EL25-49-000 · 2025-04-23 · Constellation Energy Generation, LLC
Exhibit 3 (Patterson)
PDF page 1
EXHIBIT 3
AFFIDAVIT OF AARON PATTERSON
PDF page 2
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC.
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
AFFIDAVIT OF
AARON T. PATTERSON
April 23, 2025
PDF page 3
1
I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT
A. QUALIFICATIONS
1. My name is Aaron T. Patterson. I am a partner of The NorthBridge Group, Inc (“NorthBridge”). NorthBridge is a consulting firm that provides economic and strategic advice to the electric and natural gas industries. My business address is 30 Monument Square, Concord MA 01742.
2. I joined NorthBridge in 2001. Before that, I was an analyst at Lexecon, Inc. which I joined in 1996. I have over 20 years of experience working with clients in the electric and natural gas industries. My electric industry business consulting work has focused on market design, environmental policy, finance, and mergers and acquisitions. I received a Bachelor of Arts in Environmental Science and Public Policy from Harvard University, and a Master of Business Administration from the Tuck School of Business at Dartmouth. I have previously testified before the Commission and have also submitted expert reports in proceedings before the U.S. Department of the Treasury, the Public Utility Commission of Texas and the New York State Public Service Commission.
3. A list of my past prepared testimony is provided as Attachment A.
B. BACKGROUND AND PURPOSE OF AFFIDAVIT
4. The Commission recently issued an order instituting this proceeding that requires PJM Interconnection, L.L.C. (“PJM”) and the Transmission Owners (“TOs”) in the PJM region to show cause as to whether the PJM Open Access Transmission Tariff (“Tariff”) remains just and reasonable with respect to how it handles additions of large loads, such as datacenters, that are co- located with generation and to offer potential changes to the Tariff that could remedy concerns around the addition of large co-located loads.1 PJM’s Answer stated that PJM believes the Tariff remains just and reasonable but offered, and requested guidance from the Commission and others on, several potential changes to the Tariff that PJM asserts could improve the way in which PJM
1 Docket Nos. EL25-49-000, AD24-11-000, and EL25-20-000 (consolidated), Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings, Feb 20, 2025. (“Instituting Order”)
PDF page 4
2
handles additions of large load to its system, both co-located and otherwise.2 Among the issues on which the Commission has requested comment, and which PJM discussed in its Answer, is the potential impact that co-located large load, and large loads in general, may have on resource adequacy within PJM.
5. My testimony addresses two separate topics related to both the Commission’s Order and PJM’s Answer. First, I examine the resource adequacy issues raised in the proceeding and the potential remedies offered by PJM and others. I offer several potential constructive policies that the Commission could support to improve the performance of PJM’s resource adequacy construct in the face of rapid additions of large loads while also identifying those policies which the Commission should avoid. Second, to facilitate the discussion of the appropriate means of allocating the costs of integrating large loads onto the system, I provide data that I have collected on the estimated integration costs of large loads onto the PJM system from 2022 onwards.
6. I reach five primary conclusions as a result of my analysis.
7. First, resource adequacy concerns associated with rapid large load additions such as datacenters stem from all large load additions, regardless of whether or not they are co-located, and are fundamentally driven by the large individual size of large load projects and their rapid development time from conception to energization. These characteristics make load growth very lumpy, hard to predict, and may lead to load needing service before the market can respond with additional new capacity. PJM’s market design, including its competitive capacity market, the Reliability Pricing Model (“RPM”), and other elements such as its interconnection queue and load forecasting function must continue to evolve to meet the new challenges posed by the rapid growth in large load additions.
8. Second, however, the RPM market design has not exhibited any general market failure nor are load large additions a reason to jettison the RPM altogether. The RPM has performed very well historically in terms of maintaining resource adequacy at cost-effective prices for customers. The RPM remains the best underlying platform for meeting the challenges created by large load additions, and certain improvements could better optimize it to meet this challenge.
2 Docket Nos. EL25-49-000, AD24-11-000, and EL25-20-000 (consolidated), Answer of PJM Interconnection, LLC, March 24, 2025. (“PJM Answer”)
PDF page 5
3
9. Third, there are a number of concrete steps that the Commission and PJM can take to improve the RPM’s efficacy in reliably, speedily, and cost-effectively integrating large load. These steps particularly focus on facilitating the timely entry of short lead-time supply; providing better signals for the entry of all types of supply in response to changing trends in load growth; and removing barriers to entry for all resource types. First, PJM should continue efforts to improve the accuracy of price formation in both its energy and capacity markets, with particular emphasis on removing out-of-market price distortions that lead prices to diverge from system fundamentals. Second, PJM should improve its forecasting of large load by standardizing and making mandatory the process whereby TOs report new large loads to PJM, and it should incorporate large load into the load forecast more frequently than the present once-per-year cadence and provide as much transparency and detail on this process as possible. Third, PJM should continue to improve the speed at which new projects are able to clear the generation interconnection queue and the responsiveness of the queue to emergent capacity supply needs. This should foremost take the form of streamlining, automating, and accelerating the current queue process as much as possible. If further enhancements beyond improving the base queue process are needed, PJM could consider adding a fast-track interconnection process similar to the current one-off Reliability Resource Initiative (“RRI”) that offers accelerated treatment for capacity supply resources that have the greatest impact on resource adequacy and can enter quickly that would be triggered when PJM has an acute need for incremental new supply. Fourth, PJM should seek ways to allow datacenters and other large loads to participate in the RPM as demand response as much and as easily as possible, such as by harmonizing the PJM and EPA rules regarding run-time limits for backup diesel generators. Finally, PJM should consider adding an improved backstop reliability procurement mechanism to the RPM that seeks to procure additional short-lead or higher-cost capacity supply resources in cases where the RPM does not clear sufficient supply to meet a minimum adequate level of resource adequacy.
10. Fourth, PJM and the Commission should avoid policies that undermine, distort, or circumvent PJM’s markets. In particular, PJM should avoid policies that tie load’s entry to it bringing with it self-supplied or contracted new supply, or that offer benefits or subsidies to generators that are tied to new entrant loads. Such policies distort markets because they effectively subsidize a certain set of supply resources – new resources tied to new entrant loads – whose reliability attributes are not otherwise distinguishable from other capacity supply. In addition to
PDF page 6
4
discriminating against existing resources in favor of new ones, this harms the market by suppressing prices, reducing entry of non-advantaged supply resources, and furthering the potential exit of existing resources, all of which undermine reliability and frustrate the original objective of reliably integrating new load. One of the options PJM offers as potential avenues for large load integration – Options 6 – is of this nature and should be rejected. Another of PJM’s options – Option 7 – as currently written also carries the potential to undermine markets and discriminate against non-favored resources because it appears to contemplate giving PJM broad discretion to condition new large load entry on vague PJM-determined resource adequacy concerns with new load entry under such conditions only allowed if the load provides PJM with interruption rights, distorting capacity prices when a clear signal for new entry and retention of existing resources is needed. While it is reasonable to reflect the ability and willingness of large loads to interrupt in the load integration process, interruption rights should not be a condition for new entry based on resource adequacy concerns.
