EL25-49-000 · 2025-04-25 · Clean Air Task Force

Comments of Clean Air Task Force re FERC's Order Instituting Proceeding under Section 206 of the Federal Power Act and Consolidating with Other Proceedings

PDF page 1

UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc.
American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc.
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company
Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company
Rockland Electric Company
Trans-Allegheny Interstate Line Company
Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company

AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.

AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public Utilities, Division Docket Nos. EL25-49-000

PDF page 2

2

of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company

Large Loads Co-Located at Generating Facilities

Constellation Energy Generation, LLC

v.

PJM Interconnection, L.L.C.

AD-24-11-000

EL25-20-000
(Consolidated)

ORDER INSTITUTING PROCEEDING UNDER SECTION 206 OF THE FEDERAL
POWER ACT AND CONSOLIDATING WITH OTHER PROCEEDINGS

COMMENTS OF CLEAN AIR TASK FORCE

Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure, 18 C.F.R. § 385.211, Clean Air Task Force, Inc. (“CATF”) respectfully submits these comments responding to the filings of the parties in the Show Cause Order pursuant to section 206 of the Federal Power Act (“FPA”) dated February 20, 2025, seeking information about whether the Open Access Transmission Tariff (“OATT”) of PJM Interconnection, L.L.C. (“PJM”), “remains just and reasonable and not unduly discriminatory or preferential without provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements; or (2)

PDF page 3

3

explain[ing] what changes to the Tariff would [be necessary to] remedy the identified concerns.”1

CATF is a nonprofit organization dedicated to advancing the policy and technology changes necessary to achieve a zero-emissions high-energy planet at an affordable cost. With more than 25 years of internationally recognized expertise on environmental policy and law, and a commitment to exploring all potential solutions, CATF is a pragmatic, non-ideological advocacy group with the bold ideas needed to address climate change and air pollution. CATF has offices in Boston, Washington, D.C., and Brussels, with staff working remotely around the world.

CATF thanks the Commission for initiating this inquiry. CATF’s interest in this docket arises from our mission, which includes working towards a transition to a clean and sustainable energy system, where costs are just and reasonable for all. Such a future requires careful planning for the transmission development and services required to support the addition of new loads and new generation. The recent and imminent surge in demand for co-located generation to serve data centers and other large loads makes holistic grid planning even more critical to ensuring that transmission rates, practices, and procedures are just, reasonable, and not unduly discriminatory. It is CATF’s view that, not just in PJM, FERC must consider the issues presented here as it engages with transmission planners across the country on regional planning, going beyond a case-by-case approach to create generally applicable rules for integrating new large loads onto the grid, with or without co-located generation. Furthermore, until such generally applicable rules are created, FERC should not approve any waivers for interconnection service agreements.

1 PJM Interconnection, L.L.C., Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings at ¶ 2, Docket Nos. EL25-49-000, et al. (“Show Cause Order”).

PDF page 4

4

As an initial matter, CATF supports the comments made by Public Interest Organizations (PIOs)2 and the Union of Concerned Scientists3 in this docket, and submits this additional letter to provide a few supplemental points of specific concern to CATF.

I. CO-LOCATED GENERATION TO SERVE LARGE LOADS CANNOT BE
FULLY ISOLATED FROM THE GRID
As an initial matter, CATF bases its position on the physical reality that existing and new generation that is designated to serve large loads cannot be isolated from the rest of the transmission system. CATF supports the conclusions of PJM, Indicated PJM Transmission Owners, Public Service Gas & Electric, and the Union of Concerned Scientists that all co-located load is Network Load, cannot be fully isolated, and inevitably uses and also impacts the transmission system.4 The co-located load, co-located generator, and transmission system are not only physically connected, but inter-reliant. As such, while fully isolated load configurations may be spelled out in contractual arrangements, the claim that they do not take necessary services from the transmission system is simply not factually supported by the physical operation of the system. Co-located operations routinely include unplanned generator run-backs or reductions in output, generator MW output oscillations, and co-located load utilization fluctuations. When these conditions occur, they result in “brief, but routine, imbalances between the load and the generation that would need to rely on the grid to balance.”5

