EL25-49-000 · 2025-04-29 · Rocky Mountain Institute

Amended Comments of Rocky Mountain Institute re the Answers of PJM Interconnection, L.L.C. to the Order Instituting Proceeding under Section 206 of the…

PDF page 1

Basalt, CO  /  Boulder, CO  /  New York, NY  /  Oakland, CA  /  Washington, D.C.  /  Beijing, China http:///www.rmi.org /  303.567.8716

April 29, 2025

Honorable Debbie-Anne A. Reese, Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C. 20426

Re: Comments of RMI; Docket No. EL25-49-000 (consolidated)

Dear Secretary Reese:

Attached, please find amended comments of RMI on the Answers of PJM Interconnection, L.L.C. to the Order Instituting Proceeding under Section 206 of the Federal Power Act and Consolidating with Other Proceedings.

Sincerely,

/s/Uday Varadarajan

Uday Varadarajan
Senior Principal
RMI
2490 Junction Place, Suite 200
Boulder, CO 80301

UNITED STATES OF AMERICA

PDF page 2

1
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

Order Instituting Proceeding under Section 206
of the Federal Power Act and Consolidating with
Other Proceedings
)
Docket No. AD24-11-000
)
Docket No. EL25-20-000
)
Docket No. EL25-49-000 (consolidated)

COMMENTS OF RMI

I. Introduction
RMI thanks the Federal Energy Regulatory Commission (the “Commission”) for its examination of issues related to the co-location of large loads at generating facilities in PJM Interconnection L.L.C (“PJM”), as consolidated in Docket No. EL25-49-000, and hereby submits these comments pursuant to the invitation to address “(1) whether the existing Tariff remains just and reasonable and not unduly discriminatory or preferential; and (2) if not, what changes to the Tariff should be implemented as replacement rates”, including process improvements and forecasting transparency.

RMI analysis finds that a co-location strategy — which we call “Power Couples” — can help rapidly supply clean electricity to data centers and other new, large loads without risking grid reliability. A Power Couple is the pairing of a large electricity consumer with new-build solar, wind, and battery storage resources sized to meet the on-site load, all located near an existing gas generator with an approved interconnection. The load draws no energy from the grid and is equipped with physical protections to prevent the potential emergence of a load sink should co-located generation trip, while the gas generator continues to offer the network priority access to capacity, energy, and ancillary services whenever called upon.1 Rounding out this winning combination, surplus clean electricity from the renewables will often be available to serve the grid while reducing emissions, in all likelihood achieving a net reduction of the historical emissions of the co-located gas generator.

Founded in 1982 as Rocky Mountain Institute, RMI is an independent, nonpartisan, nonprofit that transforms global energy systems through market-driven solutions to secure a clean, prosperous, zero- carbon future for all. We work in the world’s most critical geographies and engage businesses, policymakers, communities, and nongovernmental organizations to identify and scale energy system interventions that will cut climate pollution at least 50 percent by 2030.

II. Comments

1) Fully or wholly isolated co-located load is very well consistent with engineering and economic principles, and PJM contention to the contrary is unduly discriminatory

PJM expresses a clear preference for co-location solutions featuring Network Load. Adumbrating two proposed co-location options (4 and 5) in which the Network Load designation (and responsibilities) would not apply, PJM stipulates the installation of “system protection facilities…to prevent delivery of

1 RMI has modelled these network responsibilities based on historical operating data of individual gas generators.

PDF page 3

2
energy from the grid” and then proceeds to question the efficacy and economic fairness of those same facilities.2 As PJM tells it,

This configuration has been described as “fully” or “wholly” isolated by others, but this characterization is inconsistent with engineering and economic principles. This configuration relies on and takes grid services (for example, ancillary services) and should pay its fair share of those charges. Additionally, this configuration carries operational risk in that there is a dependency on the protection system to support reliability.

The allegation that fully or wholly isolated co-load is inconsistent with engineering and economic principles is not substantiated by PJM.

In the Power Couples approach, power electronics offer protection on two fronts: 1) preventing the co-located load from drawing energy from the grid if the gas generator is insufficient or unavailable to meet any of the load’s otherwise unmet needs and 2) by curtailing dispatch from the renewables and discharge of storage in the event the co-located load cannot absorb such output and the grid has no call for it.

RMI’s Power Couples Architecture

2 EL25-49-000, Answer of the PJM Interconnection, L.L.C., (March 24, 2025), at 14.

PDF page 4

3
The Power Couples architecture does not prevent the System Operator from managing the gas generator’s output as it did prior to co-location, and the same communications controls should be capable of managing the export of surplus renewables under export conditions.

