EL25-49-000 · 2025-04-23 · Constellation Energy Generation, LLC

Answer of Constellation Energy Generation, LLC re PJM Interconnection, L.L.C.’s Tariff filing

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.

Large Loads Co-Located at Generating Facilities

Constellation Energy Generation, LLC.

v.

PJM Interconnection, L.L.C.
)

)

)
)
)
)
)
Docket No. EL25-49-000

Docket No. AD24-11-000

Docket No. EL25-20-000
(Consolidated)

ANSWER OF CONSTELLATION ENERGY GENERATION, LLC
Constellation submits this answer1 and respectfully requests that the Commission adopt its preliminary finding that the existing PJM Tariff is unjust and unreasonable because it lacks clarity in how it applies to a variety of co-location arrangements.  The position favored by the Indicated Transmission Owners (and PJM to a lesser extent) for a one-size-fits-all solution with full Network Integration Transmission Service (“NITS”) billed on gross load is wrong as a matter of law and policy.  Constellation asks the Commission to (1) adopt most of PJM’s proposed options for replacement rates with the modifications proposed herein, which will permit the prompt interconnection of data centers pursuant to critical national interests while minimizing transmission upgrade costs to consumers and maximizing efficient use of existing energy infrastructure, or (2) initiate time-limited settlement discussions to establish an appropriate replacement rate.

1 Specifically, Constellation Energy Generation, LLC (“Constellation”) files this answer to the Commission’s Order to Show Cause, PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”), and also responds to the answers of PJM Interconnection, L.L.C. (“PJM”), the “Indicated Transmission Owners,” Public Service Electric and Gas Company (“PSEG”) and others pursuant to Rule 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.213.  The Indicated Transmission Owners are a subset of Transmission Owners in PJM, excluding PSEG, for example.

PDF page 2

2
TABLE OF CONTENTS
Answer of Constellation Energy Generation, LLC … 1 Executive Summary … 3 Argument … 13

Requiring All New Load to Take NITS Is Unjust and Unreasonable … 13
A. Ensuring the Prompt Connection of Data Centers Is Imperative to America’s
Economic Competitiveness and National Security … 15
B. Limiting Large New Load to NITS Imposes Billions of Dollars of Unnecessary
Transmission Upgrades … 19
C. Requiring Co-Located Loads to Always Take NITS Unduly Limits State Jurisdiction
and Flexibility … 26
D. Requiring All Large New Load to Take NITS Violates Rate Design Principles … 28
1. A Just and Reasonable Rate Design Must Account for the Different Costs Caused
by Different Configurations … 28
2. Limiting Large New Load to NITS Is Unduly Discriminatory, As Is Requiring Co-
Located Load to Pay Based On Gross Load … 32
3. Requiring Large New Loads in Every Co-Location Configuration to Pay for All
Ancillary Services Is Unjust and Unreasonable … 33
E. No Party Has Demonstrated That a NITS-Only Approach Is Just and Reasonable and
Not Unduly Discriminatory or Preferential … 35 The Commission Should Adopt a Replacement Rate of Several Co-Location Options ... 36

A. PJM’s Proposed Options Are the Foundation for Just and Reasonable Rates … 36
1. Option 1 - Firm Service Without Co-Location … 38
2. Option 2 – Firm Service With Co-Location … 38
3. Option 3—Behind-the-Meter Generation … 41
4. Option 4—Generator-Contingent Service with No Backup Grid Service … 45
5. Option 5—Generator-Contingent Service with Optional Backup Grid Service … 50
6. Option 6—Bring Your Own Generation … 52
7. Option 7—Interim Interruptible Transmission Service … 55
8. Option 8—Expansion of Demand Response Opportunities … 58
B. Co-Location Has No Difference in Effect on Resource Adequacy … 58
C. The Commission Should Adopt Constellation’s Proposed Replacement Rates or,
Alternatively, Establish Time-Limited Settlement Proceedings in this Docket … 64 Answers to the Briefing Questions … 68 Conclusion … 108

PDF page 3

3
EXECUTIVE SUMMARY
This proceeding is about clarifying the PJM Tariff—and in some cases, adding appropriate rules—so that the significant data center load coming onto the system can be served promptly and efficiently.  The Commission was right that the existing PJM Tariff lacks requisite clarity, and this has paralyzed co-location efforts and service to data centers.  Consequently, the PJM Tariff is not just or reasonable.  This load must be connected promptly because of its critical strategic importance to this nation:  we are in a race with China and other nations for supremacy in Artificial Intelligence (“AI”), and we will lose the race if we are not able to promptly connect the data centers that hyperscalers require to train their models and serve users.  President Trump has explained that the United States needs to be “very competitive with China and others” in the development of AI infrastructure and that co-location enables such development “on a very rapid basis.”2  Limiting this new load to only one type of front-of-the-meter service that requires a years-long interconnection process, or even (as we have seen in Ohio) that are subject to a moratorium on new load connection, will lead to defeat.  The load also must be connected efficiently: the Commission should be looking for ways to bring this new load online while minimizing the need for costly system upgrades paid for by all consumers.

According to the Indicated Transmission Owners, however, all new load should be required to take front-of-the-meter service and become a NITS customer paying for service based on gross load.3  The Indicated Transmission Owners read the existing Tariff to require this one-size-fits-all limitation, and they have refused to perform studies for new load seeking a different configuration. It is no surprise that they want to foreclose customers from any other option: large new NITS

2 The White House, Remarks by President Trump at the World Economic Forum, January 23, 2025, 11-12, https://www.whitehouse.gov/remarks/2025/01/remarks-by-president-trump-at-the-world-economic-forum/.
3 Answer of the Indicated PJM Transmission Owners, Docket No. EL25-49-000, et al., at 3 (filed Mar. 24, 2025) (“Indicated Transmission Owners Answer”).

PDF page 4

4
customers mean extensive system upgrades, which the transmission owners get to build and add to their rate base.  Having this be the only option in PJM is unjust and unreasonable: it results in years of delay in connecting new load, induces massive and unnecessary overbuild of the system, imposes substantial additional costs on existing customers who are already struggling to pay their bills, and fails to send efficient signals about where load should be sited.4

Requiring all new load in PJM to sign up for front-of-the-meter NITS also usurps state
authority to decide that a generator should be able to make a direct sale to an end-user.  Under the Federal Power Act, the Commission has no jurisdiction over “facilities used for the generation of electric energy” or over retail sales.5  Instead, states have jurisdiction over those subjects, and many states allow generation facilities to serve end-use customers.  The Pennsylvania Public Utility Commission explained that such a decision is not “a failure to regulate” and it is “not an oversight,” but rather “it is a deliberate choice that has been enshrined in Pennsylvania law for almost a century.”6  The Commission may not obstruct that lawful state choice by compelling generators to sell all their output at wholesale and by forcing end-use customers to pay for transmission service they do not want and do not use.7  For all these reasons, the Commission should find the existing Tariff unjust and unreasonable.

4 A finding that the PJM Tariff is unjust, unreasonable and unduly discriminatory for failing to set forth rules governing co-location arrangements would not require the Commission to amend the pro forma Open Access Transmission Tariff (OATT).  PJM is uniquely situated, with a large amount of data centers already in operation, a generator already approved to serve co-located load, and on-going disputes about what rules should apply to additional co- location arrangements, including guidance that PJM has enforced (but since rescinded) and Transmission Owners taking diverging positions on how, and if they are required to, processing co-location related requests.
5 16 U.S.C. § 824(b).
6 Comments of the Pennsylvania Public Utility Commission at 3, Docket Nos. EL25-49-000, AD24-11-000, and EL25- 20-000 (filed Apr. 22, 2025).
7 For example, nothing compels generators to become exempt wholesale generators (“EWGs”), and nothing requires existing EWGs to maintain that status.  Whether to be an EWG, or instead bear the recordkeeping burdens under the Public Utility Holding Company Act but be able to make direct sales as well as wholesale sales, is up to the generator.

PDF page 5

5
In designing a replacement rate, the Commission should embrace a range of possible models that recognize, as the Commission found, “that different co-location arrangements are likely to use or benefit from the transmission system in different ways depending on how they are configured and, moreover, that those different configurations will themselves likely have different impacts on the transmission system.”8  As PJM’s filing suggests, there are many potential configurations load could select that would allow it to connect more quickly while imposing fewer system costs than limiting load to a front-of-meter configuration.  Allowing load to select a configuration that best serves its needs will enhance national security and national economic competitiveness by speeding connection for those new customers who need to connect quickly and will save existing customers money by minimizing system upgrades.

The available options for load should include models that attempt to use the headroom on the existing transmission system as well as those that avoid or minimize costly and time- consuming system upgrades.  Some new load may want a firm, front-of-the-meter connection and be willing to wait for the requisite studies to be performed and transmission upgrades to be designed, sited, permitted, and built.  Other new load may be willing to locate behind-the-meter and forgo reliance on the grid to be connected more quickly while still ensuring grid reliability. Existing customers benefit from such alternative approaches because they reduce the amount of system upgrades that trigger cost socialization.  Existing customers also benefit from co-locating generation and supply near each other because it reduces demands on the transmission system, including the risks of grid instability caused by large load drop events such as those that recently occurred in Northern Virginia (all caused by grid-connected large loads).9  Other new loads may

8 Show Cause Order at P 76.
9 See Kormos Aff. at 7-8; Mark Lauby, NERC Activities and Plans to Address Reliability Impacts from Large Load Integration at 3-4 (Apr. 17, 2025), https://www.ferc.gov/news-events/news/presentation-nerc-seeks-address- reliability-impacts-large-load-integration (“NERC Large Load Presentation”).

PDF page 6

6
be willing to agree to interruption of service at peak times, making the most of the current grid’s headroom until the transmission upgrades needed for full NITS are constructed.  Existing customers also would benefit from that choice of service by the new load because the new load would be added without the immediate need for any additional capacity.  The Commission should establish rules that allow new load (and the states) this range of choice and adopt corresponding rates that promote efficiency and respect principles of cost causation.

In its filing, PJM has identified eight potential options for how large, new load might connect.10  All but one of these options can be just and reasonable, though some require the modifications we describe below, and the Commission should direct PJM to implement them, as modified, in a compliance filing.

Option 1 and 2 are traditional in-front-of-the-meter NITS in which load is billed on a gross basis (Option 2 merely joins the generator and the load at the same point of interconnection, but otherwise is standard NITS).  Of course, no one disputes that new load should be able to connect to the system as a NITS customer if it chooses.  But, as discussed, making NITS the only option for large new loads is unjust and unreasonable and unduly discriminatory and preferential.  In addition, Option 2, which bills for NITS on a gross basis even though the generator is actually located at the same point of interconnection as the load, eliminates the incentive from a transmission rate perspective for the load to site itself at or near the point of delivery.  This incentive could be restored if the load co-located with the generator were charged for NITS based on the greater of (i) NITS with net billing or (ii) a discounted standby charge to “reflect the fact

10 Answer of PJM Interconnection, L.L.C., Docket No. EL25-49-000, et al., Exh. A (filed Mar. 24, 2025) (“PJM Answer”).

PDF page 7

7
that many co-located generators will be on and available during the system peak, offsetting the co- located load and reducing the system cost impact of all loads in this configuration.”11 Option 3 is the existing tariff model for Behind-the-Meter Generation (“BTMG”), that allows load to take grid service when the co-located load exceeds the co-located generator’s output. The load is billed for NITS on a net basis, i.e., when the load exceeds the output of the co-located generator.  As applied to co-location, the name “Behind the Meter Generation” is misleading as a significant portion of the generation is likely to remain in-front-of-the-meter, but a portion would be dedicated to serving behind-the-meter load, thereby reducing demands the large new load would normally impose on the grid.  As PSEG explains in detail in its response, this configuration is a time-tested model for co-location, under which the load is charged a rate based on its net usage of the transmission grid.12  This model incentivizes the efficient use of the grid by encouraging new load to locate at a site that will minimize the need for system upgrades.  While PJM states that this option was intended for smaller loads,13 the Tariff contains no such restriction.  And PJM’s only expressed concern about the use of this option by larger loads is that PJM does not currently carry reserves for this load.14  That is no reason to reject the option.  PJM’s current approach can easily be modified to include reserves for large loads if necessary.  PJM focuses on a small subset of existing BTMG—that using “wholesale” BTMG—but it disregards the more common retail BTMG.  PJM’s focus on “wholesale” BTMG appears to be intended to create the false impression that use of PJM’s BTMG netting rules is limited.  In fact, as PSEG explains, it is not.15

11 Testimony of Zachary Ming, Exh. 2 at 55.
12 Response of Public Service Electric and Gas Company, Docket No. EL25-49-000, et al., at 13-18 (filed Mar. 24, 2025) (“PSEG Response”).
13 PJM Answer at 13.
14 Id. at 13, n.5.
15 PSEG Response at 13, 17.  See also, Ming Testimony at 21 (noting that over 10,000 MW of BTMG of one resource type – solar – exists in PJM.)

PDF page 8

8
Option 4 would allow load co-located with generation to elect to receive service directly from the generator, with protection schemes in place to prevent the load from drawing on the grid. (Option 5 is similar, except that the load could call on power from the grid as available.)  Many states allow generators to engage in direct sales, as PJM acknowledges in its answer.16  The Commission should not intrude on the states’ jurisdiction by foreclosing this option, as that would grossly overstep federal authority.  As the load is not drawing any power from the grid—it physically cannot do so with protection schemes in place—it is not using the transmission system, so transmission rates would not apply.  In attacking Options 4 and 5, the Indicated Transmission Owners focus almost exclusively on arguing that the load should pay ancillary services, conflating benefits received from ancillary services by the co-located generator with the use of the transmission system to deliver energy.  It may indeed be appropriate in this type of configuration to pay some amount for ancillary services, such as regulation and black start.  But that does not mean the load should be paying a NITS transmission rate for transmission services it does not use. Option 4 or 5 could also serve as a transitional service for load that prioritizes connecting immediately, but that ultimately will want to become a NITS customer once any needed system upgrades are complete.  The availability of these options facilitates prompt connection and minimizes system upgrade costs for load willing to receive generator-contingent service. Option 6 is a “bring your own generation” approach that allows new generation resources to skip the generator interconnection queue if they can demonstrate support from an individual load, rather than being favored based on their shovel-readiness and contributions to reliability, as PJM’s Reliability Resource Initiative (“RRI”) proposal envisioned or the first-ready, first-served interconnection queue reforms implemented in PJM in 2023.  While PJM does not explicitly

16 PJM Answer at 27-29.

PDF page 9

9
condition load interconnection upon a load bringing its own generation, Option 6 nevertheless creates a strong incentive for the states to pursue such a course by affording the “new” generation resource a significant advantage in the queue.  Option 6 also discriminates against existing resources and new resources that have not contracted with load.  Option 6 thus undermines the investment signal that is being sent by the capacity market, instead of reinforcing it.  PJM indicated that not all its options were created equal, and this option does not merit further consideration. Option 7 is an interruptible network transmission service that would be available on a provisional basis until – as PJM proposed, resource adequacy balance is achieved, or – as Constellation recommends, the network upgrades required for NITS are complete.  PJM would have the right to interrupt the load under pre-defined criteria relating to transmission constraints or reserve shortages.  Option 7 helps to maximize the use of existing infrastructure, allowing critical large load to be added quickly and served during virtually all hours of the year while transmission upgrades are being constructed.  PJM’s right to curtail the load during defined criteria also means that the load, while it is receiving this service, need not be counted toward the region’s reliability requirement.  A recent study by the Nicholas Institute at Duke University found that if only 0.5% of new load were willing to curtail at peak, PJM could connect an additional nearly 18 GW of load without the need for any new capacity.17  The rate for this interruptible service should be based on net usage of the transmission system and discounted to reflect the inferior curtailable service.  PJM’s proposal for Option 7 does need to be revised in one important respect: PJM’s proposal for the duration of the interruptible NITS would depend on PJM’s view of the capacity supply/demand balance.  This flaw can easily be fixed.

17 Tyler H. Norris, et al., Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems (Feb. 2025), https://nicholasinstitute.duke.edu/publications/rethinking-load-growth (“Duke Study”).

PDF page 10

10
Option 8 is merely an acknowledgment of PJM’s existing demand response provisions that could be appropriate for participation by large loads but has very little to do with co-location. Constellation encourages the Commission, at its resource adequacy technical conference, to explore how demand response programs might be expanded to wring the most out of our existing infrastructure, but this is a worthwhile endeavor separate from co-location.

In sum, all of PJM’s proposed options, with the exception of Option 6 and with just a few modifications to some of the others, are just and reasonable and should be included in a replacement rate.  If the Commission does not adopt this replacement rate, it should, after finding the existing Tariff unjust and unreasonable, set the replacement rate for time-limited settlement discussions as previously requested in this proceeding.18  The Commission’s goal should be to serve new load as quickly as it needs to be served, while minimizing transmission system costs and respecting the Commission’s jurisdictional boundaries.  The Indicated Transmission Owners’ NITS-only position accomplishes none of these objectives; instead, it frustrates them by throttling new load until costly system upgrades can be constructed, and by intruding upon state jurisdiction. That may pad the Indicated Transmission Owners’ rate base, but it does nothing to help our Nation win the contest for AI dominance.

Finally, this proceeding is not about resource adequacy.  All parties agree that load must be served, and, as PJM acknowledges, new load is no different than existing load with respect to resource planning.19  The Commission likewise stated that resource adequacy concerns are “not necessarily unique to co-location arrangements and that significant load growth more generally

18 See Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures of The Electricity Supply Association, The PJM Power Providers Group, Calpine Corporation, Cogentrix Energy Power Management, LLC, Constellation Energy Generation, LLC and LS Power Development, LLC, Docket Nos. EL25-49- 000, AD24-11-000, and EL25-20-00 (consolidated) (filed Apr. 22, 2025) (“Joint Parties Settlement Request”).
19 PJM Answer at 3 (explaining that PJM’s approach to large load expansion does not change whether that expansion is “co-located or not”).

PDF page 11

11
may raise many of the same concerns.”20  Load that takes front-of-the-meter service has the same effect on resource adequacy as load that is co-located.

As the Commission further explained, resource adequacy concerns are arising because of a mismatch between the speed with which large new load seeks to connect to the system, on the one hand, and the time needed to build new transmission and new generation, on the other.21  A NITS-only approach “solves” that problem only by delaying the entry of new load—but that solution is untenable as a policy matter.  Instead, the Commission should determine whether there are additional tools to address near-term capacity needs, while reinforcing PJM’s capacity market, which is already sending strong signals for new entry (or for delaying retirement of existing resources).  For example, PJM’s RRI, designed to advance shovel-ready projects, has drawn 94 applications consisting of 26.6 GW of new or expanded capacity.22  The Commission can also consider additional queue reform, such as deployment of interconnection automation software platforms (which Commissioner Rosner has advocated)23 or a separate queue for short lead-time resources; enhanced demand response programs; or even an appropriately limited procurement for short lead-time resources needed to satisfy the reserve margin if it turns out to be necessary (which is unlikely given the tools already in PJM’s Tariff).  Such programs should be considered outside of this proceeding, and the Commission has scheduled a two-day technical conference in June for that purpose.24  In this proceeding, however, the Commission should be focused on allowing load

20 Show Cause Order at P 85.
21 Id.
22 Reliability Resource Initiative Draws 94 Applications, PJM INSIDE LINES (Mar. 21, 2025), https://insidelines.pjm.com/reliability-resource-initiative-draws-94-applications/.
23 See Letter from David Rosner, Commissioner, Federal Energy Regulatory Commission, to Manu Asthana, President and CEO, PJM Interconnection (Mar. 17, 2025), https://www.ferc.gov/media/commissioner-rosner-letter-pjm- interconnection-automation-letter.
24 See Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Independent System Operator Regions, Supplemental Notice of Commissioner-led Technical Conference, Docket No. AD25-7-000 (issued Apr. 3, 2025).

PDF page 12

12
a range of options to connect, including some that would permit a faster connection than a NITS- only approach would otherwise allow and that would impose fewer costs on existing customers by maximizing the use of existing infrastructure.

In support of this response and the recommendations herein, we submit analyses, testimony, and affidavits of the following respected experts in their respective fields:

• Dr. Paul Stockton, former Assistant Secretary of Defense for Homeland Defense and Americas’ Security Affairs, addresses the national security imperative of serving AI loads (“Stockton Declaration”), Exh. 1 hereto.

• Zachary Ming of Energy+Environmental Economics (“E3”) is an expert in electricity market design who teaches a graduate course on this topic at Stanford University; he testifies about the rate design issues associated with large new loads (“Ming Testimony”), Exh. 2 hereto.

• Aaron T. Patterson of the NorthBridge Group, Inc., an expert in electric market design, addresses resource adequacy questions (“Patterson Aff.”), Exh. 3 hereto.

• Steven R. Herling, a former Vice President of Planning for PJM with over 30 years’ experience in the operations and planning of the transmission system, addresses how different co-location configurations use the transmission system in different ways (“Herling Aff.”), Exh. 4 hereto.

• Michael Kormos, PJM’s former Chief Operations Officer and Exelon’s Senior Vice President of Transmission and Compliance, with nearly 30 years’ experience operating and planning transmission systems and running electricity markets, addresses PJM’s reliability studies and related issues (“Kormos Aff.”), Exh. 5 hereto.

The Commission should consider this evidence in its decision-making, and keep in mind the relative credentials of those sponsoring the analyses submitted to this Commission in these dockets (e.g., lawyers are not electric system operations experts; electric system operators are).25 Constellation addresses the Commission’s briefing questions throughout this reply but also provides answers to specific questions after the argument section.

25 Contra, e.g., Show Cause Order at PP 25, 37, 46, 79 (citing a lawyer’s views on various technical planning and reliability issues).  The Commission’s Show Cause Order repeatedly failed to cite actual experts’ analyses and testimonies in the record.