2 Comments of Public Interest Organizations, Docket no. EL25-49-000 (April 13, 2025), Accession No. 20250423- 5243 (“PIO Comments”).
3 Comments of the Union of Concerned Scientists, Docket no. E;25-49-000 (April 11, 2025), Accession No. 20250411-5020 (“UCS Comments”).
4 Show Cause Order ¶ 4, citing PJM Guidance on Co-Located Load (March 22, 2024); Answer of the Indicated PJM Transmission Owners to the Order Instituting the Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings, Docket no. EL25-49-000 (April 23, 2025), Accession No. 20250324-5298 at 9; Response of Public Service Electric and Gas Company to Show Cause Order issued on 02/20/2025 under EL25- 49, et al., Docket no. EL25-49-000 (March 24, 2025), Accession No. 20250324-5299 at 1.
5 Answer of PJM Interconnection, LLC, Docket No. EL25-49-000 at 45 (March 24, 2025), Accession No. 20250324-5313 (“PJM Answer”).

PDF page 5

5

II. FERC HAS JURISDICTION IN THIS MATTER TO REQUIRE REGIONAL
TRANSMISSION TARIFF PROVISIONS FOR CO-LOCATED LOAD
The Federal Power Act tasks the Commission with the regulation of the transmission and wholesale sale of electricity to protect the public interest and ensure just and reasonable rates. 16 U.S.C. §§ 824, 824d. The Commission’s jurisdiction extends over all facilities used for the transmission or sale of electric energy in interstate commerce; states maintain jurisdiction over the regulation of facilities used for the generation of electricity. 16 U.S.C. § 824. The Commission is required to issue an order setting just and reasonable rates, rules, and practices whenever it determines that existing rates, rules, and practices involving transmission or electricity sales under its jurisdiction are unjust, unreasonable, unduly discriminatory or preferential. 16 U.S.C. § 824e. As the Commission sets forth in its Show Cause Order, it has authority and jurisdiction to “ensure that rates, charges, and classifications for . . . wholesale sale and transmission as well as the practices directly affecting such sale and transmission, are just and reasonable, and not unduly discriminatory or preferential.”6

As the Commission describes at Section VI.A. of the Show Cause Order, the issues raised by the interconnection of large loads co-located with generation resources (either new or existing), also implicate some state jurisdictional questions.7 However, as noted above and described by others, because all co-located generation configurations necessarily receive essential services from the transmission grid, this makes them subject to FERC’s jurisdiction and consequently all rates, practices, and procedures involving such facilities must be just, reasonable, and not unduly discriminatory.8 As such, considerations related to the adequacy of PJM’s tariff to properly plan

6 Show Cause Order, ¶ 66 (citing FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 278 (2016).
7 Id., ¶ 67-71.
8 See UCS Comments at 8-14 (citing Indicated PJM Transmission Owners and NERC to demonstrate how all listed configurations cannot be isolated); see id. at 17 (“We illustrate how the fully isolated load idea is a fiction…the

PDF page 6

6

for and allocate costs pertaining to such large co-located loads is clearly within FERC’s jurisdiction under section 206 of the Federal Power Act. 16 U.S.C. §824e. Where, as here, the evidence demonstrates that the existing tariff provisions are inadequate, unjust, and unreasonable, FERC is obligated to issue new rates, practices, and procedures that comply with Federal Power Act requirements. 16 U.S.C. §824d.

Co-located generation and large load configurations create both the need for additional new investment in transmission infrastructure and grid system services, and also sometimes include the ability to provide ancillary and other services back to the system. Especially in light of the anticipated size of individual generating units and the expected share of the data centers as a proportion of future load, it is absolutely critical that grid operators appropriately plan for and justly allocate the costs of such investments. As discussed further below, in developing just and reasonable rates for co-located load arrangements (particularly any “bring your own generation” configuration), the Commission must consider both the full costs of transmission services necessary to support such resources, as well as any potential benefits offered by all kinds of co- located firm generation for system reliability and to meet state clean energy requirements. As set forth in Order No. 1920, the Commission’s jurisdiction clearly extends over the holistic transmission system planning necessary to properly identify, implement, and pay for the facilities and services required to support large load growth.9 Along with Orders 888, 890, and 1000, these Commission directives represent decades of precedent establishing FERC’s authority

loads require transmission and ancillary services because the host generators are unable to operate without the grid.”).

