, first-served basis.
8
Q39. PLEASE PROVIDE MORE DETAIL ON WHY A STANDBY CHARGE OR
9
SYSTEM
IMPACT
CHARGE
ARE
INAPPROPRIATE
FOR
AN
10
“INTERRUPTIBLE” CO-LOCATION CONFIGURATION?
11
A39. As described in Section 2, an interruptible co-located load does not require the 12
transmission system to be planned, built, or adapted in any way to accommodate 13
the load because PJM can interrupt the load when needed to avoid system impacts. 14
Therefore, no standby or system impact charges are appropriate. To the extent that 15
co-located load withdraws energy from the system on an as-available basis, a 16
discounted $/MWh transmission charge would be applied (described more below), 17
meaning that there is no potential free-riding.
18
PDF page 36
35
Q40. HOW WOULD PJM ENSURE THAT CO-LOCATED LOADS INTERRUPT
1
WHEN NECESSARY AND DO NOT DRAW SYSTEM ENERGY
2
WITHOUT APPROVAL?
3
A40. While interruption would primarily be accomplished through the co-located load’s 4
response to an instruction from PJM, this would ultimately be enforced through 5
physical protection schemes. In other words, the operational security of the grid 6
would not be solely premised on actions of co-located loads themselves. PJM 7
maintains the operational security of the grid today through physical protections, 8
and the use of these components for a co-located load are not manifestly different 9
than at any other part of the grid. One common mechanism that system operators 10
use is a remedial action scheme, which are automatic controls to take predefined 11
corrective actions to prevent system impacts.47 To the extent that PJM incurs costs 12
to install or operate the remedial action scheme, this cost should appropriately be 13
borne by the co-located load.
14
Q41. ARE THE IDEAL TRANSMISSION CHARGES THAT YOU OUTLINE
15
ABOVE CONSISTENT WITH THE CONCEPTS OF GROSS OR NET
16
BILLING?
17
A41. All the rate designs that I describe above are consistent with a net billing construct 18
in the sense that none of them apply transmission charges to a separately metered 19
co-located gross load. Such a construct is consistent with precedent for all other 20
PJM customers that are billed on a net basis. A net billing construct is necessary to 21
47https://www.nerc.com/pa/stand/prjct201005_2spclprtctnsstmphs2/faq_ras_definition_0604_final.pdf.
PDF page 37
36
differentiate customers who impose different costs on the transmission system. For 1
avoidance of doubt, a gross billing construct is incapable of differentiating 2
customers who impose different costs on the transmission system through co- 3
location. With that said, the ideal rate designs that I outline do not simply assess 4
zero charges for zero net use of the transmission system as described above. 5
Q42. EVEN THOUGH THESE IDEAL RATE STRUCTURES DO NOT RELY ON
6
GROSS
BILLING
FOR
TRANSMISSION
CHARGES,
DO
YOU
7
RECOMMEND
THAT
CO-LOCATED
LOAD
BE
SEPARATELY
8
METERED?
9
A42. Yes. Co-located load should have separate revenue metering and telemetering for 10
multiple reasons. First, telemetering provides PJM operational visibility and 11
control. Second, separate revenue metering enables gross billing that may be 12
appropriate for some charges. Separate metering is also consistent with rules for 13
behind-the-meter generation.48
14
Q43. DO THE CONFIGURATIONS YOU OUTLINE ALLOW THE CO-
15
LOCATED LOADS TO DRAW ENERGY FROM THE TRANSMISSION
16
SYSTEM?
17
A43. The firm configuration allows the co-located load to draw energy from the grid on 18
a firm basis if the co-located generator is offline. The interruptible configuration 19
allows co-located load to draw energy from the grid on an as-available basis if there 20
48 “BTMG that is 10 MW or greater (or has been identified as requiring metering for operational security reasons) must have both revenue metering and telemetering for operational security purposes.” Page 180, Appendix A, PJM Manual 14D. https://www.pjm.com/- /media/DotCom/documents/manuals/m14d.pdf.
PDF page 38
37
are no system impacts. The generator-contingent configuration can be optionally 1
designed to allow for as-available energy purchases as well. In both cases, as- 2
available energy purchases would only be allowed to the extent such withdrawals 3
did not compromise transmission system reliability or system resource adequacy. 4
Any as-available energy purchases would be assessed an additional transmission 5
charge.
6
Q44. WHAT IS THE APPROPRIATE BASIS FOR TRANSMISSION CHARGES
7
FOR AS-AVAILABLE ENERGY PURCHASES?
8
A44. On the one hand, any use of the transmission system associated with as-available 9
energy purchases does not impose any costs on the transmission system because, 10
by definition, the very ability to supply as-available energy implies that the system 11
as built has available headroom to meet additional load without compromising or 12
threatening reliability. In this sense, assessing no charge would be aligned with both 13
cost causation and economic efficiency principles. On the other hand, withdrawing 14
energy from the transmission system clearly reflects a “use” of the transmission 15
system, and assessing no charge would be free-riding.
16
The appropriate transmission charge for as-available energy purchases is 17
not to provide free service but rather to discount charges by marginal cost to reflect 18
the eliminated cost impacts on the system. Providing a discount to the firm rate is 19
consistent with ensuring that all customers using the system contribute to the 20
recovery of embedded system costs and that no customers receive a free ride. 21
PDF page 39
38
Q45. PLEASE PROVIDE AN EXAMPLE OF HOW A TRANSMISSION
1
MARGINAL COST COULD BE CALCULATED IN PJM.
2
A45. One well-accepted methodology for calculation transmission marginal costs is the 3
discounted total investment method. 49 PJM’s 2024 Regional Transmission
4
Expansion Plan (“RTEP”)50 and its associated 2024 Load Forecast vintage51 can be
5
used as inputs into this method. 52 The 2024 RTEP report indicates that
6
approximately $15.8 billion in transmission capital expenditures (net present value, 7
“NPV”) are expected over the next ten years.53 While not all of these expenditures
8
are driven by load growth, a reasonable assumption is that approximately 50% are
9
driven by growing loads, totaling $7.9 billion. Over this same ten-year time
10
horizon, PJM forecasts approximately 20.3 GW54 of peak demand growth (NPV).55
11
Finally, a real economic carrying cost (“RECC”) can be estimated as 6.6%,
12
assuming a transmission asset lifetime of 40 years and a real weighted average cost 13
of capital (“WACC”) of 6.0%.56 Dividing the long-run marginal transmission cost
14
49 For example, see Section 20.1 https://www.raponline.org/wp-content/uploads/2023/09/rap-lazar- chernick-marcus-lebel-electric-cost-allocation-new-era-2020-january.pdf.