11. Finally, with respect to costs of integrating large loads into the transmission network, I find that recent historical integration costs are generally proportionate to the size of the load seeking to enter the market, but costs are extremely variable even after accounting for size differences. This variability generally appears to be due to unique locational factors that vary from load to load such as the position of the load within the broader system topology and the physical environment around the new load site. While load size is a significant determinant of the cost of integrating large loads, location clearly matters a great deal and can cause the cost to vary in idiosyncratic and unpredictable ways. This location-dependence suggests that sending the correct incentives via transmission rates to new load to locate at efficient places on the grid is important for integrating such load efficiently with respect to total system costs.
II. RESOURCE ADEQUACY ISSUES RELATED TO ADDITIONS OF LARGE LOADS TO THE PJM
SYSTEM
A. RESOURCE ADEQUACY CONCERNS RELATED TO LARGE LOAD
ADDITIONS ARE REASONABLE, BUT DO NOT REFLECT A GENERAL
FAILURE OF MARKETS, OR OF THE CAPACITY MARKET IN PARTICULAR,
THAT JUSTIFY PJM’S PROPOSALS
12. Both the Commission and PJM have voiced concerns about the resource adequacy implications of rapid additions of large loads to the PJM system, both with respect to large loads that are co-located with generation specifically, as well as large loads more generally regardless
PDF page 7
5
of configuration.3 The Commission and PJM both raise concerns that the fast pace of large load additions may lead to capacity shortfalls regardless of configuration.4 PJM states that “as to the resource adequacy dimension to co-location arrangements where conditions are tight, any additional load on the system requires either the addition of supply resources to serve that load reliably, or flexibility on the part of the load to curtail its consumption from the transmission system when necessary to maintain reliability.”5
13. In response to these resource adequacy concerns, PJM offers three “preferred” new options for interconnecting large loads “relating to adding additional supply and flexibility” in response to concerns around resource adequacy.6 While couched as responses to co-located load particularly, the proposed policies nonetheless appear to be applicable to all types of large load, co-located or otherwise. One of these options (Option 8) merely envisions the potential for new large loads to participate in PJM markets as demand response resources in line with the current tariff, but with some modifications to facilitate participation by datacenters. But the other two options – Option
6 and (as described in PJM’s Answer) Option 7 – both represent a significant departure from PJM’s non-discriminatory resource adequacy construct in that they offer unique benefits to certain forms of capacity supply tied to large loads. For Option 6, this takes the form of faster processing of interconnection for generators that are tied to large loads. Option 7, as currently proposed by PJM in its Answer, conditions integration of large load on the load providing PJM with interruption rights (that is, effectively self-supplying demand response), depending on whether PJM determines that there would otherwise be a resource adequacy “imbalance.” These proposed options appear to be a response to the general resource adequacy concerns arising from rapid large load additions, but their discriminatory and market-circumventing elements suggest that PJM desires more control than its markets afford or lacks confidence that PJM’s existing resource adequacy construct is fully up to the task of bringing forth the supply needed to maintain resource adequacy in the face of increasing load growth driven by large load additions.3 Instituting Order at PP 83-86 and PJM Answer at 8-9.4 Ibid.5 PJM Answer at 8 (emphasis added). 6 Ibid. at 9.
PDF page 8
6
14. While questions about resource adequacy in the face of rapid load growth are valid, it is important to first get the right problem diagnosis and then develop solutions that address the problem directly, without harming markets or causing other unintended consequences.
15. First, at bottom, the potential for resource adequacy problems related to large load additions arise primarily from the very fast and very lumpy load growth caused by large load interconnecting with the system, regardless of whether or not it is co-located with generation. From a resource adequacy perspective, a megawatt of load added to the system creates a need for the same amount of incremental supply regardless of whether the load is co-located with generator or not. And even in configurations where the load does not take network service and takes supply from a generator that does not participate as a capacity resource, the net effect is the same – the system has a need for incremental supply because it must replace the generation offering direct supply to the load. Thus, any consideration of resource adequacy issues driven by large load should consider all such load, regardless of whether it is co-located with generation.
16. Second, the resource adequacy concern surrounding large loads arises from the desire or need on the part of large load customers to enter the market faster and in larger quantities than many types of capacity supply resources can respond. New datacenter loads can be constructed and come online in as little as two to three years and can be as large as two gigawatts or potentially even more at a single point of interconnection. And the emerging business models surrounding artificial intelligence and other datacenter applications place high value on the ability to rapidly deploy large amounts of additional datacenter processing capacity. Figure 1 below demonstrates the speed at which data center load can potentially enter the market, as reflected by PJM’s evolving load forecasts from January 2023 to January 2025. Over this period the forecast for the 2027 summer peak, just over two years from the present date, increased by about 10 gigawatts (from 154 to 164 gigawatts). As of 2023, these loads were not part of the planning process or in the load forecast used to set demand for the RPM, but over a two-year span they progressed development to the point where they are now projected to enter in about two years from the present. Increases in the load forecast for later years suggest this trend is likely to continue.
PDF page 9
7
Figure 1
Source: PJM Load Forecasts (various years) at https://www.pjm.com/planning/resource- adequacy-planning/load-forecast-dev-process.
17. Several aspects of the RPM could be better optimized to serving such large, rapid and difficult to predict load additions as depicted in Figure 1. First, capacity from conventional generation resources can take longer to enter the market than the 2-to-3-year development cycle for a datacenter load. PJM’s consultants are currently assuming a 44-month construction cycle time for a new combustion turbine for the purposes of developing parameters for future RPM auctions, exclusive of pre-construction development activity, suggesting a floor on conventional generation development cycle time of at least 4 to 5 years.7 And the ability of conventional generation to “anticipate” load growth and thus start development prior to a firm demand signal from the capacity market is currently limited by uncertainties around PJM’s longer-term load forecast and market structure. In such an environment – large but difficult to predict demand from
7 Sixth Review of PJM’s RPM VRR Curve Parameters: Updated Gross CONE and VRR Curve Analysis, Presentation by the Brattle Group to the PJM Market Implementation Committee, Feb 21, 2025, slides 6-8. https://www.pjm.com/- /media/DotCom/committees-groups/committees/mic/2025/20250221-special/pjm-qr-cone-and-vrr-curve-deck.pdf 140,000 145,000 150,000 155,000 160,000 165,000 170,000 175,000 180,000 185,000 190,000 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 PJM RTO Summer Peak Load Forecast Evolution, 2023 to 2025 (Summer Peak MW) Actual Weather- Normalized Load Jan 2023 Load Forecast Jan 2024 Load Forecast Jan 2025 Load Forecast
PDF page 10
8
large loads of all types coupled with limitations on the ability of conventional capacity supply to respond in a timely fashion – concerns about resource adequacy are warranted.
