EL25-49-000 · 2025-04-23 · Constellation Energy Generation, LLC
Exhibit 4 (Herling)
PDF page 1
EXHIBIT 4
AFFIDAVIT OF STEVEN HERLING
PDF page 2
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC.
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
AFFIDAVIT OF
STEVEN R. HERLING
April 23, 2025
PDF page 3
1
I. QUALIFICATIONS AND PURPOSE OF AFFIDAVIT
1. My name is Steven R. Herling. I am currently President of Herling Power Grid Consulting, Inc. (“HPGC”), which provides consulting services related to planning, operational, and regulatory issues facing the electric power industry. My business address is 513 William Salesbury Drive, Downingtown, PA 19335. Through HPGC, I have served as a subcontractor to other consulting firms, such as The Brattle Group and Charles River Associates, advising on projects related to off-shore wind development and utility investment opportunities. I have also advised clients on generator and merchant transmission interconnection issues as well as a range of PJM Interconnection, L.L.C. (“PJM”) Regional Transmission Expansion Plan (“RTEP”) process issues.
2. In July 2020, I retired from PJM, where I had been employed since May 1990. At PJM, I held a number of positions in the Operations and Planning Divisions and was promoted to Vice President of Planning in May 2004. While at PJM, I contributed to or led initiatives that resulted in a wide range of milestone achievements in PJM’s evolution and growth as a regional transmission organization (“RTO”), including the creation of the RTEP process, the development of procedures and standard terms and conditions for generation and merchant transmission interconnections, the development of the competitive transmission process, and the reliability and resource adequacy aspects of successive integrations of additional control areas that more than doubled the size of the PJM market area. In addition to my work for PJM, I contributed to a wide range of activities for the North American Electric Reliability Corporation (“NERC”) and served on various regional industry working groups and committees addressing reliability and planning matters.
PDF page 4
2
3. Prior to PJM, I worked for the General Public Utilities Service Corporation (“GPU”) for three years in systems operations, where I was responsible for dispatcher training and certification, operations and planning activities, and energy management system and operational support tools. Prior to GPU, I worked for the American Electric Power Service Corporation (“AEP”) for eight years in bulk transmission planning. In that position, I performed a range of power system analyses related to the AEP 765 kV transmission system, generator and circuit breaker dynamic modeling, and the mechanical behavior of turbine-generator shaft systems.
4. I hold a Bachelor of Science in Electric Power Engineering and a Master of Engineering in Electric Power Engineering, both from Rensselaer Polytechnic Institute.1
5. I have testified on a number of occasions in proceedings before the Federal Energy Regulatory Commission (“FERC”), as well as various state commissions and legislative task forces, on matters relating to system planning and reliability issues. I have also testified in transmission line Certificate of Public Convenience and Necessity (“CPCN”) proceedings in Pennsylvania, Maryland, West Virginia, Virginia, and New Jersey, and I have testified in a transfer of ownership case for a public utility in Kentucky.
6. I have been asked by Constellation Energy Generation, LLC (“Constellation”) to provide an affidavit that discusses, from an engineering perspective, transmission and related services taken by load under the PJM Tariff for a range of co-located load configurations based on the options discussed in the Answer of PJM Interconnection, L.L.C. filed on March 24, 2025, in the above-captioned consolidated proceedings (“PJM Answer”). The PJM options range from load connected to the grid, separate from any generating resources, to a variety of co-location configurations. This affidavit and the opinions expressed herein are based on my experience in
1 Please refer to my resume attached as Attachment A.
PDF page 5
3
the field of electric power system planning, operation, and regulation and my knowledge of the electric power industry. My opinions and analyses are subject to change if additional information becomes available.
7. My affidavit will describe eight possible configurations of large co-located load projects, identified by PJM as Option 1 through Option 8, to provide an engineering basis for a discussion of the transmission and related services taken, or not taken, by co-located loads. For each configuration, I will discuss the extent to which the configuration imposes incremental burden on the PJM system with respect to the services and the circumstances under which the co-located load takes service. My conclusions are further summarized at the end of the affidavit.
II. DESCRIPTION OF CO-LOCATION PROJECT OPTIONS
8. As a general matter, co-located loads rely on direct connection to co-located generation facilities for the delivery of energy without reliance on grid transmission facilities or Network Integration Transmission Service (“NITS”).