50https://www.pjm.com/-/media/DotCom/library/reports-notices/2024-rtep/2024-rtep-report.pdf.51https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2024-load-report.pdf. 52 RTEP provides one potential methodology to estimate transmission marginal costs by estimating representative transmission projects that are load growth-driven and using their costs to determine the incremental cost required to meet an additional kW of peak load.53 Based on sum of “Estimated Cost, Inflation Adjusted ($M)” for “Baseline” and “Supplemental” projects. Note that these values, sourced directly from the 2024 RTEP, are assumed to be a NPV of the transmission investment forecast. Page 341, https://www.pjm.com/-/media/DotCom/library/reports-notices/2024- rtep/2024-rtep-report.pdf. 54 20.3 GW of peak demand growth is lower than the latest 2025 PJM load forecast. However, using this value is necessary for the purposes of calculating transmission marginal cost because it aligns with the 2024 RTEP report. An RTEP that uses higher load growth projections would also likely have significantly higher forecasted costs. The impact of higher load growth and higher costs would likely offset each other, and so the value presented in the main body reasonably represents long-run transmission marginal costs.55 20.3 GW represents the net present value of peak load growth. Value is calculated by discounting the 2024-2034 forecasted annual peak load growth in PJM’s 2024 Load Forecast report using a 6.0% real weighted average cost of capital (“WACC”), and then summing those values. 56 Note that the values presented for the transmission asset lifetime (40 years) and the real WACC (6.0%) are both assumptions. Real economic carrying charge = 6.0% * (1 + 6.0%)^40 / ( (1+6.0%)^40 - 1 ).
PDF page 40
39
($7.9 billion) by the long-run load growth (20.3 GW) and then multiplying by the 1
RECC (6.6%) yields an estimated transmission marginal cost of $26/kW-year. A 2
full overview of this calculation is provided below.
3
Figure 4: Transmission Marginal Cost Formula
4
𝑇𝑟𝑎𝑛𝑠𝑚𝑖𝑠𝑠𝑖𝑜𝑛 𝑀𝑎𝑟𝑔𝑖𝑛𝑎𝑙 𝐶𝑜𝑠𝑡= 𝑁𝑃𝑉 𝑜𝑓 𝑃𝑒𝑎𝑘 𝐷𝑟𝑖𝑣𝑒𝑛 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡𝑠 𝑁𝑃𝑉 𝑜𝑓 𝑃𝑒𝑎𝑘 𝐿𝑜𝑎𝑑 𝐺𝑟𝑜𝑤𝑡ℎ
× 𝑅𝐸𝐶𝐶× 𝑃𝑒𝑎𝑘 𝐿𝑜𝑎𝑑 𝐷𝑟𝑖𝑣𝑒𝑛 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡𝑠
5
𝑇𝑟𝑎𝑛𝑠𝑚𝑖𝑠𝑠𝑖𝑜𝑛 𝑀𝑎𝑟𝑔𝑖𝑛𝑎𝑙 𝐶𝑜𝑠𝑡= $15,808 𝑚𝑖𝑙𝑙𝑖𝑜𝑛 20,258 𝑀𝑊
× 6.6% × 50% = $25.93 𝑘𝑊
𝑦𝑟
6
This is just one reasonable methodology to estimate the marginal cost of 7
transmission in PJM. For instance, Mr. Patterson utilizes another methodology in 8
his Affidavit, which results in a transmission marginal cost estimate of $27/kW-yr 9
for a 100 MW large load when levelized using the same RECC assumed above.57 10
The general alignment of these two approaches demonstrates that different 11
methodologies can yield robustly similar results.58
12
Q46. HOW CAN THIS MARGINAL COST VALUE BE USED TO DEVELOP A
13
TRANSMISSION
DISCOUNT
FOR
AS-AVAILABLE
ENERGY
14
PURCHASES?
15
A46. The marginal cost of transmission can be used as the basis to discount the firm 16
NITS transmission rate. The firm NITS rate varies in PJM by transmission operator, 17
with a weighted average value across the entire RTO of approximately $63/kW- 18
yr. 59 This indicates that an appropriate discount for interruptible use of the 19
57 Constellation Answer, Docket Nos. EL25-49-000, et al., Exh. 3, Affidavit of Aaron T. Patterson at ¶ 52 ($41 million / 100 MW * 6.6% = $27/kW-year).58 Id. 59 Weighted average NITS rate calculated by dividing the 2024 transmission revenue requirement across all of PJM’s transmission owners ($10,990 million) by the 2024 peak load across all of PJM’s transmission owners (175,243 MW).
PDF page 41
40
transmission system is approximately 41%.60 Importantly, applying this level of 1
discount would result in both interruptible and firm customers contributing equally 2
to the non-marginal costs of the system. In other words, both types of customers 3
would be making equivalent contributions to the fixed costs of the system.
4
Q47. HOW CAN THIS DISCOUNT BE USED TO DEVELOP A SPECIFIC
5
TRANSMISSION RATE FOR AS-AVAILABLE ENERGY PURCHASES?
6
A47. As-available energy purchases are interruptible and can only be made with explicit 7
approval from PJM if there are no anticipated system impacts due to the purchases. 8
For these purchases, the relevant “use” of the transmission system is the quantity 9
of energy that is being withdrawn from it. This is different from firm customers 10
whose “use” of the system is their coincident peak demand that drives transmission 11
investment. Therefore, the appropriate transmission rate for as-available energy 12
purchases is a $/MWh transmission charge, applied to net energy withdrawals from 13
the transmission system.