PDF page 13

13
ARGUMENT

REQUIRING ALL NEW LOAD TO TAKE NITS IS UNJUST AND
UNREASONABLE
The Commission was correct in its preliminary finding that the PJM Tariff is unjust and
unreasonable because it does not contain “provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements”26 and “[t]he absence of such provisions may leave entities unable to determine what steps they can or must take to effectuate co-location arrangements of various configurations.”27  There is no Tariff ban on pursuing different co-location configurations;28 there is only ambiguity about how to effectuate co-location configurations other than a NITS-only option.  In response, the Indicated Transmission Owners, comprising most but not all of the transmission owners in PJM, insist upon a “one-size-fits-all” Tariff interpretation requiring all large loads to take NITS or point-to-point service.29  Not only do the transmission owners themselves differ in their interpretation of the Tariff, but PJM itself has adopted different interpretations over time; for example, in its Answer in this proceeding, PJM now purports to rescind its prior Guidance Document regarding co-

location.30

26 Id. at P 75.
27 Id. at P 74.
28 Nor does the order on the amended Interconnection Service Agreement (“ISA”) for Talen’s Susquehanna facility in Docket No. ER24-2172 preclude co-location configurations.  PJM Interconnection, L.L.C. 191 FERC ¶ 61,025, at P
30 (2025).
29 Since no co-location party is likely to ever take point-to-point service, we will not refer to it again.  But, technically, it is a Tariff option. 30 PJM’s Guidance Document is included as Exhibit 2 to Constellation’s complaint in Docket No. EL25-20-000.  See Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Docket No. EL25-20-000, Exh. 2 (filed Nov. 22, 2024) (“Constellation Complaint”).  PJM recently rescinded the Guidance Document (PJM Answer at 33) despite previously relying on that Guidance Document in developing changes to the ISA for Susquehanna.  Similarly, PPL Electric Utilities Corporation (“PPL”) agreed to the co-located load arrangement for Susquehanna without requiring NITS, but now, as an Indicated Transmission Owner, takes the view that co-located load must be a Network Customer, taking NITS.  Even earlier, PJM had issued guidance in the form of a “Frequently Asked Questions” document on co-location, which also contemplated co-location configurations other than the NITS- only approach now prevailing at some transmission owners’ instigation.  PJM Rules Regarding the Siting of New Load

PDF page 14

14
As an initial matter, the Tariff contains no NITS-only, “one-size-fits-all” requirement for large loads.  PJM’s Guidance Document highlighted other co-location options “consistent with PJM’s review of PJM’s current Tariff.”31  And the Commission already preliminarily found that “the Tariff does not appear to require that [NITS-only] arrangement and there is no clear record before us that [NITS] is the appropriate transmission service for all co-location arrangements.”32 The Commission found instead that “[i]t appears that PJM does not have a process for determining what transmission service different co-location configurations must take.”33  The Commission should adopt its preliminary findings that the existing Tariff is unjust and unreasonable due to the patent need for clarity.34

What is more, regardless of what the Tariff actually says and does not say, some of the Indicated Transmission Owners have refused to cooperate in PJM’s “necessary studies” process unless the load agrees to taking NITS, claiming justification under the Tariff.  Some of the Indicated Transmission Owners have refused to process necessary studies, demanded expensive upgrades under their unfiled interconnection procedures, and forced a generator seeking to serve co-located load to procure additional services not required by the Tariff.35  The lack of clarity in the Tariff, combined with the exclusionary practices of several transmission owners, has led to an

Behind the Meter of Existing Generation (Dec. 1, 2021), https://www.pjm.com/-/media/DotCom/committees- groups/committees/mic/2021/20211201/20211201-item-10b-pjm-rules-on-siting-new-load-behind-the-meter-of- existing-generation.pdf.

31 PJM Guidance Document at 1.
32 Show Cause Order at P 77.
33 Id. P 78 (emphasis added).
34 The Commission already unanimously rejected efforts by Exelon—the lead “Indicated Transmission Owner”—to “clarify” the PJM Tariff to change the definition of “Network Load” to require all new load to be NITS customers, finding that Exelon lacked the authority to revise PJM’s Tariff.  Atlantic City Elec. Co., 190 FERC ¶ 61,109 (2025). No party sought rehearing.
35 See Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Docket No. EL25-20- 000, at 7 (filed Nov. 22, 2024) (“Constellation Complaint”) (citing Protest of Constellation Energy Generation, LLC, Docket No. EL24-149-000, Exh. 2 (correspondence with Exelon) (filed Oct. 30, 2024); Motion to Lodge of Constellation Energy Generation, LLC, Docket No. EL24-149-000, Exh. 1 (November 12, 2024 Exelon Letter) (filed Nov. 18, 2024)).

PDF page 15

15
unconscionable delay in connecting large new loads, especially given our Nation’s pressing national security need for AI deployment.

Not only is a requirement that all large loads within PJM take NITS nowhere to be found in the Tariff, but it is also terrible policy.  It delays service to critically important data centers, potentially by years, due to time-consuming system studies and the likely need for new upgrades to serve data centers, to the detriment of our Nation’s economic competitiveness and national security.  It imposes massive, unnecessary transmission upgrade costs on all existing customers, rather than efficiently using existing transmission and other infrastructure.  It fails to respect state jurisdictional authority to allow generators to directly serve end-users.  And it violates fundamental rate design principles and is unduly discriminatory because it imposes a one-size-fits-all solution on loads that are not similarly-situated.

A. Ensuring the Prompt Connection of Data Centers Is Imperative to America’s
Economic Competitiveness and National Security.
In arguing that all new load should take NITS, the Indicated Transmission Owners conveniently omit the elephant in the room: it takes at least four to five years, and often seven to ten years, to complete the study process and build all the transmission upgrades necessary to provide NITS to a hyperscale data center.36  If we start today, a large data center might be able to obtain service by 2030, but more likely not before 2035.  This is an eternity to a data center customer locked in an existential competitive battle to develop the fastest and most sophisticated AI models.  The Indicated Transmission Owners completely ignore this fact.

Four years or longer is too long for any new load to wait, but this is particularly true given the global race for AI dominance.  As the Commission has previously been told, “the United States is competing in a global market for data center development” and “many of our geopolitical

36 Patterson Aff. at ¶ 17; Kormos Aff. at ¶ 3 (citing examples); Stockton Declaration at 9, n.35 (citing examples).

PDF page 16

16
competitors are working to gain this economic opportunity.”37  Earlier this year, France and the United Arab Emirates announced an agreement worth up to $50 billion to build a 1 gigawatt data center dedicated to AI operations in France.38 The Middle East is “becoming a data cent[er] powerhouse” with planned investments in Kuwait, Oman, and Bahrain.39  And a China-based company recently released DeepSeek AI which, according to President Trump, should “be a wake- up call for our industries that we need to be laser focused on competing.”40  Indeed, the Trump Administration recently outlined the policy of the United States “to preserve an open investment environment to help ensure that [AI] and other emerging technologies are built, created, and grown right here in the United States” and to “restrict foreign adversary access to United States talent and operations in sensitive technologies (especially in [AI]).”41

Experts are now warning Congress that to remain competitive, the United States needs to “[e]nsure diverse, competitive energy markets for AI advancement” and “[r]equire federal agencies to review existing policies to determine how they might be hampering AI innovation.”42 The United States can remain a leader in data center and AI-technology investment only if the Commission ensures regulatory certainty and provides paths to quick interconnection for such load and efficient use of existing infrastructure.

37 Letter of Representative John Joyce, Docket No. AD24-11-000, at 2 (filed Nov. 7, 2024).
38 John Irish, France, UAE Agree to Develop 1 Gigawatt AI Data Centre, REUTERS (Feb. 6, 2025), https://www.reuters.com/technology/artificial-intelligence/france-uae-agree-develop-1-gigawatt-ai-data-centre- 2025-02-06/.
39 See Unlocking the Data Centre Opportunity in the Middle East, PWC (Apr. 10, 2025), https://www.pwc.com/m1/en/media-centre/articles/unlocking-the-data-centre-opportunity-in-the-middle- east.html#:~:text=Other%20nations%20in%20the%20Middle,for%20a%20facility%20in%20Bahrain.
40 David Ingram, Trump says China's DeepSeek AI 'should be a wake-up call' for American tech companies, NBC NEWS (Jan. 27, 2025), https://www.nbcnews.com/tech/innovation/trump-china-deepseek-ai-wake-call-rcna189526.
41 American First Investment Policy, THE WHITE HOUSE (Feb. 21, 2025), https://www.whitehouse.gov/presidential- actions/2025/02/america-first-investment-policy/.
42 Submitted Statement of Adam Thierer, Resident Senior Fellow, Technology and Innovation R Street Institute, Before the Committee on Science, Space, and Technology, Hearing on “DeepSeek: A Deep Dive” (Apr. 8, 2025), https://www.rstreet.org/outreach/adam-thierer-testimony-hearing-on-deepseek-a-deep-dive/#_ftnref36.

PDF page 17

17
U.S. Representative Dan Meuser reminded the Commission last year that while the United States currently hosts more data centers than any other country, “dozens of countries (not all of which are allies) are competing for this economic opportunity.”43  The parenthetical in his statement cannot be overemphasized; data centers are vitally important to national security.  Paul Stockton, the former U.S. Assistant Secretary of Defense for Homeland Defense and Americas’ Security Affairs, explains that data centers are essential for national security, supporting AI services critical to peacetime and conflict operations.44  Rapid deployment of such technology is needed to keep pace with America’s competitors.45  The White House Office of Science and Technology Policy Director reiterated that point earlier this month, stating that the United States “cannot afford to remain dependent ... on Chinese inputs and products, nor can we allow our closest partners to become points of insecurity by relying on Chinese-controlled critical infrastructure, whether in telecom, the grid, or AI.”46  President Trump has emphasized that co-location is particularly valuable for data centers that support national security infrastructure, because co- location reduces that infrastructure’s vulnerability to grid outages or insufficient grid power, which could occur during a conflict.47  The Commission should allow co-location arrangements to come online rapidly to ensure that the United States does not lose AI-enabled advances in the combat activities of our military.48

43 Letter of U.S. Representative Dan Meuser, Docket No. AD24-11-000, at 2 (filed Oct. 17, 2024).
44 Stockton Declaration at 4-7.
45 Id. at 7-8 (describing “China’s drive for AI preeminence” and the “broader strategic competition between China and the United States”).
46 Remarks by Director Kratsios at the Endless Frontiers Retreat, THE WHITE HOUSE (Apr. 14, 2025), https://www.whitehouse.gov/articles/2025/04/8716/.
47 Stockton Declaration at 2.
48 Id.

PDF page 18

18
Make no mistake about what, in substance, the Indicated Transmission Owners are
proposing: to preserve their monopoly on new load interconnection, they want to throttle data center load, preventing new service to this vitally important sector of our economy and national security until they can build the rate-based upgrades needed for NITS.  AEP has made this explicit, imposing a moratorium on new data center load connection in its service territory,49 while simultaneously litigating against co-location arrangements that would enable the interconnection of that load.50  That position is indefensible when co-location arrangements would allow data centers to connect faster and at a lower cost to existing customers.

There should be no question that load must be served—and as quickly as possible,
consistent with system reliability.  Utility regulation is founded on the principle that utilities authorized to operate monopolies must submit to regulation, including price regulation and the obligation to extend service to customers within their service territory and to provide continued service once commenced.51  The latter is commonly referred to as the “duty to serve.”  Nearly every jurisdiction in the United States has promulgated regulations establishing a duty to serve.52 Although each state applies its own flavor, the general requirement is the same—an electric utility

49 See, e.g., Russell Ernst, Lack of Consensus on Ohio Datacenter Settlement Does not Compute, Says AEP, S&P GLOBAL (Oct. 16, 2024), https://www.spglobal.com/market-intelligence/en/news-insights/research/lack-of- consensus-on-ohio-datacenter-settlement-does-not-compute-says-aep (“[I]n March 2023, Ohio Power implemented a moratorium on accepting new service requests from [datacenter] customers to allow American Electric Power’s transmission planning group time to evaluate the impacts that the datacenter load requests would have on the company’s system.”).
50 See, e.g., Joint Protest of Exelon Corporation and American Electric Power Service Corporation to PJM Deficiency Response, Docket No. ER24-2172-001 (filed Sept. 24, 2024) (requesting that the Commission reject a non-conforming interconnection service agreement that would provide for the co-location of data center load).
51 Jim Rossi, Universal Service in Competitive Retail Electric Power Markets: Whither the Duty to Serve?, 21 ENERGY L. JOURNAL 27 (2000).
52 See Heather Payne, Unservice: Reconceptualizing the Utility Duty to Serve in Light of Climate Change, 56 UNIV. OF RICH. L. REV. 603, 610-12 (2022) (describing the duty to serve in various states).

PDF page 19

19
must serve customers seeking service and cannot unduly discriminate or delay such service.53 Illinois’s statute, for example, provides that the duty to serve is “without discrimination and without delay.”54  Delays of five, seven, or ten years are untenable and objectively cannot be considered service “without delay.”  While “the demand for interconnection by data centers driven by the needs of artificial intelligence and other technologies is a recent phenomenon,” the obligation to serve load without delay is as old as utility regulation.55

The PJM Tariff is not just and reasonable because it lacks clear rules and creates confusion that has enabled utilities to block alternative configurations, including co-location, that would allow faster interconnection without endangering system reliability.  The Indicated Transmission Owners’ suggested one-size-fits-all approach, meanwhile, would result in severe service delays for data centers that are key to our national competitiveness and national security.  That cannot be the answer.

B. Limiting Large New Load to NITS Imposes Billions of Dollars of Unnecessary
Transmission Upgrades.
The delay associated with standard NITS interconnection would be bad enough.  But worse
still, requiring NITS interconnection imposes costs on all customers that are unnecessary—costs that could be avoided if large loads were able to select an interconnection option that required

53 See, e.g., 220 Ill. Comp. Stat. 5/8-101 (Illinois statute stating that a “public utility shall, upon reasonable notice, furnish to all persons who may apply therefor and be reasonably entitled thereto, suitable facilities and service, without discrimination and without delay”); N.J. STAT. ANN. § 48:3-3(a) (“No public utility shall provide or maintain any service that is unsafe, improper or inadequate, or withhold or refuse any service which reasonably can be demanded or furnished....”); VA. CODE ANN. § 56-234(A) (“It shall be the duty of every public utility to furnish reasonably adequate service and facilities at reasonable and just rates to any person, firm or corporation along its lines desiring same.”).
54 220 Ill. Comp. Stat. 5/8-101.
55 Answer and Motion to Dismiss of PJM Interconnection, L.L.C., Docket No. EL25-20-000, at 5 (filed Dec. 12, 2024).

PDF page 20

20
fewer costly upgrades.56  Yet again, however, the Indicated Transmission Owners are silent about this reality.  They never acknowledge that a NITS-only approach to serving hyperscale data centers and other large new loads will create a need for massive transmission upgrades and impose billions of dollars of costs on existing customers—at a time when transmission costs already are the primary cause of rate inflation.57  Perhaps it is no wonder that this is left unacknowledged.  After all, the Transmission Owners will be the beneficiaries of these billions.

There is no question the NITS bill will be enormous.  Mr. Patterson analyzed the transmission upgrade costs of adding larger loads to the grid that are socialized to all customers. Between 2022 and April 2025, there were 144 projects to integrate loads larger than 50 MW that resulted in “supplemental projects” to build transmission upgrades.58  The projects covered 42.3 gigawatts of summer peak load with a total cost of $8.5 billion.  The data demonstrates that the “expected integration cost of a 100 MW large load is about $41 million ($9.5 [million] size- dependent plus $31.3 [million] fixed), while the expected integration cost of a 1,000 MW large load is about $126 million ($95 [million] size-dependent plus $31.3 [million] fixed).”59  Again, these transmission costs are socialized: they are paid by all transmission customers. While transmission and distribution rates have risen significantly, the “all-in” price for generation in PJM has remained stable and even decreased over the past 15 years.60  The

56 Ming Testimony at 25 (“the current tariff, which a number of transmission owners interpret as requiring all co- located customers to subscribe to a firm service, will invariably result in some customers paying higher costs to fund transmission upgrades that are not needed to provide the level of service they desire.”).
57 James Downing, FERC’s Christie Discusses Making Electricity More Affordable at NASEO, RTO INSIDER (Feb. 6, 2025), https://www.rtoinsider.com/97608-ferc-christie-discusses-electricity-affordable-naseo/ (quoting Chairman Christie that “[t]he last four years [have] seen the highest rate of inflation in people’s power bills over the last 25 years” and attributing this to escalating transmission and distribution costs).
58 Patterson Aff. at ¶ 51.
59 Id. at ¶ 52 (emphasis added).  Mr. Patterson also finds that “[t]here is a large amount of variation in the integration costs among large loads of similar size.”  Id. at ¶ 53.
60 See Patterson Aff. at Figures 4-5.

PDF page 21

21
Commission should be searching for ways to connect vitally important new load while minimizing incremental transmission costs.  A NITS-only approach cuts off that inquiry.

Even when new load is willing to wait the lengthy period needed to receive NITS
interconnection, the Commission should identify rate structures that incentivize that load to locate at the most efficient points on the grid, where the fewest system upgrades will be needed.  Mr. Patterson’s analysis of large new loads found that “locational factors specific to each load are a major additional driver of cost and can either result in much lower or higher costs than would be expected on average for a load of a given size.”61  “This location-dependence,” he explains, impacts transmission costs and the Commission should send “the correct incentives via transmission rates to new large loads to locate efficiently” to “minimize total system costs.”62  In short, co-location saves existing customers money, and new load should be incentivized to choose co-located sites.  Mr. Kormos further provides that “I can say with certainty that the closer load is to its supply, the costs, time to connect the load, and the operational risk are all likely to be reduced.”63

The Indicated Transmission Owners’ proposed approach—under which NITS is charged based on gross billing determinants, even when the load is co-located with generation—frustrates that approach.  As Mr. Ming explains, “if all load is charged equivalently regardless of its impact on the transmission system, load will have no incentive to seek configurations that could lower transmission system costs, and they therefore will not.  This will cause total costs to rise due to inefficient and ultimately unnecessary investments in the transmission system.”64  This inefficient

61 Patterson Aff. at ¶ 54.
62 Id.
63 Kormos Aff. at ¶ 4.
64 Ming Testimony at 22.

PDF page 22

22
approach to siting load is not just or reasonable and is unduly discriminatory and preferential.  As discussed further below, a just and reasonable rate would provide economic incentives to co-locate, as co-locating large load with generation resources can obviate the need for upgrades and reduce the overall system costs paid by customers at large.65  Applying net billing determinants to co- located load, rather than gross billing determinants, can help provide that incentive.

Co-location not only provides cost savings, but reliability benefits as well.  Recent widely- publicized reliability events in Northern Virginia occurred when grid-connected large loads simultaneously dropped.66  As Mr. Kormos explains, “[t]his voltage drop concern is not one exclusive to co-location and, in fact, illustrates how co-locating load and generation can provide benefits to the grid as compared to direct grid connections.”67  Mr. Kormos’ opinion as a former PJM Chief Operations Officer is that “had those data centers been co-located with a generator (especially a nuclear generator), it is possible that the load would not have dropped offline” because nuclear generators “typically have state of the art automatic voltage regulators,” and voltage deviations—like those that triggered the load drops—would be “expected to be fewer, smaller and of shorter duration, if they occur at all.”68  The load drop events are only one recent, prominent example of grid problems resulting from large, grid-connected loads, and co-location that “avoids the use of the grid” minimizes “grid operational risks (because fewer grid

65 See Michael Kormos, The Co-Located Load Solution at 9 (July 2024) (“Kormos Co-Located Load Solution”), Docket No. AD24-11-000 (filed Nov. 4, 2024) (attached hereto as an appendix to the Kormos Aff., Exh. 5) (explaining that connecting data centers to the grid can result in costs that are “substantial (easily in the billions) and can be spread beyond the data center customer to all other customers”).
66 See Statement of the North American Electric Reliability Corporation, Docket No. AD24-11-000, at 2 (filed Nov. 1, 2024) (expressing concern with an incident where data center dropped in response to a voltage drop as part of a pleading in the Co-Located Load Technical Conference proceeding); see also NERC Large Load Presentation.
67 Kormos Aff. at ¶ 7.
68 Id.; see id. (“Large generators also typically provide significant inertia that can help the local grid avoid or minimize the impact of many anomalies.  Given the reduced likelihood of a voltage drop in the first place for load co-located with a generator, it is less likely that such load will sense a voltage anomaly that will lead it to drop.”).

PDF page 23

23
infrastructure facilities and potential failure points are implicated in serving the load),” while also minimizing “transmission infrastructure costs, potential supply chain issues and delays on long- lead transmission infrastructure equipment ... [and] line losses.”69

The Commission should also be seeking to encourage interconnection configurations that make the most of existing headroom on the grid.  One of the primary benefits of co-location configurations (all of them) is that they take advantage of existing infrastructure and therefore minimize costs.  Requiring all co-located load to be served under traditional NITS (based on gross load peak load contributions) is inimical to these goals because that approach assumes 100% reliance on the grid and a firm load.  A study by the Nicholas Institute at Duke University explained the inefficiency of this approach.  The study logically explains that, if new load is required to take firm service and one assumes that such load will “operate at 100% of its maximum electricity draw at all times, including during system-wide peaks”—which is the assumption underlying traditional NITS—then it is “far more likely” that “significant upgrades, such as new transformers, transmission line reconductoring, circuit breakers, or other substation equipment” will be required.70  By contrast, if a different service was offered to such new load by which the load could “temporarily reduce (i.e., curtail) its electricity consumption from the grid during [] peak stress periods … it may be able to connect while deferring—or even avoiding—the need for certain upgrades.”71

The Duke Study concludes that a new load curtailment rate of just 0.5% annually would result in nearly 18 gigawatts (“GW”) of potential new load integration in PJM without capacity

69 Id. at ¶ 4.
70 Duke Study at 5.
71 Id. (citing ERCOT, Large Loads—Impact on Grid Reliability and Overview of Revision Request Package, Presented at the NPRR1191 and Related Revision Requests Workshop (Aug. 16, 2023), https://www.ercot.com/files/docs/2023/11/08/PUBLIC-Overview-of-Large-Load-Revision-Requests-for-8-16-23- Workshop.pptx).

PDF page 24

24
expansion.72  This amount increases to 23.6 GW with a 1.0% curtailment rate.  The chart below from the Duke Study illustrates the “curtailment-enabled headroom” in different balancing areas in the United States.73

72 Id. at 2.
73 Id. at 4.

PDF page 25

25

Source: https://nicholasinstitute.duke.edu/publications/rethinking-load-growth. The Duke Study also explains that a failure to use this headroom, reflecting the gap between the average and peak demand in the balancing area, increases costs on ratepayers.  Specifically, a

PDF page 26

26
low system utilization rate (i.e., more headroom) means that ratepayers are paying to build and maintain generation assets, transmission infrastructure, and distribution networks that may remain idle for much of the year.74  Therefore, the Commission should endorse paths that would allow new large load to connect without first requiring the completion of system upgrades needed to support NITS service at peak, and without requiring any additional capacity.  Authorizing an interruptible transmission service, as described in our discussion of PJM’s Option 7, will result in a more efficient use of the system (i.e., increased system utilization rate) and significant near-term customer savings as compared to a NITS-only framework.  The Indicated TOs rigid adherence to traditional NITS is not in the best interests of their customers or of the nation.

C. Requiring Co-Located Loads to Always Take NITS Unduly Limits State
Jurisdiction and Flexibility.
The Indicated Transmission Owners’ NITS-only approach also transgresses the
jurisdictional limits in the FPA, which expressly provides that the Commission “shall not have jurisdiction … over facilities used for generation of electric energy or over facilities used in local distribution or only for the transmission of electric energy in intrastate commerce, or over facilities for the transmission of electric energy consumed wholly by the transmitter.”75  Thus, Congress reserved to the states “regulatory authority over retail sales (as well as intrastate wholesale sales)”76 as well as facilities used for the generation, distribution, or intrastate transmission of electric energy.77  As a result, the Commission has held that states “have jurisdiction in all

74 Id. at 6.
75 16 U.S.C. § 824(b)(1).
76 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 279 (2016) (“EPSA”) (citing New York v. FERC, 535 U.S. 1, 17 (2002)) (emphasis added); id. at 265 (“[T]he law places beyond FERC’s power, and leaves to the States alone, the regulation of ‘any other sale’—most notably, any retail sale—of electricity.”) (quoting 16 U.S.C. § 824(b)) (emphasis added).
77 See, e.g., New York v. FERC, 535 U.S. at 22-23.

PDF page 27

27
circumstances over the service of delivering energy to end users.”78  Even the question of whether a retail sale has occurred is a question reserved to the states.79  Despite the well-established bounds of federal and state jurisdiction under the FPA, the PJM Tariff is being interpreted in such a way as to preclude states from exercising their jurisdictional authority.

Specifically, the Indicated Transmission Owners argue that the Commission should
“affirm” that all co-located load which is “synchronized” to the grid must take NITS.80  This would mean that all sales to co-located load (which is by design an end user)—even sales under co- location arrangements with protective relays to ensure no power is received from the grid, i.e., PJM Options 4 and 5—would become subject to wholesale transmission rates.  This is inconsistent with the Commission’s jurisdiction under the FPA.