9. A number of the PJM options, however, contemplate continued connection of the load to the grid, even following the loss of the co-located generating facility. These include PJM Options 1, 2, 3, 6, 7, and 8. In those cases, the co-located load will rely on the grid and NITS for energy.
10. In contrast, in PJM Option 4, the co-located load will not be able to draw energy from the grid. Instead, fully redundant relaying will trip the co-located load in the event of (i) the unplanned loss of the co-located generation or (ii) a reduction in generation level, thereby preventing the co-located load from being able to draw energy from the grid. In such configurations, no energy will flow under any circumstances from the co-located generation facilities over grid transmission to the co-located load and, therefore, no grid transmission service is used by or required by the co-located load. The same fully redundant relaying is true of
PDF page 6
4
PJM Option 5 with the limited exception of the load taking back-up service, if permitted by PJM, following the loss of the co-located generation resource, from generating resources to which it is not directly connected.
PJM Options:
11. PJM’s Option 1 is based on load connected to the grid at a separate Point of Interconnection from any generator. The load is Network Load and any generator that might be contractually serving the load is a capacity resource. The load and generation may be physically located at the same location, but they are electrically connected to the grid, separately, and not electrically co-located.
12. PJM’s Option 2 is based on co-located load and generation connected to the grid at the same Point of Interconnection, but separately metered. The load is Network Load and the generator is a capacity resource. While physically co-located at the same Point of Interconnection, Option 2 treats the load and generator as separate entities with respect to all services, regardless of any bilateral arrangements that may exist.
13. PJM’s Option 3 is based on the existing Behind the Meter Generation (“BTMG”) construct, where load is the primary customer, netting with a co-located generator at the same Point of Interconnection. Electrically, the physical connection of load and generation behind the same Point of Interconnection is the same in Option 3 as in Option 2. The load is Network Load when it consumes energy in excess of what the co-located generator produces, and the portion of the generator designated as BTMG is not a capacity resource.
14. PJM’s Option 4 is based on co-located load and generation connected to the grid at the same Point of Interconnection. The load is located behind the generator with protection mechanisms in place to prevent the delivery of energy from the grid to serve the load when the
PDF page 7
5
Nuclear Generator #1
Nuclear Generator #2
New transformers
34.8kV
New BTM equipment
New BTM equipment
Normally Open
Manual Cross-tie
GRID TRANSMISSION SYSTEM 1
GRID TRANSMISSION SYSTEM 2
34.5 kV
associated generator is out of service. The load is not Network Load, and the portion of the generator committed to the load is not a capacity resource.
15. I include Figure 1 as a sample design to illustrate such a co-located load configuration associated with a nuclear generating facility with two generating units. In Figure 1, the co- located load is served at 34.5 kV on a number of new buses, connected, behind-the-meter, by multiple transformers stepping down from generator step-up transformer high-side voltages to 34.5 kV. The co-located load can be served from either one of the generating units or split and served by the two units.
Figure 1 - One-Line Diagram of a Sample Co-Located Load Project Incorporating Redundant Relaying to Facilitate Disconnection from the Grid During Generation Outages
PDF page 8
6
16. As a point of reference, Constellation has previously submitted co-located load projects similar in configuration and design to PJM’s Option 4 or Option 5 to PJM for evaluation through Necessary Studies, as provided for in the PJM Tariff, to determine whether planned modifications will have a permanent material impact on the transmission system and to identify the additions, modifications, or replacements to the transmission system, if any, that are necessary.
17. PJM’s Option 5 is the same as Option 4 from a configuration perspective, including protection mechanisms, but allows for back-up service to be provided to the load from the PJM grid. Under PJM’s description, such back-up service would only be provided with PJM’s approval and such approval could be denied or withdrawn by PJM based on system conditions.
18. Option 6 is similar to Option 2, except that under PJM’s proposal the new load brings new generation to the grid with which it will be co-located to obtain the opportunity for faster interconnection. The new load does not include the type of special protection relay scheme envisioned in Option 4.
19. PJM’s Option 7 is similar to Option 2, except that the service received by the load will be interruptible. The status of the generator does not change, i.e., the generator can remain a capacity resource. The load receiving interruptible service is separately metered but does not include the type of special protection relay scheme envisioned in Option 4.
20. PJM’s Option 8 is similar to Option 2, but provides the opportunity for the co-located load to participate in an expanded form of Demand Response.
