EL25-49-000 · 2025-04-23 · Constellation Energy Generation, LLC
Exhibit 5 (Kormos)
PDF page 1
EXHIBIT 5
AFFIDAVIT OF MICHAEL KORMOS
PDF page 2
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC.
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
AFFIDAVIT OF
MICHAEL KORMOS
April 23, 2025
PDF page 3
1
I. QUALIFICATIONS AND OVERVIEW OF AFFIDAVIT
1. My name is Michael Kormos. My extensive professional experience includes transmission planning and operations as a senior executive at both PJM Interconnection, L.L.C. (PJM) and one of the largest transmission owners within the PJM region. I currently serve as an electric utility consultant helping industry participants develop transmission interconnection and transmission solutions and resolve issues related thereto. Until 2021, I was Sr. Vice President, Transmission & Compliance for Exelon Corporation, where I was responsible for the operations and long-term planning for transmission systems of Exelon utilities Atlantic City Electric, Baltimore Gas & Electric, ComEd, Delmarva Power, PECO, and PEPCO. In that role, I shaped Exelon and its utilities’ policy positions on issues related to the Federal Energy Regulatory Commission (FERC), Regional Transmission Organizations (RTOs), and national transmission matters. Before joining Exelon, I spent 27 years at PJM. As PJM’s Chief Operations Officer, I was responsible for grid planning and operations and directly involved in implementing numerous significant FERC orders, including Order No. 1000, and supported the development and implementation of competitive wholesale markets in PJM. Earlier in my career at PJM, I oversaw an operational expansion that tripled the size of the system controlled by PJM. I also held management and engineering positions in transmission operations while at PJM. In addition, I have also served on the board of directors for Reliability First Corporation; as an officer of the Eastern Interconnection Planning Collaborative and the Eastern Interconnection Data Sharing Network; and as a member of the North America Electric Reliability Corporation operating committee.
2. As such, I have significant experience in transmission planning and operations throughout the PJM region and am well-qualified to provide this affidavit. In addition, I testified
PDF page 4
2
extensively as a panelist during FERC’s Technical Conference in the AD24-11 proceeding on co- located loads and submitted my Whitepaper, The Co-located Load Solution (the Whitepaper), in that proceeding (which I understand has been consolidated into the record for this proceeding).1 For convenience, I am attaching it hereto.
3. There has been significant discussion recently at FERC and elsewhere2 about serving load that is co-located with a generator. As I discussed previously, traditional utility models for connecting large load directly to the grid are proving ineffective at keeping pace with the demands of new large loads and are taking five years or longer to connect such load.3 Based on conversations I have had with clients and others active in the industry since the Whitepaper, I understand that wait times for new large load connections in PJM are taking even longer – as long as seven to ten years.4 This is simply too long for new load to wait – a disservice to customers, and other, more expeditious, connection alternatives must be pursued.
II. BENEFITS OF CO-LOCATION
4. A more expedient and efficient alternative and one that I have strongly advocated for is to co-locate the load with the generator that is serving the load in a way that avoids making use of the grid altogether. Based on my years of experience as a grid planner and operator, I can say with certainty that the closer load is to its supply, the costs, time to connect the load, and the operational risk are all likely to be reduced. And co-locating load with a generator that avoids use of the grid will minimize: transmission infrastructure costs; potential supply chain issues and
1 Michael Kormos, The Co-Located Load Solution, Docket No. AD24-11 (Nov. 4, 2024).2 See, e.g., Senate Bill 1 Co-location Study, MD Pub. Serv. Comm’n, Docket PC61.3 Whitepaper at 1 and fn. 1.4 See, e.g., Comments of Talen Energy Corp., Docket No. AD24-11, Analysis Group Report at fn. 43 (Oct. 28, 2024) (describing wait times to plan, design, site and construct a new grid connection to be as long as seven years for Dominion and seven to ten years for AEP).
PDF page 5
3
delays on long-lead transmission infrastructure equipment; potential delays due to land- acquisition, rezoning, permitting, siting and the like; line losses; and grid operational risks (because fewer grid infrastructure facilities and potential failure points are implicated in serving the load). Conversely, if new load is connected to the grid, distant from the generator that is serving it (a far more complicated arrangement), costs will generally be greater and delays and operational problems will be more likely.5 In addition to serving new load expeditiously and on a least cost basis, certain co-located load connections provide numerous other benefits as compared to traditional grid connections including:
• Transferring risk from the grid and other customers to the co-located load;
• Directly assigning interconnection costs to the co-located load instead of existing grid customers for any necessary transmission upgrades;
• Protecting reliability through PJM’s robust necessary study process;
• Facilitating long-term commercial arrangements that provide a basis for the continued operation of generation resources including nuclear; and
• Increasing interconnection opportunities for other resources.
Rather than discuss these benefits of co-location here, these benefits are discussed in greater detail in the Whitepaper at 8-12.
III. PJM STUDIES
5. In addition, I attach hereto comments I submitted in October 2024 to the Maryland Public Service Commission explaining the efficacy of PJM’s necessary study process in response to generator interconnection modification requests to serve co-located load.6 In those comments, I
5 See, e.g., P 8, infra (describing how the likelihood of a large load drop in the wake of a system voltage drop can be reduced through co-location).6 Post-Conference Comments of Michael Kormos, MD Pub. Serv. Comm’n, Docket PC61 (Oct. 16, 2024) (Connection Study Process Comments).
PDF page 6
4
also compare PJM’s necessary study analysis to the analysis done by individual PJM transmission owners when connecting a new load directly to the grid.7
6. The Connection Study Process Comments provide a helpful summary of the different study processes used in PJM when connecting new load. While I do not have any significant objection to PJM’s description of its necessary study process (as summarized in PJM’s March 24, 2025 Answer in this proceeding),8 I disagree with any suggestion that the necessary study process is anything but a robust, highly effective study of the impact of the modification requested. Indeed, PJM’s necessary studies are: led by an independent RTO; uniform and transparent (and not guided by an opaque process and rules that differ from transmission owner to transmission owner); updated by PJM, if needed; and focused on the overall grid impacts of the new load explicitly (and not focused predominantly on local impacts or studied along with a host of other changes as part of an RTEP study).9 To the extent FERC is concerned that large load connections are not being robustly and effectively studied to ensure reliability, it should not be concerned with the necessary study process used for co-located load.
IV. MANY OF PJM’S AND OTHERS’ CONCERNS ARE NOT UNIQUE TO CO-LOCATED LOADS
7. In addition, PJM raises numerous concerns that PJM seems to suggest are caused by co- located load. PJM’s discussion fails to make clear the essential point that these concerns are caused by any large load addition to the PJM region, and do not depend on how the load is connected. A few examples include:
7 Id.8 See PJM Answer at 47-52.9 Connection Study Process Comments at 2-6.
PDF page 7
5
• PJM suggests that resource adequacy could be impacted when adding co-located load.10 But resource adequacy could be impacted when any new load is added, regardless of how that load is connected – the resource adequacy impact is the same for co-located connections as for grid connections.