14
To calculate this charge, PJM could divide the annual transmission revenue
15
requirement ($/year) by annual system energy (MWh/year) to yield a $/MWh value. 16
Discounting this value by 41% yields a final as-available energy transmission 17
charge of approximately $8/MWh.61
18
60 $26/kW-yr marginal cost of transmission divided by $63/kW-yr weighted average PJM NITS rate = 41%.
61 PJM’s transmission revenue requirement across all transmission owners totaled $10,990 million in 2024, while the annual system-wide load totaled 813,328 GWh. This would equate to an undiscounted energy charge of $13.40/MWh to cover all transmission system costs. Discounting this value by 41% yields an energy charge of $7.91/MWh. https://www.pjm.com/-/media/DotCom/markets-ops/settlements/network- integration-trans-service-january-2024.pdf; https://www.pjm.com/-/media/DotCom/library/reports- notices/load-forecast/2024-load-report.ashx.
PDF page 42
41
I perform this calculation not to be overly prescriptive with a specific value 1
but rather to illustrate a methodological framework for how loads that use the 2
system but do not impose any cost on the system can fairly contribute to the 3
recovery of fixed costs of the system.
4
Q48. IS THERE PRECEDENT FOR SUCH A $/MWH TRANSMISSION
5
CHARGE FOR AS-AVAILABLE ENERGY PURCHASES?
6
A48. Yes. One example of such a service is the Alberta Electric System Operator 7
(“AESO”) Demand Opportunity Service, which is designed to utilize surplus 8
transmission capacity.62 This service is offered on an interruptible basis, meaning 9
the AESO can recall service to ensure that system operations are not compromised. 10
This rate for this service is a $/MWh transmission charge of approximately 11
$7/MWh CAD, which is calculated using a methodology similar to what I describe 12
above.63
13
Q49. WHAT
IS
THE
IMPACT
ON
EXISTING
RATEPAYERS
OF
14
COLLECTING AS-AVAILABLE TRANSMISSION CHARGES FROM CO-
15
LOCATED LOADS?
16
A49. Collection of as-available transmission charges would directly benefit existing 17
ratepayers by reducing rates since as-available energy purchases by co-located 18
loads would contribute to the recovery of transmission costs without requiring any 19
additional costs be incurred. This is consistent with the AESO’s assessment of the 20
62https://www-integ.aeso.ca/market/market-participation/demand-opportunity-service/.63 Pdf page 11, https://www.aeso.ca/assets/documents/ISO-Tariff-Combined-2025-04-15.pdf.
PDF page 43
42
Demand Opportunity Service which states that “[t]he revenues from [Demand 1
Opportunity Service] are applied toward lowering overall transmission costs.”64 2
4.2 Ancillary Service Charges
3
4
Q50. PLEASE DESCRIBE ANCILLARY SERVICES AND THE IMPACT OF
5
CO-LOCATED LOADS ON THESE SERVICES.
6
A50. Ancillary services are procured by PJM to maintain reliability at all times. There 7
are multiple ancillary service products including:
8
• Regulation: Resources that quickly ramp up or down on a second-to- 9
second basis to keep the grid in balance despite short-term variation in load 10
and generation. The generation output may vary based on its service to co- 11
located loads and could increase system variability in the same manner 12
intermittent generation increases system variability. It may be appropriate 13
to allocate co-located load a share of regulation costs.
14
• Synchronized and Non-Synchronized Reserves: Resources that are held 15
in standby and able to quickly ramp up in response to contingencies such as 16
a generator or transmission line tripping offline. The required quantity of 17
these services is often not based on load but rather by the size of the largest 18
generator and transmission contingencies on the system. Increasing co- 19
located loads would likely not increase the cost of these services. 20
• Black Start: Resources that can start without grid power, which are 21
required to re-start service in the event of a system-wide blackout. Today, 22
64https://www-integ.aeso.ca/market/market-participation/demand-opportunity-service/.
PDF page 44
43
some generators such as nuclear units require grid power to re-start after a 1
system-wide blackout. However, generators in general have not been 2
required to purchase and pay for this ancillary service and the costs have 3
been allocated to load. An increase in co-located load would not increase 4
the requirement for black start services, but it would re-direct the output of 5
nuclear units away from the network loads that are currently allocated black 6
start costs. For this reason, it may be appropriate to allocate black start costs 7
to co-located loads, which I discuss more below.
8
• Reactive Supply and Voltage Control: Resources that can provide or 9
absorb reactive power to maintain voltage levels on the transmission system 10
within acceptable limits for reliable system operation. To the extent that co- 11
located loads produce or consume reactive power and the co-located 12
generator is not required to maintain existing power factor requirements, 13
this may necessitate additional reactive supply to counteract this and 14
maintain stable grid voltage.
15
• Day-ahead Scheduling Reserves: Resources procured in the Day-Ahead 16
Market to ensure sufficient online reserve capability is available to respond 17
to forecasted system imbalances and contingencies during real-time 18
operations. This service is similar to synchronized and non-synchronized 19
reserves (with similar co-located load impacts), except it is procured on a 20
day-ahead basis.
21
PDF page 45
44
Q51. HOW SHOULD ANCILLARY SERVICES BE CHARGED TO CO-
1
LOCATED LOADS?
2
A51. There are reasonable arguments to support billing ancillary service costs to co- 3
located loads on both a “net” and “gross” basis. On the one hand, there is a clearly 4
established FERC precedent of using net demand as the basis for ancillary service 5
charges, as loads with behind-the-meter generation are charged in this manner.65 6
On the other hand, whereas co-locating load and generation together reduces impact 7
and cost on the transmission system, the same effect does not necessarily exist for 8
ancillary services, which represent a pool of costs allocated across all consumers of 9
energy. In this respect, billing ancillary services costs on a “gross” basis may also 10
be a sensible solution. In any case, the charges for ancillary services are likely to 11
be small relative to other cost categories such as transmission service. 12
4.3 Energy Charges
13
Q52. HOW SHOULD ENERGY CHARGES BE ASSESSED TO CO-LOCATED
14
LOADS?
15
A52. Energy charges should be assessed to co-located generators and loads based on the 16
net injection to or withdrawal from the transmission system. Note that this will yield 17
the same result as separately metering co-located load and co-located generation 18
each on a gross basis.