The Commission cannot allow the inappropriate federalization of retail regulatory
determinations.  Requiring large new load to take wholesale service, rather than taking service directly from a generator, and requiring the generator to only make wholesale sales,81 rather than providing service directly to a co-located load, effectively precludes states from regulating

78 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utils., Order No. 888, 61 Fed. Reg. 21,540, at 21,626 (1996) (emphasis added), order on reh’g, Order No. 888-A, 62 Fed. Reg. 12,274 (1997), aff’d sub nom., New York v. FERC, 535 U.S. 1; see also Ind. Mun. Power Agency City of Lawrenceburg, Ind. v. PJM Interconnection, L.L.C., 174 FERC ¶ 61,035, 61,150 (2021) (“The Commission has rejected the argument that the provision of station power is a practice directly affecting rates for wholesale sales subject to the Commission’s jurisdiction, explaining that station power is a sale for end use and the Commission has no jurisdiction over sales for end use.”).
79 See 16 U.S.C. § 824(b)(1); see also Southern Cal. Edison Co. v. FERC, 603 F.3d 996, 1000-01 (D.C. Cir. 2010) (“[W]e do not understand why FERC is empowered to conclude that a retail sale has not taken place unless it can claim the transaction is, instead, a wholesale sale or a transmission.  To simply declare that the state lacks jurisdiction because FERC believes no retail sale has taken place really begs the jurisdictional question.  Unless a transaction falls within FERC’s wholesale or transmission authority, it doesn’t matter how FERC characterizes it.”); Indiana Mun. Power Auth. v. PJM Interconnection, L.L.C., 172 FERC ¶ 61,243, at P 106 (2020) (regarding station power, “the Commission lacks jurisdiction to determine whether a retail sale has occurred”); id. at P 94 (“The determination of whether a retail sale has occurred . . . is appropriately within the jurisdiction of the states.”).
80 See Indicated Transmission Owners Answer, Att. A at 2.
81 While PJM is of the view that most generators must maintain their status as EWGs and thus engage only in wholesale sales, it has been repeatedly informed that this assumption is not accurate.  It also begs the question of whether under state law the direct delivery of power from a generator to an end-use customer is a “retail sale.”

PDF page 28

28
transactions that fall squarely within their jurisdiction.  Such an outcome would be contrary to the FPA and an unwarranted preemption of a state’s sovereign authority.82  To echo the words of Chairman Christie, just because PJM and other RTOs are federally regulated does not mean that they can preempt a state’s inherent authority and to suggest otherwise “is, frankly, outrageous.”83 Retail issues are a matter of state law, and the states are well-equipped to resolve these questions without federal intrusion, including who is permitted to serve a large load and whether to regulate the sale to an end-use customer.  Indeed, many states allow both regulated direct sales, which are power services held out and generally offered to the public on a non-discriminatory basis, and one- off bespoke private transactions between a provider and end-use consumer.84  That is a matter for the states to decide—not the Commission.

D. Requiring All Large New Load to Take NITS Violates Rate Design Principles.
1. A Just and Reasonable Rate Design Must Account for the Different Costs
Caused by Different Configurations.
As the Commission correctly found, “[t]he record demonstrates that different co-location arrangements are likely to use or benefit from the transmission system in different ways depending on how they are configured and, moreover, that those different configurations will themselves likely have different impacts on the transmission system.”85  The Commission also is correct that “there is no clear record before us that [NITS] is the appropriate transmission service for all co- location arrangements or that such service would be consistent with the cost causation principle (i.e., that [NITS] appropriately aligns costs and benefits in a manner that is roughly commensurate)

82 See PJM Interconnection, L.L.C., 191 FERC ¶ 61,056 (2025) (Christie, Chairman, concurring).
83 Id. at P 4.
84 See PJM Answer at 27-29.
85 Show Cause Order at P 76 (emphasis added).  Mr. Ming agrees “with PJM’s statement that ‘whether the transmission system needs to be planned to be able to serve these large loads if they are co-located and operate behind the meter of a generator will be instructive to the question of transmission cost allocation.’”  Ming Testimony at 24 (citing PJM Answer at 38).

PDF page 29

29
for all such arrangements.”86  The key question is how each type of potential co-location configuration uses the transmission system, if at all.  And since we are determining whether a one- size-fits-all NITS approach is just and reasonable and not unduly discriminatory or preferential for every possible type of co-location configuration, another way of asking that key question is whether every possible configuration uses the transmission system in the same way.

The Indicated Transmission Owners simply assume the conclusion, repeating several times that anything “synchronized” to the grid must take NITS for their gross load and that NITS charges based on gross load regardless of configuration are just and reasonable.87  They provide no further analysis.  Never mind that there already are tens of thousands of MWs of load synchronized to the grid who do not pay NITS based on gross billing determinants.88

By contrast, Constellation asked engineering and rate design experts to analyze the issue. Mr. Ming identifies “three potential configurations of co-located load” and describes their potential transmission system usage:

First, a “firm” configuration grants the co-located load the right to draw from the grid when it is not drawing power from the co-located generation.89  In this configuration, “the transmission system must be planned and built to serve the co-located load,” even if it is “implausible that all

86 Show Cause Order at P 77 (emphasis added).
87 See, e.g., Indicated Transmission Owners Answer at 17 (“Because all loads physically connected to and synchronized with the transmission system benefit from the transmission system, any attempt to isolate or piecemeal wholesale transmission services to quantify costs would be discriminatory because it would disregard the interconnected nature of the transmission system.”); id., Att. A at 2 (urging the Commission to “affirm” that all co- located load which is “synchronized” to the grid must take NITS).
88 See, e.g., PSEG Response at 18 (identifying universities, government agencies, manufacturers, real estate companies and pharmaceutical companies); see also Ming Testimony at 21 (providing that PJM estimates there is over 10,000 MW of behind-the-meter solar capacity across its footprint in 2025).
89 Ming Testimony at 17.

PDF page 30

30
co-located generation will be unavailable at the same time.90  This is NITS.  According to the Indicated Transmission Owners, there is no other possible service, regardless of configuration. Second, a “generator-contingent” configuration means that the co-located load only has rights to power from its co-located generator and has no rights to draw on the grid—as enforced by protective relay equipment.  The grid thus does not need to be planned to accommodate this load.  For the same reason, the additional option of having the co-located load draw energy from the transmission system on an as-available basis, meaning only when PJM determines it will not cause any impacts on the transmission system—similar to PJM’s proposed Option 5—also would not require any additional investment in transmission infrastructure.  According to the Indicated Transmission Owners, this configuration is impossible because protective relays may fail. However, according to Mr. Herling, former transmission planner for PJM, these configurations can be designed to include “completely redundant primary and backup protective schemes,”91 which are relied on “to maintain the safe and reliable operations of the grid on a regular basis.”92 Moreover, there is nothing in the current Tariff that prevents a generator-contingent configuration. Third, an “interruptible” configuration lets PJM interrupt the co-located load at any time, meaning that PJM can interrupt the load in pre-defined emergency conditions regardless of whether the co-located generator is online and available.  “Interruptions may be facilitated through either load curtailment or additional backup generation,” but “PJM must be certain that the co- located load will interrupt whenever system conditions require without any limit applied to the length of the interruption.”93  This co-location configuration has “minimal if any impacts to

90 Id. 91 Herling Aff. at ¶ 21.
92 Kormos Aff. at ¶7.
93 Ming Testimony at 16.

PDF page 31

31
transmission system costs” on the grid as PJM can interrupt the load any time there are operational issues.94  This configuration is similar to PJM’s Option 7.

In case there were any doubt about the engineering feasibility of Mr. Ming’s rate design
analysis, Steve Herling, PJM’s former Vice President of Planning, analyzed the same issue of potential transmission system usage from an engineering perspective and concluded that various co-location configurations use the system differently.95  This is just as the Commission found.96 Returning to the key question—whether cost causation principles require NITS charged on

a gross basis under each of these various types of co-location configurations merely because the load is “synchronized” to the grid—the answer is no.  “[S]ynchronization does not require or suggest that energy delivery from … generation to … load flows on the transmission facilities of the grid.”97  Moreover, as evaluated by basic Bonbright rate design principles, a one-size-fits-all gross NITS rate no matter the configuration (1) fails to fairly apportion costs, because it charges the same rates to customers who impose different costs on the system, and (2) is economically inefficient, because it creates no incentive for loads to choose the lowest cost location.98  The gross NITS rate further fails the Bonbright principles of being “free from controversies as to improper interpretation,” because the Tariff mandates no such requirement to treat all configurations the same, and for the reasons set forth below, is unduly discriminatory.99

94 Id.; see also id. at 47 (same).
95 Herling Aff. at ¶¶ 9-10 (identifying co-location configurations that where “the co-located load will rely on the grid and NITS for energy” and other configurations where “the co-located load will not be able to draw energy from the grid”).
96 See Show Cause Order at P 76.
97 Herling Aff. at ¶ 32; see also id. (“Synchronization is clearly important and even necessary to the stability of the generating facility and the ability of the generating facility to deliver energy to the co-located load on an on-going basis, but that does not change the fact that the energy does not flow on the transmission facilities of the grid.”).
98 Ming Testimony at 9; see id. at 10-12 (explaining what causes transmission costs, the role of peak load, the consequences of increasing peak load, marginal costs, sending appropriate incentives, and the impact of reducing system costs); see also infra at 82 (discussing locational signal).
99 Ming Testimony at 20; see also supra at Section I.D.2

PDF page 32

32
In sum, even though the Tariff does not require gross NITS rates for every co-location configuration, that is how some Transmission Owners are currently interpreting it.  And this results in an unjust and unreasonable rate that charges the same rate to load that uses and benefits from the system differently, violating core cost causation and other rate design principles.

2. Limiting Large New Load to NITS Is Unduly Discriminatory, As Is Requiring
Co-Located Load to Pay Based On Gross Load.
Accepting the Indicated Transmission Owners’ position that only traditional NITS is allowed under the Tariff for co-location configurations also is unduly discriminatory.  Not all large loads are the same and want the same service.  Some prioritize firm transmission service, while others are willing to accept generator-contingent service if that allows them to get online faster. Some are willing to be interruptible.  Some want to rely only on carbon-free power; others are content with the mix of resources on the grid.  Some prefer to be directly connected to a generator, or a certain type of generator.  Forcing them all into the same box disadvantages those new loads that desire more bespoke or limited service, including no transmission service at all.100  Charging them all a NITS rate based on gross load (as opposed to net) no matter their actual use of the transmission system discriminates because such a construct “is incapable of differentiating customers who impose different costs on the transmission system through co-location.”101 Charging all large co-located loads a NITS rate on a gross basis is also inconsistent with the treatment of other behind-the-meter generation and loads in PJM.  This results in undue

100 See generally AI Power: Expanding Data Center Capacity to Meet Growing Demand, MCKINSEY & COMPANY (Oct. 29, 2024), https://www.mckinsey.com/industries/technology-media-and-telecommunications/our-insights/ai- power-expanding-data-center-capacity-to-meet-growing-demand (describing bespoke data center developments using fuel cells, batteries, renewables, and explaining that “[i]n the longer term, small modular reactors (SMRs) might be an option” to “help overcome transmission issues”).
101 Ming Testimony at 36.  Note that depending on the configuration type, “the rate designs that “[Mr. Ming] outline[s] do not simply assess zero charges for zero net use of the transmission system.”  Id.; see id. at 37-40 (discussing proposed charges under various configurations).

PDF page 33

33
discrimination between an undefined category of “large” new co-located loads, which must pay NITS on a gross basis, and other behind-the-meter configurations pairing generators and loads (BTMG), which are allowed to net.  Some of these existing BTMG combinations involve large generator/load combinations that are allowed to net, 3,000 MWs of which are not even required to be located at the same delivery point.102  Potentially smaller “large” co-located loads will be billed based on gross load.  None of these categories are defined in the Tariff or in any pleadings filed to date.

This discrimination is not due.  We discuss the Commission’s rationale for netting charges below in our discussion of BTMG as PJM Option 3,103 but “[t]here is no physical, technical, or economic reason why a netting construct should apply differently for customers with behind-the- meter generation or co-located generation.”104

3. Requiring Large New Loads in Every Co-Location Configuration to Pay for
All Ancillary Services Is Unjust and Unreasonable.
Another question is whether every configuration relies on ancillary services in the same way.  The Commission preliminarily found that it may be appropriate to charge co-located load configurations to the “extent” “they benefit from or contribute to the need for certain ancillary services and black start services.”105  The Commission further stated that since the “Tariff does not address this issue,” “we find that the absence of rates, terms, and conditions governing the use and sale of ancillary services and black start services by co-location arrangements may render the

102 See id. at 21. 103 See infra at Section II.A.
104 Ming Testimony at 55.
105 Show Cause Order at P 82.

PDF page 34

34
Tariff unjust and unreasonable or unduly discriminatory or preferential.”106  The Commission should adopt this preliminary finding.

Under firm configurations, loads currently pay for ancillary services but generators do not, on the theory that generators typically are providing ancillary services.  Under a generator- contingent configuration, where the load would have no right to draw on the grid for power (except possibly on an as-available basis), the load fully relies on its co-located generator for all services. Some have raised the question whether this co-located load nevertheless benefits from the provision of ancillary services to the generator.  As Mr. Herling previously explained, under a generator-contingent configuration, PJM’s necessary studies may require the co-located generator to install capacitor banks or other equipment to maintain current reactive supply and voltage control capability to the grid, and thus the co-located load has no impact on these ancillary services.107  Co-located loads in any configuration are unlikely to increase requirements for synchronized or non-synchronized reserves.108  Thus, while there may be some benefit to co- located load for some ancillary services provided to the interconnected generator, a universal requirement for every co-located load to pay for all ancillary services, regardless of their connection and use of the system (or lack thereof), is not required by the current Tariff and is unjust and unreasonable and unduly discriminatory and preferential.109  As discussed herein, it may be appropriate to include some ancillary service charges, such as regulation and black start, in replacement rates if the co-located load configuration is contributing to the costs of providing ancillary services.

106 Id.
107 See Protest of Constellation Energy Generation, LLC, Docket Nos. ER24-2888-000, et al., Att. 1, Affidavit of Steven R. Herling at ¶ 26 (Oct. 2, 2024); see also Herling Aff. at ¶ 34 (discussing same).
108 See Ming Testimony at 42.
109 See Herling Aff. at ¶ 36 (explaining that the Commission has not charged for ancillary services based on “synchronization benefits” but rather by load’s use of ancillary services).

PDF page 35

35
E. No Party Has Demonstrated That a NITS-Only Approach Is Just and Reasonable
and Not Unduly Discriminatory or Preferential.
No party has “show[n] cause as to why the Tariff remains just and reasonable and not unduly discriminatory or preferential due to the lack of provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements.”110  They barely tried to consider options other than NITS.  Rather, the Indicated Transmission Owners simply equate synchronization to the grid to firm transmission service in every case, but this has never been the standard—mere synchronization says nothing about how load is using the transmission system, if at all.111

For its part, PJM states that its Tariff is just and reasonable112 but provides no meaningful support for this conclusion.  PJM goes on to note “improvements and clarifications” may be appropriate, asks repeatedly for Commission guidance on various aspects of co-location, and also constructively provides eight options for consideration as replacement rates.  But PJM states a strong preference for configurations where the load takes firm NITS and pays based on gross load, which “does not incentivize nor facilitate interconnection in a lower cost manner through co- location” and “ultimately drives unnecessary increases in transmission system costs.”113  PJM also commits that it “remains open to modifying its Tariff as necessary to clarify any rates, terms, or conditions relating to co-location arrangements to provide the industry with needed regulatory clarity, certainty, and optionality.”114

110 Show Cause Order at P 87.
111 See Herling Aff. at ¶ 33 (“synchronization does not require or suggest that energy delivery from … generation to … load flows on the transmission facilities of the grid.”)
112 Contra PJM Answer at 4 (asserting that “[t]he record will support a finding that PJM’s existing Tariff remains just and reasonable”).
113 Ming Testimony at 62.
114 PJM Answer at 32 (response to a.ii.).

PDF page 36

36
The Commission should take PJM up on its offer.  It should find the existing Tariff unjust and unreasonable for all the reasons discussed above.

THE COMMISSION SHOULD ADOPT A REPLACEMENT RATE OF SEVERAL
CO-LOCATION OPTIONS
As a replacement rate, the Commission should require modifications to PJM’s Tariff to provide for co-location options that incentivize large new load to locate in places and on terms that maximize the efficiency of the existing transmission grid and allow for timely service without jeopardizing reliability or unjustly shifting costs.  “The existence of multiple options for co-located loads to interconnect under different arrangements is, itself, foundational to economically efficient tariff design.”115  The Commission’s overall policy goals should be to ensure that new data center load can be connected promptly, in a way that maximizes the efficiency of the existing grid, and that requires the new load to pay a just and reasonable rate for the service it receives.  PJM constructively laid out eight options and most offer appropriate frameworks for just and reasonable co-location configurations.  However, modifications are needed to some aspects of the rate design, as set forth herein.

A. PJM’s Proposed Options Are the Foundation for Just and Reasonable Rates.
PJM proposes eight potential options that could, in its view, serve as a replacement rate for integrating large loads through co-location arrangements.  The options are as follows:

115 Ming Testimony at 25; see id. (“Large customers seeking interconnection as co-located loads will have a range of expectations and preferences for the level of reliability of service, and providing multiple options enables those customers to evaluate trade-offs between reliability and cost.”).

PDF page 37

37

PJM
Rate
Option
Description
Fundamental
Configuration
(E3 Determination)
1
NITS without co-location
Firm
2
NITS with co-location
Firm
3
Load customer with BTMG
Firm
4
Co-located load with ‘generator-
contingent’ protections
Generator-Contingent
5
Co-located load with ‘generator-
contingent’ protections + as-available
energy purchase option
Generator-Contingent
6
NITS with co-location + BYOG
Firm
7
NITS with co-location where load is
interruptible
Interruptible
8
NITS with co-location where load
participates as demand response
Interruptible

The options should be evaluated under “the rate design principle” of “[f]air apportionment of costs” or, in other words, “costs should be borne by the customers that cause the costs” and the customers that do not cause the costs, should not.116  The options should also be economically efficient, “free from controversies as to improper interpretation,” and “non-discriminatory.”117  For each option, Constellation proposes rate modifications to bring the option in line with these fundamental rate principles.  Of these options, all but Option 6 can be just and reasonable as part of a selection of co-location options (though some require modifications).

As set forth below, with appropriate rate design, these eight options converge into three:
(1) a firm NITS option with the load paying based on either gross load or net load, depending on its configuration, (2) a generator-contingent option where co-located load does not pay NITS but

116 See Ming Testimony at 9.
117 Id.

PDF page 38

38
pays for any necessary upgrades and could pay a discounted transmission charge for as-available energy purchases, if any, and (3) an interruptible transmission option—lasting until network upgrades are completed—where co-located load  pays a discounted transmission charge reflecting its inferior service.118

1. Option 1 - Firm Service Without Co-Location
PJM’s first option involves the large load procuring existing NITS without being physically co-located with generation (i.e., connecting anywhere on the grid).  As PJM explains, “[b]ecause the load is taking NITS, the load and generator do not have to be sited at the same location because the load and the generation are electrically connected to the grid separately.”119  This is a firm service option, with a NITS rate paid on gross load.

Of course, NITS service is a just and reasonable option for load choosing such a configuration; but, as discussed above, it would not be reasonable to provide this option to the exclusion of any other configuration choice.  That would “drive[] unnecessary transmission build that could be avoided” through a generator-contingent or interruptible co-location configuration, and intrude on state jurisdiction to permit direct sales from a generator to co-located load if this is the only option for load.120

2. Option 2 – Firm Service With Co-Location
PJM’s Option 2 is the same as Option 1 (firm) except the load and generation are co-located at same Point of Interconnection.  Aside from specifying additional requirements for any necessary generator modifications, everything else is the same as traditional NITS service, with PJM

118 See Ming Testimony at 15, 53.  These are Option 2: NITS with Co-location; Option 5: Co-located load with ‘generator-contingent’ protections + as-available energy purchase option; Option 7: NITS with co-location where load is interruptible.  See also id. at 50, Table 1 (providing overview of appropriate transmission charges for firm, generator- contingent, and interruptible configurations).
119 PJM Answer at 10 (emphasis added).
120 See Ming Testimony at 54.

PDF page 39

39
proposing to apply the full NITS rate to gross load.121  Yet electrically Option 2 is identical to Option 3 for behind-the-meter configurations (PJM Option 3), under which NITS charges are applied to net load.122  “[C]onsistent with FERC precedent and non-discriminatory treatment with behind-the-meter generation, the starting point for a co-located load configuration should be a net billing construct that measures the actual energy flowing between the entire co-location configuration and the transmission system.”123  Ordinarily, two electrically identical options should be charged the same rate—yet PJM proposes to charge different rates.  This is not consistent with good rate design principles.124  Option 2 not only suffers the same flaws as Option 1, but also fails to “provide any discount to reflect the fact that many co-located generators will be on and available during the system peak, offsetting the co-located load and reducing the system cost impact of all loads in this configuration.”125  The failure to differentiate between a regular NITS customer—which locates wherever it wants no matter the socialized upgrade costs—and a co- located customer, which has “a lesser impact on the transmission system,” fails to “fairly apportion costs.”126

Nevertheless, load and a co-located generator, if presented with both Options (2 and 3), may prefer Option 2 (under which the generator remains a capacity resource) over pursuit of BTMG netting (under which the generator is required to delist the capacity used to serve the co- located load and PJM procures capacity based on the load’s net contribution at the coincident

121 Ming Testimony at 55, 62.
122 See id. at 55 (noting that “[c]ustomers in this configuration still represent firm loads”).
123 Id. at 28.
124 It is also a well-established principle that all similarly situated entities are charged consistent rates.  Tenaska Clear Creek Wind, LLC v. FERC, 108 F.4th 858, 868 (D.C. Cir. 2024) (citing Consol. Edison Co. of N.Y., Inc. v. FERC, 45 F.4th 265, 282 (D.C. Cir. 2022) (“And undue discrimination occurs when similarly situated entities are charged different rates for no good reason.”).
125 Ming Testimony at 55.
126 Id.

PDF page 40

40
peaks).  Thus, co-located load should have the choice to pay gross NITS (in which case the generator and the load would remain in the capacity market) or instead, if the load and generator agree, to pay NITS calculated on a net basis as in Option 3 (in which case the portion of the generator serving the load would delist and PJM procures capacity for the load based on net load during the coincident peaks).

Since “there is a high likelihood that the co-located generator will be available during the coincident peak hours, meaning that the co-located load is unlikely to be withdrawing energy during coincident peak hours” and “conventional NITS charges based on net system energy withdrawals may not fully capture the costs associated with designing the transmissions system to ensure the co-located load could be served,” it is also appropriate to add a standby charge.127  This standby charge would “reflect the fact that the transmission system must be built to a certain extent to serve the load on a firm basis.”128  The standby charge would be based on a “customer- designated firm load subscription level of what the customer could draw from the transmission system.”129  There are numerous ways to calculate the standby charge, but Mr. Ming proposes one potential methodology based on rate design principles and Commission precedent.130  For its part, the Pennsylvania Public Utility Commission also has endorsed the use of standby charges.131

127 Id. (emphasis in original).
128 Id. at 29.
129 Id. (emphasis in original).
130 See id.
131 See Pa. Pub. Util. Comm’n, Opinion and Order, Pa. P.U.C. No. R-2018-3000124, at 62 (Dec. 20, 2018) (concluding that Duquesne Light Company’s “Rider No. 16” standby service rate “is reasonable because it is voluntary, and the customers can achieve savings through Rider No. 16 because it is less than the applicable full requirements rate”); see also Exergy Partners Corp., Standby/Capacity Reservation Charge Best Practices and Review: Prepared for Pennsylvania Public Utility Commission CHP Working Group, at 12 (July 16, 2018), https://www.puc.pa.gov/Electric/pdf/CHPWG/Standby_Cap_Res_Best_Practices_Review-071618.pdf (Standby rate design should not assume that all forced outages of on-site generators occur simultaneously, or at the time of the utility system peak.”).