18. Third, while concerns around resource adequacy due to large load additions have merit and the specific issues with the RPM described above are quite real, they do not amount to a generalized failure of PJM markets or the RPM in particular. The RPM has historically performed well in delivering resource adequacy at affordable costs to PJM customers and provides a solid platform for continuing to do so in the future, albeit with ongoing improvement to meet current and future challenges. Over 19 delivery years to date for which RPM auctions have been held, the RPM has never failed to procure capacity in excess of the level needed to maintain its 1-in-10 years loss of load expectation resource adequacy standard, as Figure 2 below shows: Figure 2
Source: PJM Base Residual Auction Reports (various years) at https://www.pjm.com/markets- and-operations/rpm. PJM Reserve Requirement Studies (various years) at
https://www.pjm.com/planning/resource-adequacy-planning/reserve-requirement-dev-process.
While PJM has not faced load growth on the scale expected in coming years over this period, it has over this period faced significant incremental supply needs driven by coal retirements and successfully brought forth market-based replacement supply at the scale needed to maintain the 0%
5%
10%
15%
20%
25%
Delivery Year
PJM Installed Reserve Margins Cleared in RPM versus Target Needed
to Maintain Resource Adequacy Standard
Reserve Margin Cleared in RPM Base
Residual Auction (Including FRR)
Target Reserve Margin needed to Achieve One
Expected Event per 10 Years Resource
Adequacy Standard
PDF page 11
9
target level of resource adequacy. Figure 3 below shows PJM generation capacity additions and retirements from inception of the RPM to present. When needed, the RPM has brought forth new capacity additions of as much as 5 to 8 gigawatts in a single year and has successfully procured total capacity in excess of the PJM resource adequacy target even in years in which as much as 5 to 8 gigawatts of capacity has retired. The year-over-year average load growth for the next 5 years in PJM’s most recent load forecast (shown in Figure 1) is just under 6 gigawatts per year. Historically the RPM has been successful in bringing forth capacity at the scale needed to maintain resource adequacy of a similar order of magnitude as will be needed in the future. Figure 3
Source: Monitoring Analytics, LLC, 2024 State of the Market Report for PJM, Table 5-6. https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2024/2024-som-pjm- sec5.pdf
19. PJM’s competitive markets have not only continuously maintained resource adequacy but have done so in a cost-effective manner for consumers. Figure 4 below shows the combined real (in 2024 dollars) wholesale market energy, ancillary services, and capacity costs per megawatt- hour of load in PJM from the full first calendar year in which the RPM was in effect – 2008 - to the most recently-completed RPM auction for the 2025/26 delivery year.
737
2,041
1,196
506
3,959
2,347
629
2,828
4,831
4,631
4,694
8,462
5,120
990
3,728
5,160
3,117
(797) (1,031) (573) (1,064)
(2,718)
(5,854)
(3,075)
(5,276)
(8,554)
(866) (2,806)
(6,819)
(3,413) (3,778)
(2,323)
(7,763)
(6,590)
-10,000
-8,000
-6,000
-4,000
-2,000
0
2,000
4,000
6,000
8,000
10,000
PJM Generation Capacity Additions and Retirements (ICAP MW)
Generation Additions
Generation Retirements
PDF page 12
10
Figure 4
Source: Monitoring Analytics, LLC, 2024 State of the Market Report for PJM, Table 11. Estimated costs for 2025/26 based on RPM auction results and energy forward prices from S&P Global. Adjusted for inflation using GDP deflator as reported by the U.S. Federal Reserve.
In real terms, combined energy, ancillary services, and capacity costs have fallen by about 34% over the period simply comparing 2008 and 2025/26. And even ignoring the high prices in 2008, costs have on average remained essentially flat in real terms from 2009 onward. Over the same period transmission costs in PJM, which are not subject to competition but continue to be determined using traditional cost-based ratemaking, have more than tripled in real terms, as shown below in Figure 5.
0
20
40
60
80
100
120
140
PJM Combined Energy and Capacity Customer Costs (2024 $/MWh)
Energy and Ancillary Services
Capacity
2008: First Full
Year with RPM
2025/26: Most
Recent RPM
Auction
Average Across
Entire Period
PDF page 13
11
Figure 5
Source: Monitoring Analytics, LLC, 2024 State of the Market Report for PJM, Table 11. Adjusted for inflation using GDP deflator as reported by the U.S. Federal Reserve
20. While competitive markets are challenged presently with the need to meet accelerating load growth coupled by delays in the processing of new generation due to reforms made to the interconnection queue process, there is evidence that PJM’s markets are responding to this emergent need. Higher market price signals in line with the cost of new entry in the most recent RPM auction coupled with recent PJM rule changes to accelerate the addition of capacity supply resources with a disproportionate impact on resource adequacy through the PJM Reliability Resource Initiative have induced a strong supply response. The RRI has attracted 94 projects (both new builds and uprates) covering 26.6 Gigawatts of ICAP that had formerly not been able to enter the generation queue but are able to achieve commercial operation on an accelerated basis.8 Further, 1.1 gigawatts of generation that was scheduled to retire have reversed their retirement decisions since the most recent RPM auction.9 And finally, certain large datacenter project
8 PJM Inside Lines, “Reliability Resource Initiative Draws 94 Applications,” Mar 21, 2025. https://insidelines.pjm.com/reliability-resource-initiative-draws-94-applications/9 See https://www.pjm.com/planning/service-requests/gen-deactivations. Since the 2025/26 auction, seven combustion turbine plants/units have reversed retirement decisions including Perryman 6 (55 MW), Morgantown 1-4 (216 MW), Fisk 31-34 ((171 MW), Vienna 8&10 (167 MW), Waukegan 31&32 (100 MW), Elgin 1-4 (480 MW), and Kenilworth (15 MW). 0 2 4 6 8 10 12 14 16 18 20 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 PJM Transmission Costs per MWh (2024$)
PDF page 14
12
announcements have announced that the datacenter power supply contract will be used to support the repowering of significant generation assets.10 This market response is unsurprising given the evolving market supply and demand fundamentals. Specifically, as the supply side has contracted (e.g., due to recent retirements and queue-related slowdowns in the pace of new additions) and the demand side has expanded (e.g. due to datacenters, increased electrification, use of EVs, etc.), that shift in fundamentals – a tighter supply/demand balance – has put upward pressure on prices. As expected, the increased prices are incenting supply side investment, some of which will be secured by long-term contracts.
21. Pre-supposition of market failure is premature in the face of the present challenges brought by rapid addition of datacenter loads, as are policies which circumvent, obstruct, or even outright abandon markets. Rather, the present circumstances comprise a challenge of how best for PJM (and the Commission) to respond to the very specific issues created by datacenter load growth in a manner that builds on the solid foundation provided by competitive markets. First, how can PJM facilitate the timely entry of short lead-time capacity supply, particularly when such entry is most critical for maintaining reliability? And second, how can PJM improve the long-term entry signals for all types of supply, including longer-lead-time conventional generation, to better anticipate trends in load growth and other capacity needs and to better enable resources to initiate the development cycle in a sufficiently timely fashion to contribute to resolving resource adequacy challenges in the future? And finally, any tariff changes or other new policies should address these challenges without harming markets or creating other unintended consequences that unwind any progress or create new problems.