III. PROTECTIVE RELAY SCHEMES
21. As discussed, Options 4 and 5 will require protective relay schemes that will prevent load from drawing energy from the grid. These protective relay schemes can be designed so that there are completely redundant primary and backup protective schemes to perform this function.
PDF page 9
7
22. Such a configuration uses electric current transformers to measure the flow of power from between the co-located load and the grid, which is communicated with relays via fiber optic channels that will trip behind-the-meter circuit breakers associated with the co-located load when the electric current transformers sense the power flow from the grid to the co-located load. This can occur in the event of the sudden loss of the co-located generating unit or following a reduction in the level of energy produced by the co-located generating unit so that it is not fully supplying the co-located load. There are two circuit breakers placed in series supplying the co- located load, so that if one fails, the second will still open the circuit. Each circuit breaker has two trip coils such that either the primary or backup protective relay can successfully trip the load. All elements of the protective scheme, including the electric current transformers, the fiber channels, and the trip relays, are redundant resulting in a single-failure-proof design. The protective scheme referred to above in Figure 1 will trip the co-located load from the grid in three cycles (0.05 seconds) following a trip of the co-located generating unit or after sensing that the energy produced by the co-located generating unit has been reduced to a level such that the co-located load is attempting to draw energy from the grid.
23. PJM raises the concern that “[t]he challenge with an arrangement where there is load located behind a generator Point of Interconnection lies in how such a configuration or special protection scheme could be designed to never fail . . . .”2 PJM plans for N-1 conditions followed by a single protection system failure, such as a stuck breaker, and requires transmission system upgrades when such events result in violations of applicable NERC standards. In this instance, a stuck breaker becomes a second contingency. In most instances, the solution to stuck breaker criteria violations is to add a redundant series breaker, making the failure of both breakers
2 PJM Answer at 44.
PDF page 10
8
following an N-1 event a third contingency. PJM does not plan for or require upgrades for such third contingencies, nor would it be reasonable to do so, short of events that would result in a cascading outage of grid facilities. The protection system, discussed above, is fully redundant and, while it cannot be guaranteed to never fail, it is unreasonable to treat the failure of both primary and secondary relay system facilities following the loss of a generator as anything other than a third contingency. In fact, when I was directing transmission planning for PJM, I cannot think of an instance in which we treated such a situation otherwise. In practice, protection schemes are regularly employed on the PJM transmission system, and the successful operation of such protective systems is a common observance within PJM. There is no technical reason from my perspective to expect that protective relaying in the context of co-location would perform any less reliably. If anything, suggesting that protective relaying – a common and technically sound tool for managing the grid – cannot be used in the context of co-located configurations or must be designed to a different standard strikes me as an unduly discriminatory position.
IV. GRID SERVICES
24. With the different technical configurations for co-located load in mind, I discuss below the various transmission and related services and the extent to which the co-located load imposes incremental burden on the PJM system with respect to the services it takes or does not take. a. Network Integration Transmission Service
25. NITS is the means by which Network Load in the PJM region is served over the PJM transmission system, utilizing identified Network Resources as well as other non-designated generation resources.3 The PJM RTEP ensures the on-going reliability and ability of the PJM transmission system to provide service to load customers via NITS and long-term firm point-to-
3 PJM Tariff, Part III, Sections 28.1 and 28.3.
PDF page 11
9
point transmission service. Transmission facilities necessary to connect new load customers to the grid are identified and integrated into the RTEP to ensure the integrity of the models used in analyses and the on-going reliability of service to all customers.
26. In PJM’s Option 1, a new Network Load would be fully dependent on NITS for delivery of capacity and energy, would be included in the PJM load forecast, and would be modeled and planned for in future RTEP cycles. This is the manner in which the vast majority of load is connected to the PJM grid.
27. In PJM’s Option 2, a new load and the co-located generator are separately metered. The load is considered Network Load and the generator is a capacity resource. While energy will flow directly from the generator (when it is in service) to the load without flowing over the facilities of the PJM grid, the load would be dependent on NITS for delivery of capacity and energy at some times, would be included in the PJM load forecast, and would be modeled and planned for in future RTEP cycles. The dependence of the load on NITS covers all circumstances, whether the generator is in or out of service.
28. PJM’s Option 3 is based on the existing BTMG construct and can involve two configurations where load and generation can be co-located or connected via the distribution system of a municipal utility. The existing PJM Tariff bills for transmission and related services based on the netting of such load with its BTMG.