To reiterate, with this architecture the co-located load never takes energy from the grid. At times when the gas generator is not called upon by system operator, it may deliver energy to the co- located load, but RMI is hard-pressed to identify the use of grid services: the onsite inverter and storage resources are fully capable of maintaining voltage and following load fluctuations locally. In a black start eventuality, it stands to reason that the grid would be in distress and availing itself of its claim on the legacy gas generator; it follows that the benefits and the costs of black start service should accrue to Network Load, not the co-located load that would not be relying on any grid resources during the event. Thus, the only change from the grid’s perspective would from the variability of surplus exports from the existing interconnection; logically, the costs of managing this variability are the networked loads that benefit in real-time from the clean and affordable export electricity, not the co-located load managing power quality onsite with self-funded power electronics. The Power Couples option is in effect a rebuttal of PJM’s insistence that “At a minimum, co-located arrangements implicate the Commission’s transmission jurisdiction due to PJM’s provision of ancillary services and in light of the wholesale sales taking place over certain facilities.”3

PJM adds that its Option 4 “configuration carries operational risk” because it creates a “dependency” on technology “to support system reliability.” RMI is curious whether PJM can identify any load-serving configuration, networked or otherwise, that is devoid of technology- dependent risk. Failing such demonstration, if PJM could show that the protection systems envisioned for the RMI Power Couples solutions (and conceivably other solutions suitable for service under proposed Option 4) create more risk than current configurations, then there would be a case for a developing a tariff element to compensate the network service accordingly. PJM, however, has offered no facts in this regard.

2) PJM should rectify the current lack of a “tariffed study process for load (that is not PJM Network locating behind a generator’s Point of Interconnection,”4 implementing study processes tailored specifically for assessing such co-locations solutions

In these comments, RMI has described a co-location architecture where load sits behind an existing generator’s interconnection but cannot draw energy from the grid (thanks to physical protections), otherwise benefit from grid services, or occasion adverse impacts on the grid.

In the absence of a suitable tariffed study process, PJM currently employs the Necessary Study “for a load co-locating with an existing generation resource and not seeking to be a Network Load,”5 evaluating it for the full amount of load and reflecting any Capacity Interconnection Rights reductions, and involve generation deliverability, N-1 and N-1-1 thermal and voltage studies, special protection systems review, baseline stability, and, if applicable, a nuclear plant interface requirements voltage analysis.”6 Assessing co-located load for the full amount of load without first assessing the efficacy and reliability of the protection systems intended to prevent the addition of any load imposes, in RMI’s opinion, unnecessary costs and burdens on a Power Couple or similar architecture. Furthermore, since Power Couples do not alter the use of the existing interconnection other than

3 PJM, at 30. 4 PJM, at 47. 5 PJM, at 48.
6 PJM, at 49.

PDF page 5

4
by potentially delivering additional energy within previously studied limits (under Surplus Interconnection Service allowed by the Commission’s Order 845), thermal and voltage studies are superfluous. PJM’s Necessary Study application to co-location solutions like Power Couples is, thus, both poorly sequenced and poorly integrated with other regulatory study procedures. The Commission must give PJM clear instructions to address these deficiencies.

3) PJM should require earlier standardized information sharing between itself, large load customers, and transmission owners (TOs) to improve forecasting accuracy and reduce planning uncertainty.

PJM acknowledges in its response to Section D.v that uncertainty around large load additions can lead to overbuilding or underbuilding of system resources, and that improvements to forecasting may be warranted. RMI agrees, and underscores the importance of earlier, standardized, and more detailed load information sharing between itself, large load customers, and TOs.

Receiving critical information such as ramp rates, load profiles, project timelines, and capital commitments could help PJM more accurately determine and communicate resource adequacy needs and risks. Standardizing this information—and ensuring it is shared directly with RTOs—would improve forecasting, guide more efficient transmission planning, and help avoid infrastructure misalignment. RMI also supports aligning these planning improvements with meaningful large load corporate commitments, so that these customers contributing to new infrastructure needs are positioned to share in their costs.

III. Conclusion
RMI respectfully requests that the Commission accept the comments herein.

Sincerely,

/s/Uday Varadarajan

Uday Varadarajan
Senior Principal
RMI
2490 Junction Place, Suite 200
Boulder, CO 80301
Email: uvaradarajan@rmi.org