10 For example, Constellation Energy is restarting the Three Mile Island Unit 1 nuclear plant in combination with a 20-year contract to supply carbon-free energy to Microsoft datacenter developments (See https://www.constellationenergy.com/newsroom/2024/Constellation-to-Launch-Crane-Clean-Energy-Center- Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html), and an initiative was recently announced to construct up to 4.5 gigawatts of natural gas fired generation capacity at the site of the retired Homer City coal plant to support datacenter development. (See https://www.homercityredevelopment.com/post/former-homer-city-pa-coal-plant- officially-reopens-as-state-of-the-art-natural-gas-facility)
PDF page 15
13
B. BOTH SHORT AND LONG LEAD TIME SUPPLY RESOURCES CAN
CONTRIBUTE TO MEETING THE CHALLENGE OF LARGE LOAD
GROWTH
22. Facilitating entry of short-lead time capacity supply resources is a critical element to improving the responsiveness of the RPM to large load additions. While long-lead-time conventional generation assets form the majority of PJM’s existing capacity supply portfolio, certain types of capacity supply resource are able to enter the market on shorter lead times that are comparable to the 2-to-3-year development cycle for new datacenter load. First, demand response resources of all types can typically enter service less than three years after the start of initial development of the resource. Unlike most resource classes, demand response does not need to pass through the interconnection queue. When qualifying their resources for the RPM Base Residual Auction (“BRA”), demand response providers are allowed to offer on the basis of a projected marketing plan rather than actual contracted DR customers, effectively deferring the marketing and contracting of the underlying DR resources to the three-year period between the BRA and the delivery year. And finally, the physical investment required to qualify a new demand response resource is typically extremely modest compared to generation resources and is thus not subject to the equipment supply chain and permitting challenges that can delay more traditional resources.
23. Second, demand response provided by curtailment of new entrant datacenters themselves is a particularly compelling possible source of new short-lead time supply because by definition it will have the same lead time and similar size/scale to the new entrant load. A recent study from the Nicholas Institute at Duke University found that a significant amount of datacenter load can reliably integrate with electric systems across the country without the need to incrementally expand transmission or generation infrastructure if that load agrees to curtail in a small percentage of hours. Specifically, the study found that if new datacenter loads were willing to curtail in 0.5% of the hours in which they would normally operate, 98 GW of new load nationally and 18 GW in PJM (equivalent to about 11% of PJM’s current peak) could be integrated without the need to incrementally expand transmission or generation.1111 Tyler H. Norris, Tim Profeta, Dalia Patino- Echeverri, and Adam Cowie-Haskell, Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems, February 2025. https://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf
PDF page 16
14
24. Third, even if they are not able to curtail, new datacenter loads often have backup diesel generators or batteries that can allow them to serve as demand response if they can be run in response to an instruction by PJM and thus be deployed under the same conditions and rules as other emergency or pre-emergency demand response resources.
25. And finally, storage resources, while they must pass through the interconnection queue, typically have much shorter development cycles than other types of generation because they are a scalable, land-use-efficient, off-the-shelf technology with no fuel infrastructure needs and much- reduced permitting requirements relative to traditional generation. Taken together, these pools of potential short-lead supply represent a significant potential tool for integrating large loads while maintaining resource adequacy.
26. And while long-lead conventional generation cannot immediately respond to “surprise” load growth as shown in Figure 1, it still can play a significant role in maintaining reliability over the longer term under such conditions. Long-lead-time generation is able to respond to major directional trends as they emerge in the fundamental data such as the load forecast, and in market price signals. But to do so to the greatest extent, such resources need the best, most accurate fundamental data possible along with a robust market that produces accurate competitive market price signals.
C. THE COMMISSION SHOULD SUPPORT POLICIES THAT FACILITATE
ENTRY OF NEW SUPPLY WITHOUT HARMING MARKETS
27. Given this backdrop, there are several Commission actions and policies that could both facilitate the addition of short-lead-time capacity supply when needed while also increasing the responsiveness of longer-lead conventional resources, all without harming the underlying market.
28. First, the Commission should support ongoing efforts by PJM to improve the accuracy of the competitive market prices that generators and other capacity resources rely on to signal whether to enter, remain in, or exit the market. This should clearly include the RPM but also energy and ancillary services markets as well, which are an important source of revenue for many capacity resources. Generally, the Commission should support policies that drive market prices to accurately reflect the underlying fundamentals and reliability requirements of the system as they evolve over time. Examples of this include PJM’s recent changes to the RPM which improved the accuracy of its reliability modeling and resource accreditation to reflect the marginal contribution
PDF page 17
15
of individual resources to system resource adequacy, and PJM’s upcoming efforts to improve the ability of energy and ancillary services markets to accurately reflect PJM’s full operational reserve needs in real time and thus avoid excessively conservative operations (including out of market resource commitments) that are not reflected in market prices. Accurate and robust competitive market prices flowing from a consistent, stable and well-conceived market design are the bedrock on which all investment in new supply depends, and the Commission should support PJM’s efforts at continuous improvement towards this goal.
29. Second, while forecasting load in the current environment is challenging, Figure 1 and the PJM analytic work and committee proceedings surrounding load forecasting strongly suggest that improvements to the load forecast are possible to provide more information, and more accurate information on future large load additions to market participants. PJM currently relies on Transmission Owners to provide estimates of future large load additions to their systems, based on their interactions with customers. This process is not fully standardized across the various TOs, nor is it mandatory that all TOs provide an assessment of the large load situation in their zones every year (even if there is no activity). As a result, PJM must make a number of judgment calls about whether to include specific loads, and the timing which with the loads enter the market, in forming the load forecast. The large load situation may be uncertain in parts of the RTO because not all TOs have provided an assessment. This ultimately reduces transparency and confidence in the resulting forecast. Further, this process only occurs once per year, which means that in the current environment of rapid load growth the load forecast becomes obsolete within a couple months of issuance. Creating detailed, consistent, mandatory rules around when and how TOs must report load additions to PJM would help improve the accuracy of and confidence in the load forecast, and increasing the frequency with which large load additions are reported to PJM from once per year to two to four times per year would improve the responsiveness of the information for market participants. Finally, PJM should publicly provide as much detail and transparency as possible on the large load information provided to it by TOs and on any adjustments and assumptions it makes in incorporating the information into the load forecast.
30. Third, policies which shorten the development lead time of all capacity resource types would clearly improve the responsiveness of the market to load growth. One clear lead time constraint is the generation interconnection queue. While PJM has recently reformed its queue process from the prior first-come, first-served approach to a batch-based cycle approach which is likely to
PDF page 18
16
improve processing speed substantially, there are likely still many incremental improvements to the general process that can be made as more experience is gained with the new approach. In particular, deployment of software automation tools shows potential to greatly reduce interconnection study times. 12 PJM should prioritize the continuous improvement of the interconnection queue process with the aim of improving the entry-to-agreement cycle time, reducing administrative complexity, and improving accuracy. To this end, PJM has recently announced a collaboration with Google and Tapestry to utilize artificial intelligence tools to streamline the generation interconnection process.13 The Commission should be supportive of this effort and further efforts to improve the interconnection process.