PDF page 41

41
The ideal rate for firm transmission service for co-located loads under Option 2 would be the greater of NITS applied to net load or the standby charge—unless, as discussed above, the generator and load would prefer for the load to pay NITS on a gross basis so that the generator and load can remain in the capacity market.132  This rate would appropriately reflect the co-located load’s use of the transmission system, as well as the benefits it provides.

3. Option 3—Behind-the-Meter Generation
PJM’s third option is the existing Tariff provisions for BTMG, where the load is a NITS customer, but NITS charges only apply to the “net” of load minus BTMG at the relevant coincident peaks.  The generator must delist the capacity used to serve the load, and the load only counts toward the reliability requirement based on its net coincident peak.  Thus, the effect on resource adequacy is no different than if the generator remained a capacity resource and the load counted toward the reliability requirement based on its gross coincident peak.

There are two kinds of BTMG: (a) so-called “retail” BTMG, which is load and generation co-located at the same point of interconnection, where the total quantity is not limited, and

(b) “non-retail” BTMG, which is load at a separate point of interconnection from the generation but served by municipal utilities over a distribution system, which is limited to a certain quantity of megawatts.133  PJM’s narrative describes both kinds of BTMG,134 but its charts and most of its discussion concern only non-retail BTMG, which has quantity limitations that do not apply to the regular—and far more common—retail BTMG.135

132 Ming Testimony at 31.
133 See PJM Answer at 12.
134 PJM Answer at 12, 34-26.
135 See Ming Testimony at 21 (“non-retail behind-the-meter generation[] is capped at 3,000 MW, … PJM estimates that retail behind-the-meter solar capacity across its footprint in 2025 totaled more than 10,000 MW.”) (emphasis in original), citing Appendix A: https://www.pjm.com/-/media/DotCom/documents/manuals/m14d.pdf; and Page 2, https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/fact-sheets/distributed-energy-resources.pdf

PDF page 42

42
Under both types of BTMG arrangements, the load pays for NITS and ancillary services on a net basis—meaning only the amount withdrawn from the grid after subtracting the generation.136  The Commission found that netting was appropriate to “encourage qualifying entities with behind the meter generation to reduce their use of the PJM transmission system.”137 In another case involving ISO New England Inc. (where netting also is standard for behind-the- meter configurations), the Commission found that netting “reasonably reflect[s] each Network Customer’s usage of the transmission system and assigns the cost of providing Regional Network Service accordingly.”138  This option is readily applicable to the co-location of large loads.  As noted above, the co-location arrangement described in Option 2 is electrically identical to the BTMG arrangement currently authorized in PJM’s Tariff.  The picture below depicts the “retail” BTMG configuration.  The only difference between a “retail” BTMG configuration and a behind- the-meter co-located generation and load configuration is that the generator and load would swap positions.  Either way, they are both behind the meter, and the load uses grid power only to the extent it exceeds what the co-located generator can supply—and accordingly is billed on a net basis.

136 See id. at 21, 55.
137 PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at PP 27-28 (2004) (citing Occidental Chemical Corp. v. PJM Interconnection, L.L.C., 102 FERC ¶ 61,275, at P 14 (2003)) (emphasis added).
138 ISO New England Inc., 178 FERC ¶ 61,086, at P 49 (2022); see also Ming Testimony at 56 (arguing that for a fair apportionment of costs, the rate treatment should include both netting and an “appropriate discount that reflects the transmission costs savings” of a behind-the-meter co-location configuration).

PDF page 43

43

As Mr. Herling explains, “BTMG arrangements and co-located load arrangements can be designed from an engineering perspective in exactly the same manner.  In one, the load is typically greater in magnitude than the generating facility.  In the other, the load is typically lesser in magnitude than the generating facility.”139  Yet, “[t]he physics of energy delivery are the same in both arrangements and are not related to contractual arrangements or rate structures.”140  Accordingly, “[t]here is no physical, technical, or economic reason why a netting construct should apply differently for customers with behind-the-meter generation or co-located generation.”141  Any configuration where the generator and the load are co-located behind-the-meter is similarly situated and should qualify for netting.142

139 Herling Aff. at ¶ 30.
140 Id.
141 Ming Testimony at 55.
142 The names for BTMG all are misleading, including BTMG itself.  As shown here, both the generation and the load are behind-the-meter in a retail BTMG configuration or a PJM Option 4 configuration.  It is also unclear why this is

PDF page 44

44
PSEG, which is a Transmission Owner but not one of the “Indicated Transmission Owners” in this case, persuasively argued that “[a]n approach that aligns with cost causation principles is one that treats all co-located customers as NITS customers with netting rules applied” which “is the current construct for BTMG customers” and consistent with the treatment of other customers, e.g., universities and hospitals, which “are allowed to net BTMG out of their transmission charges reflecting the fact that when they are generating behind the meter, they are not using the system.”143 PSEG concludes that “[t]here is no reason to treat behind the meter load any differently than BTMG.”144

The second type of existing BTMG illustrates even more starkly why net billing is appropriate for a configuration like “retail” BTMG.  In a non-retail BTMG configuration, the generator and load are not at the same point of interconnection.  This configuration looks no different than a standard front-of-the-meter configuration.  Yet under the PJM Tariff rules, this special class of non-retail BTMG is still allowed to net.  It would be discriminatory to allow this type of non-retail BTMG to net but not to allow netting for generation and load co-located at the same point of interconnection, such in PJM Option 2.

PJM asserts that the existing BTMG configuration “was conceived for, and has been implemented for, substantially smaller loads.”145  But there is no size limitation for BTMG in the PJM Tariff, and it has been implemented for large loads.  This attempted differentiation between equally “large” facilities certainly smacks of undue discrimination.  And size itself is not a rationale for discriminatory rate treatment.

called “retail.”  It is simply a “BTM” configuration of generation and load.  As for the “non-retail BTMG” configuration in the existing Tariff, it is not behind-the-meter.  It is simply an example where certain privileged generators and loads are allowed to net (while most others are not).

143 PSEG Response at 13 (citations omitted) (emphasis in the original); see id. at 17 (citing cases in support).
144 Id.
145 PJM Answer at 13 & n.5.

PDF page 45

45
PJM expresses concern that load under the existing BTMG tariff is not required to carry reserves and may lean on the PJM system when the co-located generation is on outage, or when the load exceeds the rating of the co-located generation.  PJM also contends such loads should pay for certain ancillary services, such as black start, and netting may not result in a sufficiently large charge to capture these loads’ true reliance on the system.146  These concerns are easily addressed. The behind-the-meter rules under PJM Option 3 could be modified to require the co-located load to carry or pay for reserves and ancillary services.  If needed, a minimum demand charge for NITS could be fashioned to account for any non-volumetric costs the BTMG load imposes on the system. This mechanism may be appropriate for including in a replacement rate for co-location arrangements, perhaps with carrying of reserves and/or ancillary services charges, as appropriate. But one thing is clear: billing should be based on the load’s net use of the transmission grid, and this is true whether the load is “large” or “small.”147

4. Option 4—Generator-Contingent Service with No Backup Grid Service
PJM Option 4 is a generator-contingent configuration where both the generator and the load are behind the same point of interconnection with protective equipment to prevent the load from drawing power from the grid.  The diagram below illustrates this configuration.148

146 PJM Answer at 36.
147 Ming Testimony at 55-56; see also PSEG Response at 2 (“There is no justification to treat behind the meter load any differently than BTMG, and the Commission should ensure that there is no undue discrimination in the treatment of co-located arrangements.  Both should pay (and in the case of BTMG customers continue to pay) based only on actual usage of the transmission system.”).
148 Graphics Slide of Mike Kormos, Docket No. AD24-11-000 (filed Nov. 4, 2024) (the break in the lines between the nuclear plant and the data center substation represent the potential placement of protective equipment to prevent the data center from drawing load from the grid).

PDF page 46

46

Existing generators that serve new co-located load under this configuration will delist the capacity used to serve the load, and the load does not contribute toward the region’s reliability requirement.  Under this option, the load pays no transmission charges because it is not using the transmission system, but the load must pay for its own transmission system upgrades if PJM’s “necessary studies” show that the withdrawal of the existing generator’s power from the grid creates any congestion or other transmission issues.

This configuration allows load to connect more quickly and more efficiently by removing the need for costly transmission upgrades, most of the cost of which would be socialized to all customers.149  This option also is preferable from a resource adequacy perspective because reserves do not need to be procured for the large new load.

149 See Herling Aff. at ¶ 28 (“Because the associated special-purpose relay scheme …, no energy will flow to the co- located load over the transmission grid following a contingency; no new transmission infrastructure will be required on the grid to facilitate the interconnection and to ensure reliability for existing load customers other than what might

PDF page 47

47
While nothing in the current Tariff purports to foreclose this option, Constellation agrees with PJM that Tariff modifications could clarify that, under the existing Tariff, the co-location of generation and load behind-the-meter already is permissible, and memorialize the rules in PJM’s Co-Location Guidance (which are largely concerned with ensuring reliability).150  This would include the necessary studies process as well.

The Commission has voiced concern about co-location arrangements being “adequately and transparently reflected” in planning mechanisms, such as the PJM capacity market.151  Such transparency is provided under the necessary study process.  As explained by Mr. Kormos, “[t]he Necessary Study is not limited to a local focus and instead evaluates the incremental impact on the entire PJM system....”152  Further, under this process, if any reliability issue is identified then “the new load cannot come online until the issue is addressed.”153  Thus, the necessary study process provides transparency and predictability into the development of co-location arrangements.  In fact, it is likely more transparent than existing practice.  Transparency is hindered under existing practice because PJM relies on transmission owners to provide assessments of large load demand in their respective zones, but, without a standardized process to create such assessments, PJM is forced to “make a number of judgment calls.”154  Transparency can be bolstered by increasing the frequency in which transmission owners report load assessments from once to 2-4 times per year.155

be identified in the Necessary Study performed for the change in status (partial delisting) of the generator,” which the load would pay for).

150 See PJM Answer at 14 (“Tariff modifications would be needed based on the Commission’s November 1, 2024 Order in Docket No. ER24-2172.”) (citing PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024)).
151 See Show Cause Order at P 85.
152 Kormos Aff., Appendix.
153 Id.
154 Patterson Aff. at ¶ 29.
155 Id.

PDF page 48

48
Since the load also is connected directly to the generator—as opposed to the grid—the load does not rely on the grid for ancillary services; the generator does.  Commission policy does not support charging generators for ancillary services, largely because generators typically provide the ancillary services to the grid.156  Nonetheless, Constellation is open to negotiating fair charges, if any, for regulation and black start services, or other ancillary services if usage can be factually proven (as opposed to rhetorically asserted by lawyer witnesses).157  The Commission should not allow the debate over ancillary services to obscure the much more important point here: allowing load to co-locate with protective relay equipment so they cannot draw power from the grid will avoid costly and unnecessary transmission upgrades that would be required if the load were forced to become a full NITS customer.  That cost dwarfs any ancillary services costs.

PJM and the Indicated Transmission Owners oppose this configuration because they fear that the protective relays themselves might fail, and the possibility of such failure supposedly requires the Indicated Transmission Owners to plan the system as though the protective relays did not exist at all.158  The Commission should reject these arguments.  Protective mechanisms are commonplace and frequently used by PJM and others in situations beyond co-located load to ensure safe and reliable grid operations—including, for example, primary and secondary relays and redundant protection systems.159  Mr. Herling explains the engineering.  Specifically, a “fully redundant” protective relay scheme involves two circuit breakers placed in series behind the meter, each with two trip coils so that either the primary or backup protective relay can trip the load via

156 See Integration of Variable Energy Resources, Order No. 764, 139 FERC ¶ 61,246, order on reh’g, Order No. 764- A, 141 FERC ¶ 61,232 (2012), order on reh’g, Order No. 764-B, 144 FERC ¶ 61,222 (2013).
157 See Ming Testimony at 42-44 (discussing use of ancillary services and possible charges for same).
158 PJM Answer at 14, 44; Indicated Transmission Owners Answer, Att. A at 10.
159 Kormas Aff. at ¶ 6.

PDF page 49

49
fiber optic channels.160  Each element of the protective scheme, “including the electric current transformers, the fiber channels, and the trip relays, are redundant resulting in a single-failure- proof design.”161  The system is not planned for nor does PJM require upgrades to address subsequent “third contingency events”162 and it would not “be reasonable to do so, short of events that would result in a cascading outage of grid facilities.”163  Mr. Herling explains that protective systems are “regularly employed on the PJM transmission system, and the successful operation of such protective systems is a common observance within PJM.”164  Mr. Kormos, PJM’s former Chief Operations Officer, also describes such protectively relay systems as “commonly used mechanisms.”165  If a concern remains regarding third contingency events, then PJM can model for such a situation and prepare accordingly.166  As Mr. Herling confirms, it would be discriminatory to suggest that protective relaying cannot be used in the context of co-located configurations or that co-location arrangements must be designed to a different standard.167 Finally, PJM suggests that Option 4 would only be available “where state law permits such a configuration.”168  Constellation agrees.  The PJM Tariff should not attempt to interpret the various states’ laws on this topic, both because PJM has no authority to do so, and because the states themselves are far better equipped to enforce their own laws.  Further, the Commission should not inhibit state flexibility and autonomy if a state permits a configuration such as Option

160 Herling Aff. at ¶ 23.
161 Id.
162 Kormos Aff. at ¶ 7.
163 Herling Aff. at ¶ 23; see also Kormos Aff. at ¶ 7 (providing that “[t]he failure of a relaying scheme itself is also not necessarily unreliable if PJM is prepared for it”); see also Ming Testimony at 35 (discussing remedial action schemes operated by PJM).
164 Herling Aff.at ¶ 23.
165 Kormos Aff. at ¶ 7. 166Id.  Mr. Kormos also explains that in the event the co-located generator trips offline, the protective relays will simultaneously cut the load “providing PJM a benefit with less imbalance to resolve.”  Id.
167 Herling Aff. at ¶ 23.
168 PJM Answer at 14.

PDF page 50

50
4.  Doing so would effectively preclude states from regulating transactions that fall squarely within their jurisdiction.  Instead, the Commission should facilitate and encourage states to take the initiative to proactively develop regulations and procedures for such co-location configurations. The Commission can do so by directing PJM to clarify in its existing Tariff that the co-location of generation and load behind-the-meter already is permissible, and memorialize the rules in PJM’s Guidance Document, as proposed herein.

Ultimately, Option 4 (subject to resolution of regulation and black start services charges) is aligned with the rate principle of fair apportionment of costs.169  Customers should be able to select this service if they are willing to accept the tradeoffs in the nature of service.  They can later transition to full NITS if they choose (following the required studies for NITS) and remove any protective equipment previously installed to prevent drawing power from the grid.

5. Option 5—Generator-Contingent Service with Optional Backup Grid Service
This option is like Option 4 in that it is a generator-contingent configuration where load is located behind the generation with a protective mechanism to prevent delivery of energy from the grid, but backup service from PJM would be “as available” with advanced authorization for an appropriate transmission charge.

The capacity used to serve the load must delist.  The load is assigned no NITS charges if it has no network load at the coincident peaks.  Further, any network upgrades to serve the load would be borne by the co-located entities.  Charges for ancillary services would be handled the same way as in Option 4.  Thus, this option (as amended to reflect regulation and black start services, as described above for Option 4) is consistent with the fair apportionment of costs.170

169 Ming Testimony at 57.
170 Id. at 57.

PDF page 51

51
This option also aligns with the principle of economic efficiency because the lower costs assessed to the load provides a price signal for load to arrange this configuration where possible and the as- available energy purchases provide an opportunity for beneficial transactions.171 The difference between this option and Option 4 is that the co-located load has the option to draw energy from the transmission system on an as-available basis, meaning only when PJM determines it will not cause any impacts on the transmission system.89  “Because this energy would only be provided if the transmission system as built is capable of delivering it, as-available energy would not require any additional investment in transmission infrastructure.”90

As presented by PJM, this option does not provide for a usage fee associated with the as- available backup service.  Constellation proposes that it would be reasonable to provide as- available energy at the locational marginal price plus a discounted transmission charge because, while energy would be drawn from the grid, it would only be “as available” when it is not adding any burden to the transmission system (and the load would not need to be planned for reliability or resource adequacy).172  Since access to power from the grid would only be “as available,” this is an inferior service to PJM Option 3, for example, which would allow full service to the load whenever the generator was offline.

As PJM states, “[t]his option requires real-time, bespoke operational decision-making to determine whether load can continue to be served.”173  But, as with Option 4, this is not a uniquely difficult operational challenge for PJM.  As Mr. Kormos explains, PJM “has the ability to model any large load in both planning and operations in whatever detail it desires” and the configuration

171 Id.
172 See Ming Testimony 38-42 (proposing a discounted transmission rate for as available energy based on the marginal cost of transmission); Table 1.  Mr. Ming further points out that “[c]ollection of as-available transmission charges would directly benefit existing ratepayers by reducing rates since as-available energy purchases by co-located loads would contribute to the recovery of transmission costs without requiring any additional costs be incurred.”  Id. at 41.
173 PJM Answer at 15.

PDF page 52

52
of the load makes no difference with respect to such modeling.174  In other words, this concern is not unique to this co-located load configuration, and according to PJM’s former Chief Operations Officer, the challenge is not all that challenging in any event.

6. Option 6—Bring Your Own Generation
Option 6 involves firm large load additions that interconnect as Network Load and bring additional generation to serve as Capacity Resources or otherwise make arrangements with generation that has or is scheduled to deactivate.175  PJM acknowledges that not all the options it proposed are “equivalent, desirable, or even necessarily workable.”176  Such is the case with Option 6, and it should be rejected accordingly.  Some of the other options may require modification (see, e.g., the discussion of Option 7 below), but Option 6 is dead on arrival as unduly discriminatory and likely to exacerbate the very resource adequacy issues it purports to address. First, Option 6 discriminates against existing generation.  As explained in the Patterson Affidavit, “[t]his approach is functionally equivalent to an out-of-market payment or subsidy (for the same resource adequacy services) which effectively lowers the cost of the with-contract class and thus distorts and depresses market economics for all other resources (including all without- contract new resources and all existing resources).”177  Mr. Patterson further explains that the favorable interconnection queue treatment presented by Option 6 does not make up for the discriminatory nature of this option because “[t]he ultimate endpoint of such a policy is to drive all resource additions to seek contracts with large load and depress economics for other resources, leading to reduced new entry outside of the large load contract path and potentially retirements of

174 Kormos Aff. at ¶ 7.
175 PJM Answer at 16.
176 Id. at 5.
177 Patterson Aff. at ¶ 40.

PDF page 53

53
existing resources.”178  Another concern is that “because the right to integrate with the system is of very high value to large loads, and restricting that right to only those loads that bring their own generation confers an additional high-value benefit on new capacity that is able to secure a contract with a new entrant large load.” 179  As a result, this option discriminates against existing generation and new generation that for whatever reason cannot contract with a new large co-located load prior to completion of the generator interconnection queue process.  Such a result “would further advantage this subset of capacity relative to other types of capacity by paying them a large effective subsidy.”180

The undue discrimination presented by Option 6 is akin to contractual vintaging that the Commission has historically found to be ineffective for resource development.  For example, over a half century ago, the Commission analyzed the practice of establishing prices for natural gas based on contract date vintaging whereby one rate applied to “‘old’ or ‘flowing’ gas (based on historic ten year costs) and another for ‘new’ gas (based on current costs and designed to provide incentives for future development).”  The Commission held that “vintaging by contract date is an anachronism which should be eliminated.”181  The Commission’s rationale was that contract vintaging did not “respond[] to the present need for increased exploration and development” because the incentives applied to “‘new’ gas ratemaking are totally lost as to undeveloped acreage committed under old contracts.”182  The same rationale applies here.  Option 6 proposes to provide certain advantages to a subset of new capacity that can be developed simultaneously and co-located

178 Id. 179 Id. at ¶ 41.
180 Id.
181Re Area Rate Proceeding for Rocky Mountain Area, 49 FPC 924, 942 (1973) (citing Opinion No. 468, Permian I, 34 FPC 159, 185 (1965)).
182 Id.

PDF page 54

54
with large new load, which will lead to the underutilization of existing generation capacity or new capacity that cannot co-locate with new large load for whatever reason and that, in turn, will stunt overall development efforts.  This is untenable considering the importance of promptly connecting large data center load.183

The Commission has previously rejected measures to attract new entry that unduly
discriminated against existing capacity resources.184  Mr. Patterson explains the rationale for applying the same principle to Option 6, i.e., it “is essentially a form of vintage pricing in that it offers an effective subsidy for a favored class of new resources, while denying that subsidy to non- favored new resources and existing resources.”185  In turn, this will result in depressed revenue for “non-favored resources with no offsetting benefits, which ultimately chills new entry from resources that are unable to contract with new large loads and potentially leads to market exit by existing resources, undermining reliability and reducing overall market efficiency.”186 Second, this option may create perverse incentives for existing generators to retire. Although PJM has the option to enter into “reliability must-run” contracts with deactivating generators, there is no obligation on behalf of the generator to enter into such arrangements.187  If Option 6 is the prioritized option to effectuate co-located load arrangements, then PJM may find itself with an escalating list of retirement notices as generators vie for co-located load projects seeking deactivated generators that can quickly come online (or stay online). The Commission

183 See supra at Section I.A.
184 PJM Interconnection, L.L.C., 126 FERC ¶ 61,275, at P 149 (2009) (finding that PJM’s proposal to increase the RPM’s New Entry Price Adjustment provision from three years to seven years would “further bifurcate capacity markets by giving new suppliers longer payments and assurances unavailable to existing suppliers providing the same service”), order on reh’g, 128 FERC ¶ 61,157 (2009).
185 Patterson Aff. at ¶ 42.
186 Id.
187 PJM Tariff, Part V, Sections 113.2, 119.

PDF page 55

55
cannot avoid this outcome by simply saying the option will only apply to new generation because, as described above, this would be unduly discriminatory.

The only benefits of Option 6 are that it maintains resource adequacy and “offers a potentially faster interconnection path for generation resources supporting co-located loads in states that want them.”188  However, these benefits are not unique to Option 6 but are provided by other options.  In addition, expedited interconnection pathways for certain resources are also not necessarily a generally accepted benefit and have recently been challenged in other proceedings.189 PJM also states that an existing generator could utilize this option by entering into a bilateral contract with the load, as long as it remains a capacity resource (i.e., is in front-of-the-meter/no netting)—but it is unclear what this offers for existing generation beyond Options 1 or 2.190  The general benefits of Option 6 do not outweigh its fatal flaws, i.e., it is unduly discriminatory and does not make efficient use of the existing system.  For these reasons, Option 6 should not be considered as a viable option.

