EL25-49-000 · 2025-05-02 · Northern Virginia Electric Cooperative, Inc., Northeastern Remc
Answer of Northern Virginia Electric Cooperative, Inc. and Northeastern Rural Electric Membership Corporation Opposing the Joint Comments and Motion to Stay…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000
PDF page 2
2
Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
AD24-11-000
EL25-20-000
(Consolidated)
ANSWER OF NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC. AND
NORTHEASTERN RURAL ELECTRIC MEMBERSHIP CORPORATION OPPOSING
THE JOINT COMMENTS AND MOTION TO STAY PROCEEDINGS AND REQUEST
TO ESTABLISH SETTLEMENT JUDGE PROCEDURES
Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”),1 Northern Virginia Electric Cooperative, Inc. (“NOVEC”) and Northeastern Rural Electric Membership Corporation (“NREMC”) respectfully submit this answer in opposition to the Joint Parties’ April 22, 2025, “Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures” (“Motion”).21 18 C.F.R. § 385.213.2 Joint Parties, Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures, Docket Nos. EL25-49-000, et al. (filed April 22, 2025) (Accession No. 20250422-5166) (“Motion”). The Joint Parties are a group of generators and trade associations that includes the Electric Power Supply Association, the PJM Power Providers Group, Calpine Corporation, Cogentrix Energy Power Management, LLC, Constellation Energy Generation, LLC, and LS Power Development, LLC.
PDF page 3
3
I. ANSWER
The Joint Parties’ Motion asks that the Commission find the PJM Interconnection, L.L.C (“PJM”) Open Access Transmission Tariff (“Tariff”) to be unjust and unreasonable, stay the consolidated proceeding, and establish settlement judge procedures to develop a replacement rate.3 The Commission should deny the Motion and find that the PJM Tariff is just and reasonable and does not require revisions.
The Motion presupposes not only that the PJM Tariff is not just and reasonable, but that revisions to the PJM Tariff that provide for unique treatment to co-located load would be just and reasonable and not unduly discriminatory. The first assumption is incorrect. Co-location can be effectively accommodated within the existing PJM Tariff through established transmission service structures as Network Load or Point-to-Point Service.4 Every co-location arrangement that has been proposed, aside from true physical islanding, involves reliance on the transmission system for ancillary services and backup supply. This is why, as the Indicated PJM Transmission Owners explained, the PJM Tariff provides that co-located customers need to acquire firm transmission service just like every other customer.5 The fact that the rules do not produce the Joint Parties’ preferred outcome does not mean that the rules are unclear or unable to accommodate co-location arrangements. Viable and fair options exist under the current Tariff. There is no ambiguity, only the desire for a different result.
The second assumption is also incorrect. The Motion implies that co-location arrangements should not be subject to a “one-size-fits-all” solution.6 To the contrary, a uniform approach is
3 Motion at 2.4 PJM Interconnection, L.L.C., Answer, Docket Nos. EL25-49-000, et al., at 9 (filed March 24, 2025) (Accession No. 20250324-5313); Indicated PJM Transmission Owners, Answer, Docket Nos. EL25-49-000, et al., at 10 (filed March 24, 2025) (Accession No. 20250324-5298) (“Indicated PJM TOs Answer”).5 See Indicated PJM TOs Answer.6 Motion at 2-4.
PDF page 4
4
appropriate because, like other load, co-location arrangements rely on the transmission system. Prospective co-location arrangements still seek to maintain a connection to the transmission system, despite claims that these arrangements will not use or rely on the transmission system. NOVEC and NREMC believe that all load should be served but cannot agree that certain new and privileged large loads should receive preferential treatment at the expense of all other rate-paying transmission customers and the load they serve.
Because the Motion’s threshold presuppositions are incorrect, the relief the Motion requests should not be granted. Staying the proceeding is unnecessary as the Commission should dismiss the consolidated proceeding on the record before it as the existing PJM Tariff is just and reasonable, and not unduly discriminatory or preferential. A settlement process would not be productive because there is no ambiguity to resolve by settlement. If load chooses not to interconnect to the transmission system, then it does not have to pay transmission costs. If, through any configuration, load interconnects to the transmission system, it must contribute to the costs of the transmission system on which it relies – which can be adequately resolved through existing structures in the PJM Tariff. NOVEC and NREMC also agree with the reasoning underlying the Independent Market Monitor for PJM’s (“IMM”) opposition to resolving this proceeding through settlement.7 As the IMM contends, these issues should be “resolved objectively, transparently and in the public interest.”8
II. CONCLUSION
WHEREFORE, for the foregoing reasons, NOVEC and NREMC respectfully request that the Commission deny the Motion.
7 IMM, Comments, Docket Nos. EL25-49-000, et al., at 13-14 (filed April 23, 2025) (Accession No. 20250423-5260).8 Id. at 13.
PDF page 5
5
Respectfully submitted,
//s// Alexandra Jones
Alexandra Jones
Vice President & Senior Counsel
of Energy and Regulatory Affairs
Northeastern REMC
4901 East Park 30 Drive
Columbia City, IN 46725
Tel: (317) 964-1752
Email: a_jones@nremc.com
On behalf of Northeastern Rural Electric
Membership Corporation
//s// Alan I. Robbins
Alan I. Robbins
Debra D. Roby
Thomas B. Steiger III
Washington Energy Law LLP
900 17th Street. N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9313
Email: arobbins@washingtonenergylaw.com
droby@washingtonenergylaw.com
tsteiger@washingtonenergylaw.com
Counsel to Northern Virginia Electric
Cooperative, Inc.
Dated: May 2, 2025.
PDF page 6
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this consolidated proceeding.
Dated at Washington, D.C. this 2nd day of May, 2025.
//s// Jessika Dziechciowska
Jessika Dziechciowska
Energy Practice Analyst
Washington Energy Law LLP
900 17th Street, N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9308
Email: jdziechciowska@washingtonenergylaw.com