31. If improvements to the base interconnection queue process ultimately are not enough to significantly improve the queue cycle time for new capacity resources, PJM could also consider implementing a “fast lane” process modeled on its Reliability Resource Initiative available on an ongoing basis that would be triggered when PJM faces an acute need for new supply. PJM has recently begun implementing the one-time RRI to re-open the second transition cycle in its new interconnection queue framework to a limited set of additional projects that did not originally enter the queue in time for inclusion in the second transition cycle but nonetheless score highly on a set of metrics designed to select projects that are most likely to contribute highly to resource adequacy. The key metrics of likely project resource adequacy contribution include Unforced Capacity rating, Effective Load Carrying Capacity Rating, location in constrained regions, and several metrics targeting development speed and certainty. While the RRI is intended as a one-time process, the concept has potential as an approach to accelerating the interconnection queue projects with a particularly high resource adequacy contribution when the market has an acute need for accelerated supply to meet a minimum acceptable standard of resource adequacy. This could, for example, take the form of separating queue cycles into a fast lane and slower lane based on weighting criteria similar to that used for RRI. This queue separation could be implemented in the event that the RPM BRA clears at the price cap, indicating an acute need for additional supply to maintain
12 See Letter from Commissioner Rosner to PJM regarding Interconnection Automation, March 17, 2025. https://www.ferc.gov/media/commissioner-rosner-letter-pjm-interconnection-automation-letter13 PJM Interconnection, LLC News Release, “PJM, Google & Tapestry Join Forces to Apply AI To Enhance Regional Planning, Generation Interconnection,” April 10, 2025. https://www.pjm.com/-/media/DotCom/about- pjm/newsroom/2025-releases/20250410-pjm-google-and-tapestry-join-forces-to-apply-ai-to-enhance-regional- planning-generation-interconnection.pdf
PDF page 19
17
resource adequacy and could remain in effect for all cycles initiated from that point forward until a subsequent BRA clears below the price cap. Such an approach carries the potential for compressing time to market for high resource adequacy value resources when needed while maintaining a technology-neutral, non-discriminatory interconnection process. Given the potential complexity of this concept, however, PJM’s primary initial focus should be on improving and accelerating the base queue process, particularly given that it is in the process of transitioning to the new cycle-based approach. A fast lane process is a potential option in the longer term if an even more accelerated process is ultimately needed.
32. Fourth, as discussed above, demand response provided by new large loads themselves is a particularly compelling source of short-lead supply because the size and entry time of that supply are by definition tied to the entry of the large load resources that themselves create the need for new supply. In its Answer PJM has identified facilitating demand response from large load resources resulting from either the ability to curtail the load or operate on-site backup generation as a potential option (“Option 8” in PJM’s listing) for addressing the resource adequacy concerns raised by the rapid growth of large loads. In particular, PJM points to the need to harmonize PJM and EPA rules around the run-time limits for Reciprocating Internal Combustion Engines (“RICE”) to allow such resources to participate in the RPM as demand response resources to the greatest extent possible.14 The Commission should support these efforts by PJM and others to maximize the ability of large loads, whether co-located or otherwise, to provide demand response capability to PJM markets, recognizing that in some instances, the state permit under which the facility operates may further restrict run hours and thus the analysis is not as simple as just looking to change the EPA rules.
33. Finally, PJM and the Commission should carefully consider policies for contingent procurement of short lead-time capacity supply resources in the event that the normal operation of the RPM fails to clear enough supply to meet a minimum acceptable level of reliability in a given single BRA.15 While several potential approaches are possible, a workable potential design would
14 PJM Answer at 20 and 69-70.15 PJM already has a backstop mechanism in the Tariff but it is considerably less responsive to emergent resource adequacy shortfalls that what I propose here. The existing backstop mechanism is described in Tariff Attachment DD, Section 16. The existing mechanism is only triggered if the RTO clears at 1% below the Reliability Requirement for three consecutive years and procures resources for multi-year terms in an amount needed to resolve the shortfall
PDF page 20
18
be to trigger a supplemental procurement after the BRA if the BRA does not clear enough supply to meet a minimum acceptable level of reliability, which would be defined as a point no more than the point where the demand curve transitions from downward sloping to flat at the price cap (currently set at 99% of the reliability requirement). The supplemental procurement could be run several months after the conclusion of the BRA and would only be open to uncleared resources that are able to come online for the BRA delivery year. This supplemental procurement would have a higher price cap (the specific value would need to be analyzed but could be as much as twice as high or even more) than that of the BRA, but the quantity of supplemental supply cleared would be limited to the amount needed to increase total supply to what is needed to achieve a minimum acceptable level of reliability. The supplemental procurement would be limited to only the delivery year of the triggering BRA (that is, it would not be a multi-year procurement) which would in practice mostly limit it to relatively short-lead-time resources such as demand response and storage.16 The resulting price would only be paid to resources clearing in the supplemental auction (so that the resources that cleared the BRA would receive the BRA clearing price), and the cost of the supplemental auction would be allocated to loads under conventional allocation rules.
34. This supplemental procurement concept is a departure from the basic single-clearing price RPM design in that it employs discriminatory pricing for high-cost resources that would normally be unable to clear in the RPM due to the operation of the price cap. While this is not an ideal market design feature, it is balanced by limiting the supplemental procurement to only those instances where PJM has an acute resource adequacy shortfall, and limiting the quantity cleared to the amount needed to achieve minimum acceptable resource adequacy. Limiting the procurement in this way greatly reduces the potential distortionary effects it may have on markets compared to policies which are always in effect regardless of market conditions. Further, the supplemental procurement concept is effectively a workaround in response to another distortionary (albeit long- standing) market feature – the price cap – which limits the ability of the market to procure very high-cost capacity when resource adequacy needs are acute. That said, any design with multi-
relative to the trigger quantity. Thus the existing mechanism is much less likely to be triggered in a timely fashion to resolve a resource adequacy shortfall than the supplemental procurement process I am proposing here.
16 It may also be necessary to revise the RPM market power mitigation rules to address the potential for resources to hold back capacity from the BRA proper with the goal of accessing the higher prices in the supplemental procurement if it were triggered.
PDF page 21
19
tiered pricing as proposed here requires extremely careful scrutiny to avoid distortions and unintended consequences, so it would be important to subject such a design change to a full stakeholder review per PJM’s processes. The benefit is that the supplemental procurement provides a safety valve that increases the ability of PJM to maintain an acceptable level of resource adequacy in the event that large load additions exceed the ability of the market to respond within the normal parameters of the RPM design, while limiting customer costs by only paying above- cap prices to the relatively small slice of resources cleared in the supplemental procurement rather than to the full capacity portfolio. If properly designed, these benefits likely outweigh the cost of market distortions of such a policy.
