EL25-49-000 · 2025-04-23 · Constellation Energy Generation, LLC

Exhibit 3 (Patterson)

Text extracted from the eLibrary original (SHA-256 46ffe58b99cc4a31…). Download the original from the official source.

Contents · 9 sections
  1. I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT p. 3
  2. A. QUALIFICATIONS p. 3
  3. B. BACKGROUND AND PURPOSE OF AFFIDAVIT p. 3
  4. II. RESOURCE ADEQUACY ISSUES RELATED TO ADDITIONS OF LARGE LOADS TO THE PJM p. 6
  5. A. RESOURCE ADEQUACY CONCERNS RELATED TO LARGE LOAD p. 6
  6. B. BOTH SHORT AND LONG LEAD TIME SUPPLY RESOURCES CAN p. 15
  7. C. THE COMMISSION SHOULD SUPPORT POLICIES THAT FACILITATE p. 16
  8. D. THE COMMISSION SHOULD AVOID POLICIES THAT ARE UNDULY p. 21
  9. III. LARGE LOAD INTEGRATION COSTS VARY WIDELY DUE TO SIZE AND LOCATION p. 27

Read the parent filing

Read topic-matched comments in EL25-49

Topics in the text: Reliability and curtailment · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 31.

Opening text

opening text

EXHIBIT 3 AFFIDAVIT OF AARON PATTERSON UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.
Read this passage

I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT

printed heading

QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT
Read this passage

A. QUALIFICATIONS

printed heading

I am a partner of The NorthBridge Group, Inc (“NorthBridge”).
Read this passage

B. BACKGROUND AND PURPOSE OF AFFIDAVIT

printed heading · Topic match: Reliability and curtailment

PJM’s market design, including its competitive capacity market, the Reliability Pricing Model (“RPM”), and other elements such as its interconnection queue and load forecasting function must continue to evolve to meet the new challenges posed by the rapid growth in large load additions. 8.
Read this passage Filed comments: Reliability and curtailment

II. RESOURCE ADEQUACY ISSUES RELATED TO ADDITIONS OF LARGE LOADS TO THE PJM

printed heading · Topic match: Reliability and curtailment

RESOURCE ADEQUACY ISSUES RELATED TO ADDITIONS OF LARGE LOADS TO THE PJM SYSTEM
Read this passage Filed comments: Reliability and curtailment

A. RESOURCE ADEQUACY CONCERNS RELATED TO LARGE LOAD

printed heading · Topic match: Reliability and curtailment

While PJM has not faced load growth on the scale expected in coming years over this period, it has over this period faced significant incremental supply needs driven by coal retirements and successfully brought forth market-based replacement supply at the scale needed to maintain the 0% 5% 10% 15%…
Read this passage Filed comments: Reliability and curtailment

B. BOTH SHORT AND LONG LEAD TIME SUPPLY RESOURCES CAN

printed heading · Topic match: Connecting load and generation

And finally, storage resources, while they must pass through the interconnection queue, typically have much shorter development cycles than other types of generation because they are a scalable, land-use-efficient, off-the-shelf technology with no fuel infrastructure needs and much- reduced…
Read this passage Filed comments: Connecting load and generation

C. THE COMMISSION SHOULD SUPPORT POLICIES THAT FACILITATE

printed heading · Topic match: Reliability and curtailment

As a result, PJM must make a number of judgment calls about whether to include specific loads, and the timing which with the loads enter the market, in forming the load forecast.
Read this passage Filed comments: Reliability and curtailment

D. THE COMMISSION SHOULD AVOID POLICIES THAT ARE UNDULY

printed heading · Topic match: Reliability and curtailment

In Option 7, PJM proposes to offer expedited treatment of large load with respect to the various local transmission studies needed to integrate as Network Load when new loads would otherwise create a “resource adequacy supply/demand imbalance.” To qualify for this expedited treatment, large loads…
Read this passage Filed comments: Reliability and curtailment

III. LARGE LOAD INTEGRATION COSTS VARY WIDELY DUE TO SIZE AND LOCATION

printed heading

As PJM discusses in their answer, when a singular new large load such as a datacenter seeks to interconnect with the PJM system and initiate transmission service, there are a number of steps that PJM and others must take in order to ensure that the load can be integrated while preserving…
Read this passage