• PJM suggests that special protection schemes or remedial action schemes used to support co-located loads could fail.11 But PJM fails to acknowledge that such mechanisms are not exclusive to co-located load or that PJM can and should be prepared to respond to even the low likelihood of potential problems with them. Protection schemes are commonly used mechanisms to ensure safe and reliable grid operations, and transmission system planners and operators rely on a host of system protections schemes (including primary and secondary relays as well as redundant protection systems) to maintain the safe and reliable operations of the grid on a regular basis. While planners and operators are careful to design protection schemes to meet the particular need and protection schemes are not appropriate for every situation, they are viewed across the industry as effective and reliable tools. Restricting their use by planners or operators would represent a fundamental shift in the way the transmission system is planned and operated. Relatedly, I have reviewed the affidavit of Steven R. Herling which is included with my affidavit as part of Constellation’s filing, and I concur with Mr. Herling’s conclusions as to the efficacy of redundant relay schemes to ensure co-located load is isolated from the grid and unable to draw power therefrom in the event the co-located generator trips.
10 See, e.g., PJM Answer at 62.11 Id. at 44, 52.
PDF page 8
6
• The failure of a relaying scheme itself does not create a reliability issue if PJM is prepared for it. If a co-located generator trips but the co-located load is not simultaneously disconnected, PJM will experience the same generation/load imbalance that would have occurred if the generator tripped and the load was not co- located. In the co-located load situations, the load is likely to be removed simultaneously with a generator loss providing PJM a benefit with less imbalance to resolve. And because contingency overloads are typically tolerated based on a four- hour transmission line rating specification, PJM should have more than adequate time to manually remove the load if necessary.
• In addition, I agree with Mr. Herling’s view that PJM does not plan or require upgrades to cover third contingency events (such as would occur if two serially connected breakers fail simultaneously) and add that I am aware of no grid operators who model such contingencies. If PJM nonetheless remains concerned, it can model such third contingency and take any further action it believes necessary and consistent with prudent practices. While not standard to perform such studies, PJM can model the potential failure of redundant relays to remove the load when the co-located generator trips to assess in real-time what the impact of a relay failure would be and thereby be prepared to act.
• PJM suggests that it may be worthwhile to explore enhancements to the load forecasting process.12 It makes perfect sense to enhance load forecasting, but more
12 Id. at 66.
PDF page 9
7
accurate forecasts again are not exclusive to co-location and would be helpful regardless of how load is connected.
• PJM also describes its effort to leverage back up diesel generators,13 but the potential to increase reliance on backup diesels as part of a resource adequacy solution again is not exclusive to co-location and could be considered for any new load and should not be dependent on how it is connected.
• PJM suggests there may be concerns with the stability impact of co-located loads under certain conditions including light-load and summer peak conditions.14 But stability impacts are not a concern relevant only to co-located loads. Rather, prudent grid planners and operators should consider the stability impact of any load regardless of its connection configuration.
• PJM suggests “extensive transmission level equipment modelling and data” that could be “unique” are needed for co-located load.15 The need for information on load characteristics is not unique to co-located load – grid planners and operators would need such information regardless of how the load is connected. And there is no serious issue here; PJM routinely models complicated transmission scenarios and routinely obtains all the information it needs to do so. Thus, PJM also has the ability to model any large load in both planning and operations in whatever detail it desires. How the load is commercially connected and takes service should have no impact on what and how PJM models new large loads to maintain reliability. Given the growing
13 Id. at 63, 68-69.14 Id. at 53.15 Id. at 60.
PDF page 10
8
prevalence of large loads in PJM, I would expect PJM to increase its consideration of such loads and understanding of their operations regardless of how they are connected and served.
• There has been some suggestion that grid issues could arise if large load suddenly drops from the grid in response to a voltage drop event in both these proceedings on co-located loads in PJM16 and in other proceedings.17 This voltage drop concern is not one exclusive to co-location and, in fact, illustrates how co-locating load and generation can provide benefits to the grid as compared to direct grid connections. First, as is clear in the recent NERC Presentation (at 3), the large load drop incidents in Northern Virginia all involved grid connected data center loads where the load was located remote from generation supply source. Second, had those data centers been co-located with a generator (especially a nuclear generator), it is possible that the load would not have dropped offline as a result of the load being closer to the voltage source, and because - nuclear generators are managed to a strict voltage bandwidth and typically have state of the art automatic voltage regulators. As a result, I would expect voltage deviations -- like those that triggered the load drops in Northern Virginia –– to be fewer, smaller and of shorter duration, if they occur at all, for load located in close proximity to a large generator. Large generators also typically provide significant inertia that can help the local grid avoid or minimize the impact of many anomalies. Given the reduced likelihood of a voltage drop in the first place for
16 See Statement of the North American Electric Reliability Corporation, Docket No. AD24-11, at 2 (Nov. 1, 2024) (expressing concern with an incident where data center dropped in response to a voltage drop as part of a pleading in the Co-Located Load Technical Conference proceeding).
17 See NERC Activities and Plans to Address Reliability Impacts from Large Load Integration, Docket No AD25-10 (Apr. 17, 2025) (NERC Presentation).
PDF page 11
9
load co-located with a generator, it is less likely that such load will sense a voltage anomaly that will lead it to drop. Third, to the extent a large load drop risk remains, NERC appears to be on the correct path towards rectifying it (i.e., as explained in the NERC Presentation, NERC has an ongoing process to study the issue, develop risk mitigation strategies, etc.). NERC’s path is consistent with the path grid operators followed several years ago to adjust to operational challenges encountered as wind and solar resource intermittency issues became increasingly prevalent on the grid. PJM’s discussion of these issues in this consolidated proceeding – in particular PJM’s focus on resource adequacy concerns – are not issues specific to co-located load at all. In the case of resource adequacy concerns, FERC has already announced an entirely separate proceeding to specifically address such concerns.
PDF page 12
[No extractable text on this page.]
PDF page 13
APPENDIX
Michael Kormos, The Co-Located Load Solution Docket No. AD24-11 (Nov. 4, 2024)
PDF page 14
Michael Kormos
JULY 2024
The Co-Located
Load Solution
PDF page 15
Michael Kormos | The Co-Located Load Solution | July 20241
Table of Contents
The Co-Located Load Solution … 2
Separating Co-Location Facts from General Concerns About New Load … 5
Serving any new load will affect market prices … 5 Serving any new load may affect infrastructure costs … 5 Serving any new load may affect reliability … 6 Behind-the-meter service imposes no new costs on grid customers … 7 The Benefits of Co-Location … 8 Serve the Load … 8 Improve Grid Efficiency … 8 Transfer Risk from the Grid to the Co-Located Load … 8 Charge Data Centers Instead of Grid Customers for More of the Transmission Facilities … 9
Protect Reliability … 9 Facilitate Steady Customers for Nuclear Units to Remain in Service … 10 Increase Interconnection Opportunities for Renewables … 11 There Is No Cost Shift Without a Fundamental Market Redesign … 12
Transmission Service … 13 Distribution Service … 14 Capacity … 14 Energy … 14 Ancillary Services … 14 Next Steps … 16 Biography … 17
PDF page 16
Michael Kormos | The Co-Located Load Solution | July 20242
The Co-Located Load Solution
An influx of large new loads is projected to seek to connect to the transmission grid over the next several years—including most prominently hyperscale data centers. The standard utility models are struggling to accommodate large data center projects on a workable timeline, and can take five years or longer.1 These delays are caused in part by the increasing size of data centers, which in the past did not typically exceed 100 megawatts (MWs) but now can be up to ten times larger to accommodate artificial intelligence and other sophisticated applications.