9 Building for the Future Through Elec. Reg’l Transmission Plan. & Cost Allocation, 89 Fed. Reg. 49,280 (June 11, 2024), 187 FERC ¶ 61,068 (May 13, 2024), (hereinafter “Order No. 1920”) at ¶¶ 253-258, order on reh’g & clarification, Order No, 1920-A, 89 Fed. Reg. 97,14 (Dec. 6, 2024), 189 FERC ¶ 61,126 (2024) order on reh’g & clarification, Order No, 1920-B, 191 FERC ¶ 61,026 (Apr. 11, 2025).

PDF page 7

7

to require transmission stakeholders to meet transmission planning practices and procedures necessary to ensure just and reasonable rates.10 Supreme Court Justice Thomas, with Justice Scalia and Justice Kennedy concurring in part, have weighed in on FERC’s extensive authority over transmission, stating that the Federal Power Act “unambiguously grants FERC jurisdiction over all interstate transmission and § 824e mandates that FERC remedy undue discrimination with respect to all transmission within its jurisdiction …,” and finding that the statute “require[s] FERC … to engage in reasoned decisionmaking to determine whether there is undue

discrimination with respect to transmission associated with retail bundled sales, and if so, what remedy is appropriate.”11

III. PER ORDER NO. 1920, DATA CENTERS MUST BE INTEGRATED INTO
LONG TERM PLANNING TO ADDRESS IMPLICATIONS OF LARGE
LOADS ON TRANMISSION SYSTEM
While the Commission is asked to look at PJM’s tariff of today, as it considers issuance of a broader ruling it must ensure that planning to meet transmission needs associated with large loads in the immediate term also aligns with the requirements of Order No. 1920, the central aim of which is to ensure that transmission planners accurately identify long-term transmission needs and implement efficient and cost-effective solutions to meet those needs.

As the Commission has found, effective long-term transmission planning is critical to unblocking interconnection queue delays that currently thwart the ability to expeditiously bring

10 See, e.g., Transmission Access Policy Study Group v. FERC, 225 F.3d 667, 343 U.S. App. D.C. 151 (D.C. Cir. 2000) ("TAPS"), aff'd sub nom. New York, 535 U.S. 1 (2002) (upholding Order No. 888 in nearly all respects, concluding that the Commission had authority under FPA Section 206 to require open access as a generic remedy for systemic anti-competitive behavior); South Carolina Pub. Svc. Comm. v. FERC, 762 F.3d 41, 63 (D.C. Cir. 2014) (Statute supports Commission's assertion of authority over transmission planning matters in the challenged orders, notwithstanding petitioners' contention that the orders intrude on the States' authority).
11 New York v. FERC, 535 U.S. 1, 42 (2002).

PDF page 8

8

on new load or develop supply.12 Central to Order No. 1920’s reforms is the transparency of information regarding future load and supply, without which the ability of transmission planners to meaningfully conduct scenario-based planning and choose the best transmission solutions become impossible. The Order No. 1920 planning process must incorporate information about expected large loads, with or without co-located generation, in order to ensure that regional transmission infrastructure is accurately sized and appropriately located. Such information is also essential to ensure that the costs of building the transmission system are fairly assessed and allocated. Especially in light of estimates regarding the magnitude of potential load growth from data centers, cryptocurrency, electrification, and increased manufacturing, if Order No. 1920 reforms are to succeed, FERC must require these and other large loads be planned as part of that process.