29. In PJM’s Option 4, a new load is co-located behind a generating resource. As shown in Figure 1 above, the connection is radial, behind the Point of Interconnection of the generator. Therefore, energy can only flow directly from the co-located generator’s grid voltage substations to the behind-the-meter co-location project’s substations (at the same grid voltage level) and, from there, over step-down transformers to the co-located load connected at 34.5 kV. There is no
PDF page 12
10
other transmission path from the co-located generation to the co-located load, i.e., there is no parallel path for energy to flow out from the co-located generator onto the transmission grid and back, eventually, to the co-located load. Because the associated special-purpose relay scheme will remove the co-located load from the grid in the event of a sudden loss of the generating facility, no energy will flow to the co-located load over the transmission grid following a contingency; no new transmission infrastructure will be required on the grid to facilitate the interconnection and to ensure reliability for existing load customers other than what might be identified in the Necessary Study performed to determine whether the generator’s modification to serve the behind-the-meter load has any reliability impact, and no NITS service will be provided by the grid to the co-located load. Excess energy, beyond the level required by the load, will flow from the generator to the grid. Accordingly, the load is not dependent on NITS for delivery of capacity and energy, would not be included in the PJM load forecast, and would not be modeled and planned for in future RTEP cycles.
30. In PJM’s Option 5, a new load is co-located behind a generating resource in the same manner as Option 4. As shown in Figure 1 above, the connection is radial, behind the Point of Interconnection of the generator and, therefore, energy is delivered from the generator directly to the load without flowing on any grid transmission facilities. Excess energy, beyond the level required by the load, will flow from the generator to the grid. Protection mechanisms are in place to prevent the delivery of energy from the grid to the load in the event that the generator is offline. The significant difference with Option 5 is that the load can take back-up service from PJM with advance authorization. The load is not dependent on NITS for delivery of capacity and energy while the primary generation source is in service, but may rely on transmission facilities of the PJM grid for back-up service, depending on the electrical location of the back-up
PDF page 13
11
generation source. To the extent that back-up service is supplied by a second generating resource at the same electrical location, energy from that resource would also not flow on any grid transmission facilities.
31. With respect to PJM Option 4 and PJM Option 5, PJM notes that co-location
arrangements may involve the sale of power from generators to intermediaries and then to load under certain circumstances.4 This, however, is a contractual difference, not a physical, electrical, or interconnection design-based difference. The delivery of energy from generation to load in co-location arrangements such as PJM’s Option 4 and Option 5 does not involve the flow of that energy over the transmission facilities of the grid. This fact is a function of the design of the interconnection between the co-located load and generation and is not impacted by the ownership of the generation facility or the co-located load or any contractual relationship between those parties. BTMG arrangements and co-located load arrangements can be designed from an engineering perspective in exactly the same manner. In one, the load is typically greater in magnitude than the generating facility. In the other, the load is typically lesser in magnitude than the generating facility. The physics of energy delivery are the same in both arrangements and are not related to contractual arrangements or rate structures.
32. Finally, Option 7 contemplates the ability to curtail load in advance of
emergency conditions. While not specifically a co-location configuration feature, this contractual arrangement can provide a valuable tool to PJM operators with which to manage operational emergencies. It could be implemented as a transitional service while required transmission system upgrades are under construction.
4 PJM Answer at 25.
PDF page 14
12
b. Synchronization
33. Comparing PJM’s Option 4 and PJM’s Option 5 with the BTMG construct (the basis for PJM Option 3), clearly both arrangements involve load and generation that is synchronized to the grid. However, synchronization does not require or suggest that energy delivery from that generation to that load flows on the transmission facilities of the grid. Synchronization is clearly important and even necessary to the stability of the generating facility and the ability of the generating facility to deliver energy to the co-located load on an on-going basis, but that does not change the fact that the energy does not flow on the transmission facilities of the grid.