7. Option 7—Interim Interruptible Transmission Service
Option 7 is a provisional, interruptible service that can be curtailed by PJM during pre- defined conditions; as modified by Constellation, the service would be available until the transmission upgrades needed for NITS service are completed.  With the necessary rate design modifications discussed below, this option could provide large data center loads speed-to-service if they are willing to be interruptible under pre-defined conditions (with the load then either being

188 PJM Answer at 17.
189 See, e.g., Letter of Former FERC Commissioners, Docket No. ER25-1674-000 (filed Apr. 7, 2025) (challenging the Midcontinent Independent System Operator’s proposed Expedited Resource Addition Study as an “opportunity for self-dealing by utilities to advance their affiliated generation” and running “counter to everything FERC has tried to do to preserve open access since the Commission’s landmark issuance of Order No. 888”); Motion to Intervene and Protest of NextEra Resources, LLC, Docket No. ER25-1674-000 (arguing that MISO’s proposal is contrary to open access and unduly discriminatory and preferential). 190 Id.

PDF page 56

56
served by backup generation or not at all).  The Duke Study identifies the significant benefits to the efficient use of the transmission grid and existing capacity when loads can “temporarily reduce (i.e., curtail) its electricity consumption from the grid during [] peak stress periods.”191 Some modifications to PJM’s discussion of this option are needed.  PJM states this option would be available “for a transitional period until any resource adequacy supply/demand imbalances associated with the large load addition could be addressed and the load could assume full Network Load.”192  This misunderstands the purpose of an interruptible NITS, which is to facilitate speedier connection for critical customers such as data centers by making the most of the headroom on the existing transmission system until the system upgrades needed for full NITS can be completed.  New load should not need to wait for the completion of all the system upgrades needed to provide them with NITS if they can be connected earlier on an interruptible basis while those upgrades are being constructed.  Such “unfettered discretion to decide what constitutes a ‘supply/demand imbalance’ and how long it lasts ... harms markets because the functional effect of [this option] as written is that PJM would be conditioning the availability and term of valuable load integration rights on its subjectively determined view of resource adequacy.”193  The result is that resource developers could justifiably lose faith in market price signals and their ability to decide whether to enter the market and when so much is left to PJM’s discretion.194  Accordingly, the interruptible service should cease to be available once the upgrades are complete—not based on PJM’s assessment of resource adequacy.195

191 Duke Study at 5 (citing ERCOT, supra n.45).
192 PJM Answer at 18-19.
193 Patterson Aff. at ¶ 43.
194 See id.
195 Id.

PDF page 57

57
Nevertheless, an interruptible NITS could also provide some resource adequacy benefit if the conditions for interruptibility included both local transmission constraints and reserve shortages.  In the latter scenario, the resource would effectively be supplying a demand response- like product that, unlike other demand response, would be enforceable by PJM through a right to interrupt; because capacity would not need to be procured for that load, the load could avoid capacity payments during the duration of this provisional interruptible service.  Again, even under this latter interruptible NITS option, the service should terminate upon completion of the transmission facilities needed to enable full NITS.  This is because the availability of transmission service for any customer regardless of size or configuration is based on an evaluation of transmission security, not resource adequacy, and co-location itself has no effect on resource adequacy relative to a traditional NITS configuration.

PJM also proposed a full NITS transmission charge (based on gross usage during the coincident peaks) but a bypass of capacity charges for the load.  A NITS charge based on gross load is appropriate if the load is not co-located with the generator, but for co-located load, the rate for Option 7 should include netting as with any other co-located load (see discussion of Option 2 and Option 3 above).196  In addition, “an interruptible co-located load does not require the transmission system to be planned, built, or adapted in any way to accommodate the load because PJM can interrupt the load when needed to avoid system impacts. Therefore, no standby or system impact charges are appropriate.”197

196 Ming Testimony at 50, at Table 1.
197 Id. at 34.

PDF page 58

58
8. Option 8—Expansion of Demand Response Opportunities
The eighth option involves co-located load that elects to be Network Load and participates as a Demand Response resource.198  The primary difference between Option 7 and Option 8 is that PJM controls the curtailment in Option 7 whereas the load controls it in Option 8.  Like Option 7, this option presents a non-discriminatory approach and an efficient use of the existing system.199 In addition, “demand response provided by new large loads themselves is a particularly compelling source of short-lead supply because its size and entry time are by definition tied to the entry of the large load resources that themselves create the need for new supply.”200

The Commission and PJM will need to consider enhancements or revisions to demand response products to better suit co-located load such as data centers, including the circumstances when the load will be interruptible.201  Nonetheless, Constellation supports the Commission’s and PJM’s efforts to take such considerations under advisement and explore this option further.

B. Co-Location Has No Difference in Effect on Resource Adequacy.
In setting an appropriate replacement rate, the Commission should reject any notion that NITS is required to maintain resource adequacy, and thus—effectively—that all other options are off the table.  This is one of the primary arguments of the Indicated Transmission Owners, who paint any alternative to NITS as endangering resource adequacy.202  But NITS is not a resource adequacy construct.  It is a type of transmission service.  PJM does not evaluate resource adequacy when studying a request for NITS because PJM uses a different set of tools, including the capacity

198 PJM Answer at 19-20.
199 See Duke Study at 8-9 (stating that data centers have historically exhibited low participation in demand response programs, but acknowledging that demand response promotes efficient utilization of the transmission system).
200 Patterson Aff. at ¶ 32 (supporting efforts “to maximize the ability of large loads, whether co-located or otherwise, to provide demand response capability to PJM markets”).
201 PJM Answer at 20; see also Duke Study at 9.
202 As set forth in the prior section, the Indicated Transmission Owners also argue that NITS is mandated by the Tariff, but there is no such mandate in the PJM Tariff.

PDF page 59

59
market, i.e., the Reliability Pricing Model (“RPM”), to evaluate and ensure resource adequacy for the collective set of customers that are receiving transmission service.  PJM studies transmission security when evaluating requests for transmission service, regardless of the type of service being requested or provided.  The decision of how to facilitate transmission service to a load, whether or not co-located, is entirely distinct from resource adequacy.

Resource adequacy “is the ability of the electric system to meet the energy needs of electricity consumers,” which generally means that the system has “sufficient generation to meet projected electric demand.”203  Constellation, the Commission, PJM, the Indicated Transmission Owners, and every other party is concerned about maintaining resource adequacy as we serve large new loads.  But the co-location debate we are having in this proceeding does not turn on resource adequacy questions.  The Commission acknowledged this in the Show Cause Order, stating that it “recognize[s], as does PJM, that these [resource adequacy and related] concerns are not necessarily unique to co-location arrangements and that significant load growth more generally may raise many of the same concerns.”204  The Indicated Transmission Owners admit this themselves, arguing that “[a]ll load additions create new demands for energy regardless of their location.  The resource adequacy and reliability challenges exist regardless of whether end-use load is connected to the grid at a generator site or elsewhere, and regardless of whether the point of connection lies ‘behind’ or ‘in front of’ the generator’s meter.”205  Mr. Ming agrees in his testimony that, “[t]he

203 Reliability Explainer, FED. ENERGY REGULATORY COMM’N (accessed Apr. 18, 2025), https://www.ferc.gov/reliability-explainer.
204 Show Cause Order at P 85 (citing Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. EL25-20-000, at 15 (filed Jan. 20, 2025); Large Loads Co-Located at General Facilities, Technical Conference Tr.  (“Tech. Conf. Tr.”) at 104:17–105:18 (Bowring) (Nov. 1, 2024) (“…co-located load is a distraction….the issue is reliability.  At the moment PJM is right on the edge, in talking about dumping or not dumping.  Adding 10 or 20,000 megawatts of load on a system that is already very tight doesn’t make a lot of sense, so the question is what’s the problem?  The problem is reliability.  How do we deal with it?  It’s about expanding generation.”)).
205 Indicated Transmission Owners Answer, Att. A at 19.

PDF page 60

60
resource adequacy impact of a new load is not dependent upon whether it is connected directly to the transmission system or co-located” because the net effect of co-located load, which decreases the supply of capacity possibly available to the system, is the same as load connected to the transmission system, which increases capacity demand.206  In other words, as Mr. Patterson explains, “[f]rom a resource adequacy perspective, a megawatt of load added to the system creates a need for the same amount of incremental supply regardless of whether the load is co-located with generator or not.”207

It appears everyone agrees with this.  But the import is that the Commission should not reject alternative co-location configurations on the theory that they may somehow impact resource adequacy more than load receiving NITS.  All parties likewise agree that load must be served, and, as PJM acknowledges, new load is no different than existing load with respect to resource adequacy planning.208  PJM has sufficient tools to ensure resource adequacy, including RPM, which is designed to send strong price signals to add new generation when needed and to maintain existing resources.  The Affidavit of Mr. Patterson, an electric market design expert, includes empirical data demonstrating that RPM has previously “faced significant incremental supply needs driven by coal retirements and successfully brought forth market-based replacement supply at the scale needed to maintain the target level of resource adequacy.”209  Mr. Patterson further explains that, “[h]istorically the RPM has been successful in bringing forth capacity at the scale needed to maintain resource adequacy of a similar order of magnitude as will be needed in the future.”210 According to Mr. Patterson, the PJM markets are capable of responding to increased load demand

206 Ming Testimony at 45.
207 Patterson Aff. at ¶ 15.
208 PJM Answer at 57.
209 Patterson Aff. at ¶ 18.
210 Id.

PDF page 61

61
and any “[p]re-supposition of market failure is premature.”211  And recent reversals by several generators of their prior retirement decisions indicates that market incentives are effectively responding.212  Mr. Patterson proposes mechanisms by which the RPM can be optimized, if

necessary.213  PJM also has the RRI, which resulted in 94 applications consisting of 26.6 GW of new or expanded “shovel-ready” capacity.214  If these tools are inadequate to ensure resource adequacy, the Commission should address those concerns in separate proceedings.  The

Commission already has scheduled a technical conference on resource adequacy.215
One refrain from those opposing co-location arrangements is that the speed with which
new co-located load can be developed—as opposed to front-of-the-meter load—may pose unique
resource adequacy concerns.216  If there are concerns that more short lead-time capacity is needed than PJM’s existing tools can procure, other reforms are available, such as potential queue reform, including deployment of interconnection automation software platforms217 or including a separate queue for a short lead-time resources, enhanced demand response programs (including PJM’s

211 Id. at ¶ 21.
212 Patterson Aff. at ¶ 20 n.9.
213 See id. at ¶¶ 24-30 (advising that the Commission should support (1) ongoing efforts by PJM to improve the accuracy of the competitive market prices that generators and other capacity resources rely on to signal whether to enter, remain in, or exit the market; (2) improvements to the load forecast to provide more information (qualitatively and quantitatively) on future large load additions; (3) polices which shorten the development lead time of all capacity resource types to improve responsiveness of the market to load growth, including considerations to accelerate interconnection queue cycles based on criteria similar to that used for the Reliability Resource Initiative; (4) efforts to maximize the ability of large loads, whether co-located or otherwise, to provide demand response capability to PJM markets; and (5) policies for contingent procurement of short lead-time capacity supply resources in the event that the normal operational of the RPM fails to clear enough supply to meet a minimum acceptable level of reliability in the base residual auction).
214 Reliability Resource Initiative Draws 94 Applications, PJM INSIDE LINES (Mar. 21, 2025), https://insidelines.pjm.com/reliability-resource-initiative-draws-94-applications/.
215 Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Independent System Operator Regions, Supplemental Notice of Commissioner-led Technical Conference, Docket No. AD25-7-000 (issued Apr. 3, 2025).
216 Show Cause Order at P 85 (citing Illinois Attorney General’s Office December 12 Comments of Complaint at 6).
217 See Patterson Aff. at ¶ 30 (regarding Commissioner Rosner’s letter to PJM).

PDF page 62

62
Option 8), or an updated backstop procurement for short lead-time resources needed to satisfy the reserve margin.

Moreover, some of the co-location options the Commission should adopt would enhance resource adequacy in a non-discriminatory manner.  For example, as discussed above, under Option 7 as it should be modified, new co-located load could voluntarily elect to receive an interruptible transmission service that would be available until transmission upgrades necessary to enable NITS are put in place and that would be curtailed in emergency grid conditions; such load would pose no new resource adequacy burden on the grid.  After all, the grid sees peak load only for a few hours a year.  The rest of the time, there are many gigawatts of unused capacity sitting idle.  As noted above, a recent Duke University study has found that if only 0.5% of new load were willing to curtail at peak, PJM could connect an additional nearly 18 GW of load without the need for any new capacity.218  Constellation supports efforts by PJM to use the existing headroom on the transmission system to facilitate the addition of new load until upgrades are completed.  Such an option would enable quicker connections and promote efficiency by maximizing the use of existing infrastructure.

It is also important not to conflate resource adequacy and reliability.  Reliability is “the ability to withstand sudden electric system disturbances that can lead to blackouts.”219  PJM and the transmission owners conduct studies of proposed configurations to ensure reliability. Reliability would be safeguarded under the generator-contingent configurations (Options 4 and 5) if the Commission amended the Tariff to implement the Guidance Document procedures. Specifically, the Guidance Document provides that any co-location arrangement will be subject to

218 Duke Study at 20.
219 Reliability Explainer, FED. ENERGY REGULATORY COMM’N (accessed Apr. 18, 2025), https://www.ferc.gov/reliability-explainer.

PDF page 63

63
a necessary study process by which such impacts would be evaluated and determined.  The Commission states that co-location technical conference witness, Vincent Duane, PJM’s former General Counsel, voiced concerns about the scope of the necessary study process.220  Mr. Duane suggested to the Commission that the necessary study process is “a much more localized study” and not a system impact evaluation.221  This is not the case, as Mr. Kormos, PJM’s former Chief Operations Officer with significant transmission operations and planning experience, explained. The necessary study process implemented by PJM and described in the Guidance Document “evaluate[s] the potential reliability impact of a proposed addition or reduction of a co-located configuration on the PJM Transmission System, and determine[s] what, if any, system reinforcements are required prior to the addition or reduction of the planned co-located load configuration.”222  Mr. Kormos further explained that if any reliability impacts are identified then “the generator pays for changes at its facility and any necessary network upgrades to cure the potential issue.”223  The necessary study process is not limited to localized regions or delivery areas.  Rather, it is a system-wide study that determines whether any system-wide reinforcements are necessary to ensure resource adequacy and reliability.

Constellation appreciates that resource adequacy and reliability are crucial focuses of the Commission.  Keeping the lights on is the Commission’s most important responsibility.  But PJM and the Commission have many mechanisms to ensure resource adequacy—some already in place, and some that can be developed.  These are not issues specific to co-location and should not be determining factors with respect to implementing a just and reasonable replacement rate.

220 Show Cause Order at P 79 (citing Post-Technical Conference Comments of Vincent Duane, Docket No. AD24-11- 000 (Dec. 9, 2024)).
221 Id. (citing Tech. Conf. Tr. at 46:4-20 (Duane)).
222 PJM Guidance Document at P 7 (emphasis added).
223 Kormos Co-Located Load Solution at 9; see also Kormos Aff. at ¶ 6 (a necessary study is “a robust, highly effective study ... focused on the overall grid impacts of the new load (and not focused predominantly on local impacts).”

PDF page 64

64
C. The Commission Should Adopt Constellation’s Proposed Replacement Rates or,
Alternatively, Establish Time-Limited Settlement Proceedings in this Docket
The Commission should adopt all but Option 6 as a menu of options, as modified, as the replacement rate.  As PJM stated, “identified options are not mutually exclusive, as it is possible several of the options may be used seriatim or concurrently.”224  With Constellation’s proposed rate modifications, PJM’s eight co-location options (less Option 6) largely converge into three options consistent with the “ideal rate” for each type of co-location configuration,225 a firm NITS option (derived from PJM Options 2 and 3), a generator-contingent option (PJM Option 4, or with as available energy, Option 5), and an interruptible option (PJM Option 7), with proposed (and in some cases, modified) rate treatment as follows:

224 PJM Answer at 5.
225 See Ming Testimony at 50-51 (explaining how the eight options converge into three).

PDF page 65

65

Co-location Configuration
Rate
 Component
Firm
(derived from
Options 2, 3)
Generator-
Contingent
(derived from
Options 4, 5)
Interruptible
(derived from
Option 7)
Transmission
Greater of 1)
Standby charge at
discounted NITS
rate applied to firm
subscription level
or 2) standard
NITS applied to
net usage
One-time system
impact charge
based on studied
network upgrade
costs. If as
available energy
purchases are
allowed, these are
billed at discounted
$/MWh charge
Discounted
$/MWh charge for
as-available energy
purchases
Ancillary
Services
Charges for all
ancillary services
consumed based on
net load (if needed
to avoid
discrimination) or
gross load
Charges for all
ancillary services
consumed based on
net load (if needed
to avoid
discrimination) or
gross load
Charges for all
ancillary services
consumed based on
net load (if needed
to avoid
discrimination) or
gross load
Energy
LMP energy
charges based on
net injection or
withdrawal
LMP energy
charges based on
net injection or
withdrawal
LMP energy
charges based on
net injection or
withdrawal
Capacity
Co-located load
participates in
capacity market at
firm subscription
level. Co-located
generator
participates in
capacity market at
accredited capacity
level
No charges to co-
located load served
by dedicated
portion of
generator (PJM
does not procure
capacity for co-
located load);
capacity market
sales from the co-
located generator
may be made if the
accredited capacity
of the co-located
generator exceeds
the capacity of the
co-located load
No charges to load
(PJM does not
procure for load);
co-located
generator is not
dedicated to co-
located load and
can participate in
capacity market at
full accredited
capacity
Non-PJM
States decide
States decide
States decide

PDF page 66

66

Ancillary services should be charged on a gross or net load basis for firm and interruptible configurations, as required to avoid discrimination.226  For generator-contingent configurations, some charge for regulation or black start service may be appropriate.  Energy charges should be assessed based on a net injection or withdrawal of the co-located load generator and load to the transmission system.227

Capacity charges should also be consistent with the configuration of the co-located load. For firm co-located load, the entire load and co-located generator should participate in the capacity market at a level equal to its subscription and accredited capacity, respectively.228  Note that with Option 3, PJM is only procuring for the load PLC above the generation and the generator delists. Generator-contingent co-located load should not be assessed capacity charges because the co- located load cannot draw energy from the grid.229  Interruptible co-located load should also not be assessed capacity charges because the output of the co-located generator can be re-directed by PJM form the co-located load to the broader system.230

Finally, non-PJM charges such as non-bypassable charges to fund state energy efficiency programs, renewable programs, and stranded cost recovery are under the jurisdiction of states and should be governed by state law that is not relevant to charges under the PJM Tariff.231 The replacement rate proposed herein most appropriately allocates costs and, in so doing, avoids any improper cost shifting to existing customers.  In fact, the primary benefit of the proposed replacement rate is that it is consistent with rate design fundamentals, including a fair

226 Id. at 44.
227 Id.
228 Id. at 46-47.
229 Id. at 47.
230 Id. at 47-48.
231 Id. at 48.

PDF page 67

67
apportionment of costs.  The proposed replacement rate is appropriately tailored to ensure that new load pays for its fair share of costs and, equally significant, avoids extensive and unnecessary network upgrade costs under a NITS-only approach, most of which would be socialized and paid for by existing customers.  The Commission should adopt the proposed replacement rate as just and reasonable accordingly.

If the Commission declines to adopt our proposed replacement rate, the Commission should order time-limited settlement discussions in this docket to consider the replacement rate.232 In ordering any settlement to address an appropriate replacement rate, the Commission should accept PJM’s request and “issue a compliance directive under its section 206 authority to set a clear deadline for future filings given the important national interests implicated.”233  Data center development in the PJM region has already been negatively affected by a cloud of uncertainty over the rules of the road for over three years.  Our national security and national economic competitiveness depend on providing clear guidance promptly.  A finding by the Commission that the existing Tariff is unjust and unreasonable and unduly discriminatory and preferential as part of its order establishing settlement discussions would help discipline the discussions.  Further, settlement “efforts would be greatly assisted by Commission guidance as to the reasonableness of any of the [eight] existing and proposed options for co-located load,”234 including, for example, an express Commission finding that generator-contingent and interruptible configurations use the transmission system differently than a firm configuration and thus justify different rate treatment.235

232See Joint Parties Settlement Request.
233 PJM Answer at 4-5 (emphasis added). 234 PJM Answer at 32-33.
235 See Show Cause Order at P 76.

PDF page 68

68
ANSWERS TO THE BRIEFING QUESTIONS
a. General Issues
i. Do you agree with the jurisdictional principles outlined in section VI.A and should the Commission reach any other conclusions regarding jurisdiction in a final order it may issue in this proceeding?  Why or why not?

Constellation generally agrees with the jurisdictional principles outlined in section VI.A., although Constellation disagrees with the suggestion that the manner in which generating resources “are allowed to operate to serve co-located load”236 is a matter of exclusive state jurisdiction.  The interaction of the generator with the PJM markets (the rules for which are implicated in every co-location option presented by PJM) are a matter of exclusive FERC jurisdiction.  We assume that this language in the Show Cause Order refers to the uncontroversial concept that the state decides whether and under what rules generation may engage in direct sales to end use customers.  Constellation generally agrees with PJM’s response to this question, but disagrees with the positions PJM has taken with respect to EWGs and the import of EWG status for generators vis-a-vis Option 3.  Constellation supplements PJM’s analysis in its answer with a review of the Commission’s jurisdictional boundaries and their application to PJM’s Options 4 and 5.

The Jurisdictional Boundaries of the Commission and the States are Well-Settled Under the FPA.

The Commission is a “creature of statute,” having “only those authorities conferred upon it by Congress.”237  The FPA gives the Commission authority over “the transmission of electric energy in interstate commerce and … the sale of electric energy at wholesale in interstate

236 See Show Cause Order at P 71.
237 Atl. City Elec. Co. v. FERC, 295 F.3d 1, 8 (D.C. Cir. 2002) (emphasis in original).

PDF page 69

69
commerce,”238 which means a sale of electric energy to any person for resale.239  The Commission’s jurisdiction is limited to rules or practices that “directly affect the wholesale rate.”240

The FPA expressly provides that the Commission “shall not have jurisdiction … over
facilities used for generation of electric energy or over facilities used in local distribution or only for the transmission of electric energy in intrastate commerce, or over facilities for the transmission of electric energy consumed wholly by the transmitter.”241  Thus, Congress reserved to the states “regulatory authority over retail sales (as well as intrastate wholesale sales)”242 as well as facilities used for the generation, distribution, or intrastate transmission of electric energy.243  As a result, the Commission has held that states “have jurisdiction in all circumstances over the service of delivering energy to end users,”244 including bundled retail transmission service.245 The Commission is allowed to “exercise jurisdiction over generation facilities to the extent necessary to regulate interstate commerce.”246  In other words, the Commission may properly exercise jurisdiction directly over matters federalized by the FPA in a way that also affects areas over which the states exercise exclusive regulatory authority as long as the Commission does not

238 16 U.S.C. § 824(b)(1).
239 Id. § 824(d).
240 EPSA, 577 U.S. 260, 278 (2016) (internal quotations and citations omitted).
241 16 U.S.C. § 824(b)(1).
242 EPSA at 279 (citing New York v. FERC, 535 U.S. 1, 17 (2002)) (emphasis added); id. at 265 (“[T]he law places beyond FERC’s power, and leaves to the States alone, the regulation of ‘any other sale’—most notably, any retail sale—of electricity.”) (quoting 16 U.S.C. § 824(b)) (emphasis added).
243 See, e.g., New York v. FERC, 535 U.S. at 22-23. 244 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utils., Order No. 888, 61 Fed. Reg. 21,540, at 21,626 (1996), order on reh’g, Order No. 888-A, 62 Fed. Reg. 12,274 (1997), aff’d sub nom., New York v. FERC, 535 U.S. 1; see also Ind. Mun. Power Agency City of Lawrenceburg, Indiana, 174 FERC ¶ 61,035, 61,150 (2021) (“The Commission has rejected the argument that the provision of station power is a practice directly affecting rates for wholesale sales subject to the Commission’s jurisdiction, explaining that station power is a sale for end use and the Commission has no jurisdiction over sales for end use.”).
245 Order No. 888 at 21,577-78.
246 Transmission Access Pol’y study Grp. v. FERC, 225 F.3d 667, 718 (D.C. Cir. 2000).