D. THE COMMISSION SHOULD AVOID POLICIES THAT ARE UNDULY
DISCRIMINATORY AND UNDERMINE MARKETS, INCLUDING PJM
OPTION 6 AND OPTION 7 (AS PROPOSED)
35. Two of the policy options outlined by PJM in their Answer, Option 6 and Option 7 (as proposed), are discriminatory and have distortionary and market-circumventing aspects that apply in a much broader set of circumstances than the supplemental procurement concept discussed above. Without modification, these policies discriminate in favor of new resources over existing ones and are likely to harm the market, ultimately undermining reliability and increasing customer costs.
36. When considering how to handle large load additions, the Commission should generally avoid policies that discriminate among similarly situated resources and circumvent, distort, or otherwise undermine PJM markets. Policies that offer discriminatory subsidies or advantages to certain resource classes based on their vintage or the entities that they contract with are examples of this. Such policies are counter-productive to the goal of ensuring resource adequacy in the face of rapid load growth because they undermine the very markets that are critically needed to bring forth supply to meet increasing demand, and thus ultimately risk a breakdown of markets altogether and a need to rely on high-cost, non-market approaches to an ever-increasing extent. To the extent that a policy does go outside the normal operation of markets it should be carefully designed to minimize market impacts and only go into effect when the reliability need is critical, such as the supplemental procurement concept I discuss above.
37. Related to this, the Commission should also avoid policies that seek to ration new demand entry due to resource adequacy concerns either by outright denying or delaying demand entry or
PDF page 22
20
conditioning entry on the resource effectively bringing with it supply that matches its need. Fundamentally such policies harm markets and economic activity more generally because they impede the ability of new demand that produces economic value to enter in a timely manner. If new entry is conditioned upon or incentivized to bring new supply resources with the load, it is likely to subsidize the new resources in a manner that will undermine and harm the market, , and will discriminate against the supply (both new and existing) that is dependent upon the market.
38. In violation of these principles, PJM’s Option 6 proposes that new large loads that build or contract with new or otherwise-retiring capacity supply resources (whether co-located or not) would secure favorable treatment for those supply resources in the PJM generator interconnection process. PJM suggests that this favorable treatment could take the form of accelerated interconnection studies and/or enhanced provisional interconnection service options that accelerate the ability of new generation to achieve commercial operation.17 The core problem with Option 6 is that it offers a thing of value – favored treatment in the generation interconnection process – in exchange for an action – contracting with a new large load - that is unrelated to the underlying cost and resource adequacy aspects of a given capacity supply resource, and is only available to a new resources that are able to secure a contract with a large load.
39. Favorable interconnection queue treatment is unquestionably of high value in the present tight market environment: resources that get through the queue quicker incur lower financing costs during development and are able to access market revenues sooner than resources without this advantage. But this advantage would only be conferred on a subset of resources that 1) are new (or would otherwise retire, although expedited interconnection service is not of value to retiring resources), and 2) are able to secure a contract with (or are self-built by) a new large load resource. Neither of these features has any bearing on the ability of resources to physically supply capacity, nor does it have any bearing on their underlying cost of providing capacity. Such treatment is discriminatory because it offers a benefit to a specific subset of new resources while denying that benefit to existing resources and to new resources that are unable to contract with new large loads.
17 PJM Answer at 17. PJM also suggests modifications to the State Agreement Approach to support large load investment in their jurisdictions as part of this option, but it is unclear if/how this change would be connected to large loads bringing their own new generation.
PDF page 23
21
40. Consider two otherwise-identical gas combined cycle generation resources, one contractually-tied to a new large load and one not. The amount of Unforced Capacity awarded to each resource will be identical, and but-for any favored interconnection treatment awarded by PJM in connection with this proposed policy, their costs of construction and operation will be similarly identical. PJM Option 6 would nonetheless discriminate between these two resources, effectively lowering net cost of entry of the with-contract resource while not conferring such benefits to the other resource. This approach is functionally equivalent to an out-of-market payment or subsidy (for the same resource adequacy services) which effectively lowers the cost of the with-contract class and thus distorts and depresses market economics for all other resources (including all without-contract new resources and all existing resources). The ultimate endpoint of such a policy is to drive all resource additions to seek contracts with large load and depress economics for other resources, leading to reduced new entry outside of the large load contract path and potentially retirements of existing resources. Moreover, unlike the supplemental procurement concept that I previously outlined, PJM Option 6 as proposed has no limitations that would restrict its application to only those instances when it is needed to avoid a resource adequacy shortfall, meaning that the discriminatory treatment and market distortions that it causes would be applicable under all types of market conditions. It also potentially lays the foundation for entities serving large loads – which would the incumbent TOs if they prevail in their tariff interpretation – to obtain an advantage in the generation queue for proposed new build (developed by the TOs or others) that is tied to a specific load rather than the market as a whole.
41. Option 6 is essentially a form of vintage pricing in that it offers an effective subsidy for a favored class of new resources, while denying that subsidy to non-favored new resources and existing resources. This lowers the effective cost of procuring capacity from the favored resources relative to their competitive level, which results in depression of market clearing prices below the competitive level within the RPM market clearing framework. This depresses revenue for non- favored resources with no offsetting benefits, which ultimately chills new entry from resources that are unable to contract with new large loads and potentially leads to market exit by existing resources, undermining reliability and reducing overall market efficiency. For these reasons, the Commission has indicated a preference for utilizing non-discriminatory, market-based solutions
PDF page 24
22
that pay a single clearing price to similarly-situated resources to the greatest extent possible.18 This principle remains correct and should lead the Commission to reject Option 6.
42. PJM already has a market that is intended to bring forth new supply and a recently-reformed non-discriminatory interconnection queue process. And as discussed above, there are a range of improvements that can be made to markets to improve their ability to accommodate new demand from large loads. To the extent that PJM seeks to differentiate between resources within the queue cycle process, that differentiation should be made based on the underlying contribution to resource adequacy that resources provide, such as the factors considered in the RRI process, and not based on contractual ties with specific loads that are unrelated to the underlying resource adequacy contribution of the resource. Or it should be targeted narrowly to address a demonstrated resource adequacy shortfall, as with the supplemental procurement discussed above. Accordingly, Option 6 should be rejected. To the extent that the Commission nonetheless considers PJM Option 6 it should at a minimum seek to limit its application to periods where the RPM clears at its price cap, and it should require that any generation resource benefiting from expedited interconnection under Option 6 be subject to the Minimum Offer Price Rule so as to reduce the detrimental price suppressing effect of any subsidy.
43. PJM’s Option 7, as proposed by PJM, presents similar conceptual problems as Option 6. However, Option 7 can be revised and become a useful option that the Commission should incorporate into PJM’s tariff. In Option 7, PJM proposes to offer expedited treatment of large load with respect to the various local transmission studies needed to integrate as Network Load when new loads would otherwise create a “resource adequacy supply/demand imbalance.” To qualify for this expedited treatment, large loads would need to offer to curtail (or run behind-the-meter backup generation) at PJM’s request in response to reliability or resource adequacy issues on the system.19 The portion of the large load that is available for curtailment would be removed from the demand curve and would not pay for capacity. While the curtailment service provided by the
18 PJM Interconnection LLC, 117 FERC ¶ 61,331 at P 141 (2006): “In a competitive market, prices do not differ for new and old plants or for efficient or inefficient plants; commodity markets clear at prices based on location and timing of delivery. . . Such competitive market mechanisms provide important economic advantages to electricity customers. . . This market result benefits customers, because over time it results in an industry with more efficient sellers and lower prices.”19 PJM Answer at 18-19.
