Exhibit 5 (Kormos)
Text extracted from the eLibrary original (SHA-256 d6c7a2bf2e93d2c8…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 12.
Opening text
opening text
EXHIBIT 5 AFFIDAVIT OF MICHAEL KORMOS UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.Read this passage
I. QUALIFICATIONS AND OVERVIEW OF AFFIDAVIT
printed heading · Topic match: Connecting load and generation
As I discussed previously, traditional utility models for connecting large load directly to the grid are proving ineffective at keeping pace with the demands of new large loads and are taking five years or longer to connect such load.3 Based on conversations I have had with clients and others…Read this passage Filed comments: Connecting load and generation
II. BENEFITS OF CO-LOCATION
printed heading · Topic match: Connecting load and generation
And co-locating load with a generator that avoids use of the grid will minimize: transmission infrastructure costs; potential supply chain issues and 1 Michael Kormos, The Co-Located Load Solution, Docket No.Read this passage Filed comments: Connecting load and generation
III. PJM STUDIES
printed heading · Topic match: Connecting load and generation
In addition, I attach hereto comments I submitted in October 2024 to the Maryland Public Service Commission explaining the efficacy of PJM’s necessary study process in response to generator interconnection modification requests to serve co-located load.6 In those comments, I 5 See, e.g., P 8, infra…Read this passage Filed comments: Connecting load and generation
IV. MANY OF PJM’S AND OTHERS’ CONCERNS ARE NOT UNIQUE TO CO-LOCATED LOADS
printed heading · Topic match: Connecting load and generation
A few examples include: 7 Id. 8 See PJM Answer at 47-52. 9 Connection Study Process Comments at 2-6. 5 • PJM suggests that resource adequacy could be impacted when adding co-located load.10 But resource adequacy could be impacted when any new load is added, regardless of how that load is connected…Read this passage Filed comments: Connecting load and generation
Table of Contents
printed heading · Topic match: Connecting load and generation
Michael Kormos | The Co-Located Load Solution | July 2024 7 must find mechanisms to allow all new types of load to be connected in their preferred configuration and on their timeline and not claim some new load can connect but others must wait or not be served at all. 4.Read this passage Filed comments: Connecting load and generation