19
65 See Motion for Leave to Answer and Joint Answer of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Delmarva Power & Light Company, PECO Energy Company and Potomac Electric Power Company to Limited Protest of Natural Resource Defense Council, Atlantic City Elec. Co., Docket No. ER24-2888-000, Baltimore Gas and Elec. Co., Docket No. ER24-2889-000, Commonwealth Edison Co., Docket No. ER24-2890-000, Delmarva Power & Light Co., Docket No. ER24-2891-000, PECO Energy Co., Docket No. ER24-2893-000, Potomac Elec. Power Co., Docket No. ER24-2894-000 (Sep. 27, 2024) (collectively, the “Exelon Answer”), at 6.
PDF page 46
45
4.4 Capacity Charges
1
Q53. WHAT IS THE IMPACT OF CO-LOCATED LOADS ON RESOURCE
2
ADEQUACY?
3
A53. The resource adequacy impact of a new load is not dependent upon whether it is 4
connected directly to the transmission system or co-located, but instead upon the 5
type of arrangement under which PJM provides that load with transmission service. 6
For example:
7
• If the load is connected directly to the transmission system and takes 8
NITS, it increases demand for capacity which increases the capacity 9
price.
10
• If a load is co-located with a dedicated generator (for example in a 11
generator-contingent configuration), this decreases the supply of 12
capacity (since the generator is dedicated to the load and no longer 13
offering as a capacity resource) which increases the capacity price. 14
15
In both cases, increased load – either directly or indirectly – causes higher 16
capacity prices, which incentivizes more capacity to enter the market. This, in turn, 17
drives the capacity price back down into equilibrium. In fact, new capacity often 18
pre-emptively plans to enter the market in anticipation of higher demand (or lower 19
supply), meaning that a higher capacity price may never materialize in the first 20
place. Finally, because new capacity enters the market in response to higher prices, 21
there is no expected resource adequacy impact due to additional load, either in a 22
co-located or NITS configuration.
23
PDF page 47
46
In both a separately metered or co-located configuration, the load can be 1
interruptible (either through load curtailment or backup generation) which would 2
eliminate its resource adequacy impact. Once again, the impact on resource 3
adequacy is identical under either configuration.
4
Q54. CAN A CO-LOCATED GENERATOR PARTICIPATE IN THE CAPACITY
5
MARKET?
6
A54. For any generator to participate in the capacity market, it is expected to provide 7
output to the grid when system conditions require and when ordered to by PJM. If 8
a co-located generator clears in the capacity market, this means that, at a minimum, 9
it must output to the grid when needed or face performance penalties, even if that 10
means interruption of the co-located load, either through curtailment or backup 11
generation. 66 I agree with PJM’s statement that “no portion of a committed 12
Capacity Resource (whether composed of one or multiple physical generating 13
units) may prioritize serving load that PJM is not responsible for serving.”67 14
Q55. HOW SHOULD CAPACITY CHARGES BE ASSESSED ON CO-LOCATED
15
LOADS?
16
A55. Capacity charges should be consistent with the configuration of the co-located load: 17
• Firm: Because the load is firm with PJM obligation to serve, the entire 18
subscribed load should participate in the capacity market, similarly to any 19
other load. This would assign a capacity requirement to the load based on 20
66 Capacity resources also have a “must-offer obligation” into the day-ahead energy market.
67 Pages 59-60, PJM Filing.
PDF page 48
47
its coincident peak plus a reserve margin. Correspondingly, the entire co- 1
located generator should also participate in the capacity market at a level 2
equal to its accredited capacity. To the extent that the co-located load’s 3
capacity requirement and the co-located generator’s capacity accreditation 4
are not exactly equal, there may be some net capacity sales or purchases. 5
• Generator-contingent: any capacity of the co-located generator 6
exclusively dedicated to the co-located load would not offer into the 7
capacity market. The quantity of the co-located generator that is dedicated 8
to the co-located load would be determined by a subscription designation 9
made by the co-located load. To the extent capacity of a co-located 10
generator is exclusively dedicating its output to a co-located load, it should 11
not be able to offer that capacity into PJM’s capacity market (Reliability 12
Pricing Model, “RPM”) or to any other buyer. Capacity market sales from 13
the co-located generator may be made if the accredited capacity of the co- 14
located generator exceeds the capacity dedicated to the co-located load. Co- 15
located load would be required to curtail to the level of the designated 16
subscription, if necessary, in order to facilitate delivery of any co-located 17
generator capacity sales to PJM or others. Because the co-located load 18
cannot draw energy from the grid, no capacity charges are applied to the 19
load.
20
• Interruptible: the co-located load can be interrupted by PJM when system 21
conditions require regardless of co-located generator availability. 22
Therefore, the output of the co-located generator can be re-directed by PJM 23
PDF page 49
48
from the co-located load to the broader system. Accordingly, no capacity 1
charges should be assessed to the co-located load, and the full accredited 2
capacity of the co-located generator should be able to participate in the 3
capacity market.
4
4.5 Non-PJM Charges
5
Q56. HOW SHOULD NON-PJM CHARGES SUCH AS STATE PUBLIC
6
PURPOSE PROGRAM CHARGES BE ADMINISTERED TO CO-
7
LOCATED LOADS?
8
A56. Non-PJM charges vary by state and local utility and may include non-bypassable 9
charges to fund energy efficiency programs, renewable programs, stranded cost 10
recovery, or more. The jurisdiction of these charges lies with the states. 11
4.6 Summary
12
Q57. CAN THESE IDEAL RATE DESIGNS FOR CO-LOCATED LOADS BE
13
MADE AVAILABLE ON AN INTERIM BASIS?
14
A57. The ideal rate designs that I outline are consistent with rate design principles and 15
can be made available on a long-term or interim basis. To the extent that the 16
customer desires a “firm” or “generator-contingent” configuration that requires 17
system upgrades that are not immediately available, the “interruptible” 18
configuration and rate design could be made available on an interim basis. PJM 19
appears to agree with this position by stating that “certain studied co-located load 20
configurations may require the construction and energization of transmission 21
planning solutions … if such solutions are not yet operational, it may be necessary 22
PDF page 50
49
for the studied co-located load to operate subject to interim operational procedures 1
until the solutions are in service.”68 The relevant interim operational procedure is 2
interruptibility.