The system is already experiencing bottlenecks due to the need for additional transmission buildout. Studies estimate that a three to four-fold increase in transmission is needed to meet the demand of the next thirty years.13 Approximately 2,600 gigawatts of generation and storage capacity – of which 95 percent are zero-carbon, low or zero air polluting resources – are waiting to connect to the grid today and more transmission is necessary to connect many of these and other resources that have been waiting in interconnection queues for years.14 The Commission

12 Order No. 1920 at ¶¶ 107-108.
13 Nicole Pavia, Future-fitting the grid: How to accelerate federal transmission permitting, Clean Air Task Force (Jul. 18, 2024), https://www.catf.us/2024/07/future-fitting-grid-how-accelerate-federal-transmission-permitting/; Clean Air Task Force & Niskanen Center, How are we going to build all that clean energy infrastructure? (Aug. 2021), https://www.niskanencenter.org/wp- content/uploads/2021/08/CATF_Niskanen_CleanEnergyInfrastructure_Report.pdf.
14 Nicole Pavia, Testimony Before the United States Senate Committee on Environment and Public Works Improving the Federal Review and Permitting Processes, https://www.epw.senate.gov/public/_cache/files/4/d/4dbae8e8-0f66-4ddc-9d2e- 8ec431e6ed26/18CF4B86636126A39982FF1854890BB02118CC591EA301C8C1C3D3307E78AE66.02-19-2025- pavia-testimony.pdf (citing Lawrence Berkeley National Laboratory, Queued Up: Characteristics of Power Plants

PDF page 9

9

and grid stakeholders have already invested years in building consensus for a path forward to deal with all of the resources in need of increased transmission and have embodied those solutions in Order Nos. 1920 and 2023.15 Improved regional and interregional transmission will alleviate current grid congestion, provide lower-priced energy, and reduce incentives for large loads to try and avoid the long delays associated with the planning and interconnection processes.16 But if the Commission were to bless the ability of large loads capable of buying resources currently relied upon by the entire grid to essentially exempt themselves from these processes, those reforms will fail.

Per Order No. 1920, transmission planners must integrate data centers and co-located generation into their long-term planning for upgrading transmission. As stated above, see Section I, data centers with co-located generation are not wholly isolated from the grid in the first place and thus must not be permitted to be treated as such. The load growth from data centers is unprecedented,17 but must be treated as a long-term issue–their usage is but one driver of exponential load growth and must be planned for accordingly. While it may appear faster for data centers to “skip” the interconnection process and pursue behind-the-meter connections to load without connection to the transmission system, evidence in this docket has shown such an arrangement to be physically impossible, presenting major risks in reliability and costs to the

Seeking Transmission Interconnection (April 2024), https://emp.lbl.gov/queues.); Department of Energy, National Transmission Needs Study (October 2023) 20, 74-79, at: https://www.energy.gov/sites/default/files/2023- 12/National%20Transmission%20Needs%20Study%20-%20Final_2023.12.1.pdf (hereinafter “National Transmission Needs Study”).

15 Improvements to Generator Interconnection Procedures and Agreements, 184 FERC ¶ 61,054 (2023) (“Order No. 2023”).

16 Id. at 32-34.
17 See Arman Shehabi et al., 2024 United States Data Center Energy Usage Report (Dec. 2024), available at https://www.energy.gov/articles/doe-releases-new-report-evaluating-increase-electricity-demand-data-centers (showing domestic energy usage from data centers is expected to double or triple by 2028).

PDF page 10

10

entire grid system.18 Many loads urgently need to be connected to the grid,19 and data centers are but one kind of such demand. There is little reason and considerable risk in establishing tariff terms that allow data centers and co-located generation to effectively do an end run around the much needed and required long-term transmission planning process designated by Order No. 1920 or the interconnection queue reforms put into place by Order 2023.