PDF page 70

70
“aim[] at” or “target” the states’ domain.247  When determining the bounds of its jurisdiction with respect to co-location arrangements, the Commission should consider the questions guiding the D.C. Circuit’s decision-making in NextEra Energy Resources, LLC and NextEra Energy Seabrook, LLC v. FERC.248  In that case, the D.C. Circuit explained that it asks three questions in considering jurisdictional arguments with respect to the Commission: “[f]irst, whether the action at issue directly affects facilities or transactions that FERC may regulate; second, whether FERC has impermissibly regulated matters outside its jurisdiction; and third, whether the contested assertion of authority is consistent with the statute’s core purposes.”249

The D.C. Circuit’s guidance is based on first principles, i.e., ensuring the regulation of a facility or transaction at issue is consistent with the applicable FPA text and does not over-extend federal or state jurisdiction into matters under the exclusive jurisdiction of the other. Based on the text and purpose of the FPA as described above, the Commission cannot regulate a generating resource; however, it can and should regulate certain activities associated with a generator’s operation such as: interconnection of the generator to the interstate transmission grid, including standard interconnection service agreement provisions and modifications; participation in wholesale markets; transmission and ancillary service charges; and bulk power system reliability.  By contrast, states retain sole jurisdiction over distribution and retail rates and sales, non-bypassable charges, and interconnection of load at distribution voltage levels.  Even the question of whether a retail sale has occurred is a question reserved to the states.250

247 EPSA, 577 U.S. at 282 (quoting Oneok, Inc. v. Learjet, Inc., 575 U.S 373, 385-86 (2015)).
248 118 F.4th 361 (D.C. Cir. 2024) (“NextEra”).
249 Id. at 368.
250 See 16 U.S.C. § 824(b)(1); see also Southern Cal. Edison Co. v. FERC, 603 F.3d 996, 1000-01 (D.C. Cir. 2010) (“[W]e do not understand why FERC is empowered to conclude that a retail sale has not taken place unless it can claim the transaction is, instead, a wholesale sale or a transmission.  To simply declare that the state lacks jurisdiction because FERC believes no retail sale has taken place really begs the jurisdictional question.  Unless a transaction falls

PDF page 71

71
Federal Jurisdiction Does Not Correspond With “Synchronization.”
There are potential jurisdictional disputes with PJM Options 4 and 5, which involve
behind-the-meter sales between a co-located generator and load.251  Under these options, system protection facilities are installed to prevent the delivery of energy to the co-located load from the grid (with Option 5 allowing for back-up service from the PJM system with permission).  PJM acknowledges that under such a configuration “load is not Network Load unless designated by the customer subject to applicable state law.”252  Even the Indicated Transmission Owners

acknowledge that the PJM Tariff should not interfere with state jurisdiction.253  Nonetheless—and inconsistently—the Indicated Transmission Owners posit that all co-located load, including under Options 4 and 5, should be treated as Network Load and required to take NITS because the load is “synchronized” to the grid.254  But the Commission does not have authority to decide what kind of service a load must take merely because that load is synchronized to the grid.  After all, every generator and every end-user within the Eastern Interconnection is synchronized to the grid.  The fact that a home, grocery, or any other load is synchronized to the grid does not give the Commission authority to decide that the load must purchase its energy from the Commission-

within FERC’s wholesale or transmission authority, it doesn’t matter how FERC characterizes it.”); Indiana Mun. Power Auth. v. PJM Interconnection, L.L.C., 172 FERC ¶ 61,243, at P 106 (regarding station power, “the Commission lacks jurisdiction to determine whether a retail sale has occurred”); id. at P 94 (“The determination of whether a retail sale has occurred . . . is appropriately within the jurisdiction of the states.”); see also Ming Testimony at 48 (“Non- PJM charges vary by state and local utility and may include non-bypassable charges to fund energy efficiency programs, renewable programs, stranded cost recovery, or more. The jurisdiction of these charges lies with the states.”).

251 PJM Answer at 13-15.
252 Id. at 14.
253 Indicated Transmission Owners Answer, Att. A at 18 (“Because the federal role in end-use load is limited, PJM and the Commission should not create processes in the PJM Tariff that would interfere with state jurisdiction.”) (emphasis added).
254 See id. at 9 (“The Indicated TOs consider all the arrangements being contemplated or requested as being interconnected with and synchronized with the transmission and/or distribution grid and thus not ‘fully isolated.’”) (emphasis in original); id. at 3 and n.6 (providing that co-located end-use loads should be treated as front-of-the-meter Network Load with applicable firm transmission service).

PDF page 72

72
regulated wholesale market or that energy must be delivered on the Commission-regulated interstate transmission grid.  Nor does the fact that a generator is synchronized to the grid authorize the Commission to require the generator to make only wholesale sales or inject its output onto interstate transmission lines.  That would upend the traditional division of authority under the FPA. The Commission has authority to set rates for wholesale sales or interstate transmissions when they occur, but states get to decide whether to allow direct sales between a generator and a customer.

The Indicated Transmission Owners’ position violates this limit on the Commission’s jurisdictional authority.  They contend that generators should not be permitted to make direct sales to load in a co-located arrangement, arguing instead that such sales must use the transmission system and pay for transmission service.  They seek a Commission directive to prohibit a generator from selling directly to a co-located load – something the Commission has no authority to do. Differing Treatment of Direct Sales by States Does not Mean There are “Regulatory Gaps” in Options 4 and 5, and the Commission Should Not Usurp the States’ Jurisdiction By Adopting the Indicated TO’s Preferred “NITS Only” Approach.

PJM warns against an assumption of state regulation with respect to direct sales and a “risk in painting with too broad a brush” in establishing co-location arrangements that may or may not be regulated or permitted by the states.255  This presents the potential, in PJM’s assessment, of “regulatory gaps with respect to co-located load arrangements.”256  As PJM acknowledges, however, some states allow direct sales between a generator and end-use consumer over wires that

255 PJM Answer at 25-28, 29.
256 Id. at 21.  PJM also suggests that an Exempt Wholesale Generator (“EWG”) engaging in wholesale transactions with a counterparty that then engages in retail sales is somehow a nefarious shield of regulatory invisibility.  See id. at 25 (“Yet under certain co-located load arrangements (Options 4 and 5 in Exhibit A, for example), EWGs could seek to sell power to an intermediary that then engages in retail sales.”).  The requirements to certify and maintain EWG status are clear.  Constellation has and will comply with such regulations.  Exemption from PUHCA does not mean that the EWG’s sales are exempt from rate regulation.  PUHCA exemptions are not a reason to prevent the states from choosing how to regulate co-location however they choose within their authority.

PDF page 73

73
are not committed to public use.257  Whether to do so is a matter for states to decide—not the Commission.  Differing treatment of direct sales by states is not indicative of a regulatory gap,258 nor is it “a failure to regulate.”  Rather, it is likely indicative of “a deliberate policy choice that has been enshrined” in state law.259  It is also not an invitation for the Commission to extend its jurisdiction beyond that established by the FPA.

Retail issues are a matter of state law, and the states are well-equipped to resolve these questions without federal intrusion, including who is qualified to sell to end use customers and how and whether to regulate retail transactions.  Thus, the real risk in “painting with too broad a brush” would be to use the PJM Tariff to preclude state flexibility to regulate (or choose not to regulate) direct sales between a generator and a behind-the-meter load, intruding on matters that Congress left to the states.  Any requirement to take NITS would inappropriately preclude states from regulating transactions involving direct sales to end users, which may involve delivery facilities that do not transmit power in interstate commerce and fall squarely within the states’ sole

257 See id. at 27-28.  See also Comments of the Pennsylvania Public Utility Commission, Docket No. EL25-49-000, AD24-11-000, and EL25-20-000 (filed Apr. 22, 2025) (“The PA PUC agrees, and it is well-established in Pennsylvania law that when electric service is provided to a ‘defined, privileged, and limited group’ it is not provided ‘to or for the public’.”) (internal citations omitted). 52 Pa. Code § 69.1401 (any one of three non-binding criteria could cause the Commission to find that an entity is not providing service “to or for the public”:
(1) The service being provided by the utility project is merely incidental to nonutility business with the customers which creates a nexus between the provider and customer.

(2) The facility is designed and constructed only to serve a specific group of individuals or entities, and others cannot feasibly be served without a significant revision to the project.

(3) The service is provided to a single customer or to a defined, privileged and limited group when the provider reserves its right to select its customers by contractual arrangement so that no one among the public, outside of the selected group, is privileged to demand service, and resale of the service is prohibited, except to the extent that a building or facility owner/operator that manages the internal distribution system serving the building or facility supplies electric power and related electric power services to occupants of the building or facility.)

See also, e.g., Wyo. Stat. Ann. § 37-1-101(a)(vi)(H)(VI) (“Public utility” provides an exception for generation, transmission, or distribution of electricity from a producer for use of tenants and not for sale to others; however, this exemption does not apply for direct sales of electricity by a producer to tenants).

258  Show Cause Order at P 18 (providing that the Organization of PJM States, Inc. contends that “there is no regulatory gap involving co-location arrangements”).
259 Comments of the Pennsylvania Public Utility Commission at 3, Docket Nos. EL25-49-000, AD24-11-000, and EL25-20-000 (filed Apr. 22, 2025).

PDF page 74

74
jurisdiction.  Applying the guidance questions from NextEra, the Commission should conclude that such action would be an inappropriate and unlawful extension of the Commission’s jurisdiction because it would require the Commission to exert jurisdiction over objectively state- regulated facilities and transactions that are outside of its jurisdiction under the FPA and contrary to the FPA’s purpose.

The states likewise cannot take actions that unduly interfere with the Commission’s jurisdiction over wholesale rates.260 For example, no state could legally mandate that all sales between co-located generation and load occur as wholesale transactions over the transmission grid. Constellation supports the Commission’s effort to create a standard approach to co-location arrangements that is in accordance with and respects the jurisdiction of the Commission and the states.  Just as states should not be permitted to alter or intrude upon the Commission’s jurisdiction, the Commission has no role in interpreting or wading into matters delegated to the jurisdiction of the states or indirectly stripping any state of its ability to exercise its jurisdiction.  Any final policy adopted by the Commission in this proceeding should adhere to this fundamental understanding.

ii. Does the Tariff sufficiently address co-location arrangements with respect to each issue listed in this order?  Please include specific tariff provisions or other governing documents that may apply.

Constellation agrees with the Commission’s preliminary findings that the Tariff does not address with sufficient clarity the methods to effectuate co-location arrangements.261  The Tariff lacks clarity with respect to rules for transmission service applicable to co-located load, if any, and the use and payment for ancillary services, if any are used.  The Tariff is also particularly deficient with respect to interconnection procedures for co-located load (e.g., amendments to ISAs).  For

260 See, e.g., Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 166 (2016) (rejecting a state program because it interfered with the wholesale rate required by FERC).
261 See, e.g., Show Cause Order at PP 74, 78, 79.

PDF page 75

75
example, the Tariff is silent with respect to the procedures, services, and facilities required to effectuate co-location arrangements where the co-located load will not take service from the PJM Transmission System, i.e., PJM Option 4.  The Tariff is also silent with respect to methods to implement Option 5 (co-location with protective systems and back-up service ability) and Option 7 (co-located load electing a new transitional interruptible network service offering).262  The PJM Guidance Document provided useful language to implement PJM’s Option 4, but it is not part of the Tariff and has now been rescinded, underscoring the need to ensure inclusion of relevant provisions in the Tariff.  The lack of clarity results in disparate treatment of co-located load “resulting in different interpretations and applications of the tariff by different transmission owners within PJM.”263  As the Commission aptly recognized, “these dynamics raise the potential for undue discrimination.”264  As discussed in the response below to Question a.iii., the Tariff is unjust and unreasonable and unduly discriminatory and preferential because of such lack of clarity and should be revised accordingly.

iii. If the Tariff does not sufficiently address co-location arrangements, how should the Tariff be modified to do so?  As part of your answer, address whether portions of the Guidance Document may serve as a just and reasonable and not unduly

discriminatory or preferential replacement rate.  Alternatively, address whether existing rules in the Tariff may or should be modified to address co-location

arrangements.
In its filing, PJM has identified eight potential options for how large new load might connect.  Except for Option 6, which is unsalvageable, PJM’s other proposed options are just and reasonable, or can be made just and reasonable with only a few modifications and should be included in a replacement rate. See discussion supra, Section II.

262 See PJM Answer at 15, 17.
263 Ming Testimony at 19; id. (such disparate treatment by transmission owners is not aligned with accepted rate design principles); see also Show Cause Order at P 75 (comparing and contrasting Exelon’s treatment of Constellation’s requests to co-located load and PPL’s treatment of Susquehanna Nuclear’s request to co-located load).
264 Show Cause Order at P 75.

PDF page 76

76
iv. Parties may also address how co-located loads are similar to or disparate from other types of arrangements where load and generation share the same point of

interconnection (such as Behind the Meter Generation as defined in PJM’s Tariff or non-retail behind the meter generation) and should consider how any proposed

replacement rate would interact with these other arrangements.
Co-located loads where load and generation share the same point of interconnection can be configured in various ways.  In some configurations, the generator and load are both “behind-the- meter.”  This is true, for example, of PJM Option 3 (BTMG, which is co-located behind-the-meter generation and load) and PJM Option 4 (behind-the-meter load co-located with generation with protective relays in place to prevent draws of power from the grid).  Other behind-the-meter options would include switching equipment to permit load to draw from the grid with permission (Option 5, behind-the-meter load with back-up service), curtailment by PJM (Option 7, interruptible load), or curtailment by the load (Option 8, demand response).  (Under PJM Option 2, the generator and load would share a point of interconnection but be separately metered.  Our comments on PJM Option 2 are discussed supra at Section II.A.2.).

The Indicated Transmission Owners suggest that no matter the configuration
“synchronized” load is taking transmission service and should be charged full gross transmission rates.  According to the Indicated Transmission Owners, “[c]o-located load that is physically interconnected with and synchronized to the grid uses the transmission system.  Neither the fact that co-located load is geographically near a generator, nor its agreement to buy energy from the co-located generator, changes that, legally or physically.  This is a straight-forward, engineering- based decision.”265  Yet BTMG—which is just as synchronized to the grid as co-located behind- the-meter generation and load—only pays for transmission service on a net basis, meaning the

265 Indicated Transmission Owners Answer, Att. A at 4 (emphasis added); see also id., Att. A at 2 (“[T]he Commission and PJM should affirm that co-located loads that are physically interconnected to and synchronized with the PJM transmission system are utilizing the transmission system.”).

PDF page 77

77
amount of power drawn from the grid after subtracting the power from their behind-the-meter generator.  The Indicated Transmission Owners even admit that BTMG “applies to arrangements that ‘deliver[] energy to load without using the Transmission System.’”266  The Indicated Transmission Owners never explain how “synchronized” behind-the-meter co-located load “uses the transmission system” but “synchronized” BTMG does not.  For its part, PJM points out that “inside the fence” QF cogeneration facilities “were not electrically islanded” but still “established and maintained interconnections” to the grid.267  In other words, they also are synchronized to the grid.  The same is true of BTMG.  Yet, “[a]s PJM described in 2004 when it proposed its BTM Generation Tariff revisions, BTM Generation ‘refers to generating units that are located with load at a single electrical location such that no transmission or distribution facilities are used to deliver energy from the generating unit to the load.’”268

There is nothing that sets apart the “synchronization” of BTMG versus the synchronization of any other co-location configuration that would justify disparate treatment.269  Accordingly, it should be “a straight-forward, engineering-based decision” to treat behind-the-meter co-located load like other BTMG configurations involving co-located generation and load—by allowing netting, for example.  While PJM calls into question the continued use of netting for BTMG,270 it fails to offer any sort of detailed critique or Tariff support for limiting the long-standing practice of netting consumption and generation at the same point of interconnection.

266 Id., Att. A at 4 (emphasis added).
267 PJM Answer at 24. 268 Id. at 34-35 (citing PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 4 (2004)) (emphasis added).
269 Herling Aff. at ¶ 33 (“Comparing PJM’s Option 4 and PJM’s Option 5 with the BTMG construct (the basis for PJM Option 3), clearly both arrangements involve load and generation that is synchronized to the grid.  However, synchronization does not require or suggest that energy delivery form that generation to that load flows on the transmission facilities of the grid.”).
270 PJM Answer at 35-36.

PDF page 78

78
For a full discussion of various potential co-location configurations, how they use the transmission system, and appropriate rate treatments, please see our discussion of PJM’s eight options, supra, Section II.A.

b. Transmission Service
i. Please explain whether and to what extent different configurations of co-located load rely on or otherwise use the transmission system to receive power, directly or indirectly, from the co-located generator;

Please see our lengthy discussion of PJM’s eight options, supra at Section II.A.  In sum, there are three broad categories of transmission system usage that generally correspond to one or more of PJM’s proposed options: firm (see Options 1, 2, 3 and 6), generator-contingent (see Options 4 and 5), and interruptible (see Options 7 and 8).271  Constellation identifies which category of transmission service applies to each of PJM’s eight options, although it should be noted that the ”interruptible” category applies to options where the transmission service itself is interruptible (Option 7) or the load is interruptible as Demand Response (Option 8).272 The Indicated Transmission Owners answer this question by repeating their claim that a “straight-forward, engineering-based decision” results in a finding that “[c]o-located load that is physically interconnected with and synchronized to the grid uses the transmission system.”273 Nowhere is this assertion more patently untrue than with respect to Option 4, which contains as a component a commonly used protective relay scheme to prevent power flows from the PJM Transmission System (which is a defined term under the PJM Tariff) to the load.  As a result, this reductive view is not as “straight-forward” as the Indicated Transmission Owners would like it to be.  In fact, as explained by Mr. Ming, it ignores the disparate transmission system impacts

271 Ming Testimony at 15-18; see also infra at Section II.A. (discussing same).
272 Ming Testimony at 53.
273 Indicated Transmission Owners Answer, Att. A at 4.

PDF page 79

79
associated with different configurations of load and generation.274  It is also the opposite of how BTMG is treated.275

ii. Please explain whether and to what extent different co-location configurations impose costs on the transmission system or increase transmission costs allocated to other parties.  How can those costs be approximated, given that certain co-location

configurations may change power flows on the grid and necessitate upgrades to the transmission system?  Retail loads typically take service from wholesale entities that pay for Network Integration Transmission Service that allocates these costs; co- located loads may not.  Network Loads pay directly for Network Integration

Transmission Service.  How should PJM estimate the effects that different
configurations of co-located load have on the transmission system?  Should these costs be passed through to co-location arrangements in some way, and, if so, how?

The three broad categories of transmission system usage referenced in the answer to the prior question (firm, generator-contingent, and interruptible), and which generally correspond to one or more of PJM’s proposed options, impose different costs.276  Constellation proposes appropriate rate treatment supra in Section II.A.277  In certain configurations, Constellation also proposes usage charges when the load calls on the grid (as available and when allowed by PJM). We reiterate that the largest potential cost by far is for transmission upgrades.  Under standard firm NITS based on gross load (PJM Options 1 and 2), existing customers will be required to pay the costs of substantial system upgrades to accommodate large, new data center loads.278 Other options minimize or avoid these costs entirely, with the co-locating load being responsible for all costs, such as with Options 4 and 5.  This is one of the primary distinguishing benefits of Options 4 and 5.

274 Ming Testimony at 15-16.
275 See supra, Answer to a.iv. (discussing uselessness of “synchronization” standard for determining whether transmission system is being used).  Contrasting the “synchronization” standard with Mr. Ming’s analysis makes this point obvious.
276 Ming Testimony at 15-18; see also infra at Section II.A. (discussing same). 277 Id. at 5-51
278 See Patterson Aff. at ¶¶ 52-53 (calculating costs of transmission upgrades).

PDF page 80

80
The Indicated Transmission Owners suggest that a benefit of NITS is that it sends no locational signal: “PJM’s rate design ... permits transmission owners to recover, on a postage stamp basis without consideration of the distance between load and generation, the embedded costs of their respective portions of the transmission grid from network customers.”279  In a world where all co-located load is required to pay NITS based on gross load, and the cost of transmission upgrades is paid for mostly by other customers, a load would be relatively indifferent to where it locates and have little incentive to locate in a place that is most efficient for the system as a whole. While the Indicated Transmission Owners may be technically correct that “[i]n general, transmission upgrades required for a co-located load will be similar or the same as those required for an equivalent load addition close to, but not co-located with, the relevant generator,” they gloss over the fact that a one-size-fits-all NITS rate approach makes the load indifferent to locational costs and that this indifference can significantly increase overall costs.280  This is because, as the Indicated Transmission Owners remind us, the “costs of these transmission upgrades are typically recovered from all load on the system via the Network Service rate.”281  An appropriate rate treatment should create incentives for the load to reduce locational costs, not be indifferent to them.

iii. Please explain whether co-location arrangements are or should be required to take Network Integration Transmission Service or Point-to-Point Transmission Service; or whether a more tailored new category of transmission service is warranted.  Please also address any cost allocation implications of your position on this issue.

Requiring all co-location arrangements to take NITS is technically and economically inefficient and a poor policy choice, as explained supra in Section I.  The Tariff does not support this approach, and the lack of clarity combined with the shifting sands of PJM’s guidance on how

279 Indicated Transmission Owners Answer, Att. A at 5 (emphasis in the original).
280 Id., Att. A at 6.
281 Id.

PDF page 81

81
to address co-location creates an opportunity for differing discriminatory outcomes depending on the Transmission Owner involved.  As explained supra in Section II, the Commission should adopt several co-location options that reflect different co-location arrangements (firm, generator- contingent, and interruptible) and their respective use (or lack thereof) of the PJM Transmission System.  Constellation also proposes a rate treatment for each PJM Option to ensure proper cost allocation between load and existing customers, including proposing charges for co-located load to contribute to the embedded costs of the transmission grid when the load uses the grid. In their answer to this question, the Indicated Transmission Owners claim that “[t]here has been no allegation ... that the current regime requiring [NITS] has impaired any load’s ability to secure service safely, reliably, and at reasonable cost, or that service had been unobtainable as a result of the PJM Tariff’s longstanding requirements.”282  This is patently false.  Constellation has repeatedly demonstrated that requiring all large loads to take NITS for its gross load unreasonably delays service to critical data center loads.283  Delay is an impairment of “load’s ability to secure service.”284  Constellation similarly has shown that a one-size-fits-all NITS approach will lead to massive transmission upgrade costs—and this is the largest potential cost associated with co- location configurations by far.  Since other configurations would make these transmission upgrade costs largely unnecessary, forcing all large new loads to impose such costs on the grid is unjust and unreasonable.285

282 Indicated Transmission Owners Answer, Att. A at 7 (emphasis added).
283 See supra at Section I.A.
284 Indicated Transmission Owners Answer, Att. A at 7.
285 See supra at Section I.B.1.

PDF page 82

82
iv. What changes to the rates, terms, and conditions of Network Integration
Transmission Service or Point-to-Point Transmission Service or, alternatively, what new form of transmission service(s) may be necessary for different configurations of co-location to ensure that the Tariff is consistent with cost causation principles and the beneficiary pays principle?

