Comments of Clean Air Task Force re FERC's Order Instituting Proceeding under Section 206 of the Federal Power Act and Consolidating with Other Proceedings
Text extracted from the eLibrary original (SHA-256 b3000433a7e86b25…). Download the original from the official source.
Contents · 6 sections
- I. CO-LOCATED GENERATION TO SERVE LARGE LOADS CANNOT BE
- II. FERC HAS JURISDICTION IN THIS MATTER TO REQUIRE REGIONAL
- III. PER ORDER NO. 1920, DATA CENTERS MUST BE INTEGRATED INTO
- IV. FERC MUST ENSURE COSTS ASSOCIATED WITH CO-LOCATED LARGE
- V. PJM’s SUGGESTION THAT THERE IS NEED FOR LESSENED AIR
- VI. CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
It is CATF’s view that, not just in PJM, FERC must consider the issues presented here as it engages with transmission planners across the country on regional planning, going beyond a case-by-case approach to create generally applicable rules for integrating new large loads onto the grid, with or…Read this passage Filed comments: Connecting load and generation
I. CO-LOCATED GENERATION TO SERVE LARGE LOADS CANNOT BE
printed heading · Topic match: Connecting load and generation
CATF supports the conclusions of PJM, Indicated PJM Transmission Owners, Public Service Gas & Electric, and the Union of Concerned Scientists that all co-located load is Network Load, cannot be fully isolated, and inevitably uses and also impacts the transmission system.4 The co-located load,…Read this passage Filed comments: Connecting load and generation
II. FERC HAS JURISDICTION IN THIS MATTER TO REQUIRE REGIONAL
printed heading · Topic match: Connecting load and generation
As discussed further below, in developing just and reasonable rates for co-located load arrangements (particularly any “bring your own generation” configuration), the Commission must consider both the full costs of transmission services necessary to support such resources, as well as any potential…Read this passage Filed comments: Connecting load and generation
III. PER ORDER NO. 1920, DATA CENTERS MUST BE INTEGRATED INTO
printed heading · Topic match: Connecting load and generation
PER ORDER NO. 1920, DATA CENTERS MUST BE INTEGRATED INTO LONG TERM PLANNING TO ADDRESS IMPLICATIONS OF LARGE LOADS ON TRANMISSION SYSTEM While the Commission is asked to look at PJM’s tariff of today, as it considers issuance of a broader ruling it must ensure that planning to meet transmission…Read this passage Filed comments: Connecting load and generation
IV. FERC MUST ENSURE COSTS ASSOCIATED WITH CO-LOCATED LARGE
printed heading · Topic match: Cost allocation
In order for the cost allocation of improved transmission to be just, reasonable, and not unduly discriminatory, FERC must first require clean and transparent accounting of benefits and burdens of each large co-located load interconnection for the transmission system and detailed accounting of what…Read this passage Filed comments: Cost allocation
V. PJM’s SUGGESTION THAT THERE IS NEED FOR LESSENED AIR
printed heading · Topic match: Connecting load and generation
In response to the Commission’s original request to PJM and the Transmission Owners to discuss the benefits of back-up service in co-located load situations, PJM suggests an option that would allow more reliance on stationary reciprocating internal combustion engines (“RICE”), as back up resources…Read this passage Filed comments: Connecting load and generation
VI. CONCLUSION
printed heading
Co-located large loads and generation cannot be fully isolated from the grid, and the costs associated with the additional load, as well as the benefits provided to the system and to the states by clean firm co-located generation, must be reflected in rates, practices, 35 Regulatory Impact Analysis…Read this passage
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that the foregoing has been served in accordance with 18 C.F.R. § 385.2010 upon each party designated in the official service list compiled by the Secretary in this proceeding, by email. /s/ Ann Brewster Weeks Ann Brewster Weeks, Of Counsel Clean Air Task…Read this passage