3
Q58. WHAT IS THE BENEFIT OF MAKING INTERRUPTIBLE SERVICE
4
AVAILABLE ON AN INTERIM BASIS?
5
A58. Making interruptible service available on an interim basis provides the important 6
benefit of facilitating faster interconnection for loads relative to a generator- 7
contingent or firm configuration. This is because transmission reinforcements and 8
network upgrades required for a generator-contingent or firm configuration can 9
take many years to plan and build. Faster interconnection in and of itself is an 10
enormous efficiency enhancing improvement by allowing the opportunity for both 11
the loads themselves to benefit as well as other ratepayers through better utilization 12
of the existing transmission system and collection of as-available energy 13
transmission charges.
14
Q59. PLEASE SUMMARIZE THE IDEAL RATE STRUCTURE FOR EACH
15
CONFIGURATION OF CO-LOCATED LOAD IN THE TABLE BELOW.
16
A59. The table below provides a summary of the ideal rate design for each potential 17
configuration of co-located load.
18
68 Page 7, Bresler.
PDF page 51
50
Table 1: Summary of Ideal Rate Design for Potential Co-location Configurations 1
Co-location Configuration
Rate
Component
Firm
Generator-
contingent
Interruptible
Transmission
Greater of 1)
Standby charge at
discounted NITS
rate applied to firm
subscription level
or 2) standard
NITS applied to
net usage
One-time system
impact charge
based on studied
network upgrade
costs. If as
available energy
purchases are
allowed, these are
billed at discounted
$/MWh charge
Discounted
$/MWh charge for
as-available energy
purchases
Ancillary
Services
Charges for all
ancillary services
consumed based on
net load (if needed
to avoid
discrimination) or
gross load
Charges for all
ancillary services
consumed based on
net load (if needed
to avoid
discrimination) or
gross load
Charges for all
ancillary services
consumed based on
net load (if needed
to avoid
discrimination) or
gross load
Energy
LMP energy
charges based on
net injection or
withdrawal
LMP energy
charges based on
net injection or
withdrawal
LMP energy
charges based on
net injection or
withdrawal
Capacity
Co-located load
participates in
capacity market at
firm subscription
level. Co-located
generator
participates in
capacity market at
accredited capacity
level
No charges to co-
located load served
by dedicated
portion of
generator (PJM
does not procure
capacity for co-
located load);
capacity market
sales from the co-
located generator
may be made if the
accredited capacity
of the co-located
generator exceeds
the capacity of the
co-located load
No charges to load
(PJM does not
procure for load);
co-located
generator is not
dedicated to co-
located load and
co-located
generator can
participate in
capacity market at
full accredited
capacity
Non-PJM
States decide
States decide
States decide
2
PDF page 52
51
Q60. DO THE RATE DESIGNS YOU SUMMARIZE ABOVE FOR EACH CO-
1
LOCATION
CONFIGURATION
ALIGN
WITH
RATE
DESIGN
2
PRINCIPLES?
3
A60. Yes, each of the rate designs above aligns with well-established Bonbright rate 4
design principles for each co-location configuration. For this reason, each of these 5
rate designs is just and reasonable.
6
PDF page 53
52
5 Assessment of PJM Proposed Rate Options
1
Q61. PLEASE PROVIDE AN OVERVIEW OF THE RATE DESIGN OPTIONS
2
THAT PJM HAS PUT FORWARD IN THIS PROCEEDING.
3
A61. PJM has put forward eight options for service to large loads, three of which they 4
describe as “already existing” and five of which they describe as “potential options 5
that have been proposed by others or developed by PJM in response to issues raised 6
in the various predecessor co-located load proceeding.” PJM’s description for each 7
option is reproduced below.69
8
• Existing Option 1: Load with a separate Point of Interconnection (POI) 9
that is Network Load (Existing NITS rules)
10
• Existing Option 2: Co-located load that is at the same Point of
11
Interconnection (POI) but separately metered that is Network Load
12
(Existing NITS rules)
13
• Existing Option 3: Existing Behind The Meter Generation (BTMG) where 14
the load is the customer
15
• New Option 4: Co-located load with connection to the grid with protections 16
to avoid delivery of system energy to serve the load
17
• New Option 5: Co-located load with connection to grid with protections to 18
avoid delivery of system energy to serve the load or receive back-up service 19
from PJM with permission
20
69 Exhibit A, PJM Filing.
PDF page 54
53
• New Option 6: Co-located load that elects to be Network Load and bring 1
own generation (BYOG)
2
• New Option 7: Co-located load that takes Interruptible Service (load 3
willing to curtail in advance of emergency procedures)
4
• New Option 8: Co-located load that elects to be Network Load and that 5
participates as Demand Response
6
Q62. HOW DO THESE EIGHT OPTIONS ALIGN WITH THE THREE CO-
7
LOCATION CONFIGURATIONS AND RATE DESIGN THAT YOU HAVE
8
OUTLINED?
9
A62. Each of these eight options generally correspond to one of the three fundamental 10
configurations (firm, generator-contingent, interruptible), as demonstrated in the 11
table below.
12
Table 2: Mapping of PJM Rate Options to E3 Fundamental Configurations 13
PJM
Rate
Option
Description
Fundamental
Configuration
(E3 Determination)
1
NITS without co-location
Firm
2
NITS with co-location
Firm
3
Load customer with BTMG
Firm
4
Co-located load with ‘generator-contingent’
protections
Generator-contingent
5
Co-located load with ‘generator-contingent’
protections + as-available energy purchase
option
Generator-contingent
6
NITS with co-location + BYOG
Firm
7
NITS with co-location where load is
interruptible
Interruptible
8
NITS with co-location where load
participates as demand response
Interruptible
14
PDF page 55
54
Q63. DO PJM’S PROPOSED RATE DESIGNS FOR EACH OF THE EIGHT
1
OPTIONS ALIGN WITH RATE DESIGN PRINCIPLES FOR EACH
2
CORRESPONDING CO-LOCATION CONFIGURATION?