PDF page 25
23
large load in Option 7 would not be offered into the RPM as demand response, it functionally has a similar impact on the RPM because the associated load is removed from the RPM demand curve.20 PJM states that this treatment would be “transitional” in that a given large load could only elect the treatment until the “resource adequacy supply/demand imbalances” associated with that particular load are resolved, without providing any clarification as to how such a determination would be made. Option 7 thus effectively seeks to condition entry for new large loads on providing demand response for as long as PJM determines there is a “resource adequacy supply/demand imbalance.” As written, PJM appears to claim unfettered discretion to decide what constitutes a “supply/demand imbalance” and how long it lasts, with the further potential for political pressure to be brought to bear on any PJM decisions in this regard. This harms markets because the functional effect of Option 7 as written is that PJM would be conditioning the availability and term of valuable load integration rights on its subjectively determined view of resource adequacy. Resource developers that look to market price signals to decide whether to enter would rightfully be concerned if PJM retained the ability to decide when, in its discretion, resource adequacy supply and demand balance had been achieved. The very unpredictability of a core element of PJM’s proposal will undermine the price signal generated by the capacity market.
44. Providing PJM with the capability to curtail large loads could in some cases provide benefits in terms of resolving local and regional transmission reliability issues related to integrating the large load. If curtailment of the load would allow the new load to provisionally integrate with the system prior to completing some of the investments needed to otherwise integrate as network load, then it would be reasonable to allow the load to integrate and qualify as network load on an interim basis prior to completion of the upgrades, so long as the load offers PJM curtailment rights sufficient to resolve the operational concerns during the period prior to the completion of the transmission upgrades needed to reliably serve it. But the eligibility and term of such a transitional service should be directly linked to the primary service being provided – transmission service – and not based on resource adequacy concerns as PJM proposes with Option 7. Specifically, only loads that trigger transmission security violations that are resolved by curtailment should be
20 The Option 7 curtailment service is not fully equivalent to demand response because demand response receives a DR-specific Effective Load Carrying Capacity rating in determining its UCAP, while simply removing load from the demand curve shifts the demand curve inward by the load’s peak load contribution multiplied by the forecast pool requirement.
PDF page 26
24
eligible for this type of treatment, and the term should be limited to the time needed to construct the required transmission upgrades needed to resolve the violations. But these benefits are separate and distinct from resource adequacy – PJM’s resource adequacy construct does not reflect or seek to address local transmission security issues but is rather concerned with the ability to meet load during peak conditions with available capacity supply resources, which is a different problem and analysis entirely. PJM’s Option 7 as written inappropriately ties these two separate concerns together in a manner that is likely to distort the capacity market because it seeks to use the transmission service policy as a means of rationing load entry in the face of resource adequacy concerns. The appropriate policy would be to keep transmission security and resource adequacy separate. If a large load’s ability to curtail provides benefits with respect to transmission security, then those benefits should be reflected in the load integration process but should not act as a bar to entry when PJM determines that there are resource adequacy concerns. And if a large load’s ability to curtail allows it to contribute to resource adequacy, then it should offer that service as a demand response capacity resource.
45. It should be noted however, that when comparing PJM’s Options 6 and 7, Option 7 rates as a more narrow intervention than Option 6 because it is limited in scope to only self-supplied demand response from new entrant large loads, rather than any type of contracted or self-supplied new capacity supply located anywhere on the grid as in Option 6. Moreover, Option 7, unlike Option 6, is “transitional” in that it would only be in effect for the duration of a “supply/demand” balance as determined by PJM. As such, my opinion is that Option 7, even in the currently proposed form, is likely to be less damaging to the market than Option 6, although the specifics of implementation, which have not been fully fleshed out in PJM’s Answer, matter a great deal in this judgment.
46. Beyond PJM’s proposals, various other types of market interventions are possible in response to the rapid growth of large load on the PJM system, both co-located and otherwise. Concepts that have been raised over the years in response to resource adequacy concerns include the building of regulated generation, state-backed contracts for new generation, and restrictions or rationing of the ability of load to interconnect with the system above and beyond the normal load integration process. Without getting into the details, the Commission should be wary of proposals that seek to intervene in, subsidize, or otherwise undermine PJM competitive markets. The benefits of PJM markets are maximized when markets are allowed to respond to price signals and changes in
PDF page 27
25
fundamentals. Policies which pre-empt, mask, or otherwise intervene in this response degrade the efficacy of markets over time and ultimately raise costs for consumers. Further, all load has a right to seek service on the PJM system, and PJM has an existing non-discriminatory process for integrating new load; while improvements to that process are possible the Commission should not support efforts to add discriminatory elements to it.
III. LARGE LOAD INTEGRATION COSTS VARY WIDELY DUE TO SIZE AND LOCATION
47. I have analyzed the estimated costs incurred by PJM TOs to integrate new large loads onto the system. The purpose of this analysis is to support discussion of the appropriate approach to allocating and ultimately recovering these costs. I do not myself offer any specific policy recommendations on this topic – I leave that to others – but rather present the data on load integration costs and provide observations on the main empirical trends that can be gleaned from it.
48. As PJM discusses in their answer, when a singular new large load such as a datacenter seeks to interconnect with the PJM system and initiate transmission service, there are a number of steps that PJM and others must take in order to ensure that the load can be integrated while preserving transmission system reliability.21 First, the local TO must conduct what PJM refers to as a “Transmission Owner load integration study” to “identify local upgrades needed to reliably accommodate the load based on local transmission planning criteria.”22 This study will typically result in a set of proposed upgrades that take the form of a Supplemental Project presented to the Transmission Expansion Advisory Committee (“TEAC”) or Sub-Regional RTEP Committees. Such upgrades typically take the form of a transmission line(s) to the site of the new load, potentially a new substation or upgrades to an existing substation, and sometimes more remote system reinforcements to reliably accommodate the load within the TO’s zone. Once the TO has proposed a solution in the form of a Supplemental Project, PJM conducts a “PJM Do No Harm” study to “evaluate whether a proposed Supplemental Project will adversely impact the reliability of the Transmission System as represented in the planning models used in other PJM reliability standard studies.”23 If the PJM Do No Harm study finds that the proposed Supplemental Project
21 PJM Answer at 6-8.22 Ibid. at 7.23 Ibid.
PDF page 28
26
causes violations, PJM will propose additional transmission upgrades as needed to resolve them. The upgrades that result from Supplemental Projects associated with the new load, as well as any additional upgrades resulting from the PJM Do No Harm Study are fully cost-allocated to loads within the local TO’s zone and are not subject to PJM Board approval.