34. Whether synchronization could be conceptualized and designated as an ancillary service, one thing is clear: it is not an ancillary service within PJM. The ability to provide other ancillary services, if they are required or used, is facilitated by synchronization, but one is not the equivalent of the other. Synchronization may allow black start service to be provided, but if black start service is not required or used by a co-located load, the fact that the load is synchronized to the grid does not make the service required or used. In response to question b.vi., PJM states that “[s]ynchronizing to the grid means the generator matches the voltage, frequency, and phase of the entire grid (including all load connected to the system) before connecting to the grid in order to facilitate safe and stable power transfer. As noted above, co- located load is connected to and synchronized with the multi-state bulk power system. At bare minimum, it is benefiting from ancillary services.”5 Load benefits from being synchronized to the grid, but not from services that it does not use. One standard on which charges for grid services can be properly based is use of those services. This applies to both transmission service and ancillary services. Synchronization, alone, should not be the standard for such charges.
5 Id. at 43.
PDF page 15
13
c. Other Grid Services
I have previously analyzed grid services in connection with a co-located load configuration that, while synchronized to the grid, provides for disconnection from the grid when the co-located generation facility is unavailable. In short, my prior analysis shows that co- located load configurations that include sufficiently redundant protective relay systems, e.g., configurations consistent with PJM’s Options 4 and 5, prevent the physical flow of power to the co-located load and do not use transmission service from the grid.6 Moreover, my prior analysis shows that these configurations do not impose burdens on the PJM system that would require the procurement of additional amounts of ancillary services.7
35. Further, the PJM Tariff, which establishes the procedures for calculating charges for services provided in PJM markets, dictates for all of the services discussed herein, that the obligation of a behind-the-meter co-located load is based on the amount of such load, netted by the generation that is operating behind-the-meter.
36. My presentation here is an engineering analysis that, among other things, considers whether non-grid connected co-location configurations consistent with PJM Options 4 and 5 impose additional burdens on the PJM grid. I note that I do not take a position here, nor did I in my prior analysis, whether the co-located load under the non-grid connected configurations of PJM Options 4 and 5 may nevertheless benefit indirectly by virtue of synchronization through the host generator’s interconnection to the grid. To date, however, FERC has not allocated charges for any such synchronization benefits.
37. This concludes my affidavit.
6 Protest of Constellation Energy Generation, LLC to the Exelon Companies’ Rate Filings, Docket Nos. ER24-2888- 000, et al., Att. 1, Affidavit of Steven R. Herling at ¶¶ 14-34 (Oct. 2, 2024).7 Id.
PDF page 16
VERIFICATION
I declare under penalty of perjury that the foregoing Affidavit is true and correct to the best of my knowledge, information, and belief.
Executed this 23rd day of April 2025.
________________________
Steven R. Herling
Satze
PDF page 17
Attachment A to Herling Affidavit
PDF page 18
Page 1
Steven R. Herling
PROFESSIONAL EXPERIENCE
Herling Power Grid Consulting, Inc. (2020 – Present)
President
Provide expertise to support strategic decision making related to the development of planning processes and the integration with electric power grid market structures.
Provide expertise to support strategic decision making related to the integration of renewable technologies onto the electric power grid.
Provide expert witness services in transmission line siting proceedings.
Yoh Staffing Services (2020 – 2021)
Executive Consultant (2020 – 2021)
Provide expert witness services in transmission line siting proceedings.
PJM Interconnection, LLC (1990 – 2020)
Executive Consultant, Planning (2019 – 2020)
Provide expert witness services in support of the Transource 500/230 kV IEC Project. Provide leadership to the development of planning processes related to aging infrastructure and grid resilience.
Provide leadership to the development of planning processes related to the integration of off-shore wind into the grid.
Support the transition of responsibility to the new Vice President, Planning.
Vice President, Planning (2004 – 2019)
The Vice President, Planning reports directly to the CEO.
Responsible for the oversight of System Planning division of PJM which includes Transmission Planning, Interregional Planning, Interconnection Analysis, Interconnection Projects, Infrastructure Coordination and Resources Adequacy Planning.
Position Summary:
Develop long range strategies to achieve PJM’s Planning business objectives.
Provide overarching methodology for the monitoring and analysis of Planning studies as well as the introduction of improved and emerging technologies in the Planning space.
Support the leadership of the Planning organization in large and complex engineering assignments to support present and future needs of the PJM system.
PDF page 19
Page 2
Support the activities of PJM and industry committee or task forces involved with issues related to planning and engineering.
Prepare board reports, presentations as well as expert testimony regarding Planning and Interconnection recommendations.
In conjunction with subject matter experts, coordinate delivery of all communication regarding the regional transmission expansion and enhancement plans.
Ensure the Planning division and staff can support the requests of PJM as well as external entities regarding Interconnection queue activities and feasibility studies.