3
A63. While PJM’s initial eight rate designs provide a promising start for developing new 4
rates for co-located loads, I believe changes are needed to improve their adherence 5
to the key principles of 1) fair apportionment of costs and 2) economic efficiency. 6
The reasons that each proposed design falls short of the ideal rate design for co- 7
located load are described below; later in this section, I show how three of these 8
designs can be modified to more fairly allocate costs and improve economic 9
efficiency.
10
• Existing Option 1: NITS without co-location
11
While this rate fairly allocates costs and is efficient for firm customers that 12
directly connect to the transmission system, it does not provide any incentive 13
for large loads to co-locate with generators in a manner that would reduce 14
system costs.
15
Only offering this rate without options for different co-location
16
configurations would drive unnecessary transmission build that could be 17
avoided. Such an outcome is misaligned with the principle of economic 18
efficiency.
19
• Existing Option 2: NITS with co-location
20
This rate provides an option for customers to co-locate in a firm
21
configuration, indicated through PJM’s stated affirmative obligation to serve. 22
Assessing transmission charges based on “full load during coincident peak” – 23
PDF page 56
55
which appears to refer to the gross load of the co-located customer – does not 1
provide any discount to reflect the fact that many co-located generators will be 2
on and available during the system peak, offsetting the co-located load and 3
reducing the system cost impact of all loads in this configuration. Because a co- 4
located customer would incur the same costs as a similar customer connected 5
directly to the transmission system despite a lesser impact on the transmission 6
system, this option does not fairly apportion costs.
7
Additionally, if this were the only co-location rate option that was made 8
available (as some parties have proposed) this would provide no incentive for 9
large loads to interconnect in a lower cost ‘generator-contingent’ or 10
‘interruptible’ manner. It would therefore drive unnecessary transmission build 11
that could be avoided and/or discourage new loads from seeking to interconnect 12
in PJM. Such an outcome is misaligned with the principle of economic 13
efficiency.
14
• Existing Option 3: Load customer with BTMG
15
This rate is aligned with PJM precedent for billing customers based on their 16
net use of the system. There is no physical, technical, or economic reason why 17
a netting construct should apply differently for customers with behind-the- 18
meter generation or co-located generation. Therefore, applying this rate option 19
to firm customers in a co-located configuration would be non-discriminatory. 20
Customers in this configuration would still represent firm loads, as 21
evidenced by PJM’s stated affirmative obligation to serve, so the system must 22
be planned and built accordingly. While the aggregate BTMG reduces 23
PDF page 57
56
transmission system costs since some of it will be on and available during the 1
system peak, some discount relative to gross billing is appropriate. However, a 2
“net withdrawal during coincident peak” transmission rate structure does not 3
necessarily provide the appropriate discount that reflects the transmission costs 4
savings that should be determined through a study as described in Section 4. 5
Therefore, this rate is mixed in its alignment of fair apportionment of costs. 6
Providing customers a means to reduce their transmission charges through 7
BTMG sends a price signal for customers to use BTMG, which ultimately 8
reduces transmission system costs. However, price signals that do not align bill 9
savings with transmission cost savings may result in inefficiently high or low 10
investment in BTMG. For this reason, this rate is mixed in its alignment with 11
economic efficiency.
12
• New Option 4: Co-located load with ‘generator-contingent’ protections 13
This rate provides an option for customers to interconnect in a co-location 14
configuration that reduces or eliminates incremental transmission system costs 15
by imposing protections that ensure the load cannot draw energy from the grid. 16
This is equivalent to a “generator-contingent” configuration that never elects to 17
draw as-available energy from the system. PJM appropriately reflects these 18
lower transmission system costs through transmission charges based on net 19
usage, which will by definition be zero due to no net usage. Additionally, PJM 20
indicates that the generator would be “responsible for any system upgrades to 21
serve the load.” Both charges are consistent with the ideal rate structure I 22
PDF page 58
57
describe for a generator-contingent configuration. For these reasons, this rate is 1
aligned with the principle of fair apportionment of costs.
2
The lower transmission charges assessed to customers in this configuration 3
provides a price signal for customers to configure in this manner and is therefore 4
broadly aligned with the principle of economic efficiency. However, this rate 5
does not offer an as-available energy purchase option, and such transactions 6
between the system and the co-located may be mutually beneficial. It therefore 7
has mixed alignment with the principle of economic efficiency.
8
• New Option 5: Co-located load with ‘generator-contingent’ protections + 9
as-available energy purchase option
10
The only apparent difference between Options 4 and 5 is that whereas 11
Option 4 prohibits any draw of electricity from the grid, Option 5 allows for 12
“back-up service from the PJM system with permission. This is equivalent to 13
“as-available” energy that I describe in Section 4. However, this option does 14
not posit any potential charge for this “use” of the transmission system when 15
granted permission by PJM, which enables free-riding. For these reasons, it has 16
mixed alignment with the principle of fair apportionment of costs. 17
The lower charges assessed to customers in this configuration provides a 18
price signal for customers to configure in this manner. Additionally, this rate 19
offers an as-available energy purchase option, providing the opportunity for 20
beneficial transactions for co-located load. For these reasons, this option has 21
good alignment with the principle of economic efficiency.
22
• New Option 6: NITS with co-location + BYOG
23
PDF page 59
58
This rate provides a means for customers to co-locate in a “firm” 1
configuration, indicated through PJM’s stated affirmative obligation to serve. 2
However, assessing transmission charges based on “full load during coincident 3
peak” does not provide any discount to reflect the fact that a firm co-location 4
configuration reduces transmission system costs as described above. For this 5
reason, this option does not fairly allocate costs.
6
Additionally, if this were the only co-location rate option that was made 7
available, there would be no incentive for large loads to interconnect in either a 8
“generator-contingent” or “interruptible” manner, both of which would reduce 9
overall transmission system use and costs. Option 6 would drive unnecessary 10
transmission build that could be avoided. Such an outcome is misaligned with 11
the principle of economic efficiency.