Connecting a new gigawatt-sized load to the power grid would almost certainly require construction of new transmission lines, which is one of the most difficult challenges faced by the power sector. Based on my experience as chief operations officer of PJM Interconnection and related roles in the power industry, it can take up to a decade to plan, design, permit, and construct new transmission lines if they are contested (as are most large projects). These long delays risk impeding economic growth as well as technological advances.
In order to bring large data center projects online efficiently and equitably, the electric industry should be focused on finding solutions that best manage reliability, affordability (for all), efficiency, and speed. In the restructured markets where sellers compete to serve new demand, one such solution is for the new load to serve its own power needs “off the grid,” and the most promising configuration is for this load to co-locate behind-the-meter with an existing power plant.
By not taking service from the transmission grid, the new load expedites the timeline but must pay for its behind-the-meter delivery facilities and assume the costs and risks of not being served by the grid. Because the new load has no ability to “lean” on the grid,2 there is no need for expensive new network transmission projects to connect the load or the associated regional cost allocations to other customers. In addition, by partnering with an existing plant, the load avoids the long lead time for grid interconnection and the generator secures a steady customer, which can be critical for plants needing predictable, long-term
1 See, e.g., “AI, data center electricity demand could drive advanced nuclear investment: NERC head Jim Robb,” Utility Dive (June 6, 2024) ("it takes me about four years to build a substation," according to David Schleicher, Northern Virginia Electric Cooperative CEO), https://www.utilitydive.com/news/ai-data- center-electricity-demand-advanced-nuclear-investment-Robb/718181/; “Elk Grove Mayor Meets With ComEd on Substations for Data Centers,” Journal & Topics (Mar. 14, 2024) (Mayor of Elk Grove, Illinois, “expressed frustration with ComEd, saying the electricity utility was ‘dragging their feet’ in building substations to support the growing data center industry”), https://www.journal-topics.com/articles/elk- grove-mayor-meets-with-comed-on-substations-for-data-centers/.2 To be clear, the co-located behind-the-meter load configuration I suggest here is one where the load is unable to take energy or other services from the grid and in fact pays for and installs equipment to automatically disconnect in the event its co-located power supply trips. The load instead must rely on its co-located generator(s), batteries or other back-up resources to meet its needs. While other co-located load configurations may be considered, I have not done so here.
PDF page 17
Michael Kormos | The Co-Located Load Solution | July 20243
revenues to ensure continued operation and justify renewal of operating licenses and potential uprates.
Co-Located Behind-the-Meter Configuration
Grid-Supplied Front-of-Meter Configuration
While co-location could involve the pairing of any type of power plant with any large load, existing nuclear plants provide some of the best opportunities for data centers. Nuclear plants are large, often with multiple units, carbon-free and sustainable, and capable of and
PDF page 18
Michael Kormos | The Co-Located Load Solution | July 20244
preferring to run at maximum power for up to 18 to 24 months, which matches perfectly with the data center load profile.3 Nuclear units have the highest reliability and availability of any of the existing resources.
Despite their benefits, nuclear units have, in the recent past, faced economic challenges that led many to announce retirements. In the last decade, over 10 GW of capacity retired, mostly due to economic factors, and 20 nuclear units representing 20.3 GW of capacity avoided retirement by seeking and obtaining state-based economic support. Although the federal government has stepped in to prevent further retirements through enactment of the nuclear production tax credit (PTC), that program expires in 2032 at which time federal agencies project a new wave of nuclear retirements far exceeding the generating capacity lost over the last decade.4
Under a co-location configuration, the data center gets the carbon-free electricity it wants without lengthy delays (but must pay for any on-site delivery facilities), and the nuclear plant gets a steady customer (forestalling premature retirement and enabling NRC license extension and potential uprates). And with the nuclear unit now supplying the data center load and not some distant network load, deliverability on the transmission grid is freed up for other existing and newly-interconnecting resources, typically wind and solar projects.
3 Nuclear plants have the added benefits of usually being remote, secure, and well-buffered, minimizing the potential for noise, visual or other impacts that can be associated with data center development.4 U.S. Energy Info. Admin., Annual Energy Outlook 2023, Table 9 (Electric Generating Capacity, Reference Case), https://www.eia.gov/outlooks/aeo/data/brower/#/?id=9- AEO2023&cases=ref2023&sourcekey=0; EPA, Power Sector Modeling, Post-IRA 2022 Reference Case (last updated Mar. 1, 2024), https://www.epa.gov/power-sector-modeling/post-ira-2022-reference-case; EPA, Power Sector Modeling, Pre-IRA 2022 Reference Case (last updated Dec. 13, 2023), https://www.epa.gov/power-sector-modeling/pre-ira-2022-reference-case. 0 10 20 30 40 50 60 2032 2034 2036 2038 2040 2042 2044 Retirement from 2012 to 2032 2033+ Retirements Projected by EIA GW Additional 2033+ Retirements Projected by EPA
PDF page 19
Michael Kormos | The Co-Located Load Solution | July 20245
Separating Co-Location Facts from General Concerns
About New Load
Some have raised questions about whether pairing data centers with nuclear behind-the- meter increases costs for other customers and ratepayers via higher prices, system upgrades, or cost shifts, or otherwise harms reliability. Based on my years of experience operating power systems, I think these concerns have very little to do with co-location itself. In most cases the questions raised are a consequence of adding load anywhere on the grid and not how it is served, whether connected to the grid or co-located behind-the-meter.
1. Serving any new load will affect market prices
One frequently mentioned issue relating to co-located load is the impact on energy and capacity markets by “removing” an existing generator that is currently serving network load. All things being equal, co-locating data centers with nuclear units will not raise network prices any more than serving the same load in front of the meter in the same general location.5 Any new demand will affect price, so unless we assume the new load would disappear or not otherwise be served, how the load is served does not materially change the effect on market prices. While every situation is unique, dedicating a portion of existing generation to a particular customer behind-the-meter through a direct connection will have the same effect on the supply/demand dynamic as serving the same amount of new load through deliveries over the transmission system from participating in the market or from a remote generator under a power purchase agreement. This new load, regardless of configuration, can be met using existing market and system planning tools.
2. Serving any new load may affect infrastructure costs
Another common misconception is that if an existing generator is used to serve a behind- the-meter load, new infrastructure (most likely transmission) will be needed and existing customers will have to pay for it. In my experience, it is far more likely that connecting a data center to the grid in front of the meter will require more transmission upgrades than co- locating it behind a generator, which does not rely upon the grid for service. Larger loads (those approaching 1000 MWs) must connect to the grid on an extra high voltage line (230 kV or greater). This requires an extra high voltage substation and associated facilities to accommodate the front-of-the-meter data center. The construction costs for this type of transmission project will depend on the circumstances but can range from $150 million up to $250 million.6 In a co-location configuration, these costs will be paid
5 Given both nuclear plants and data centers operate generally as baseload facilities, the impact of adding new load or “removing” such supply will have virtually the same effect on market prices.6 See “Transmission Expansion Advisory Committee – PPL Supplemental Projects,” April 2, 2004 at https://www.pjm.com/-/media/committees-groups/committees/teac/2024/20240402/20240402- item-08---ppl-supplemental-projects.ashx (identifying $244 million PPL supplemental project); see also PJM, Transmission Expansion Advisory Committee: AEP Supplemental Projects, at 7 (June 4, 2024),
PDF page 20
Michael Kormos | The Co-Located Load Solution | July 20246
by the co-located load. In a front-of-the-meter configuration, by contrast, some of these costs will be allocated to grid customers.