Ensure relationships with the PJM community as well as other regulatory entities are productive and in alignment with the PJM strategic plan.
Various Staff and Management Positions at PJM (1990 – 2004)
General Public Utilities Service Corporation (1987 – 1990) – System Operations
American Electric Power Service Corporation (1979 – 1987) – Bulk Transmission Planning
Expert Witness Testimony:
Kentucky proceeding related to the transfer of ownership and control of Kentucky Power Company.
Pennsylvania and Maryland CPCN proceedings related to the Transource 500/230 kV IEC Project.
Pennsylvania and New Jersey CPCN proceedings related to Susquehanna – Roseland 500 kV transmission line.
Pennsylvania, West Virginia, and Virginia CPCN proceedings related to TRAIL and Meadowbrook – Loudoun 500 kV transmission lines.
West Virginia, Virginia, and Maryland CPCN proceedings related to PATH 765 kV transmission line.
Maryland CPCN proceeding related to MAPP HVDC and 500 kV transmission lines.
Virginia CPCN proceeding related to Surry – Skiffes Creek 500 kV transmission line.
Numerous FERC hearings, settlement proceedings, and technical conferences, most recently including: o Panelist at FERC’s Competitive Transmission Development Technical Conference (Docket No. AD16-
18) regarding Regional Transmission Planning and Other Transmission Development Issues relative to Order No. 1000 implementation and compliance. June 2016.
o Panelist at FERC’s PJM Solution-Based DFAX Technical Conference related to the assignment of cost allocation using PJM’s solution-based distribution factor (DFAX) cost allocation method. January 2016
o Panelist at FERC’s Technical Conference related to the NIPSCO Complaint (Docket No. EL13-88) on two panels: (i) Transmission Planning Cycles: Whether the Commission should require the PJM- MISO cross-border transmission planning process to run concurrently with the RTOs regional planning cycles as opposed to after the regional transmission planning cycles; and (ii) Lower Voltage Transmission Projects: Whether the Commission should require the RTOs to have a process for joint planning and cost allocation of lower voltage and lower cost cross-border upgrades. June 2015 o IMO Potomac-Appalachian Transmission Highline LLC and PJM Interconnection, L.L.C. (Docket No. ER09-1256-002 and ER12-2708-003). Offered expert testimony relative to the PATH Abandonment Costs matter. April 2015
o Duquesne Light Company (Docket No. ER13-90-002). Provided Declaration in support of PJM Transmission Owners’ compliance filing with the March 22, 2013 Order to add more detail regarding
PDF page 20
Page 3
how the solution-based DFAX values will be used to calculate assignments of cost responsibility. July 2013
o Public Service Electric and Gas Company (Docket No. ER13-90). Provided expert testimony on behalf of the PJM Transmission Owners revisions to the PJM Tariff to modify the cost allocation methodology describing PJM’s current use of distribution factors (DFAX) in allocating the costs of certain transmission upgrades and expansions and discuss how PJM would implement the solution-based DFAX proposed by the PJM Transmission Owners. October 2012
o Panelist at FERC’s Review of Small Generator Interconnection Agreements and Procedures Technical Conference (Docket No. AD12-17) on a panel entitled: Review of Required Upgrades, which explored improving the small generator interconnection process for identifying upgrades to support interconnection including whether interconnection customers should have the opportunity to engage in an expedited independent third-party expert review of upgrade requirements that are perceived as excessive by the interconnection customer. July 2012
Most Recent Publications:
Before the United States District Court for the Middle District of Pennsylvania, Case No. 1:21-cv-01101- JPW, Expert Report of Steven R. Herling in Transource Pennsylvania, LLC, vs. Pennsylvania Public Utility Commission, January 20, 2023.
“New Jersey State Agreement Approach for Offshore Wind Transmission: Evaluation Report (with H. Pfeifenberger, J.M. Hagerty, J. DeLosa, M. Kaplin, D. Sullivan, C. Peacock, E. Bennett, and E. Snyder), prepared for the New Jersey Board of Public Utilities, October 6, 2022
“The Sponsorship Model” – IEEE Power & Energy Magazine – July/August 2016
Education:
MEEPE, Rensselaer Polytechnic Institute, (1979)
BSEPE, Rensselaer Polytechnic Institute, (1978)
Senior Member of the Institute of Electrical and Electronics Engineers