12
Even if this rate were one of several options, this rate does not offer any 13
transmission
cost
savings
to
customers
despite
PJM’s
explicit
14
acknowledgement that it would provide transmission system benefits as 15
demonstrated through anticipated faster interconnection, likely due to avoided 16
transmission upgrades. Because this option does not provide an incentive for 17
customers to configure in a manner that minimizes transmission system costs, 18
it is misaligned with the principle of economic efficiency
19
Finally, rate design principles aside, the suggestion that new generation that 20
directly contracts with a customer – regardless of location, reliability impact, or 21
development status – should be allowed to skip the generation interconnection 22
queue undermines PJM market signals, particularly those of the capacity 23
PDF page 60
59
market. These generation developers will be, in effect, allowed to circumvent 1
the queue process that applies to all generation being built to serve PJM load in 2
a manner that is unfair and not competitive. It has the potential to afford 3
incumbent utilities a distinct advantage against competitive suppliers in a 4
manner that appears misaligned with the premise of PJM competitive markets. 5
Additionally, the BYOG requirement in Option 6 could signal existing 6
generators to deactivate – the opposite signal of what is needed to support 7
resource adequacy. To the extent that loads choose to BYOG, they should be 8
free to do so, but they should not be required to do so.
9
• New Option 7: NITS with co-location where load is interruptible 10
This option offers a means for customers to interconnect in a “interruptible” 11
configuration. As demonstrated above, this configuration would impose 12
minimal if any costs on the transmission system and thus has the potential to 13
interconnect loads in a very beneficially low-cost manner. However, because 14
this option proposes to charge for transmission service based on “full load 15
during coincident peak”, it would not provide any discount relative to firm 16
customers that directly connect to the transmission system, even though a firm 17
co-location configuration reduces transmission system costs as described 18
above. It is therefore misaligned with the principle of fair apportionment of 19
costs.
20
Additionally, while this rate highlights the benefits that interruptibility can 21
provide to the system, it does not actually provide a transmission price signal 22
for customers to operate in an interruptible manner, because customers are 23
PDF page 61
60
billed for transmission service equivalently to firm customers that directly 1
connect to the transmission system. It therefore is less likely that customers will 2
configure and operate in this manner, driving unnecessary and inefficient 3
transmission build that could be avoided. Because it does not drive efficient 4
behavior that minimizes transmission system costs, this rate option (as proposed 5
by PJM without modifications) is misaligned with the principle of economic 6
efficiency.
7
• New Option 8: NITS with co-location where load participates as demand 8
response
9
This rate offers customers the option to interconnect in a “interruptible” 10
configuration. Even though PJM affirmatively states an obligation to serve, 11
PJM also retains the right to ask the co-located load to curtail through demand 12
response. In any event, the load is proposed to be charged for transmission 13
service equivalently to firm customers that directly connect to the transmission 14
system. Because this option does not provide any transmission discount relative 15
to customers that impose higher costs on the system, it is misaligned with the 16
principle of fair apportionment of costs.
17
Additionally, it provides no transmission price signal for customers to 18
configure and provide demand response services. It is therefore less likely that 19
customers will do so, driving unnecessary and inefficient transmission build 20
that could be avoided. Because it does not drive efficient behavior that 21
minimizes transmission system costs, it is misaligned with the principle of 22
economic efficiency.
23
PDF page 62
61
Q64. WHAT IS YOUR ASSESSMENT OF THE RESOURCE ADEQUACY
1
FOCUS OF NEW OPTIONS 6, 7, AND 8 PROPOSED BY PJM?
2
A64. PJM’s preference for these options appears to be premised on the notion that these 3
transmission rates “maintain Resource Adequacy.” This misplaced notion ignores 4
the fact that new load without any of these features (i.e. BYOG, interruptibility, or 5
demand response) increases demand in the capacity market which provides a price 6
signal to attract new capacity, which is the very mechanism to ensure resource 7
adequacy that underpins the existence of the capacity market. To the extent that 8
loads choose to BYOG, be interruptible, or participate as demand response, they 9
should be free to do so, but they should not be required to do so.
10
PJM’s misplaced emphasis on resource adequacy has even led to several 11
unclear statements in their filing. For example, they state that “large loads would 12
be offered the option to be classified as a non-capacity backed load for a transitional 13
period until any resource adequacy supply/demand imbalances associated with the 14
large load could be addressed.” The PJM capacity market is by definition designed 15
to clear an equivalent quantity of supply and demand, meaning that there could only 16
be an “imbalance” relative to the reliability target, which would likely be entirely 17
outside of the control of the load in question. Against this backdrop, how much 18
“imbalance” would PJM tolerate? As proposed, this option is unlikely to be 19
“free[…] from controversies as to proper interpretation,” which is a foundational 20
Bonbright principle.70
21
70 James C. Bonbright, Principles of Public Utility Rates, page 291.
PDF page 63
62
Q65. WHAT IS YOUR ASSESSMENT OF PJM’S STATED PREFERENCE FOR
1
OPTIONS 1, 2, 6, 7, AND 8?
2
A65. The commonality among all of these rate options is that all loads interconnect as 3
Network Load and pay NITS based on their gross load. While this construct 4
reasonably allocates costs for customers wishing to interconnect in a “firm” 5
configuration, it does not incentivize nor facilitate interconnection in a lower cost 6
manner through co-location. This ultimately drives unnecessary increases in 7
transmission system costs.
8
Q66. HOW WOULD YOU RECOMMEND THESE OPTIONS BE USED IN THE
9
DEVELOPMENT OF NEW RATES FOR CO-LOCATED LOADS?
10
A66. First, I recommend that a different rate option be implemented for each of the three 11
fundamental configurations of co-located load. Even if a single rate is “ideal” for 12
one customer type, it may not be ideal for another customer type, and providing 13
options that align with the services that each customer desires provides a means to 14
only invest in new transmission infrastructure that is necessary. Therefore, the 15
existence of multiple options for co-located loads to interconnect under different 16
configurations is, itself, necessary to achieve economic efficiency in totality. 17
Q67. HOW DO PJM’ PROPOSED “FIRM” OPTIONS ALIGN WITH RATE
18
DESIGN PRINCIPLES RELATIVE TO THE IDEAL RATE?