Moreover, in a front-of-the-meter configuration, there will be additional costs associated with other transmission upgrades required to get power to the new substation built for that customer. The costs can be significant. In Northern Virginia, for example—where no data centers have co-located—data center growth combined with generator retirements has required over $5 billion of transmission investment to reliably serve the new load. The costs of those new transmission facilities, like all transmission facilities, will be shared by all customers in accordance with PJM’s and the transmission owner’s tariffs.
As discussed later, serving that same load behind-the-meter at a power plant can reduce the need for new transmission lines compared to a grid-connected configuration. The nuclear unit is also giving up use of the transmission system to others. Some transmission investment might be required in a co-location configuration to replace the generation with excess or new units. But if the load were in front of the meter, it is far more likely that a greater amount of transmission investment would be needed. The overall costs to grid customers should be significantly less in a co-location configuration.
So again, unless we are simply assuming these large new loads will not be served, any addition of that load will result in incremental infrastructure costs and the co-located configuration ensures that the costs incurred to serve the new load are paid for by the data center, not by customers of the surrounding utilities.
3. Serving any new load may affect reliability
The next common refrain is reliability, and that we should not let nuclear resources “take megawatts off the grid” to serve new loads because we cannot adequately replace the critical generation in a timely manner. Again, the issue is not whether we are serving the load behind-the-meter versus using the transmission grid to serve the load in front of the meter but instead is about serving new load, period. And again, unless one assumes the new load would not otherwise be built or delayed for years, the effect on grid reliability is the same. Tools already are in place in every restructured market to bring on any new resources needed to serve network load.
As an aside, the challenges of integrating new generation resources to replace retiring fossil generation and to meet all new load are a rightful focus of policymakers. In my view, markets should provide better incentives to attract new resources and the generation interconnection process should be significantly improved to get needed resources timely connected. What should not happen, however, is discrimination against one type of large new load (data centers) or one type of generation (nuclear). It cannot be that, after many years of financial struggles by nuclear units, we are now troubled by arrangements with counterparties that are willing to contract to ensure continued operation of those units. We
https://www.pjm.com/-/media/committees-groups/committees/teac/2024/20240604/20240604- item-05---aep-supplemental-projects.ashx (identifying $155.69 million AEP supplemental project).
PDF page 21
Michael Kormos | The Co-Located Load Solution | July 20247
must find mechanisms to allow all new types of load to be connected in their preferred configuration and on their timeline and not claim some new load can connect but others must wait or not be served at all.
4. Behind-the-meter service imposes no new costs on grid customers
The last general claim is that behind-the-meter load causes “cost shifts” that negatively impact existing customers. For example, in the recent Exelon/AEP protest to the Susquehanna Interconnection Service Agreement amendment, a consultant from Concentric claimed up to $140 million in “cost shifts” from the data center to grid customers. This calculation is nothing more than the revenue that the transmission owner would have been paid if the data center had connected in front of the meter where it would take grid service and benefit from being connected from the grid. But in the co-location scenario, the extension cord to the grid is cut – the data center does not cause grid costs to be incurred, cannot take any service from the grid, and is not a customer of the transmission owner. There are no costs to shift in the co-location scenario.
It is true that existing grid customers cannot share the costs of their service with the data center supplying its own service, but no one can reasonably expect to share costs with someone who is not taking service.
Not only is there no cost shift, but co-location can help grid customers save money. The existing grid customers do not pay for new costs assumed by the data center or the costs for any upgrades identified in the host generator’s updated interconnection studies. As elaborated below, many risks (e.g., outage risk) are directly the responsibility of the loads in this co-located configuration, alleviating the need for other customers to share in costs to cover such risks.
* * * * *
We must not compare serving new data center load behind-the-meter with not serving it at all, as some suggest. Adding new load in any location may add new costs, so the question is how the configurations at issue—grid-connected or behind-the-meter—result in efficiency, reliability, and affordability for all customers, including the new data center load.
PDF page 22
Michael Kormos | The Co-Located Load Solution | July 20248
The Benefits of Co-Location
The beneficiaries of co-location behind-the-meter extend well beyond the data center and the host generator. In many cases, these configurations are better for all than if the data center were served in front of the meter. Co-location behind-the-meter helps to:
1. Serve the Load
Remember that co-location allows us to serve large new loads that otherwise would have to wait years for service, and thus to meet the technology needs and fuel economic growth on a much more expedited basis. As I noted above, connecting a new gigawatt-sized load to the power grid will almost always require construction of new transmission infrastructure, which can take years to plan, design, permit, and construct. Our goal should always be to serve customers when and how they want to be served, and co-location offers an excellent alternative.
2. Improve Grid Efficiency
The best and most cost-efficient way to supply a new large load is by generating as close as possible to that customer. The further the generation is from the load, the more expensive it becomes to move the power and the more at risk the system is to overloading existing transmission lines. By placing a data center where it can be directly served by a generator versus locating the load somewhere remote from the ultimate generation needed to serve it, the grid requires fewer upgrades to serve that new demand.
Similarly, the geographic proximity inherent in co-location also is likely to reduce energy losses (“line losses”) resulting from transmitting long-distances from the power plant to data center, which at the transmission level are in the range of 1-3 percent. For a gigawatt-sized data center, that would avoid the loss of 90,000-260,000 megawatt hours of electricity. Given that large data center customers generally seek sources of carbon-free power, this prevents the unnecessary loss of an increasingly important commodity: clean electricity.
3. Transfer Risk from the Grid to the Co-Located Load
Greater risks equal greater costs and the co-locating data center load bears its own risks, while imposing no incremental risks on the network.
The risks the data center itself takes on are significant. If the data center were supplied from the grid, it could expect supply certainty in 99+% of hours given the diversity of resources in a region like PJM. This is very different for load connected to a single resource, even a very- well run nuclear resource that can be expected to run ~93% of the time.7 To the extent a co- located load seeks to improve the reliability of the individual resource(s) it is co-located with,
7 See DOE, Office of Nuclear Energy, 5 Fast Facts About Nuclear Energy (June 11, 2024), https://www.energy.gov/ne/articles/5-fast-facts-about-nuclear- energy#:~:text=Nuclear%20energy%20is%20one%20of%20the%20most%20reliable%20energy%20s ources%20in%20America (noting that nuclear power plants operated at full capacity more than 93% of the time in 2023).
PDF page 23
Michael Kormos | The Co-Located Load Solution | July 20249
it must pay for additional back-up (e.g., on site back-up generators, batteries, etc.). Some customers might also choose to size to one unit at a dual unit site and use the second unit during refueling outages, i.e., have the second unit be part of its additional supply. Another way to view this is from the perspective of the data center itself: a grid-supplied data center avails itself of the redundancy and high availability inherent in a wholesale market overseen by an RTO as well as all the grid-supplied ancillary services. If the data center were in front of the meter and thus on the network, if one grid supply resource fails, another would be started to make up for the lost output from the failed resource, allowing grid connected load to continue seamless service under most scenarios.
