EXHIBIT 4 AFFIDAVIT OF STEVEN HERLING UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.Read this passage
I. QUALIFICATIONS AND PURPOSE OF AFFIDAVIT
printed heading · Topic match: Connecting load and generation
While at PJM, I contributed to or led initiatives that resulted in a wide range of milestone achievements in PJM’s evolution and growth as a regional transmission organization (“RTO”), including the creation of the RTEP process, the development of procedures and standard terms and conditions for…Read this passage Filed comments: Connecting load and generation
II. DESCRIPTION OF CO-LOCATION PROJECT OPTIONS
printed heading · Topic match: Connecting load and generation
Instead, fully redundant relaying will trip the co-located load in the event of (i) the unplanned loss of the co-located generation or (ii) a reduction in generation level, thereby preventing the co-located load from being able to draw energy from the grid.Read this passage Filed comments: Connecting load and generation
III. PROTECTIVE RELAY SCHEMES
printed heading · Topic match: Connecting load and generation
Such a configuration uses electric current transformers to measure the flow of power from between the co-located load and the grid, which is communicated with relays via fiber optic channels that will trip behind-the-meter circuit breakers associated with the co-located load when the electric…Read this passage Filed comments: Connecting load and generation
IV. GRID SERVICES
printed heading · Topic match: Connecting load and generation
Because the associated special-purpose relay scheme will remove the co-located load from the grid in the event of a sudden loss of the generating facility, no energy will flow to the co-located load over the transmission grid following a contingency; no new transmission infrastructure will be…Read this passage Filed comments: Connecting load and generation