IV. FERC MUST ENSURE COSTS ASSOCIATED WITH CO-LOCATED LARGE
LOADS ARE FAIRLY ALLOCATED
Allocating the transmission system costs of co-located loads and generation in a just, reasonable, and not unduly discriminatory manner requires a thorough and transparent evaluation of the costs and benefits associated with large co-located loads. The need for FERC to act expeditiously to establish straightforward rules applicable across the regions is necessary to get in front of a rapidly growing industry whose attendant load, costs, and operations could upend grid operations if not the Commission does not act. There is already considerable pressure on regional and interstate grid operators due to large loads seeking interconnection, with or without co-located generation.20 This pressure is exacerbated by interconnection queue delays in PJM that have motivated data centers to “skip” the queue via co-location and proposed reshuffling of queues.21 There is already clear evidence of such queue skipping occurring, where large loads

18 See, e.g., generally, UCS Comments; PIO Comments at 30-32.
19 Nicole Pavia, supra note 14.
20 National Transmission Needs Study at 87.
21 See, e.g., Protest of Public Interest Organizations, at 2-4, 6-11, Docket No. ER24-2045 (June 20, 2024), Accession No. 20240620-5242 (documenting PJM’s backlogged interconnection queue and significant delays in processing interconnection requests); Final Brief of Respondent-Intervenors Interconnection Reform Advocates, at 39-44, Advanced Energy United et al.
v. FERC, Case No. 23-1282, Document No. 211411 (Apr. 16, 2025) (“PJM had, and still has, one of the longest and most-backlogged interconnection queues of any region”).

PDF page 11

11

“shop” multiple queues, making the amount of co-located load pressure on the system seem larger than it is.22

This uncertainty makes planning for such rapid growth both precarious and expensive. As PIOs aptly point out, energy costs in the PJM region are skyrocketing, and PJM has already issued a call to build $5.9B in new transmission lines needed largely to serve expected growth from data centers—incurring immense costs23 that are being borne by PJM’s ratepayers.24 FERC has recently approved price ceilings for capacity markets limiting price hikes for consumers,25 but more needs to be done to ensure that the costs and benefits of transmission infrastructure and services associated with the growth of data centers are accurately assessed and justly allocated. The evidence of speculation and queue jumping by generators seeking to quickly serve data centers via co-location end runs around standard planning and interconnection requirements, along with attendant risks to reliability and market manipulation as outlined by PIOs,26 reinforces the need to level the planning playing field by requiring co-located generation serving large loads to be addressed as part of a holistic grid planning, interconnection, and cost-allocation process applicable to all stakeholders connected to the grid. To do otherwise for an economic sector that

22 PIO Comments at 17, n.43, citing 2025 Pennsylvania Environmental Law Forum (April 14, 2025), https://www.pbi.org/product/pba-environmental-energy-law-section-annual-dinner/; id. at 18 n.44, citing Technical Conference Transcript at 26 Docket No. AD24-11 (Nov. 1, 2024), https://www.ferc.gov/media/transcript-technical- conference-regarding-large-loads-co-located-generating-facilities
23 Zachary Skidmore, PJM approves $5.9bn in new transmission projects to support data centers, Data Center Dynamics (Mar. 4, 2025), https://www.datacenterdynamics.com/en/news/pjm-approves-59bn-in-new-transmission- projects-to-support-data-centers/.
24 Renee Sanders, 2025-2026 PJM Capacity Auction & Its Consumer Impact, Integrity Energy, (last edited Feb. 27, 2025), https://www.integrityenergy.com/about/news-media/pjm-announces-expensive-energy-changes-in-2025/ (“Businesses can expect commercial energy bills to increase by up to 29% starting in June 2025”); Ethan Howland, Maryland electric customers face up to 24% bill hikes from PJM capacity auction: report, Utility Dive (Aug. 15, 2024), https://www.utilitydive.com/news/maryland-bge-pepco-electricity-bill-pjm-capacity-auction-opc- ratepayer/724319/ (price hikes from 2024 in the PJM region).
25 Peter Behr, FERC approves ceiling on PJM power supply payments, EnergyWire (Apr. 23, 2025), https://www.eenews.net/articles/ferc-approves-ceiling-on-pjm-power-supply-payments/. 26 See PIO Comments at 17-19, 26-30.

PDF page 12

12

is estimated to consume as much as 12 percent of the nation’s electricity as soon as 202827 could fatally undermine the critical reforms necessary to develop transmission infrastructure for all stakeholders that was achieved as part of Order Nos. 1920 and 2023.