In contrast, a co-located center must accept the outage risk associated with a discrete resource which will always be higher than grid power even if that resource is individually highly reliable. It also must carry—and pay for—its own reserves. This is a critical distinction between the two configurations: the services co-located data centers receive from a generator are not the same as the services the data center would receive if supplied by the power grid.
4. Charge Data Centers Instead of Grid Customers for More of the
Transmission Facilities
Not only are risks transferred to the data center, so too are many of the costs. The data center pays for the private behind-the-meter delivery facilities as well as the electricity. And as I discussed above, in my experience it is very likely that a data center connecting to the grid will impose significantly more grid upgrade costs that will be socialized than a data center supplied behind-the-meter. The costs for this can be substantial (easily in the billions) and can be spread beyond the data center customer to all other customers.
5. Protect Reliability
Reliability always is paramount, and the data center/nuclear pairing will be studied appropriately to ensure reliability is maintained on the electric grid. If anything, co-location helps reliability by not trying to move more power a further distance.
The independent grid operator responsible for reliability studies the impacts of the new configuration at the nuclear facility to ensure reliability is maintained. In the PJM process, for example, PJM conducts a “necessary study” to determine whether a generator’s modification to include behind-the-meter load has any reliability impact on the generator’s interconnection with the grid.8 If so, the generator pays for changes at its facility and any necessary network upgrades to cure the potential issue. PJM also reduces the available capacity for sale through the reduction of the capacity interconnection rights of the generator to reflect any behind-the-meter sales. Changes to the Interconnection Service
8 PJM has provided detailed guidance for the current process to connect co-located load and all the steps required to ensure reliability. See PJM Guidance on Co-Located Load (March 22, 2024) (Updated April 17, 2024), https://pjm.com/-/media/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located- load.ashx. Numerous proposals to adjust these rules have been raised at PJM and in other fora.
PDF page 24
Michael Kormos | The Co-Located Load Solution | July 202410
Agreement on file at FERC may also be made to clarify reliability procedures given the behind-the-meter configuration.
Because a co-located data center served in a behind-the-meter scenario has equipment to prevent it from taking service from the grid, the grid will not be planned for or otherwise accommodate the load. Data centers almost always have their own backup power supply, further reducing demands that would exist if their backup supply was the network, or if the backup supply itself relied on the network for transmission services.
In the case of a nuclear unit, it will also remain connected to the network, as required by law. Any power at the nuclear station not committed to the behind-the-meter load still will be available for sale to the network or to others. The electricity is not disappearing or retiring. It is being used to serve load, just as it would if it were injecting into the grid and delivering to the data center over the transmission system.
6. Facilitate Steady Customers for Nuclear Units to Remain in Service
Speaking of nuclear, the behind-the-meter configuration supports long-term investment in nuclear power plants and the grid and environmental benefits they provide. It creates the financial security needed to support a subsequent license renewal (the application itself cost tens of millions of dollars), making it more likely the nuclear plant and its emissions-free output remain available well into the future and able to consider uprate projects to increase output.
Over the last decade, nuclear resources faced significant financial uncertainty and one-third of the fleet either retired or obtained state support to preserve the assets and prevent higher prices and increased emissions.9 The federal government followed with the PTC, which provides near-term financial stability for the nuclear fleet. However, it expires in 2032 just as a large portion of the fleet will be going through the NRC regulatory process to extend operating licenses, which can take five years or longer to complete. Thirty percent of the merchant nuclear units will need to renew operating licenses in the next 10 years to prevent shutdown, increasing to 50 percent over the following decade. Hosting a data center with a long-term power sales agreement would certainly play the key role in a unit owner’s decision
9 See, e.g., D. Murphy & M. Berkman, The Brattle Group, The Impacts of Illinois Nuclear Power Plants on the Economy and the Environment (2019) (prepared for Ill. IBEW State Council and Ill. AFL-CIO), https://www.brattle.com/wpcontent/uploads/2021/05/17147_the_impacts_of_illinois_nuclear_power_p lants_on_the_economy_and_the_environment.pdf; D. Murphy & M. Berkman, The Brattle Group, Pennsylvania Nuclear Power Plants’ Contribution to the State Economy (2016) (prepared for Penn. Building and Construction Trades Council, et al.), https://www.brattle.com/wpcontent/uploads/2017/10/5732_pennsylvania_nuclear_power_plants_cont ribution_to_the_state_economy.pdf; D. Murphy & M. Berkman, The Brattle Group, Salem and Hope Creek Nuclear Power Plants' Contribution to the New Jersey and Local Economies (2020) (prepared for PSEG), https://www.brattle.com/wpcontent/uploads/2021/05/20628_salem_and_hope_creek_nuclear_power_ plants_contribution_to_the_new_jersey_an d_local_economies.pdf.
PDF page 25
Michael Kormos | The Co-Located Load Solution | July 202411
of whether to undertake the multi-year regulatory process and related investments needed to relicense.
7. Increase Interconnection Opportunities for Renewables
Finally, other beneficiaries of co-location would be renewable projects being curtailed because of inadequate capacity on the transmission system to deliver from remote locations to load centers. Co-location of data center and nuclear generation frees up transmission headroom for new generator resources by making available the transmission capacity currently used by the host power plant. This benefit can be significant, such as in Illinois where transmission congestion is projected to increase in the next decade as the state adds more wind and solar generation to meet decarbonization goals. Co-locating data centers at Illinois nuclear plants could reduce curtailment of wind and solar output by over 80%.10
10 Analysis provided by Constellation Energy reflecting anticipated wind and solar expansion needed to comply with the Climate and Equitable Jobs Act.
PDF page 26
Michael Kormos | The Co-Located Load Solution | July 202412
Renewable Curtailments – Annual, GWh (Bars)
Renewable Curtailments – Cumulative, GWh (Lines)
Co-locating data centers at nuclear plants also could benefit renewable projects idling in the interconnection queue. As mentioned above, PJM’s rules, for example, require a co-locating generating resource to forgo its capacity interconnection rights which can then free up capacity rights for another resource, which based on PJM’s current queue is likely to be wind, solar or batteries. This can allow those resources to more quickly connect to the transmission grid with no (or fewer) transmission upgrades needed.
There Is No Cost Shift Without a Fundamental Market
Redesign
Notwithstanding these benefits and the fact that new load connecting behind-the-meter imposes no new costs on grid customers—and cannot use grid power—some opposing voices still claim that transmission and related services are being provided to the disconnected load through the co-located generator. They claim because the generator remains connected to the grid, any load connected to the generator is “free riding” on the network including because they are synchronized through the generator.11 For proof, they point to ancillary and other grid services provided to generation from the grid and claim that the co-located load benefits. This argument is creative but reflects a fundamental misunderstanding of the open access rate design established by the Federal Energy Regulatory Commission (FERC) thirty years ago.
While it is true nuclear plants must remain connected to the grid, any surface appeal this “cost shift through the generator” argument has falls apart when we look at current practices and precedent. Generators always have been connected to the grid and have never been
11 Simply being synchronized to the grid through a generator which in turn is synchronized to the power grid does not mean the co-located load receives the same service as those relying on the grid for service. This misses the point elaborated below that the co-located load is not taking service from the grid, even if the co-located generator may be.