As established in the previous questions, Constellation identifies the applicable rates and charges for each of PJM’s eight configurations (except Option 6, which is unjust and unreasonable).  Changes to the rates, terms, and conditions of service will be required for any rule changes associated with these recommendations.286

Contrary to assertions raised by the Indicated Transmission Owners, the Commission has not rejected requests for “special third categories” where loads are not required to take transmission service.287  In the proceeding cited by the Indicated Transmission Owners, the load owner, Amtrak, challenged NITS pass-through charges because its electric supply from PPL was obtained from a nearby and directly-connected Safe Harbor hydroelectric generation facility.  However, Amtrak acknowledged that “when power from Safe Harbor is insufficient, [Amtrak] uses PPL transmission facilities to obtain power.”288  The Safe Harbor facility was therefore designated as a Network Resource and the load was designated as Network Load, and the Commission held that the NITS charges were appropriate.289  This case is distinguishable from the physical arrangements under PJM Option 4, for example, where the co-located load is not connected to the grid and there are physical protections to prevent the delivery of system energy from the grid.  Such non-connected load is not taking and cannot take transmission service from the grid and should not be required to pay for transmission service accordingly.  PJM even acknowledges that an “open question” is

286 See supra at II.C. (Ming chart summarizing proposed rates).
287 Indicated Transmission Owners Answer at 17-18 (citing Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp. et al., 171 FERC ¶ 61,237 (2020), order on reh’g, 173 FERC ¶ 61,043 (2020)).
288 Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp. et al., 171 FERC ¶ 61,237, at P 43 (2020).
289 Id. at PP 38-39.

PDF page 83

83
“what level of NITS charges, if any, should be assessed in certain co-location arrangements in accordance with cost causation principles.”290  For non-connected load, such as in Option 4, the answer is none.

The cost causation principle supports a finding that co-located load which by design is prevented from receiving power from the grid should not pay for NITS.  The cost causation “principle requires that ‘[t]he cost of transmission facilities … be allocated to those within the transmission planning region that benefit from those facilities in a manner that is at least roughly commensurate with estimated benefits.’”291  It is also a well-established principle that all similarly situated entities are charged consistent rates.292  Under this principle, co-located load that does not receive power from the grid is not benefitting from the Transmission System and such entities should not be required to pay for a service from which it is not benefitting.293

Co-located load that is not taking firm service from the grid is not necessarily causing costs with respect to constructing and maintain the Transmission System; however, as Mr. Ming explains, they are benefiting from the existence of the Transmission System and certain minimum charges could be applicable.294  Payment for certain ancillary services (e.g., black start and regulation) is a separate consideration and discussed below in response to Question c.i.

290 PJM Answer at 40 (emphasis added). 291 Tenaska Clear Creek Wind, LLC v. FERC, 108 F.4th 858, 868 (D.C. Cir. 2024) (citing S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 53 (D.C. Cir. 2024) (per curiam)).
292 See id. (citing Consol. Edison Co. of N.Y., Inc. v. FERC, 45 F.4th 265, 282 (D.C. Cir. 2022) (“And undue discrimination occurs when similarly situated entities are charged different rates for no good reason.”).
293 Ming Testimony at 31-33.
294 See id. at 32.

PDF page 84

84
v. Parties may also wish to address how to determine which co-located load configurations should be required to take Network Integration Transmission Service or Point-to-Point Transmission Service or a new form of transmission service (i.e., whether generalized policies or tests, such as a multi-factor test, to be applied case- by-case, may be appropriate), as well as the magnitude (i.e., how the service taken by co-located load compares to service by other types of load).  For example, if a co- located generator is synchronized to the grid but the load can be configured to be wholly isolated from the grid in the event the co-located generator trips offline, what technical and operational factors should determine whether the co-location arrangement still relies on the transmission system in ways that warrant a requirement that the co-located load take Network Integration Transmission Service or Point-to-Point Transmission Service or a new form of transmission service?  Are there potential co-located load configurations for which tailored approaches may be appropriate?

For a discussion of proposed rate treatments under each of PJM’s eight configurations, see supra at II.A.

For a discussion of the “synchronized to the grid” issue, see Answer at a.iv and Herling Affidavit at paragraphs 33-34.  Mr. Herling, Mr. Kormos, and Mr. Ming all address the use of protective relay schemes, which are “commonly used” in the PJM Transmission System.295

vi. With respect to the Guidance Document, please explain what it means to be “electrically connected and synchronized to the PJM Transmission System when consuming power” and how that implicates the use of Network Integration Transmission Service or Point-to-Point Transmission Service or a new form of transmission service;

Please see answer to a.iv and Herling affidavit at paragraphs 33-34.  As discussed there and elsewhere, synchronization is not an appropriate standard and the test should be whether the load is actually using the Transmission System for delivery of power, in which case it should pay for NITS on a gross or netted basis, or benefiting from the Transmission System, in which case some payment for ancillary services may be justified.

295 Kormos Aff. at ¶ 7; see also Herling Aff. at ¶ 8 (describing protective relaying as “a common and technically sound tool for managing the grid”).

PDF page 85

85
vii. What operational or commercial factors of a co-location arrangement would result in a co-located load not needing to take any form of transmission service, including what types of special protection schemes or backup arrangements may be necessary to ensure the co-located load never takes any form of transmission service?

Of PJM’s eight options for co-location configurations, only Option 4 would not take any form of transmission service, although several of the configurations would rely on standard protective relays or switching equipment (see Answer to a.iv.).  PJM’s proposed Option 5 is the same as Option 4 from a configuration perspective, including protection mechanisms, but allows for as-available back-up service to be provided to the load from the PJM grid with PJM permission. Under Option 4 and 5, the protective scheme can be designed to trip the co-located load from the grid in three cycles (0.05 seconds) following a trip of the co-located generating unit or after sensing that the energy produced by the co-located generating unit has been reduced to a level such that the co-located load is attempting to draw energy from the grid.  PJM points to potential concerns about relying on protective schemes.296  Constellation addresses this issue in its discussion of PJM Option 4, supra in Section II.A.4.  See also, Herling Aff. at III.

c. Ancillary or Other Wholesale Services
i. Please explain whether and to what extent different configurations of co-location arrangements rely on or benefit from ancillary services or black start services297 and, if so, provide specific details about the type of service and how the co-location arrangement relies on it.  To what extent are these benefits distinct from the benefits that other Network Integration Transmission Service and Point-to-Point

Transmission Service customers derive from ancillary services?
Please see the discussion supra in Section I.D.3.  Co-located loads benefit from ancillary services and black start under PJM Options 1-3 and 7-8 (we ignore Option 6).  The benefits are less clear under Options 4 and 5, since the benefits are for the co-located generator in the first instance (and generators are not charged for ancillary services, as generators typically provide

296 PJM Answer at 44.
297 See supra notes 244-245.

PDF page 86

86
them).  In any event, Constellation is willing to consider payment for regulation and black start as part of a generator-contingent option in a replacement rate.  But it remains the case that co-located load’s minimal use of ancillaries does not alone justify NITS charges assessed on gross load and that total ancillary service costs are only a small fraction of NITS charges and transmission upgrades required under a one-size-fits-all NITS approach to co-location.

ii. Please explain whether and to what extent co-location arrangements impose costs related to ancillary services or black start services or increase the costs for such services allocated to other parties and how those costs could be approximated. See answer to c.i.

iii. Please explain whether and to what extent co-location arrangements use, benefit from, provide, or contribute to the need for transmission system services in a manner that does not fit into a pre-existing category of ancillary services or black start services, and, if so, should new categories of services be created to accommodate that use?  Alternatively, please explain whether an alternative mechanism of cost

allocation for pre-existing ancillary services would be more appropriate.
No new categories of ancillary or black start services are needed, although the application of existing services to load co-located with generation in a generator-contingent configuration (PJM Options 4 and 5) is an open question.  As discussed above, co-located load that is not taking firm service from the grid is not necessarily causing costs with respect to constructing and maintaining the Transmission System, but as Mr. Ming explains, it is benefiting from the existence of the Transmission System and certain minimum charges could be applicable.298  Payment for certain ancillary services (e.g., black start and regulation) is a separate consideration and discussed above in response to Question c.i.

298 See Ming Testimony at 27.

PDF page 87

87
iv. What changes to rates, terms, and conditions of ancillary services, including ancillary services procured in PJM’s markets, are necessary for different configurations of co- location arrangements to ensure that the Tariff is consistent with cost causation principles and the beneficiary pays principle?

Please see supra at Section II.C. (table summarizing rate treatment under firm, generator- contingent, and interruptible configurations).  Constellation proposes that co-located load be assessed ancillary service charges based, in the first instance, on use of the Transmission System and, if the Transmission System is not used, based on the benefit received from the service.299  For Options 4 and 5 please see supra at answer c.i.

v. Please explain how PJM should determine which co-located load configurations take ancillary services or black start services (i.e., whether generalized policies or tests, such as a multi-factor test, to be applied case-by-case may be appropriate), as well as the amount of such service (i.e., how the service taken by co-located load compares to service taken by other types of load);

See answer to c.iv.
d. Interconnection Procedures and Cost Allocation
i. Does the necessary study process adequately address potential impacts caused by a co-location arrangement or is an additional study or new study process warranted, e.g., a system impact study or generator deactivation study?  PJM should provide the details regarding the geographic scope of the existing necessary study process, what is studied, and how the results are reported, including what opportunities stakeholders, the interconnected transmission owner, or the PJM IMM have to review the results, if any.

Yes.  Constellation notes that while we generally agree with PJM’s description of the necessary study process, we disagree that the current necessary study process offers any less “visibility” or transparency than the current Regional Transmission Expansion Planning (“RTEP”) process (and note that, in some respects, it offers more).300  Mr. Kormos makes clear the robust nature of the necessary study process as follows:

299 Ming Testimony at 44, 50.
300 See PJM Answer at 48.

PDF page 88

88
I disagree with any suggestion that the necessary study process is anything but a robust, highly effective study of the impact of the modification requested.  Indeed, PJM’s necessary studies are: led by an independent RTO; uniform and transparent (and not guided by an opaque process and rules that differ from transmission owner to transmission owner); updated by PJM, if needed; and focused on the overall grid impacts of the new load explicitly (and not focused predominantly on local impacts or studied along with a host of other changes as part of an RTEP study).  To the extent FERC is concerned that large load connections are not being robustly and effectively studied to ensure reliability, it should not be concerned with the necessary study process used for co-located load.301

The one key problem with the current rules is the ability of some Transmission Owners refusing to cooperate with the necessary study process and lack of any enforcement of the Tariff to require the Transmission Owner to fulfill its Tariff obligations.

ii. Please explain whether PJM’s necessary study process allows a co-location arrangement to demonstrate its capability to flexibly adjust its withdrawals from or injections to the transmission system (e.g., by using secondary backup generation or by curtailing on-site load), and reflect this capability in the operating assumptions PJM considers when estimating the co-location arrangement’s impacts on the

transmission system?  If not, would it be appropriate to establish a new or revised study process that allows for such a demonstration?

Yes.  Constellation generally agrees with PJM’s answer but notes that PJM can perform any sensitivity analyses it deems appropriate and propose any Tariff language it deems appropriate. Constellation does not agree with PJM’s suggestion that there is a reasonable risk that protection facilities are likely to fail in co-location arrangements when PJM otherwise assumes they will operate when planning and operating the Transmission System.302  As Mr. Herling explains, “protection schemes are regularly employed on the PJM transmission system, and the successful

301 Kormos Aff. at ¶ 6 (citations omitted).
302 See Herling Aff. at ¶ 23 (“PJM does not plan for or require upgrades for such third contingencies, nor would it be reasonable to do so, short of events that would result in a cascading outage of grid facilities. The protection system, discussed above, is fully redundant and, while it cannot be guaranteed to never fail, it is unreasonable to treat the failure of both primary and secondary relay system facilities following the loss of a generator as anything other than a third contingency”); Kormos Aff. at ¶ 7 (“PJM does not plan or require upgrades to cover third contingency events (such as would occur if two serially connected breakers fail simultaneously) and add that I am aware of no grid operators who model such contingencies.”).

PDF page 89

89
operation of such protective systems is a common observance within PJM.  There is no technical reason from my perspective to expect that protective relaying in the context of co-location would perform any less reliably.  If anything, suggesting that protective relaying – a common and technically sound tool for managing the grid – cannot be used in the context of co-located configurations or must be designed to a different standard strikes me as an unduly discriminatory position.”303

iii. What changes to interconnection procedures and agreements may be necessary to ensure that PJM identifies the reliability impact to the transmission system of load co-locating with existing generation including the need for dynamic response models? For PJM Options 4 and 5, the necessary study process is sufficient, and Constellation supports adding provisions to the PJM Tariff to address reliability issues for this type of configuration.304  The Tariff also would benefit from the addition of a clear obligation on the part of the relevant Transmission Owner to cooperate and provide timely feedback on the necessary studies when requested by PJM and in the interconnection agreement amendment process.  There is language in the Tariff that provides a general duty to cooperate with PJM studies,305 but this obligation should be clarified for the reasons outlined in Constellation’s Complaint.  Constellation otherwise does not object to PJM’s answer.

303 Herling Aff. at ¶ 23.
304 See Constellation Complaint at 25-28 and Exhibit 1 (detailing proposed Tariff language originally included in PJM’s Guidance Document).
305 PJM OATT, Part VII, subpart E, section 322 (“Responsibilities of Transmission Provider and Transmission Owners”) specifies that:

Transmission Provider shall be responsible for the preparation of all studies required by the Tariff. Transmission Provider may contract with consultants, including the affected Transmission Owner(s), to obtain services or expertise with respect to any such study, including but not limited to (1) the need for Interconnection Facilities, Network Upgrades, and Merchant Transmission Upgrades, (2) estimates of costs and construction times required by all such studies, and (3) information regarding distribution facilities. Transmission Owner(s) shall supply such information and data reasonably required by Transmission Provider to perform its obligations under this Part VII.

PDF page 90

90
iv. To what extent does a co-location arrangement raise potentially distinct cost- allocation issues relative to a deactivating generator that causes the need for transmission upgrades?  What principles should the Commission apply to allocate the costs of any transmission upgrades needed to mitigate the impacts of co-locating load? What steps should PJM take to ensure these costs are transparent to all parties? As a preliminary matter, in a co-location scenario, there is no deactivating generator.  A delist, which reduces capacity rights but does not affect the unit’s maximum facility output (MFO)—the energy interconnection rights—is not equivalent to a deactivation, which affects both energy and capacity rights.  Under a generator-contingent co-location configuration, the load relies on a generator for its own power and has no right to withdraw power from the grid (as enforced by physical protection systems).  This is equivalent to PJM Option 4, or Option 5 if the load can call on grid power when available.  Under either Option 4 or Option 5, PJM conducts a necessary study to determine whether the re-direction of a generator’s output to a co-located load causes any transmission issues and requires transmission reinforcements or network upgrades.306  If any such upgrades are required, the co-located load pays for them.  This is in contrast to a NITS approach (PJM Options 1-3 and 7-8) (we do not address Option 6) where significant transmission upgrades may be required, the bulk of which will be socialized to existing customers.307  This is the primary benefit to existing customers of a generator-contingent configuration.

For details on cost allocation under each of PJM’s options, please see supra at Section II.308

306 Ming Testimony at 32.
307 See Indicated Transmission Owners Answer, Att. A at 15 (under their NITS-only approach, the “costs of transmission upgrades as a result of new end-use load additions are shared among transmission customers.”).
308 Ming Testimony at 50, Table 1.

PDF page 91

91
v. Are changes needed to how PJM allocates the costs of any transmission upgrades needed to mitigate the transmission system impacts of co-locating load, if any, including whether the costs of those upgrades can ever be allocated to a party other than the co-located generator, co-located load, and/or co-location arrangement? Please see supra at Section II where Constellation proposes a cost allocation methodology for each of PJM’s options based on rate design principles (other than Option 6, which should be rejected outright).

vi. Are changes to the pro forma interconnection-related agreements necessary to accommodate the addition of co-located load to existing generation?

No.  The Susquehanna ISA proceeding dictates that generic rules on co-location, such as those contained in the now-withdrawn Guidance Document, should be in the Tariff.

vii. Please explain whether changes to interconnection procedures and agreements are necessary to accommodate new generation interconnecting with co-located load, including whether the existing queue process is sufficient for such arrangements? No changes are necessary.  Any interconnection reforms should be generally applicable and not tied specifically to co-located load.

viii. Please explain whether or not it would be appropriate to establish an interconnection study process outside of PJM’s interconnection queue process for newly interconnecting co-location arrangements that do not exchange power with the transmission system and do not require network upgrades?

Constellation agrees with PJM’s answer that it would not be appropriate.309  See also Constellation’s Answer e.iv., below, for discussion of the efficacy of PJM’s existing necessary study process, which is especially relevant for Options 4 and 5.

309 PJM Answer at 56.

PDF page 92

92
ix. A generator with a co-located load that is not a party to a transmission service agreement is arguably distinguishable from other generators.  To the extent co-

located arrangements create costs, or benefit from bulk power system services, but the generator and load are not exposed to these costs because of their contractual relationship, should PJM modify the Tariff and related agreements to allocate those costs to the generator directly?

Constellation agrees with PJM’s response to this question.310
e. PJM Capacity Market, Reliability, and Resource Adequacy
i. What changes to PJM’s capacity market rules are necessary to ensure that the Tariff specifies how co-located generation and/or load participates in the capacity market in a way that reflects the potentially unique physical and operational characteristics of the co-location arrangement (e.g., the presence of secondary backup generation, the capability to curtail on-site load or other operational flexibilities, among others) and is otherwise just, reasonable, and not unduly discriminatory or preferential?

No changes to PJM’s capacity market rules are necessary to ensure that the Tariff specifies how co-located generation and load participate in the capacity market.311  Although Constellation supports opportunities to further improve market rules and processes,312 the existing rules suffice. As Mr. Ming explains in his testimony, under the existing rules, “[f]or any generator to participate in the capacity market, it must output to the grid when conditions require and when ordered to by PJM.  If a co-located generator clears in the capacity market, this means that it must output to the grid when conditions require even if that means interruption of the co-located load, either through curtailment or backup generation.”313  And to be clear, Constellation’s view is that any Existing Generation Capacity Resources that would prioritize serving co-located load over following PJM

310 Id.
311 Elsewhere in this pleading, Constellation suggests several improvements that can be made to PJM’s capacity market and rules related to it.  See also Patterson Aff., at Section II.C (suggesting several improvements to markets and mechanisms that effect markets).
312 See Patterson Aff. at ¶¶ 8-9 (providing that PJM’s “RPM market design has not exhibited any general market failure” but “PUM should continue efforts to improve the accuracy of price formation in both its energy and capacity markets, with particular emphasis on removing out-of-market price distortions that lead prices to diverge from system fundamentals”).
313 Ming Testimony at 46.

PDF page 93

93
dispatch should instead seek removal of Capacity Resource status or otherwise seek appropriate replacement capacity to cover its capacity supply obligation.314  This can be accomplished via existing capacity market rules where necessary.

ii. What Tariff change or changes to the interconnection service agreement are necessary to ensure that PJM and the interconnected transmission owner have

sufficient visibility into the co-located load configuration?
Please see supra at Section II.A.4., discussing PJM Option 4, where Constellation responds to the question of “visibility.”  Constellation is not aware of any specific changes that are necessary to the Tariff or interconnection service agreements.  For a generator-contingent configuration, Constellation’s Complaint proposed to add various reliability provisions to the Tariff from PJM’s Guidance Document.315  Constellation does not oppose such clarifying additions for each type of co-location configuration.  Our understanding is that the interconnection service agreement would be updated to reflect any specific arrangements related to the particular co-location arrangement, one-line diagrams and the like, which provide adequate visibility.  Please also see supra at Section II.B. (addressing resource adequacy issues).

iii. Please explain whether the existing Tariff rules are sufficient to ensure resource adequacy if increasing numbers of large existing generators choose to co-locate with load.

Please see supra at Section II.B. (addressing resource adequacy issues),316 and the Patterson Affidavit attached hereto as Exhibit 3.  In addition, we agree with PJM’s positions that “[t]o the extent the Existing Generation Capacity Resource relinquishes Capacity Resource status commensurate with its obligation to the co-located load, PJM’s capacity market is designed to

314 PJM Answer at 59-60.
315 Constellation Complaint at Section II.B (Nov. 22, 2014).
316 See also Patterson Aff. at Section II (providing an extensive discussion on resource adequacy issues related to additions of large loads in PJM).

PDF page 94

94
send a price signaling the relative need for the additional capacity”317 and that “[s]elf-supply, either through direct ownership or longer-term bilateral contracting, is a critical part of how [its] markets function to ensure resource development to support future reliability.”318

iv. What deactivation or interconnection modification studies should PJM undertake to ensure resource adequacy and/or protect reliability should an existing generator seek to enter into a co-location arrangement?  If PJM finds that the co-location would cause reliability standards violations, what remediation techniques would be

appropriate (e.g., reliability must-run contracts, delaying the co-location
arrangement until the reliability violations are addressed, etc.)?
As stated above in response to question d.iv., there is no deactivating generator in the context of co-location; rather, under certain co-location configurations, the capacity interconnection rights will be reduced but the energy interconnection rights would generally stay the same.  We also agree with PJM’s position that “[t]o the extent the Existing Generation Capacity Resource relinquishes Capacity Resource status commensurate with its obligation to the co-located load, PJM’s capacity market is designed to send a price signaling the relative need for the additional capacity.”319

With respect to potential transmission system impacts, for generators seeking to serve co- located load under PJM Options 4 and 5, the generators’ ISA would be modified to reflect such co-location, and PJM would perform a necessary study to ensure the grid can accommodate such arrangement, with the costs of any transmission reinforcements and system upgrades to accommodate such co-location typically being born by the co-locating parties.320  PJM’s necessary study process is sufficient for PJM to ensure resource adequacy and/or protect reliability.  Under

317 PJM Answer at 64.
318 Id. at 63.
319 PJM Answer at 64.
320 See id. at 54 (citing PJM Interconnection, L.L.C., 190 FERC ¶ 61,080 (2025) (accepting interconnection construction service agreement assigning upgrade costs to generator seeking to modify interconnection to accommodate co-located load)).

PDF page 95

95
this process, PJM will “perform studies to evaluate the potential reliability impact of a proposed addition or reduction of a co-located load configuration on the PJM Transmission System, and determine what, if any, system reinforcements are required prior to the addition or reduction of the planned co-located load configuration.”321  As Mr. Kormos confirms, the necessary study process is “a robust, highly effective study of the impact of the modification requested....  To the extent FERC is concerned that large load connections are not being robustly and effectively studied to ensure reliability, it should not be concerned with the necessary study process used for co-located load.”322

For co-located load that is Network Load and taking NITS, the relevant Transmission Owner would study the transmission system (as would PJM as part of its ensuing RTEP review) and any transmission upgrades necessary to accommodate the load must be completed prior to effectuating the co-location proposal.323

Given that these existing mechanisms address both potential resource adequacy concerns and transmission system concerns under grid-connected as well as co-located arrangements, there is no need nor authority to consider “remediation techniques.”

321 PJM Answer at 49.
322 Kormos Aff. at ¶ 6 and Appendix.
323 See Kormos Aff., Appendix (explaining the transmission study process for direct connects to the grid).