In order for the cost allocation of improved transmission to be just, reasonable, and not unduly discriminatory, FERC must first require clean and transparent accounting of benefits and burdens of each large co-located load interconnection for the transmission system and detailed accounting of what costs and benefits actually flow to the broader group of ratepayers charged with paying them. As other commenters have demonstrated, this is not currently occurring.28 Transparent and accurate accounting is crucial for ensuring accurate load forecasts that directly determine what rates are set.

Tariffs should also enable potential benefits of co-located load and generator arrangements to flow toward the grid, including establishing provisions for co-located facilities to perform demand response or other grid services based on the full value of any benefits they may provide from either side of the meter. These include but are not limited to avoided investment costs, access to lower cost power, or blackstart and other ancillary services, and in certain situations where zero- or low-carbon firm generation is co-located, helping states to meet their clean energy obligations. Tariff provisions also can and should be written to enable participation by any type of resource and establish reasonable penalties for non-performance that reflect the operating limitations of the type of resource.29 Co-located generation and storage could increase

27 Arman Shehabi, et al., 2024 United States Data Center Energy Usage Report, 5, LBNL-2001637, Lawrence Berkley Nat‘l Lab at: lbnl-2024-united-states-data-center-energy-usage-report.pdf.

28 See Comments of PIOs, pages 11-14.
29 Order Denying Complaint, 184 FERC ¶ 61,137 (Aug. 31, 2023), Cmr’s Phillips and Clements concurring, at ¶ 3 (“Should DIRs become significantly and demonstrably more likely to clear ancillary services when they are deliverable, a tariff that fails to allow DIRs to provide those services could be rendered unjust and unreasonable and unduly discriminatory or preferential.”)

PDF page 13

13

the flexibility potential of the net-load of the whole facility (load and generation resources) relative to traditional load. As the Nicholas Institute describes in a recently-issued study concerning planning for the interconnection of large loads into the U.S. power system, “load flexibility can accelerate interconnections, reduce ratepayer costs through higher system utilization, and expand the role of demand response, particularly for A.I.-specialized data centers,”30 which are of high concern.

V. PJM’s SUGGESTION THAT THERE IS NEED FOR LESSENED AIR
POLLUTION STANDARDS FOR CO-LOCATED GENERATION SHOULD
BE REJECTED
The Commission can and should prioritize transmission planning and tariff provisions for co- located configurations that do not rely on additional diesel generator back up supply or the lessening of air pollution standards. In response to the Commission’s original request to PJM and the Transmission Owners to discuss the benefits of back-up service in co-located load situations, PJM suggests an option that would allow more reliance on stationary reciprocating internal combustion engines (“RICE”), as back up resources to serve the co-located load when the primary co-located generator is not available.31 Additionally, PJM suggests that current limitations on the situations and total number of hours when units can be used should be loosened “to address resource adequacy concerns in the short term.”32

CATF disagrees with assertions that current restrictions on the use of diesel RICE must be lifted or lessened in order to avoid resource adequacy concerns. As noted above, co-located

30 T. Norris, T. Profeta, D. Patino-Echeverri, A. Cowie-Haskell, Nicholas Institute for Energy, Environment & Sustainability, “Rethinking Load Growth Assessing the Potential for Integration of Large Flexible Loads in U.S. Power Systems” (February, 2025) at 2, available at: https://nicholasinstitute.duke.edu/publications/rethinking-load- growth.

31 PJM Answer at 9, 19, 69-70 & Exh. A (Option 8).
32 Id. at 70. Notably, a decision to weaken air quality standards is not FERC-jurisdictional.

PDF page 14

14

generation and loads cannot be fully islanded, and indeed new large loads even where they bring their own generation should be considered full transmission system participants. FERC should prioritize transmission planning efforts to accommodate even large loads and co-located generation interconnections that can alleviate the asserted need for additional onsite diesel backup RICE units.