PDF page 27
Michael Kormos | The Co-Located Load Solution | July 202413
charged for most of the services in question. This is a core design choice made by FERC when it adopted its open access transmission requirements in Order No. 888.12
Like any grid-connected generator, the co-located generator will continue to deliver any generation not consumed by the data center onto the grid for the benefit of the network’s customers. Reducing the output of these generators has no material bearing on the system or its costs. It would be discriminatory to charge only a few generators for these services and would take a fundamental market design shift to start charging all generators for things like fluctuations in their output before these alleged cost shifts could be credible. In other words, for there to be a credible cost shift here, two things would need to happen: first, FERC would need to overhaul the basic open access rates applicable to all generators to start charging them for these services; and, second, co-located generators would have to be the only generators that do not pay them.13
Such a market redesign also would require regulators to reevaluate how costs are allocated when generation is located behind a grid customer’s meter, i.e., when it is generation that is behind-the-meter, not load. Load that owns generation, such as a municipal customer with city-owned generation or a retail customer with roof-top solar, use that generation to reduce the volume of grid-delivered electricity for which they pay. It would be highly discriminatory to apply grid charges to load co-located behind-the-meter of a generator without doing the same to the portion of a customer’s load met by behind-the-meter generation. To put all this in context, let’s consider each type of grid service and how it applies to a co- located behind-the-meter load configuration where the generator is connected to the grid and the co-located load takes power only from the generator:
• Transmission service – Since the co-located load is not able to take power from the grid, no system power is transmitted from the grid to the load. Indeed, equipment is installed to automatically switch the load off in the event the nuclear resource and any backup generation supply become unavailable so that the co-located load is never served by the grid. Any power that is transmitted over the grid is an injection from the existing nuclear unit to and for the benefit of network load and—like all generating resources in every RTO/ISO market—the generator is not required to pay any transmission service, either network or point to point to serve internal network load. The generator has an
12 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996).
13 Prompted by the increase in variable-output renewable generation across the country, FERC undertook a multi-year investigation fifteen years ago to evaluate whether open access rules should be altered to assign generators the cost of certain ancillary services. FERC declined to do so, instead providing a framework for any public utility that might seek to impose such costs on generators that includes, among other things, requirements to justify with operational data any distinction between different types of generators. Integration of Variable Energy Resources, 139 FERC ¶ 61,246 at P 315-335 (2012).
PDF page 28
Michael Kormos | The Co-Located Load Solution | July 202414
interconnection service agreement, which will be amended as needed, that provides for the ability to inject power into grid. No cost shift.
• Distribution service – Since any power supplied by the co-located resources to the load would be provided over a privately-owned line and not a utility’s distribution (or transmission) system, no distribution services are being provided by the utility. Sale of power from the generating facility to the co-located load remains subject to the state’s authority, including how the state assesses charges used to fund infrastructure and social programs. Depending on the state, there could be state-level charges that co-located load would pay—not for utility distribution infrastructure, but for those state-jurisdictional services or programs. No cost shift.
• Capacity – Whether the new load is in front of the meter or behind-the-meter being served by existing resources, new resources or excess from existing resources will be needed to meet remaining customer demand. As described above, reducing the amount of output an existing generator sells into the market or adding new load to be served by that market has the same effect on capacity—one adds to the “demand” side of the equation, while the other subtracts from the “supply” side.14 No cost shift.
• Energy – Since the co-located load would have no ability to draw power from the grid, there is no grid energy purchased. Any energy sold into the market by the generator in excess of what the co-located load is consuming is treated like every other generator connected to the grid, subject to both day-ahead and real-time pricing. As with any generator connected to the grid, generators have the right and the ability to sell energy to anyone on the grid including externally to other systems. Like capacity, any new load behind-the-meter or in front of the meter is going to increase energy requirements by either reducing the supply curve or increasing the demand curve but the effect on the overall market is the same. No cost shift.
• Ancillary Services
• Regulation and Frequency Response (aka Load Following) – Variations in the co- located generator/load balance will change the amount of megawatts a generator is injecting into the grid. This is not the same as withdrawing power from the grid. While it is true the grid is absorbing the variations in the generator’s injections, the grid does this for every generator regardless of whether on-site load is being served. Many resource types, particularly intermittent wind and solar, inject into the grid at levels that vary from moment to moment, with grid injections fluctuating up (or down) quite quickly and significantly in response to variable weather patterns or other factors. No generator—regardless of type—in any RTO/ISO region pays for regulation service to
14 While current PJM rules do not give a generator serving behind-the-meter load the ability to retain its rights to sell that capacity into the PJM markets, those rules could evolve in a way that enables the generator to retain such rights (and the related obligations), making that alternative available to co- located data center customers.
PDF page 29
Michael Kormos | The Co-Located Load Solution | July 202415
ensure the grid is prepared to absorb their moment-to-moment fluctuations in power output. Nuclear units are no exception. It would require a fundamental policy change to begin charging all generators for this service, as discussed above. No cost shift without fundamental market redesign.
• Operating Reserves – Reserves are primarily to respond to a reduction in generator output or outages; they allow the grid to make up for a sudden change in the generation/load balance.15 As with regulation service, generators do not pay for reserve services regardless of generator type and regardless of whether they have co- located, on-site load. As for the co-located load, it provides its own reserves through its supply arrangement with the host generator and has no ability to obtain reserves from the grid, nor does the presence of the co-located load increase or affect the existing grid reserves required in any way. Instead, if its co-located generator has an outage, the co-located load is on its own to either shed its load or provide its own reserves via interruptible power supplies and backup generation. No cost shift without fundamental market redesign.
• Reactive Power – Co-located generators are under the same NERC and RTO requirements to provide reactive power to the system as any other units. If, for example, PJM determines as part of its “necessary study” that any reactive deficiencies are caused by the co-location configuration, it will require the co-located generator to supply the reactive power—most likely through the installations of capacitors at the location that are paid for entirely by the generator—before the co- located load is connected to the generator. Generator already pays/contributes in kind.
• Black Start – Today no generator pays for black start, yet all generators (and all loads) benefit from the grid being restored. To the extent the nuclear plant’s location is included and prioritized in any restoration plan, FERC could change the current paradigm and find that it may be appropriate for generators to pay a share regardless of whether it hosts co-located load. The cost would be minimal. Using PJM as an example, assigning a 1,000 MW nuclear unit a share of PJM’s total $73 million annual black start costs would amount to a $590,000 per year charge for the nuclear unit that reduces costs assigned to others by 0.008 percent. Even if black start charges were assessed to generators, it does not follow that full network service should apply to co- located load. Generators could pay, but it would require fundamental market redesign.
• Station Power Services and Emergency Services Supporting Nuclear Units – To the extent that a nuclear resource is relying on grid-supplied power to meet its station power service needs and/or NRC license obligations, it should pay for those services. This is no different than how any other resource connected to the grid is treated and there is no reason to alter that treatment just because there is a load behind that
15 Rapid load changes or dispatch error can also cause the needs for reserves.
PDF page 30
Michael Kormos | The Co-Located Load Solution | July 202416
resource because that load is unable to avail itself of those services. Generator already pays.
The only way serving co-located behind-the-meter generation could create a cost shift to grid customers is if we implement market design changes to begin charging all generators for load following, reserves, and black start but then excused a generator supporting a behind- the-meter load from those charges. I am not aware of any current efforts to enact any such proposals as the general view is that the provision of these services to generators benefits the grid much more than it costs.
