EL25-49-000 · 2025-04-23 · Constellation Energy Generation, LLC

Answer of Constellation Energy Generation, LLC re PJM Interconnection, L.L.C.’s Tariff filing

Text extracted from the eLibrary original (SHA-256 5ceaa382de69ad00…). Download the original from the official source.

Contents · 15 sections
  1. A. Ensuring the Prompt Connection of Data Centers Is Imperative to America’s p. 2
  2. B. Limiting Large New Load to NITS Imposes Billions of Dollars of Unnecessary p. 2
  3. C. Requiring Co-Located Loads to Always Take NITS Unduly Limits State Jurisdiction p. 2
  4. E. No Party Has Demonstrated That a NITS-Only Approach Is Just and Reasonable and p. 2
  5. C. The Commission Should Adopt Constellation’s Proposed Replacement Rates or, p. 2
  6. EXECUTIVE SUMMARY p. 3
  7. A. Ensuring the Prompt Connection of Data Centers Is Imperative to America’s p. 15
  8. B. Limiting Large New Load to NITS Imposes Billions of Dollars of Unnecessary p. 19
  9. C. Requiring Co-Located Loads to Always Take NITS Unduly Limits State p. 26
  10. D. Requiring All Large New Load to Take NITS Violates Rate Design Principles. p. 28
  11. E. No Party Has Demonstrated That a NITS-Only Approach Is Just and Reasonable p. 35
  12. A. PJM’s Proposed Options Are the Foundation for Just and Reasonable Rates. p. 36
  13. B. Co-Location Has No Difference in Effect on Resource Adequacy. p. 58
  14. C. The Commission Should Adopt Constellation’s Proposed Replacement Rates or, p. 64
  15. CONCLUSION p. 108

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

EL25-20-000 (Consolidated) ANSWER OF CONSTELLATION ENERGY GENERATION, LLC Constellation submits this answer1 and respectfully requests that the Commission adopt its preliminary finding that the existing PJM Tariff is unjust and unreasonable because it lacks clarity in how it applies to a variety of…
Read this passage

TABLE OF CONTENTS

printed heading

TABLE OF CONTENTS Answer of Constellation Energy Generation, LLC ........................................................................ 1 Executive Summary ........................................................................................................................ 3 Argument…
Read this passage

A. Ensuring the Prompt Connection of Data Centers Is Imperative to America’s

printed heading

A.
Read this passage

B. Limiting Large New Load to NITS Imposes Billions of Dollars of Unnecessary

printed heading

B.
Read this passage

C. Requiring Co-Located Loads to Always Take NITS Unduly Limits State Jurisdiction

printed heading · Topic match: Retail and wholesale authority

A Just and Reasonable Rate Design Must Account for the Different Costs Caused by Different Configurations. ............................................................................................. 28 2.
Read this passage Filed comments: Retail and wholesale authority

E. No Party Has Demonstrated That a NITS-Only Approach Is Just and Reasonable and

printed heading · Topic match: Reliability and curtailment

E.
Read this passage Filed comments: Reliability and curtailment

C. The Commission Should Adopt Constellation’s Proposed Replacement Rates or,

printed heading

C.
Read this passage

EXECUTIVE SUMMARY

printed heading · Topic match: Reliability and curtailment

Similarly, PPL Electric Utilities Corporation (“PPL”) agreed to the co-located load arrangement for Susquehanna without requiring NITS, but now, as an Indicated Transmission Owner, takes the view that co-located load must be a Network Customer, taking NITS.
Read this passage Filed comments: Reliability and curtailment

A. Ensuring the Prompt Connection of Data Centers Is Imperative to America’s

printed heading · Topic match: Connecting load and generation

There should be no question that load must be served—and as quickly as possible, consistent with system reliability.
Read this passage Filed comments: Connecting load and generation

B. Limiting Large New Load to NITS Imposes Billions of Dollars of Unnecessary

printed heading · Topic match: Connecting load and generation

Stat. 5/8-101 (Illinois statute stating that a “public utility shall, upon reasonable notice, furnish to all persons who may apply therefor and be reasonably entitled thereto, suitable facilities and service, without discrimination and without delay”); N.J.
Read this passage Filed comments: Connecting load and generation

C. Requiring Co-Located Loads to Always Take NITS Unduly Limits State

printed heading · Topic match: Connecting load and generation

Specifically, the Indicated Transmission Owners argue that the Commission should “affirm” that all co-located load which is “synchronized” to the grid must take NITS.80 This would mean that all sales to co-located load (which is by design an end user)—even sales under co- location arrangements with…
Read this passage Filed comments: Connecting load and generation

D. Requiring All Large New Load to Take NITS Violates Rate Design Principles.

printed heading · Topic match: Connecting load and generation

Ming identifies “three potential configurations of co-located load” and describes their potential transmission system usage: First, a “firm” configuration grants the co-located load the right to draw from the grid when it is not drawing power from the co-located generation.89 In this configuration,…
Read this passage Filed comments: Connecting load and generation

E. No Party Has Demonstrated That a NITS-Only Approach Is Just and Reasonable

printed heading

PJM goes on to note “improvements and clarifications” may be appropriate, asks repeatedly for Commission guidance on various aspects of co-location, and also constructively provides eight options for consideration as replacement rates.
Read this passage

A. PJM’s Proposed Options Are the Foundation for Just and Reasonable Rates.

printed heading · Topic match: Connecting load and generation

Although PJM has the option to enter into “reliability must-run” contracts with deactivating generators, there is no obligation on behalf of the generator to enter into such arrangements.187 If Option 6 is the prioritized option to effectuate co-located load arrangements, then PJM may find itself…
Read this passage Filed comments: Connecting load and generation

B. Co-Location Has No Difference in Effect on Resource Adequacy.

printed heading · Topic match: Reliability and curtailment

All parties likewise agree that load must be served, and, as PJM acknowledges, new load is no different than existing load with respect to resource adequacy planning.208 PJM has sufficient tools to ensure resource adequacy, including RPM, which is designed to send strong price signals to add new…
Read this passage Filed comments: Reliability and curtailment

C. The Commission Should Adopt Constellation’s Proposed Replacement Rates or,

printed heading · Topic match: Connecting load and generation

See discussion supra, Section II. 262 See PJM Answer at 15, 17. 263 Ming Testimony at 19; id. (such disparate treatment by transmission owners is not aligned with accepted rate design principles); see also Show Cause Order at P 75 (comparing and contrasting Exelon’s treatment of Constellation’s…
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading · Topic match: Cost allocation

CONCLUSION WHEREFORE, Constellation respectfully requests that the Commission adopt its preliminary finding that the PJM Tariff is unjust and unreasonable and unduly discriminatory and preferential because it lacks clear provisions for the treatment of large loads co-located with generation, and…
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Hivick Kirkland & Ellis LLP 1301 Pennsylvania Ave., N.W.
Read this passage