And, as noted above in the Section IV, co-located loads offer demand response attributes that can and should be considered in developing tariff provisions, and in transmission planning generally. Where those loads “bring their own generation” resources, those too can provide support and ancillary services where interconnected with the transmission system. And where co-located generation provides clean firm service, it may also yield a benefit to states in meeting their own clean energy standards or portfolio requirements; such benefits also should be recognized.33 Those considerations mitigate against the need either for a larger number of back up diesel RICE or loosened air quality regulatory requirements on RICE units. Importantly, limitations on backup RICE to supply electricity to co-located loads, except in emergency situations, are a necessary requirement in order for those RICE units to comply with standards established by the Environmental Protection Agency (“EPA”) for the control of emissions of hazardous and other air pollutants.34 RICE units emit several toxic air pollutants, including formaldehyde and benzene which are known human carcinogens, as well as smog-

33 For an explanation of the benefits of clean firm generation, see Clean Air Task Force, Clean Firm Electricity Supply and Load Growth (March 26, 2025), https://www.catf.us/events/clean-firm-electricity-supply-load-growth/; see also Clean Air Task Force, Tracking clean energy in U.S. states (2025), https://www.catf.us/us/state- policy/clean-electricity-standards/ (showing state requirements for clean energy).
34 NESHAP for Hazardous Air Pollutants for Reciprocating Internal Combustion Engines, and New Source Performance Standards, 78 Fed. Reg. 6674 (Jan. 30, 2013).

PDF page 15

15

forming NOx and VOCs, and particulate matter which causes and worsens respiratory ailments.35 Calls for lessening those requirements are both outside of FERC’s jurisdiction, as the standards are completely within EPA’s authority, 42 U.S.C. § 7412, and unnecessary. FERC planning and tariff provisions must accommodate co-located loads and generation, assuming all onsite generation is compliant with environmental regulations.

It is CATF’s position that as FERC considers co-located generation and large loads in its transmission planning processes, and in developing tariff provisions, there are many transmission system benefits offered both by co-located clean firm generating resources, and by the co-located large loads, that make the need to add additional RICE or longer run hours for existing RICE unnecessary. And CATF disagrees that “accessing this additional [RICE] capability more actively” by loosening air quality and public health-beneficial limitations on RICE run time is needed to facilitate large load interconnections.36

VI. CONCLUSION
CATF applauds FERC’s consideration of these important issues. Increased demand for transmission services, driven in part by large loads such as data centers, whether or not co- located with generation have made careful consideration of how tariff provisions properly can support interconnection and transmission access and assure just, reasonable, and non- discriminatory rates. Co-located large loads and generation cannot be fully isolated from the grid, and the costs associated with the additional load, as well as the benefits provided to the system and to the states by clean firm co-located generation, must be reflected in rates, practices,

35 Regulatory Impact Analysis (RIA) for the Reconsideration of the Existing Stationary Compression Ignition Engines (SI) RICE NESHAP (January 2013) at Ch. 7, https://www.epa.gov/sites/default/files/2020- 07/documents/ic-engines_ria_reconsider-existing-si-engines_2013-01.pdf.
36 PJM Answer at 70.

PDF page 16

16

and procedures that are consistent with transmission access and cost-causation principles applicable to all other loads and generators. That analysis must consider the benefits to the grid presented by flexible load that is demand responsive, as well as the costs to the grid of the additional services the new load or generator will necessarily require. FERC must require large loads with co-located generation (such as data centers) to follow the same interconnection requirements of Order 2023 and long-term transmission process set forward in Order No. 1920, assuming all co-located generation meets otherwise applicable environmental standards. We thank the Commission for the opportunity to comment on this matter.

Respectfully submitted on this 24th day of April 2025.

/s/ Ann Brewster Weeks

Ann Brewster Weeks

Clean Air Task Force

114 State Street, 6th Floor

Boston, MA 02109

(617)-642-0234

aweeks@catf.us

PDF page 17

17

CERTIFICATE OF SERVICE
I hereby certify that the foregoing has been served in accordance with 18 C.F.R. § 385.2010 upon each party designated in the official service list compiled by the Secretary in this proceeding, by email.

/s/ Ann Brewster Weeks
Ann Brewster Weeks, Of Counsel
Clean Air Task Force
114 State Street, 6th Floor
Boston, MA 02109
aweeks@catf.us