PDF page 96

96
v. What changes are necessary, if any, to other PJM planning processes to better plan for and address the resource adequacy and reliability impacts of co-location

arrangements, including, for example, whether or not the frequency of such processes might be changed?  Similarly, should PJM consider changes to load forecasting

methods, informational postings, or the reserve margin study process to better plan for and address the resource adequacy and reliability impacts of co-location

arrangements?
Please see supra at Section II.B. (addressing resource adequacy issues),324 and the Patterson Affidavit attached hereto.  With respect to load forecasting, as explained in the Patterson Affidavit, PJM currently relies on Transmission Owners to provide estimates of large load additions based on customer interactions on an annual basis.325  Mr. Patterson proposes that PJM adopt detailed, mandatory rules with respect to how Transmission Owners report anticipated load additions.  Moreover, such reporting should occur two to four times per year to improve the responsiveness of the information for market participants.326  PJM appears open to pursuing improvements to its forecasting process,327 an effort that Constellation supports.

vi. Under what circumstances can PJM direct the operators of co-location arrangements to shed such load if deemed necessary to preserve system reliability during a declared emergency?

Existing rules allow for PJM to direct load shedding if the co-located load is connected to the grid as a Network Customer.328  Co-located load with protective systems that prevent it from connecting to the grid would not be a Network Customer,329 and thus PJM’s existing load shedding

324 See also Patterson Aff. at Section II (providing an extensive discussion on resource adequacy issues related to additions of large loads in PJM).
325 Patterson Aff. at ¶ 29.
326 Id.
327 PJM Answer at 66.
328 See, e.g., PJM Tariff, Section 33.6 (“To the extent that a system contingency exists on the Transmission Provider’s Transmission System and the Transmission Provider determines that it is necessary for the Transmission Owners and the Network Customer to shed load, the Network Customer and the Transmission Owners shall shed load in accordance with previously established procedures under the Operating Agreement.”)
329 Suggestions by the Indicated Transmission Owners that if a co-located generator trips offline, “the unmetered load ‘appears’ on the system and draws power from the grid” (Indicated Transmission Owners Answer, Att. A at 19) are

PDF page 97

97
rules would not directly apply to such co-located load.  In such instances, any load shedding would have to be coordinated through the co-located generator.330

Finally, the potential interruptions of a new interruptible transmission service (i.e., PJM’s Option 7) in response to declared emergencies are discussed supra in Section II.A.7., and, while PJM already has rules applicable to demand response interruptions, Constellation would be open to discussing changes thereto as suggested supra in Section II.A.8.

f. Other
i. Are any changes to PJM’s energy or ancillary services market rules necessary to
address co-location arrangements?
As discussed above, a rate for regulation and black start service in a generator-contingent
configuration (PJM Options 4-5) could be appropriate to include as part of a replacement rate. However, no changes are necessary to PJM’s energy and ancillary service market rules to address co-location arrangements.

ii. Please discuss whether back-up service can provide benefits to customers or
otherwise help minimize system costs, including with specific examples or best
practices, if possible.
Back-up service can reduce the impact of co-located loads on the transmission system
design, thereby decreasing costs, and can allow grid operators to better manage system

“unreasonable.”  Herling Aff. at ¶ 23; see also Kormos Aff. at ¶ 7 (“I agree with Mr. Herling’s view that PJM does not plan or require upgrades to cover third contingency events (such as would occur if two serially connected breakers fail simultaneously) and add that I am aware of no grid operators who model such contingencies.”).

330 See PJM Answer at 67, n.89 (citing PJM Operating Agreement, Section 11.3.1 (“To facilitate and provide for the work of the Office of the Interconnection and of the several committees appointed by the Members Committee, each Member shall, to the extent applicable . . . (e) Comply with the requirements of the PJM Manuals and all directives of the Office of the Interconnection to take any action for the purpose of managing, alleviating or ending an Emergency, and authorize the Office of the Interconnection to direct the transfer or interruption of the delivery of energy on their behalf to meet an Emergency and to implement agreements with other Control Areas interconnected with the PJM Region for the mutual provision of service to meet an Emergency, and be subject to the emergency procedure charges specified in Operating Agreement, Schedule 9 for any failure to follow the Emergency instructions of the Office of the Interconnection.”)).

PDF page 98

98
reliability.331  Developing more innovative means of taking advantage of the potential flexibility provided through the more effective use of backup service is well worth the effort. Mr. Kormos has explained that “[d]ata centers almost always have their own backup power supply, further reducing demands that would exist if their backup supply was the network, or if the backup supply itself relied on the network for transmission services.”332  Mr. Ming also explains that “[i]n both a separately metered or co-located load configuration, the load can be interruptible (either through load curtailment or backup generation) which would eliminate its resource adequacy impact.”333  The Duke Study provides clear evidence that there is significant “headroom” available on the grid (including in PJM) that can be used “to more quickly integrate new loads, reduce the cost of capacity expansion, and enable greater focus on the highest-value investments in the electric power system.”334 Specifically, the Duke Study found that curtailing new load at just 0.5% annually could result in 18 GWs of potential load integration in PJM without any capacity expansion.335  This is known as “headroom” on the system, and more headroom in the system—meaning a larger gap between average and peak demand—means ratepayers are paying to build and maintain assets that may remain idle for most of the year.  More effective utilization of this headroom should be pursued.

In addition, storage could play a role in providing back-up flexibility and efforts to tap into storage more effectively are worth pursuing.  For example, large energy-capacity battery energy storage systems (“BESS”) can supply a consistent level of energy for several hours.336

331 See generally Ming Testimony at 28.
332 Michael Kormos, The Co-Located Load Solution at 10; Kormos Aff., Appendix.
333 Ming Testimony at 46.
334 Duke Study at 3.
335 Id.
336 Electricity Explained: Energy Storage for Electricity Generation, U.S. ENERGY INFORMATION ADMINISTRATION (Aug. 28, 2023), https://www.eia.gov/energyexplained/electricity/energy-storage-for-electricity-generation.php.

PDF page 99

99
Accordingly, back-up service, such as that provided by a BESS, for example, can immediately minimize costs related to outages by preserving energy and transmission capacity for remaining load and minimize costs related to system design.

PJM seems to recognize the potential value of making more efficient use of resources and suggests some avenues that can be pursued to increase their efficacy.337  On the other hand, the Indicated Transmission Owners remain focused on their steadfast desire to build, own and earn a return on transmission assets in arguing that any flexibility provided through back-up service should “not exempt load from paying the costs of transmission service.”338  The Commission should not countenance such inflexibility in developing cost-effective, efficient solutions.

iii. Parties may also choose to address how co-location arrangements may provide
benefits, including potentially reducing required transmission upgrades to
interconnect large loads, reducing congestion, or providing operational flexibility
during system peaks or emergencies?
The record is replete with evidentiary support for co-location arrangements.  Constellation respectfully directs the Commission to the Kormos Affidavit attached hereto for a discussion on the benefits of co-location and his whitepaper (attached to his Affidavit and filed in Docket No. AD24-11) for a summary of the benefits of co-location.339 As Mr. Kormos summarized:

I can say with certainty that the closer load is to its supply, the costs, time to connect the load, and the operational risk are all likely to be reduced . . . . Conversely, if new load is connected to the grid, distant from the generator that is serving it (a far more complicated

337 See, e.g., PJM Answer at 20 (suggesting options to enhance its existing demand response product to make more efficient use of back-up resources).
338 Indicated Transmission Owners Answer, Att. A at 20.  The Indicated Transmission Owners also suggest that any backup service provided by a nuclear unit “is dependent on continued grid operation to function at all.”  Id.  Again, the Commission should not countenance efforts to increase transmission expenditure at the expense of more flexible, efficient and less costly use of existing assets.  In addition, Constellation already responded to the Indicated Transmission Owners’ suggestion (Id.) that nuclear connection arrangements are somehow different from other resource connection arrangements or that their reliance on station power service somehow equates to transmission service to a co-located load, and the Commission should include and consider such evidence in this proceeding. Second Motion for Leave and Answer of Constellation Energy Generation, LLC, Docket Nos. ER24-2888-000, et al., at Section II and Attachments 1 and 2 (filed Nov. 12, 2024).
339 Kormos Aff. at ¶ 4; Kormos Aff., Appendix, The Co-Located Load Solution at 8-12.

PDF page 100

100
arrangement), costs will generally be greater and delays and operational problems will be more likely.340

More granularly, the benefits of co-location include, but are not limited to, the following:
1. Speed to Market – It can take up to ten years to complete the requisite transmission upgrades to serve a hyperscale data center in front of the meter.  This is untenable for data center developers, especially data centers that are essential for national security.341 co-location arrangements 342 come online sooner, which can ensure that the United States does not lose AI-enabled advances in combat activities critical to our military.  The speed to market (as compared to traditional large load connections) is a result of fewer required transmission upgrades, less “potential supply chain issues and delays on long-lead transmission infrastructure equipment,” and less “delays due to land acquisition, rezoning, permitting, siting and the like.”343  Co-location enables significantly quicker load connections which is vital to national security and economic prosperity.

2. Lower Costs – Less delays and transmission upgrades associated with co-location also means lower costs.  Serving large co-located new loads through a NITS-only approach will impose substantial costs on existing customers.344  As elaborated in Section I.B.1, Mr. Patterson explains that supplemental projects for transmission upgrades to serve load costs approximately $9.5 million for each 100 MW of load size (plus a fixed, size independent component of about $31 million).345  Between

340 Kormos Aff. at ¶ 4. 341 Id. at n.5. 342 Stockton Declaration at 2.
343 Kormos Aff. at ¶ 4.
344 Supra at Section I.B.1.
345 Patterson Aff. at ¶ 53.

PDF page 101

101
2022 and April 2025, there were 144 projects to integrate large loads covering 42.3 GW of summer peak load with a total cost of $8.5 billion.346  By contrast, co-located load under PJM Options 4 and 5 would impose no upgrade costs on existing customers.347  The bottom line is that co-location reduces the overall cost for transmission and the potential cost impacts on existing customers.

3. System Efficiency – Co-location benefits system efficiency by decreasing line losses and increasing system utilization.  Energy losses or “line losses” resulting from transmitting power long distances are in the range of 1-3 percent.348  That is the equivalent of 90,000-260,000 MWh of electricity for a 1 GW-sized data center.349  Co-location prevents such unnecessary loss.

4. Increased Interconnection Availability – System efficiency goes hand in hand with interconnection availability.  Co-location arrangements “free[] up transmission headroom for new generator resources by making available the transmission capacity currently used by the host power plant.”350  Transmission congestion can significantly delay the interconnection of new generation resources and force other resources to be curtailed even when their operating costs indicate they are economic and should run.  Co-location can help ameliorate these problems.  For example, “[c]o-locating data centers at Illinois nuclear plants could reduce curtailment of wind and solar output by over 80 [percent].”351

346 Supra at Section I.B.1.
347 Id.
348 Kormos, The Co-Located Load Solution at 8.
349 Id.
350 Id. at 11-12. 351 Id. at 11 (internal citation omitted).

PDF page 102

102
5. Appropriate Risk Allocation – Mr. Kormos explains in his whitepaper that “a co- located center must accept the outage risk associated with a discrete resource which will always be higher than grid power even if that resource is individually highly reliable,” and the co-located load “must carry—and pay for—its own reserves.”352 Bearing such risks directly will inversely decrease the risk for other grid customers.

6. Enhanced Cost Causation – Connecting large loads to the grid can impose “significantly more grid upgrade costs that will be socialized than” a co-located load.353  Such costs can be spread to all customers in a grid-connected arrangement, whereas, in a co-location arrangement, the co-located load pays for the private behind-the-meter delivery facilities directly.354  Such direct assignment of interconnection costs is aligned with cost causation principles.  The Commission has explained that “the cost causation principle provides that costs should be allocated to those who cause them to be incurred and that otherwise benefit from them.”355  There can be no more equitable allocation of costs than that of a co- location arrangement.

7. Increased Reliability – “[C]o-location helps reliability by not trying to move more power a further distance.”356  In addition, data centers that cannot draw power from the grid (e.g., Option 4) will also reduce demands that would exist if their primary and backup supply were on the network or relied on the network for transmission

352 Id. at 9.
353 Id.
354 See id.
355 Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, Order No. 1000, 136 FERC ¶ 61,051, at P 535 (2011); see also BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014 (“[T]he cost causation principle itself manifests a kind of equity.  This is most obvious when we frame the principle (as we and the Commission often do) as a matter of making sure that burden is matched with benefit.”).
356 Kormos, The Co-Located Load Solution at 9.

PDF page 103

103
services.357  Reliability is also ensured through the necessary study process.358  Mr. Kormos explains that the PJM necessary study process is a robust, highly effective study that is “focused on the overall grid impacts of the new load (and not focused predominantly on local impacts).”359  In addition, as Mr. Kormos explains, co- locating large load with a generator can reduce the likelihood of a sudden large load drop in response to a grid voltage drop.360  NERC has recently become increasingly concerned with such issues, and co-locating load with a generator can relieve this concern.361

8. Extended Facility Utilization – Co-location arrangements present “a basis for the continued operation of generation resources.”362  This is particularly true for nuclear resources.363  Co-location “creates the financial security needed to support subsequent license renewal . . . making it more likely the nuclear plant and its emissions-free output remain available well into the future and able to consider uprate projects to increase output.”364  Mr. Kormos explains that 30 percent of merchant nuclear units will need to renew their licenses in the next decade and 50 percent will need to renew their licenses over the next two decades.365  Co-location arrangements present the financial certainty necessary to continue operations.

357 Id.
358 Id.
359 Kormas Aff. at ¶ 6.
360 Id. at ¶ 7.
361 Id.
362 Id. at ¶ 4.
363 See id.
364 Kormos, The Co-Located Load Solution at 10.
365 Id.

PDF page 104

104
9. Maximized State Flexibility – Congress reserved to the states “regulatory authority over retail sales (as well as intrastate wholesale sales)”366 as well as facilities used for the generation, distribution, or intrastate transmission of electric energy.367  Any requirement to treat sales or service to co-located load as wholesale no matter what effectively precludes states from regulating transactions that fall squarely within their jurisdiction.  Co-location arrangements allow states to exercise their Congressionally-protected authority to incentivize and regulate retail sales as they see fit.  If states truly are the laboratory of democracy, then co-location permits states to creatively pursue such arrangements and other states or regions can benefit from the lessons learned.

iv. Parties may also address whether, and if so, how, the Tariff should be modified to best accommodate or encourage co-location arrangements to be constructed in such a way as to minimize total system costs or otherwise provide certain benefits, including protections for existing customers and allocation of costs consistent with the cost-causation principle.

Please see supra at Section II (discussing appropriate replacement rate).368  The charges for each variation, as described by Mr. Ming, maximize benefits while protecting existing customers through the allocation of costs most consistent with the cost causation principle.

v. What Tariff provisions, if any, are necessary to ensure clarity regarding the aspects of service to co-located load and generation facilities that may be administered through the Tariff versus state jurisdictional retail tariffs?

No revisions to PJM’s Tariff are necessary with respect to clarifying the jurisdictional bounds of PJM and the states.  PJM acknowledges that “additional Tariff revisions may not be

366 EPSA, 577 U.S. 260, 279 (2016) (citing New York v. FERC, 535 U.S. 1, 17 (2002)) (emphasis added); id. at 264 (“[T]he law places beyond FERC’s power, and leaves to the states alone, the regulation of ‘any other sale’—most notably, any retail sale—of electricity.”) (quoting 16 U.S.C. § 824(b)) (emphasis added).
367 See, e.g., New York v. FERC, 535 U.S. at 22-23.
368 See Ming Testimony at 24-51.

PDF page 105

105
necessary....”369  PJM is correct.  PJM also states that interested parties “need to have assurances and an understanding of relevant law to respect the jurisdictional principles” at issue.370  That assurance can and should be provided by the Commission as set forth in Constellation’s answer to Question a.i.; however, no Tariff revisions must necessarily result from such clarification. The Indicated Transmission Owners suggest what the Commission “might” or “could” do, but likewise do not set forth any specific Tariff revision proposals.371  The suggestion proposed by the Indicated Transmission Owners to clarify in PJM’s Tariff that co-located load is Network Load and must arrange for NITS or Point-To-Point Service accordingly is entirely inappropriate.  As explained in detail supra in Section I.C., this would, in turn, prohibit states from exercising their valid jurisdiction over distribution and load connections.  The Indicated Transmission Owners effectively seek the Commission’s blessing to obstruct every state’s lawful regulation of co-located load.  This is an untenable result that the Commission should reject outright.

vi. We also encourage parties to address any national security implications associated with co-location arrangements, including with respect to the specific issues discussed in this show cause order, and what actions, if any, the Commission should take in response.

Data centers supporting AI services are critically important to the national security mission of the country.  As described by Paul Stockton, data centers support AI services critical to peacetime and conflict operations.372  Rapid deployment of such technology is needed to keep pace with America’s competitors.373  Any Commission order resulting from this proceeding should

369 PJM Answer at 71.
370 Id.
371 Indicated Transmission Owners Answer at 9; id., Att. A at 21.
372 Stockton Declaration at 4-5.
373 Id. at 7-9 (describing “China’s drive for AI preeminence” and the “broader strategic competition between China and the United States”).

PDF page 106

106
(1) facilitate data center speed to market; and (2) refrain from precluding any particular co-location arrangement option.

Secretary of Energy Chris Wright recently compared America’s effort to incentivize nuclear fuel and AI technological development to “the start of Manhattan Project 2.”374  China takes the role of antagonist in this analogy, which is apt considering that “China views DeepSeek as a major step forward in its AI-enabled military capabilities and, more broadly, a breakthrough that reshapes the balance of power in the U.S.-China AI competition.”375  Co-location can enable data center development years before grid-connected alternatives.376 Indeed, “[s]peed is of the essence for national security.”377

The Indicated Transmission Owners understand that moving “forward rapidly” is a
necessity for national security.378  However, they incorrectly claim the “most straightforward way to accomplish that goal is simply to recognize that co-located load is Network Load . . . and should pay for Network Service like all other customers.”379  This is farcical.  Such a declaration would result in unnecessary processes for co-locating certain load and additional regulatory burdens thereby decreasing efficiency, and increasing the wait time for defense-critical load to connect. In addition, co-location options provide a potential resilience benefit that can be critical during times of war.380  The Stockton Declaration makes certain that the Department of Defense should have “all options available to accelerate the connection of [data] centers....”381  And the decision

374 Peirce Gentry, ‘We’re at the Start of Manhattan Project 2’: U.S. Energy Secretary Visits Oak Ridge, WPLN NEWS (Mar. 3, 2025), https://wpln.org/post/were-at-the-start-of-manhattan-project-2-u-s-energy-secretary-visits-oak-ridge/.

375 Stockton Declaration at 8.
376 Id. at 9-10.
377 Id.
378 Indicated Transmission Owners Answer, Att. A at 21.
379 Id.
380 Stockton Declaration at 10-13. 381Id. at 10.

PDF page 107

107
as to which connection option to pursue should be made by the customer, not by the Commission, PJM, or a transmission owner.382  The Commission should not preclude co-location configurations that save existing customers money and do not endanger reliability.

vii. Finally, for generation units paid for originally by consumers in base rates prior to restructuring, is it fair and/or just and reasonable if these units are taken out of the system’s supply stack and devoted exclusively to serving co-location arrangements with one or a few large customers?

The premise of this question is based on a fundamental misunderstanding of the
predominantly merchant generator model in place across most of PJM.  Under this model, generating resources were sold by most utilities to merchant owners over 20 years ago and, for the most part, have since participated in markets administered by PJM or in bi-lateral markets. Consumers bear no risk related to owning and operating these generating resources.  Rather, the merchant owners bear these risks exclusively and have no ratebase or other consumer fail-safe mechanism to fall back on if things do not go as planned.  If, for example, revenues are insufficient to support ongoing operations and a return for a generator, consumers have no obligation to provide any “make whole” payment (let alone a return payment) to support that uneconomic generator— the generator is forced to go out of business, with any loss borne entirely by its owner.  And this risk is real.  For example, in 2019, Constellation was forced to prematurely retire its Three Mile Island nuclear facility (now the Crane Clean Energy Center) for economic reasons.  And consumers bore no risk in that unfortunate development just as they bear no risk in Constellation’s recently announced plan to restart the facility.383

382 Id. at 2.
383 Constellation to Launch Crane Clean Energy Center, Restoring Jobs and Carbon-Free Power to The Grid (Sept. 20, 2024), https://www.constellationenergy.com/newsroom/2024/Constellation-to-Launch-Crane-Clean-Energy- Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html.

PDF page 108

108
In addition, we do not believe there was ever any basis for consumers to claim that
resources were devoted to serving their needs exclusively even under the rate-base model that may have applied previously to some merchant-owned facilities (and may still apply in same parts of the PJM region).  In a nutshell, consumers paid for service, not for assets.384  Regardless, even if there was some speculative claim under that model, it was severed over 20 years ago for merchant- owned resources when the merchant owners purchased those resources and assumed all the

operating risks related to them.
CONCLUSION
WHEREFORE, Constellation respectfully requests that the Commission adopt its
preliminary finding that the PJM Tariff is unjust and unreasonable and unduly discriminatory and preferential because it lacks clear provisions for the treatment of large loads co-located with generation, and this lack of clarity has caused undue discrimination against large loads seeking to co-locate.  The Commission should then either (1) fix the replacement rates set forth herein— namely a group of co-location configuration options and rate treatments that recognize the different uses of the transmission system of these different configurations, or (2) set the replacement rates for time-limited settlement proceedings.

384 As previously explained above with respect to the “duty to serve,” utilities are provided authorizations to hold natural monopoly positions and in exchange are subject to price regulation and have a duty to serve customers in their service territory.  The customers or ratepayers pay for the service they receive.  The price for that service is established by cost-of-service ratemaking through which the utility can “yield a reasonable return on the value of the property used at the time it is being used to render the service.”  Bluefield Waterworks & Imp. Co. v. Pub. Serv. Comm’n of W. Va., 262 U.S. 679, 690 (1923).  The utility undertakes an investment in transmission and distribution infrastructure and, in some instances, generation.  The utility receives the yield or rate of return on that capital investment in an amount that is “sufficient to assure confidence in the financial integrity of the enterprise, so as to maintain its credit and attract capital.” Fed. Power Comm’n v. Hope Natural Gas Co., 320 U.S. 591, 603 (1944).  The ratepayers did not make the investment in capital infrastructure.  Instead, ratepayers pay the utility to provide a service, i.e., delivering energy to their home or business.  The service rate is not a downpayment or investment in the underlying assets by which the utility provides that service.  If a specific generation unit is no longer being used to render service to ratepayers, then it is reasonable for the utility to be able to optimize that unit by other means.

PDF page 109

109
Respectfully submitted,
 /s/ Paul F. Wight
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel Seth Lucia

Assistant General Counsel
Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001

carrie.allen@constellation.com
seth.lucia@constellation.com

Christopher A. Wilson
Managing Director, Federal Regulatory Affairs Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001

(202) 347-7500
FERCe-filings1@constellation.com

Paul F. Wight
Kirkland & Ellis LLP
1301 Pennsylvania Ave., NW
Washington, D.C. 20004
(202) 389-3321
paul.wight@kirkland.com

Counsel for Constellation Energy
Generation, LLC

April 23, 2025

PDF page 110

110
CERTIFICATE OF SERVICE
I hereby certify that I have on this 23rd day of April, 2025, caused to be served a copy of the foregoing upon all parties on the service list in these proceedings in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2024).

/s/ Kevin W. Hivick

Kevin W. Hivick
Kirkland & Ellis LLP

1301 Pennsylvania Ave., N.W.

Washington, D.C. 20004