19
A67. The table below summarizes my conclusions regarding the alignment of rate 20
options that represent a “firm” configuration with the rate design principles of 1) 21
PDF page 64
63
fair apportionment of costs and 2) economic efficiency.71 Because the ideal rate 1
bills for transmission using the greater of NITS applied to net load and a discounted 2
standby charge, it performs well against both rate design principles. 3
Table 3: Assessment of “Firm” Rate Options Alignment with Rate Design Principles 4
Rate Option
Description
Fair Apportionment
of Costs
Economic
Efficiency
PJM Option 1 NITS without co-
location
N/A for Co-Location
PJM Option 2 NITS with co-
location
Poor
Poor
PJM Option 3 Load customer
with BTMG
Mixed
Mixed
Ideal “Firm”
Rate
Greater of 1) NITS
with net billing or
2) Discounted
standby charge
Good
Good
Q68. HOW DO PJM’ PROPOSED “GENERATOR-CONTINGENT” OPTIONS
5
ALIGN WITH RATE DESIGN PRINCIPLES RELATIVE TO THE IDEAL
6
RATE?
7
A68. The table below summarizes my previous conclusions regarding the alignment of 8
rate options that represent a “generator-contingent” configuration with the rate 9
design principles of 1) fair apportionment of costs and 2) economic efficiency. 10
Because the ideal rate bills for transmission using a one-time system impact charge 11
that reflects the costs that the generation interconnection modification is imposing 12
on the system, instead of full gross load during coincident peak, it performs well 13
71 Note that even though PJM Rate Option 6 appears to represent a “firm” option, it has been excluded from consideration in the table below, as it is misaligned with the premise of open and fair competition as described above.
PDF page 65
64
against both rate design principles. Additionally, if this rate option is structured to 1
include the efficiency-enhancing ability to draw energy from the transmission 2
system on an as-available basis, this should be billed at a discounted $/MWh 3
transmission charge.
4
Table 4: Assessment of “Generator-contingent” Rate Options Alignment with Rate Design 5
Principles
6
Rate
Option
Description
Fair
Apportionment of
Costs
Economic
Efficiency
PJM
Option 4
Co-located load with
‘generator-contingent’
protections
Good
Mixed
PJM
Option 5
Co-located load with
‘generator-contingent’
protections + as-
available energy
purchase option
Mixed
Good
Ideal Rate Generator-contingent
with as-available energy
purchases billed at
discounted $/MWh
charge
Good
Good
Q69. HOW DO PJM’ PROPOSED “INTERRUPTIBLE” OPTIONS ALIGN
7
WITH RATE DESIGN PRINCIPLES RELATIVE TO THE IDEAL RATE?
8
A69. The table below summarizes my previous conclusions regarding the alignment of 9
rate options that represent an “interruptible” configuration with the rate design 10
principles of 1) fair apportionment of costs and 2) economic efficiency. Because 11
the ideal rate does not assess a standby or system impact charge (since these 12
customers have no impact or cost on the transmission system), it performs well 13
against both rate design principles. Additionally, the inclusion of a discounted 14
PDF page 66
65
$/MWh transmission charge for as-available energy purchases is important for the 1
performance of the ideal rate along both rate design principles.
2
Table 5: Assessment of “Interruptible” Rate Options Alignment with Rate Design Principles 3
Rate Option
Description
Fair Apportionment
of Costs
Economic
Efficiency
PJM Rate
Option 7
NITS with co-location
where load is
interruptible
Poor
Poor
PJM Rate
Option 8
NITS with co-location
where load participates
as demand response
Poor
Poor
Ideal Rate
Interruptible with As-
Available discounted
$/MWh charge
Good
Good
4
PDF page 67
66
6 Recommendations & Summary
1
Q70. IN LIGHT OF THE ARGUMENTS YOU MAKE, DO YOU HAVE A
2
RECOMMENDATION?
3
A70. Yes. Most broadly, I recommend that FERC ensure that loads have the opportunity 4
and incentive to interconnect to the transmission system in a manner that reflects 5
fair apportionment of costs and economic efficiency for the level of service that 6
they require. I recommend that FERC find the current transmission tariff unjust and 7
unreasonable because it does not clearly provide this opportunity. I further 8
recommend that FERC implement this vision by developing three new distinct rate 9
options for three configurations of co-located load: firm, generator-contingent, and 10
interruptible. These rate options can be implemented by modifying PJM’s proposed 11
options.
12
Q71. PLEASE SUMMARIZE YOUR TESTIMONY.
13
A71. Yes. The key takeaways of my testimony are:
14
• The PJM tariff should align with rate design principles, including 1) fair 15
apportionment of costs and 2) economic efficiency;
16
• Transmission costs are primarily caused by draw from the system during the 17
peak, and loads that can configure or operate in a manner that reduce peak load 18
draw on the system can reduce transmission system costs – gross billing 19
regardless of configuration undermines the incentive to minimize costs; 20
• Co-location of generation and load provides one mechanism to reduce the 21
load’s peak load draw on the system and reduce transmission system costs; 22
PDF page 68
67
• There are multiple potential co-location configurations, each with different 1
transmission system impacts: firm, generator-contingent, and interruptible; 2
• The current tariff lacks clarity, unfairly apportions costs, is inequitable, and 3
does not provide the opportunity and incentive for loads to interconnect in a co- 4
location configuration that reduces costs, which results in unnecessary and 5
inefficient transmission buildout, harming affordability – for these reasons it is 6
unjust and unreasonable;
7
• PJM’s current proposed rate options do not align with rate design principles, 8
but I show how several options can be modified to improve alignment; and 9
• PJM should immediately implement new tariff options for multiple co-location 10
configurations: firm, generator-contingent, and interruptible, either as enduring 11
or transitional rates.
12
Q72. DOES THIS CONCLUDE YOUR TESTIMONY?
13
A72. Yes
14
PDF page 69
VERIFICATION
I declare under penalty of perjury that the foregoing Testimony is true and correct to the best of my knowledge, information, and belief.
Executed this 23rd day of April 2025.
________________________
Zachary Ming