Next Steps
Policymakers, regulators, and industry have a basic obligation to serve load. There is no dispute that it will take years for large data centers and other loads to connect to the grid under the standard utility models. Our collective focus should be on finding solutions that best manage reliability, affordability (for all), efficiency, and speed, without standing in the way of data centers choosing to pay for and provide their own transmission facilities and power supply (and backup power supply). Under the co-location behind-the-meter model, data centers and nuclear plants can do so without risking reliability or shifting costs to network customers, including those in other states. This data center/nuclear pairing is not only symbiotic for the parties, but for anyone with an interest in the promises of the digital age and a sustainable future.
PDF page 31
Michael Kormos | The Co-Located Load Solution | July 202417
Biography
Michael Kormos is an electric utility consultant with extensive
experience solving complex problems and leading large teams across
the energy industry. Until 2021, Mr. Kormos was Sr. Vice President,
Transmission & Compliance for Exelon Corporation, where he was
responsible for the operations and long-term planning for transmission systems of Exelon utilities Atlantic City Electric, Baltimore Gas &
Electric, ComEd, Delmarva Power, PECO, and PEPCO. Mr. Kormos
shaped Exelon and its utilities’ policy positions on issues related to the Federal Energy Regulatory Commission, Regional Transmission
Organizations (RTOs), and national transmission matters.
Before joining Exelon, Mr. Kormos spent 27 years at PJM Interconnection, the RTO responsible for transmission systems in 13 Mid-Atlantic and Midwestern states, and Washington, D.C. As PJM’s Chief Operations Officer, he supported the development and implementation of competitive wholesale markets in PJM and earlier in his career at PJM, he oversaw an operational expansion that tripled size of the system controlled by PJM. He also held management and engineering positions in transmission operations while at PJM.
Mr. Kormos has also served on the board of director for Reliability First Corporation; an officer of the Eastern Interconnection Planning Collaborative and the Eastern Interconnection Data Sharing Network; and as a member of the North America Energy Reliability Corporation operating committee.
PDF page 32
Michael Kormos Post-Conference Comments
Md. Pub. Serv. Comm’n Docket PC61
PDF page 33
1
BEFORE THE PUBLIC SERVICE COMMISSION OF MARYLAND
*
SENATE BILL 1 CO-LOCATION STUDY
*
ADMINISTRATIVE DOCKET
*
PC 61
*
*
*
*
*
*
*
*
*
*
*
*
*
POST-CONFERENCE COMMENTS OF MICHAEL KORMOS
Pursuant to the Public Service Commission’s (Commission) notice inviting comments on issues discussed during the September 24, 2024 technical conference (Technical Conference) in this docket, I submit these comments to address potential confusion regarding the efficacy of PJM Interconnection, L.L.C.’s (PJM) Necessary Study process used to evaluate a generator’s proposed addition of co‐located load and how that Necessary Study compares to analysis done by a Transmission Owner and ultimately PJM in response to a request to connect a similar load to the grid. Given that the discussion of these issues spanned multiple panels during the conference, I summarize below the scope and timing of these various studies to aid the Commission in the preparation of its report to the legislature.
1. Transmission Owner study process for a new load connected to and served from the
transmission system
I start by reviewing the study process for new loads seeking to connect to and receive service from the transmission system, which I refer to simply as network load, since that is the model against which it appears the Commission is evaluating the impacts of fully isolated co‐located load.11 I use the term “fully isolated co‐located load” to mean load that is connected to a generator behind the generator’s meter and that, due to equipment and systems installed by the load and/or the generator, has no ability to receive electricity from the transmission system. The Commission’s use of the term non‐networked co‐ located load at the Technical Conference appeared intended to refer to this type of load configuration. I use the term fully isolated co‐located load because it clearly communicates that this load is isolated from the power grid and, therefore, only capable of receiving electricity from the host generator. A load that is connected to a generator behind the generator’s meter but that also has access to electricity from the transmission system could be referred to as networked co‐located load. For purposes of transmission planning, the addition of a networked co‐located load would be studied similar to the addition of a network load, since both would be connected to and take power from the transmission system.
PDF page 34
2
Requests for new network load are made to the local distribution utility which then refers that request to the host Transmission Owner (if different) to determine if upgrades to the transmission system are needed, as is the case with most large loads. The host Transmission Owner conducts studies to ensure that the addition of that load to its transmission system does not impair reliability. The criteria and specifics of these studies are at the discretion of the Transmission Owner and can (and do) differ from Transmission Owner to Transmission Owner. In general, though, Transmission Owners evaluate local delivery headroom at the point of interconnection to determine if local upgrades – i.e., upgrades on that Transmission Owner’s system – are needed to enable the addition of the new network load. If any upgrades are identified, the Transmission Owner typically proceeds with those upgrades through the Supplemental Project planning process at PJM, which results in the posting of those upgrades for stakeholder awareness and a “do no harm” check by PJM. As a Supplemental Project under the PJM Tariff, the costs of these upgrades can be allocated to the Transmission Owner’s entire zone rather than being assigned individually or directly to the new network load. While robust for what it evaluates, the Transmission Owner’s study of new network load is locally focused. This is because each individual Transmission Owner generally focuses its analysis on impacts within its own system rather than impacts on the broader grid. Only PJM typically applies such a system‐wide focus but, per the PJM tariff, PJM is not involved in the local studies conducted by the Transmission Owner. The “do no harm” analysis conducted by PJM for Supplemental Projects considers only whether the local upgrades identified by the Transmission Owner will cause any new, incremental reliability violations. Under this “do no harm” analysis, PJM adds the Supplemental Project to its Regional Transmission Expansion Plan (RTEP) model and runs the RTEP analysis with the Supplemental Project. If there is no violation, the test is passed; if there is a violation, the Transmission Owner works with PJM to modify its project or otherwise address the problem. However, PJM does not review,
PDF page 35
3
evaluate or otherwise verify the Transmission Owner’s studies. The “do no harm” review is therefore inherently limited by design.
The system‐wide review conducted by PJM does not occur until PJM begins its RTEP process in the planning year following the Transmission Owner’s processing of the local planning studies. This means that the interaction of the new network load with other changes that are occurring across the broader grid are not evaluated until PJM aggregates that new network load with all other new load, as well as changes in the generation stack, as part of the baseline RTEP analysis. Given the local focus of the Transmission Owner’s study and the somewhat limited nature of PJM’s “do no harm” review, the addition of the new network load is a potential driver of additional upgrades across the broader PJM system. By that point, though, the Transmission Owner has already moved forward with connecting the new load, baking that demand into its load forecast and thus contributing to the need for RTEP upgrades.2
As discussed at the Technical Conference, this is a critical distinction between the studies conducted for new network load and new fully isolated co‐located load (which I discuss in more detail below). When the annual baseline RTEP is run, a new network load most likely already has an interconnection arrangement with the Transmission Owner and PJM has no authority to prevent or delay the Transmission Owner from bringing the new network load online. PJM can only work with the Transmission Owner and/or load to delay service until any needed upgrades uncovered in the annual RTEP study are completed. PJM is not a signatory to any arrangements between the Transmission Owner and the load and, thus, has limited ability to adjust new load implementation timing. This sequenced process starting with the Transmission Owner’s locally focused review can result in reliability problems being uncovered only after the annual baseline RTEP is run. For example, a number
2 PJM is evaluating how it can improve the forecasting of and planning for data centers and other large loads in its annual RTEP process. One risk to earlier inclusion of projected data center network load, however, is that transmission will be built for load that does not materialize, needlessly increasing costs for consumers.