49. As PJM further discusses, integration of new large loads on the system may result in additional costs beyond those revealed by the Transmission Owner load integration study and the PJM Do No Harm study because new loads are ultimately integrated into the PJM load forecast, which is an input into the PJM Regional Transmission Expansion Plan (“RTEP”) process.24 Large load additions may in part drive a need for additional baseline system projects identified through the RTEP. These projects are identified through a holistic system-level analysis, however, and are not explicitly tied to any particular new load or other discrete change in system topology.
50. The TEAC and/or Sub-Regional RTEP Committees review all proposed Supplemental Projects associated with the integration of new large loads. These reviews describe the location, size, and development timetable of the new load, the nature of the proposed transmission solution to integrate the load, and an estimated cost and timeline to implement the solution. If the PJM Do No Harm study reveals the need for additional upgrades, then similar information is provided for them as well. The various proposed Supplemental Projects for individual new large loads are publicly available on PJM’s website in the sections for the relevant committees.
51. I have gathered information on the integration costs of individual large loads in the form of Supplemental Projects proposed in the relevant PJM Committees from 2022 through the present (as of April 2025).25 The relevant data for each new large load includes its projected size (in summer peak megawatts) and the estimated cost of transmission investments needed to reliably integrate the load as determined by the Transmission Owner Load Integration and PJM Do No Harm studies. The results of this analysis are shown below in Figure 6:
24 Ibid. at 7-8.25 The specific data utilized in forming this data includes various TO-specific presentations on Supplemental Projects to the Transmission Expansion Advisory Committee (located at https://www.pjm.com/committees-and- groups/committees/teac), and the Sub-Regional RTEP Committees for the Western, Mid-Atlantic, and Southern Sub- Regions (located at https://www.pjm.com/committees-and-groups/committees/srrtep-w, https://www.pjm.com/committees-and-groups/committees/srrtep-ma, and https://www.pjm.com/committees-and- groups/committees/srrtep-s, respectively).
PDF page 29
27
Figure 6
Each point shown on Figure 6 shows the integration cost and size of a discrete new large load seeking to integrate with the PJM system. The data includes 144 load-integration supplemental projects in total covering 42.3 gigawatts of summer peak load with a total cost of $8.5 billion. The integration costs include the estimated cost of Supplemental Projects identified through the Transmission Owner load integration study as well as the estimated cost of any additional projects (if any) identified through the PJM Do No Harm study.26 The costs do not include any regional projects identified through the RTEP process (which cannot be tied to any specific discrete new load). I have assumed that any singular load with an ultimate size of 50 megawatts or more is a large load for the purposes of this analysis.
52. The trendline shown on Figure 6 is the result of a simple linear regression estimating integration cost as linear function of size. The trendline indicates that there is both a fixed and size-dependent component to expected large load integration costs, with larger loads driving higher costs. Based on the trendline, each 100 MW of load size on average increases integration cost by about $9.5 million, with a fixed, size-independent component of about $31 million. Thus, for
26 In certain cases, multiple individual large loads may trigger a shared project. In these instances, I have allocated the cost of the shared project equally across all large loads identified as contributing to the need. 0 50 100 150 200 250 300 350 400 0 500 1000 1500 2000 2500 Integration Cost ($ millions) Load Size (MW) Large Load Integration Cost ($M) versus Size (MW) in PJM 2022 through April 2025 Trend: Cost = $0.095M x Size (MW) + $31.3M Totals: 144 projects 42.3 GW of load $8.5 B total cost
PDF page 30
28
example, the expected integration cost of a 100 MW large load is about $41 million ($9.5M size- dependent plus $31.3M fixed), while the expected integration cost of a 1,000 MW large load is about $126 million ($95M size-dependent plus $31.3M fixed).
53. There is a large amount of variation in the integration costs among large loads of similar size. The trendline relating integration cost to size only explains about 25% of the variation in integration costs among individual new large loads. 27 Among loads in the 100 MW range integration costs can range from close to zero to as high as $180 million. For very large loads in the 1,000 MW range, integration costs can range from as low as $70 million to as much as $240 million. In general, this high degree of variation is present across the full range of load sizes.
54. The high degree of size-independent variation in large load integration costs suggests that locational factors specific to each load are a major additional driver of cost and can either result in much lower or higher costs than would be expected on average for a load of a given size. A review of the nature of the actual supplemental projects that form this data confirms that this is the case. Key factors driving load integration costs include the location of the large load site relative to existing transmission elements, the terrain and land use around the large load site, whether integrating the load requires construction of a new substation or allows use of an existing substation, and whether or not the existing transmission system in the local region is robust enough so as not to require additional reinforcements to reliably integrate the load.
55. It is clear that location matters a great deal for and can cause the cost to vary in idiosyncratic and unpredictable ways. This location-dependence suggests that sending the correct incentives via transmission rates to new large loads to locate efficiently is important for minimizing total system costs.
56. This concludes my affidavit.
27 More technically, the R-squared for the linear regression summarized by the trendline shown on Figure 6 is 0.25.
PDF page 31
[No extractable text on this page.]
PDF page 32
Attachment A to Patterson Affidavit
PDF page 33
Aaron T. Patterson Testimony and Expert Reports Date
On Behalf Of
Commission/Court
Subject Matter
Docket/Case Number
Jan-25
Constellation Energy FERC
Affidavit – Treatment of RMR
Resources in PJM Capacity
Market
ER25-682-000
Feb-24
Nuclear Energy
Institute
U.S. Department of
the Treasury
Expert Report (with Frank
Huntowski and John
Hutchinson) – “Assessing the
Incrementality Requirement
of Treasury’s Proposed 45V
Regulations”
REG-117631-23
Dec-23
Constellation Energy FERC
Reply Affidavit – PJM
Capacity Market Reforms
ER24-99-000 and ER24-98-000
Nov-23
Constellation Energy FERC
Affidavit – Market Monitor
Complaint regarding PJM
Capacity Market
EL24-12-000
Nov-23
Constellation Energy FERC
Affidavit – PJM Capacity
Market Reforms
ER24-99-000 and ER24-98-000
Nov-22
Constellation Energy FERC
Joint Affidavit (with Michael
M. Schnitzer) – New England
Winter Gas-Electric Forum
AD22-9-000
June-21
Exelon Corporation
FERC
Reply Affidavit – PJM
Capacity Market Seller Offer
Cap
EL-19-63-000
May-21
Exelon Corporation
FERC
Affidavit – PJM Capacity
Market Seller Offer Cap
EL19-63-000
Nov-20
Exelon Corporation
FERC
Declaration (with Michael M.
Schnitzer) – NYISO Capacity
Market Buyer Side Mitigation
EL21-07-000
Nov-19
Exelon Corporation
State of New York
Public Service
Commission
Expert Report – “Impact of
Carbon Pricing on Potential
Expanded Buyer-Side
Mitigation in the NYISO
Markets”
19-E-0530
Dec-17
Exelon Corporation
Public Utility
Commission of Texas
Expert Report (with David
Coleman) – “Economic
Equilibrium and Reliability in
ERCOT”
Project No. 47199