PDF page 36
4
of data centers were granted service by a Transmission Owner in Northern Virginia only to later be told by PJM that the aggregation of data center projects in the area was triggering billions of dollars of transmission upgrades in order to maintain reliability on the regional grid. Even though the new network load had been cleared by the Transmission Owner through its local planning process, the data centers have been asked to defer in‐service dates in order to avoid the reliability problems identified by PJM during its later‐in‐time RTEP analysis. Meanwhile, the costs of these regional upgrades are being spread across customers throughout PJM. Unlike Supplemental Projects that are allocated only to the Transmission Owner’s zone, PJM rules require that the cost of RTEP upgrades be spread across the region in proportion to a combination of power flows and peak load contribution, depending on the characteristics of each upgrade. This is why Maryland consumers are paying for roughly $550 million of the $5 billion in RTEP upgrades being constructed to enable network load data centers in Northern Virginia.3
2. Necessary Study process for fully isolated co‐located load
Unlike a new network load, PJM leads the evaluation of new fully isolated co‐located load from the outset. A generator connected to the PJM transmission system is not permitted to alter its equipment in order to serve co‐located load without prior review and approval of PJM. This review is initiated through the submission of a request to modify the generator’s equipment under the Interconnection Service Agreement, which is evaluated by PJM through what is referred to as a Necessary Study. The Necessary Study is not limited to a local focus and instead evaluates the incremental impact on the entire PJM system of the generator’s proposed reduction in deliveries to the grid in order to instead deliver that energy to the co‐located customer. The Necessary Study usually includes all of the reliability screens, North American Electric Reliability Corporation (NERC) considerations and other review criteria
3 Protest and Comments of Maryland People’s Counsel, PJM Interconnection, L.L.C., FERC Docket No. ER24‐843 (filed Feb. 9, 2024), at 2.
PDF page 37
5
evaluated by PJM in its annual RTEP analysis, including incorporation of each Transmission Owner’s local planning requirements. But unlike the Transmission Owner’s local evaluation of a new network load, PJM’s evaluation of a new fully isolated co‐located load includes all relevant grid information because PJM uses the most recent RTEP case as the starting point for its analysis. PJM confirmed this at the Technical Conference: “The necessary study process would have the same reliability criteria of what we would do in our normal regional transmission expansion planning.”4By design, then, the Necessary Study for a new fully isolated co‐located load takes a broader view than the local studies performed by a Transmission Owner when it evaluates a service request for new network load. The Necessary Study ensures that the addition of new fully isolated co‐located load will not adversely impact reliability of the PJM grid including the host Transmission Owner’s system in one step, while the Transmission Owner’s study of new network load first ensures that the addition of that load will not adversely impact reliability of the Transmission Owner’s system (at which point the Transmission Owner typically grants service) only to be subsequently incorporated into a baseline RTEP analysis in order to fully evaluate impacts on PJM grid reliability as a second step. For a new fully isolated co‐located load PJM ensures that local transmission issues are considered as part of its Necessary Study process by explicitly including an opportunity for the host Transmission Owner to review its analysis. That review should result in the Transmission Owner conducting studies comparable to those used to evaluate a new network load but as described above, PJM has no role in those studies and so it is not entirely clear what level of analysis is conducted by the Transmission Owner. Another key distinction with the Necessary Study is that, as discussed during the Technical Conference, PJM can hold up the timing for when a generator can begin serving fully isolated co‐located load because PJM must agree to the changes proposed by the generator in order for the generator to move forward. If PJM identifies any issue as part of the Necessary Study, the new load cannot come online until the issue is addressed. PJM explained at the Technical
4 Technical Conference Tr. at 57.
PDF page 38
6
Conference that “[PJM] can definitely say these transmission reinforcements need to be, obviously not only paid for by the generator, but they need to be completed and in service before the co‐location occurs. And so, in that sense, we can ensure that the transmission system is reliably supplied.”5 In addition, PJM requires that the costs for any upgrades uncovered by a Necessary Study be borne by the generator and/or its associated co‐located load with no costs spread to other grid customers. As PJM stated during the Technical Conference: “Any required transmission upgrades to support the requested configuration will be identified and must be implemented at the cost of the generator before the co‐ located load is permitted.”6
3. Study timing and related considerations
To be clear, all the studies described above are performed using snapshots in time of the relevant system. This includes Necessary Studies, annual RTEP analysis and Transmission Owner studies of their systems. This is, however, an added benefit of using the Necessary Study process to evaluate the reliability impact of adding a large load within the PJM footprint. Baseline RTEP studies and Necessary Studies use the same model, updated to include all the relevant changes for the applicable period and reason studied. Thus, the analyses performed for a Necessary Study reflect all changes already made to the PJM system to ensure reliability at the time of the analysis, with the one additional change of adding the proposed fully isolated co‐located load. This ensures that any reliability issues identified in the Necessary Study are only caused – and paid for – by the proposed fully isolated co‐located load. Subsequent RTEP analysis (including the annual baseline RTEP analysis) will include the new load and any system changes to accommodate it, regardless of configuration (co‐located or networked),
5 Technical Conference Tr. at 70; see also PJM Guidance on Co‐Located Load, at ¶ 7 April 17, 2024), https://www.pjm.com/‐/media/marketsops/ rpm/rpm‐auction‐info/pjm‐guidance‐on‐co‐located‐load.ashx (PJM noting that “[s]ervice to the co‐located load pursuant to the co‐located load configuration may not commence until the necessary PJM service agreement(s) has been fully executed by the parties, filed with and accepted by the FERC, and all required system reinforcements, system protection facilities, and metering are in place.”).6 Technical Conference Tr. at 13.
PDF page 39
7
along with all other changes in load and generation (including generation retirements and delists), and transmission topology elsewhere in the PJM footprint that have already been reviewed by PJM. Any upgrades required to ensure reliability will be identified and implemented, and the costs of those upgrades will be allocated per PJM’s rules. Here we find another benefit of co‐locating large loads. As noted above, PJM rules require that the cost of annual RTEP upgrades be spread across the region in proportion to power flows and/or peak load contribution. Because fully isolated co‐located loads do not take power from the grid, they are not included in peak load calculations, which results in lower RTEP allocations compared to that same load being network load. By encouraging large loads to co‐locate at generators on a fully isolated basis, states like Maryland can reduce the amount of regional transmission costs allocated to consumers in the state.
* * * * *
In summary, PJM’s Necessary Study process consists of a rigorous set of system‐wide analyses that are consistent with its baseline RTEP analysis while also considering local issues in order to capture all impacts of the co‐located load on the system. Any impacts identified must be resolved and paid for directly by the generator and/or the fully isolated co‐located load, and the generator may not proceed with its proposed new configuration until PJM agrees that any detrimental grid impacts have been resolved. While Transmission Owner and PJM studies of new network load consider these same issues, they do so through a two‐step process that disconnects the granting of service by the Transmission Owner from the evaluation of PJM grid impacts, and that provides PJM with no authority to prevent or delay the Transmission Owner from bringing the new network load online. Maryland should encourage large loads to choose co‐location because of the increased transparency and accountability provided by the Necessary Study process.
Dated: October 16, 2024
/s/ Michael Kormos
Michael Kormos